Amendment_1_08Apr2015.pdf

PDF 367 KB Posted

Attached to
Fairport Harbor Dredging Federal contract opportunity
Solicitation number
W912P4-15-B-0003
Issued by
Department of the Army Corps of Engineers Engineering District Buffalo

About this file

Please see attachment above with Amendment 1.

View the file

Other files for this federal contract opportunity

Other files attached to Fairport Harbor Dredging, newest first.
File Type Posted
Bid_Abstract_Schedule_B_01May2015.pdf PDF
Bid_Abstract_Schedule_A_01May2015.pdf PDF
Bid_Abstract_Schedule_C_01May2015.pdf PDF
Final_Solicitation_31Mar2015.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W912P4‐15‐B‐0003

MAINTENANCE DREDGING:

FAIRPORT HARBOR

GRAND RIVER, OHIO

AMENDMENT NO. 1

08 APRIL 2015

Amendment No. 1 is an updated bid schedule.

Note 1 for all schedules as been changed to read as follows:

NOTE 1: Bids must be submitted on at least one bidding schedule. Bids must be complete as to all the items on the schedule. Failure to complete all items on a bid schedule will render the bid nonresponsive.

SECTION 00010

SOLICITATION, OFFER, AND AWARD (SF1142) AND BIDDING SCHEDULE

BIDDING SCHEDULE "A"

Bid on Bidding Schedule “A” will be based upon dredging and placement of dredged material from Fairport Harbor & Grand River in the Government-designated Open-Lake Placement Site and Nearshore Placement Area 2 (-11’ LWD to +4.2’ LWD), as shown on the contract drawing, and in accordance with these specifications.

Item No. Description

Estimated Quantity

Unit Unit Price

Estimated Amount

1 Mobilization and Demobilization 1 JB $ $

2 Maintenance Dredging:

Sta. 1+43 ~ 29+00 & Grand River w/ Open-Lake Placement

60,000

CY $ $

3 Maintenance Dredging:

Sta. 29+00 ~ 26’ Contour w/ Nearshore Placement in Placement Area 2 (-11’ LWD to +4.2’ LWD) 50,000

Total Estimated Amount (Items 1,2, & 3) $

OPTION "A"

4 Additional Maintenance Dredging:

w/ Open-Lake Placement 40,000

Total Estimated Amount (Items 1, 2, 3, & 4) $

OPTION "B"

5 Additional Maintenance Dredging:

Area 2 (-11’ LWD to +4.2’ LWD) 10,000

Total Estimated Amount (Items 1, 2, 3, 4, & 5) $

(Cont.)

NOTE 1: Bids must be submitted on at least one bidding schedule. Bids must be complete as to all the items on the schedule. Failure to complete all items on a bid schedule will render the bid nonresponsive.

NOTE 2: Award of this contract will be made based on lowest price at the time of award. The bid form includes bid schedules for placing dredged sediment at various disposal depths: -11’ LWD, - 8’ LWD and –4’ LWD for the Nearshore Disposal portion of the contract. The USACE has determined that disposal at –11’ LWD is the Federal Standard though the non-Federal sponsor has a preference that sediment be placed at the shallower depths. Initial consideration will be given to the lowest price offer.

NOTE 3: The Government may elect to award both Option Items, one of the Option Items, or none of the Option Items. If any of the Option Items are awarded, the Government reserves the right to limit the quantity of material up to the Estimated Quantity of the awarded Option Item.

Additionally, the Government may elect to award any Option within a period of sixty (60) calendar days from the date of Contract Award.

NOTE 4: For bid evaluation purposes, the total bid will be based upon the base bid amount shown above (Items 1, 2, and 3) and the Options (Items 4 and 5) shown above. The Government reserves the right to award to the lowest Bidder based on needs of Government. Only one Schedule of the three will be awarded per this solicitation, Schedules are as follows "A", "B", or "C"

BIDDING SCHEDULE "B"

Bid on Bidding Schedule “B” will be based upon dredging and placement of dredged material from Fairport Harbor & Grand River in the Government-designated Open-Lake Placement Site and Nearshore Placement Area 3 (-8’ LWD to +4.2’ LWD), as shown on the contract drawing, and in accordance with these specifications.

Item No. Description

Estimated Quantity

Unit Unit Price w/ Open-Lake Placement 60,000

Area 3 (-8’ LWD to +4.2’ LWD) 50,000

Area 3 (-8’ LWD to +4.2’ LWD) 10,000 nonresponsive.

NOTE 2: Award of this contract will be made based on lowest price at the time of award. The bid form includes bid schedules for placing dredged sediment at various disposal depths: -11’ LWD, -8’ LWD and –4’ LWD for the Nearshore Disposal portion of the contract. The USACE has determined that disposal at –11’ LWD is the Federal Standard though the non-Federal sponsor has a preference that sediment be placed at the shallower depths. Initial consideration will be given to the lowest price offer.

NOTE 3: The Government may elect to award both Option Items, one of the Option Items, or none of the Option Items. If any of the Option Items are awarded, the Government reserves the right to limit the quantity of material up to the Estimated Quantity of the awarded Option Item. Additionally, the Government may elect to award any Option within a period of sixty (60) calendar days from the date of Contract Award.

NOTE 4: For bid evaluation purposes, the total bid will be based upon the base bid amount shown above (Items 1, 2, and 3) and the Options (Items 4 and 5) shown above. The Government reserves the right to award to the lowest Bidder based on needs of Government. Only one Schedule of the three will be awarded per this solicitation, Schedules are as follows "A", "B", or "C"

BIDDING SCHEDULE "C"

Bid on Bidding Schedule “C” will be based upon dredging and placement of dredged material from Fairport Harbor & Grand River in the Government-designated Open-Lake Placement Site and Nearshore Placement Area 4 (-4’ LWD to +4.2’ LWD), as shown on the contract drawing, and in accordance with these specifications.

Item No. Description

Estimated Quantity

Unit Unit Price w/ Open-Lake Placement 60,000

Area 4 (-4’ LWD to +4.2’ LWD) 50,000

Area 4 (-4’ LWD to +4.2’ LWD) 10,000 CY $ $ nonresponsive.

NOTE 2: Award of this contract will be made based on lowest price at the time of award. The bid form includes bid schedules for placing dredged sediment at various disposal depths: -11’ LWD, -8’ LWD and –4’ LWD for the Nearshore Disposal portion of the contract. The USACE has determined that disposal at –11’ LWD is the Federal Standard though the non-Federal sponsor has a preference that sediment be placed at the shallower depths. Initial consideration will be given to the lowest price offer.

NOTE 3: The Government may elect to award both Option Items, one of the Option Items, or none of the Option Items. If any of the Option Items are awarded, the Government reserves the right to limit the quantity of material up to the Estimated Quantity of the awarded Option Item. Additionally, the Government may elect to award any Option within a period of sixty (60) calendar days from the date of Contract Award.

NOTE 4: For bid evaluation purposes, the total bid will be based upon the base bid amount shown above (Items 1, 2, and 3) and the Options (Items 4 and 5) shown above. The Government reserves the right to award to the lowest Bidder based on needs of Government. Only one Schedule of the three will be awarded per this solicitation, Schedules are as follows "A", "B", or "C"