Attachment_2_H-SeriesDoorSectionDetails.pdf
PDF 2 MB Posted
- Attached to
- Repair Main Hangar Doors B801 Federal contract opportunity
- Solicitation number
- W912LA-19-B-9001
- Issued by
- Department of the Army National Guard
About this file
Attachment 2, Door Specs
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Abstract_-_RPR_Main_Hangar_Door.pdf | ||
| Hangar_Doors_SV_Attendees.pdf | ||
| Attachment_3_B801_Hangar_Door_As-Builts.pdf | ||
| Attachment_1_SOW_-_Rpr_Hgr_Doors_B801.pdf | ||
| W912LA-19-B-9001_Solicitation.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
LEADING EDGE
CLOSING DIRECTION
EXTERIOR
1. DOOR FRAMING LEAD EDGE TOWER ASSEMBLY
2. DOOR FRAMING TRAIL EDGE TOWER ASSEMBLY
3. TOP SPLICE CHANNEL DOOR FRAMING
4. INTERMEDIATE CHANNELS DOOR FRAMING
5. BOTTOM SPILCE CHANNEL DOOR FRAMING
6. DOOR FRAMING CROSS-BRACING
7. FORMED VERTICAL WEATHERSEAL STAND-OFF SHEETING
SUPPORT ASSEMBLY
8. VERTICAL WEATHERSEALS ARE A BULB TYPE SHEET
RUBBER EPDM (ETHYLENE, PROPYLENE, DIENE,
TERPOLYMER) WITH A RESILIENT URETHANE FOAM CORE�
9. HEADER AND SILL WEATHERSEALS ARE SHEET
TYPE RUBBER EPDM (ETHYLENE, PROPYLENE, DIENE,
TERPOLYMER)
10. HEXHEAD CAP SCREWS WITH HARDENED FLAT WASHERS
AND HEX NUTS
11. QUICK DISCONNECT OPERATOR ASSEMBLY
12. PRE-WIRED CONTROLS
13. SOLID STEEL WHEEL MACHINED TO FIT A.S.C.E BOTTOM RAIL
14. ELECTRICAL RECESS PAN FOR JUNCTION BOX AND
LIMIT SWITCHES
15. TELESCOPING TOP ROLLER ASSEMBLY
- TWO VERTICAL ROLLERS AND FOUR HORIZONTAL ROLLERS
HANGAR DOOR COMPONENTS
EXPLODED VIEW SHOWING TYPICAL FIELD
ASSEMBLY REQUIRED FOR DOOR SECTIONSX
XX
INTERIOR ELEVATION AT THE TOP ROLLER AND BOTTOM WHEEL ASSEMBLYX
LEADING EDGE
CLOSING DIRECTION
EXTERIOR
Telescoping top roller assemblies accommodate the designed wind load specification and also meet the buildings deflection criteria.
- The maintenance free vertical and horizontal rollers guide the door with a smooth and secure operation. The telescoping pipe captivates the upper portion of each door section to the W-Beam guide track assembly.
Bottom wheel assemblies also accommodate the specified loading criteria.
- Tapered roller bearings with high pressure grease fittings provides years of trouble free service.
- The wheel housing is designed to allow removal of the wheel without having to take down the door framing.
Perimeter Weather Seals.
- Vertical door to door, door to jamb and sill weather seals are sheet rubber EPDM (Ethylene, Propylene, Diene, Terpolymer). Vertical weather seals between the door sections shall seal against the lead edge stand-off assembly and not come in contact with the door sheeting. Vertical center door to door bulb seals will compress tightly when the door sections are in their closed position. Head Sill weather seals are flap type sheet rubber EPDM (Ethylene, Propylene, Diene, Terpolymer). All weather seals shall be retained with full binding strips attached with rust resistant fasteners.
Neoprene cushioned bumper pick-up system.
- Interconnects door sections. Allowing one operator to move multiple panels.
COLLAR PLATE
SCH 40 OR 80 PIPE
DOOR
FRAMING
VERTICAL
TOP HORIZONTAL
TOP SPLICE CHANNEL
OPTION - ADDED
INTERIOR SILL
WEATHERSEAL
FOR PAINT BOOTH
FACILITIES
1. DOOR FRAMING TOWER ASSEMBLY
2. VERTICAL WEATHERSEALS ARE A BULB TYPE SHEET
RUBBER EPDM (ETHYLENE, PROPYLENE, DIENE, TERPOLYMER) WITH
A RESILIENT URETHANE FOAM CORE�
3. FORMED VERTICAL WEATHERSEAL STAND-OFF/SHEETING SUPPORT
ASSEMBLY
4. HEADER AND SILL WEATHERSEALS ARE SHEET TYPE RUBBER EPDM
(ETHYLENE, PROPYLENE, DIENE, TERPOLYMER)
5. TOP GUIDE TRACK BUMPER ASSEMBLY
6. TELESCOPING TOP ROLLER ASSEMBLY
- TWO VERTICAL ROLLERS AND FOUR HORIZONTAL ROLLERS
7. W-BEAM TOP GUIDE TRACK ASSEMBLY IN FACTORY FABRICATED
ASSEMBLIES
8. SOLID STEEL WHEEL MACHINED TO FIT THE A.S.C.E. BOTTOM RAIL
9. SINGLE AND DOUBLE BUMPER PICK-UP BRACKETS. INTERCONNECTS
MULTIPLE DOOR SECTIONS
HANGAR DOOR HARDWARE
COLLAR PLATE CHANNEL
SINGLE BUMPER ASSEMBLY
FINISHED FLOOR
ELEVATION
FLAT BAR BUMPER PLATE
SPACER
NEOPRENE BUMPER
HEXHEAD CAP SCREW
DOOR FRAMING
WEATHERING BINDING
EPDM WEATHERING
SQUARE NUT
- WELDED TO INSIDE
OF FRAMING VERTICAL
DOUBLE BUMPER ASSEMBLY
CORRUGATED SHEETING IS COMMON TO
MATCH THE BUILDING SHEETING (BY OTHERS)
1. DOOR FRAMING TOWER ASSEMBLY
2. LEAD EDGE VERTICAL WEATHERSEALS ARE A BULB TYPE SHEET
RUBBER EPDM (ETHYLENE, PROPYLENE, DIENE, TERPOLYMER) WITH
A RESILIENT URETHANE FOAM CORE�
3. EMT ELECTRICAL CONDUIT, WITH ELECTRICAL RACEWAY WIRE WITHIN
4. FORMED ELECTRICAL RECESS PAN ASSEMBLY
5. ELECTRICAL - LOCKABLE - DISCONNECT
6. PRE-WIRED ELECTICAL CONTROL PANEL ASSEMBLY -TESTED AT THE FACTORY
7. PUSHBUTTON STATION - OPEN AND CLOSE
8. FLEXIBLE ELECTRICAL CONDUIT TO THE OPERATOR ASSEMBLY
9. GEAR REDUCER
10. ELECTRIC BRAKE
11. ELECTRIC MOTOR
12. QUICK DISCONNECT OPERATOR BASE ASSEMBLY
13. MANUAL MECHANICAL DISCONNECT FOR USE IN "NO-POWER" SITUATIONS
14. TOW BAR FOR OPERATING DOORS WITH A TUG IN "NO POWER" SITUATIONS
15. SINGLE ROW ROLLER CHAIN
16. SPUR GEAR/SPROKET ASSEMBLY
17. DRIVE WHEEL/DRIVE WHEEL HOUSING ASSEMBLY
18. LOCKABLE FLUSH LATCH
19. BOTTOM RAIL WIPE
20. OPERATOR ACCESS COVER WITH WEATHER TIGHT PERIMETER SEAL
ELECTRICAL OPERATOR ASSEMBLY
LEADING EDGE
CLOSING DIRECTION
EXTERIOR
CHAIN ADJUSTMENT BOLT
Our pre-wired controls and all wiring internal to the powered door section is completed and tested at the factory minimizing field wiring requirements.
The quick disconnect operator assembly is a feature unique to Door Engineering and Manufacturing, LLC.
- The single lever disengage mechanism completely separates the motor assembly from the drive wheel for a non-electrical powered operation. This system eliminates the possibility of any damage to the gear reducer and electric motor due to the reversal effort through the gear reducer and electric motor. It also does not require release of the electric motor brake.
- Horse Power 1/4 hp - 2 hp
- Electrical "Primary" standard
-480 volt, 3 phase, 60 Hz
• Option electrical
- 575 volt, 3 phase, 60 Hz
- 208 volt, 3 phase, 60 Hz
- 110 volt, single phase, 60 Hz
- Electical "Secondary" standard
- Control voltage, 24 volt DC
• Option - 110 volt AC
- Fixed Speed 45 (fpm) standard
• Option Speeds 30 fpm and 60 fpm
• Option "VFD"
(Variable Frequency Drive)
- Traction - Designed to meet .2 coeffiecent friction
OPERATOR SPECIFICATION
INTERIOR ELEVATION AT THE OPERATOR ASSEMBLYX