STATEMENT OF WORK
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| CAPABILITIES_QUESTIONNAIRE.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
REPAIR BUILDING ENVELOPES
PHASE 3
BUILDINGS 2274 & 2275
PDPG172014
163 ATTK WING, MARCH AIR RESERVE BASE CA
CALIFORNIA AIR NATRIONAL GUARD
163 Civil Engineering Squadron
4 DEC 2017
1 GENERAL REQUIREMENTS
1.1 SCOPE
The exterior cement plaster at buildings 2274 & 2275 and two site enclosures is weathered, worn, stained, discolored, and poorly patched. The purpose of this project is to provide construction services necessary to repair cement plaster, prepare and cement coat all exteriors for the 163d Attack Wing, March ARB, CA. Additional work includes grading demolition, and painting adjacent metal.
1.2 COST PROPOSAL
| ITEM | AREA | |
| CLIN 1 – 2274 & Enclosure | 7,200 SF | |
| CLIN 2 – 2275 & Enclosure | 13,300 SF |
1.3 PERIOD OF PERFORMANCE
Period of Performance (POP) shall be 60 days from the Notice to Proceed (NTP).
1.4 GRADING & DEMOLITION
A Remove crushed rock at base to expose wall typical.
B Remove grade 3” below paving typical.
| 1 2274: | Remove 70 CY berms. Remove 22’ 8’H chain link fence on berm, salvaging 25’ TV antenna. Remove 50’L x 2’H stacked retaining wall and 70’L x 2’H CMU retaining wall and foundation. Relocate 10 TN boulder to material storage area. |
| 2 2275: | Remove 70 CY berms. |
1.5 PAINT
A Inspect existing metal flashing at approximately 4 feet height around certain sections of facilities and beneath windows. Calk where damage is minor, and where damage is unfixable repair/replace flashing.
B Refurbish anodized aluminum reglets and building numbers.
C Prep and paint to match cement coating metal flashing, gutters, downspouts, thru wall drains, trim, sills, wall and roof caps, louvers, and accesses hatches, etc.
| 1 | 2274: | Paint pump, galvanized duct, rusted framing and pipe. Clean sun louver. Cut rebar in ceiling and patch. |
| 2 | 2275: | Relocate conduit and low voltage wire in mound to 12” below grade. Lower backflow to 12” above grade. Paint concrete reveal. Paint ladder and enclosure gates with industrial acrylic grey paint. |
1.6 CEMENT COATING
A Provide La Habra Allegro II cement coating. Color: Sandstone.
B Provide lath and plaster at exposed walls where berms have been removed. Match existing finish.
C Clean out and repair chips, cracks, and holes in the existing cement plaster to match adjacent surfaces.
D Scrape loose paint of cast-in-place and concrete masonry walls.
E Power wash all surfaces.
F Mask windows and trim.
G Spray apply cement coating on cement plaster, cast-in-place concrete wing walls and loading dock walls, and painted concrete masonry walls per manufactures recommendations.
1.7 CHAIN LINK FENCE
2274: Provide 8’ 22’ long chain link fence with additional 3 strand barbed wire to match existing. Remove and reinstall 25’ high TV antenna to fence post.
1.8 STAGING AND SITE ACCESS
Materials and Equipment shall be staged in adjacent parking lots. Contractor and Government shall establish schedule of use.
1.9 DEMOLITION
Dispose all waste per industry standards and regulations to approved off-base location.
1.10 SITE CLEAN UP
Remove and dispose of all project debris in accordance with industry standards and regulations to approved off-base location.
2 GENERAL CONDITIONS
2.1 CONTRACT MANHOURS REPORTING APPLICATION (CMRA)
The Contractor shall report ALL contractor Labor Hours (including subcontractor labor hours) required for performance of services provided under this contract for the Department of the Air Force via a secure data collection site. The contractor is required to completely fill in all required data fields using the following web address: https://www.ecmra.mil/. Reporting inputs will be for the labor executed during the period of performance during each Government Fiscal Year (FY) which runs from October 1 thru September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year. Contractors may direct questions to the helpdesk at https://www.ecmra.mil.
2.2 SUBMITTALS
Submit Cement Coating and Paint product data in PDF format.
2.3 SCHEDULE
Submit project schedule for the proposed work in PDF format.
2.4 CHANGES
All work shall be completed in a workmanlike manner according to generally accepted standard practices. Any alteration, or deviation from the drawings/specifications or contract involving extra costs or credits will be executed as mutually agreed upon and be verified by written change order.
2.5 TESTS & INSPECTIONS
Provide all required tests and inspections required by code.
2.6 WARRANTY
Guarantee the material and workmanship for a minimum of one (1) year following the date of substantial completion.
2.7 PROJECT CLEANUP
Construction debris will be removed on a daily basis. Prior to final acceptance, contractor shall remove all waste materials and debris arising from construction and shall present all construction areas in a broom clean condition.
2.8 TEMPORARY FACILITIES
Government provided sanitary facilities are located in Building 2279.
2.9 HOURS OF OPERATION
Construction shall be performed during normal duty hours which are 0700-1600, Mondays through Fridays, excluding federal holidays, unless otherwise required in the contract or approved by the COR. There may be situations that require the contractor to work at times other than normal working hours. When the Contractor’s work schedule conflicts with an Air Force mission requirement, the COR reschedule the work to minimize disruption.
2.10 RECOGNIZED HOLIDAYS
Contractor is not required to provide service on federal holidays, except in emergency situations. When a federal holiday falls on Saturday, the preceding Friday will be observed. If these holidays fall on Sunday, the following Monday will be observed. If a holiday falls on a scheduled service day, the Contractor will be responsible for rescheduling services for the first day post the holiday observance.
2.11 BASE CLOSURES
Work scheduled but not accomplished because of base closure due to weather, exercises, or actual alert, will be accomplished as soon as possible after reopening the base.
2.12 CONTRACTOR IDENTIFICATION BADGES
March Air Reserve Base is a DOD installation. All badging and security checks will be done in accordance with DOD, Air Force and base Security Forces requirements.
A Badges or temporary base passes will be issued. All commercial vehicles will be inspected each time they enter the base.
B Badges will be issued by the 452d Security Forces Squadron (SFS) to the contractor through the 163d Civil Engineering Squadron (CES) Construction Inspector. Badges shall be issued, tracked, and collected in accordance with instructions from Security Forces.
C The following are the requirements and procedures for the contractor:
1 Contractors and sub-contractors working on the installation for 30 calendar days or more must be issued contractor identification badges. Contractors must submit a list of all workers using govt-provided form which will be routed through 452 SFS for approval. Once approved, passes will be picked up at the visitor center.
2 Contractors working in Controlled or Restricted areas or any area on the flight line must be issued a specific contractor identification badge or be escorted.
2.13 PERFORMANCE OF SERVICE DURING CRISIS OR HEIGHTENED SECURITY
In the event of crisis or heightened security caused by a national emergency, natural disaster, or other cause, continue performance as required in support of the Air Force mission. The Contract price and delivery schedule may be adjusted to reflect any change of work that may be directed. This service is not determined to be essential for performance during crisis according to DODI 3020.37.
2.14 SPECIAL QUALIFICATIONS
Contractor shall provide the name and telephone number of the Contractor’s on-site contract manager and alternate. The Contractor’s on-site manager and alternate must both be able to speak and write in the English language. Wither the on-site manager or alternate must be present on site at all times to provide quality control and oversite of project operations.
2.15 INTERFACES
Do not unduly interfere with regularly scheduled Government operational activities in the performance of contract requirements. In the event a Government supervisor so requests, temporarily cease work in the area and report the instructions, to include name of the Government person involved, to the COR immediately by the most expedient means. Notify the COR verbally of disputes with customers or other base contractors and follow-up in writing.
2.16 WORK CLEARANCE/DIG PERMIT REQUESTS
Contractor shall obtain an approved Work Clearance Request, AF Form 103, for all work which involves excavation including minor digging. Blank digging permits are available from the 163d CES Operations Section and must be routed through the 452d CES and other on- base parties as listed on the form. The approval process takes roughly two weeks to complete.
2.17 SAFETY REQUIREMENTS AND REPORTS
Contractor shall perform work in a safe manner as required by OSHA Safety and Health Requirements. Provide a verbal report to the COR as soon as possible of each occurrence of damage to Government property or an accident resulting in death, injury, occupational disease, or adverse environmental impact. Provide a completed copy of required Accident Investigation Reports to the COR within five calendar days of each occurrence.
2.18 PARTNERING AGREEMENT
COR may require a partnering agreement between the Government and Contractor to facilitate joint cooperation and a sound partnership of all parties involved in the execution of this contract. Partnering is the creation of a Government-Contractor relationship that promotes achievement of mutually beneficial goals. It involves an agreement in principal to share the risk involved in completing the project and to establish and promote a nurturing partnership environment. Representatives from each organization are encouraged to participate in developing a partnering agreement. The partnering agreement that results may be formal or informal. If formal, it should be reduced to writing and signed by the parties involved.
3 ATTACHMENTS
3.1 PHOTOS
3.2 DRAWINGS
REPAIR BUILDING ENVELOPES
PHASE 3
March Air Reserve Base California