Statement_of_Work_-_Mobile_Crash_Barriers.pdf

PDF 142 KB Posted

Attached to
Mobile Crash Barriers Federal contract opportunity
Solicitation number
W912KC-18-R-9023
Issued by
Department of the Army Pennsylvania Army National Guard

View the file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE AIR FORCE

193D SPECIAL OPERATIONS WING (AFSOC)

81 CONSTELLATION COURT

MIDDLETOWN PENNSYLVANIA

The Voice of the Quiet Professionals of AFSOC Never Seen – Always Heard

1 August 2018

MEMORANDUM FOR: STATEMENT OF MINIMUM REQUIREMENTS

SUBJECT: Portable Barrier – Crash Certified Barrier System

1. Background:

The 193d SOW has been utilizing the same main gate with a passive barrier plan as well as a manually operated mechanical in/out bound gate entrances for many decades. Due to multiple penetration attempts/ successes at DOD installations worldwide, it is imperative we maintain the ability to have reactive barriers to prevent unauthorized access to our installation.

2. Discussion:

The 193 SOW’s current protective posture does not meet minimum DOD Antiterrorism Gate construction standards. In order to mitigate existing risk and comply with DOD UFC minimum construction standards these pop-up barriers are necessary.

3. Specifications:

3.1 Portable barrier-crash certified barrier system, Delta Model MP5000 or equal. Barrier system shall be a minimum, 15,000lb vehicle rated (traveling at least 30mph) portable crash barrier system. Upon vehicle impact, the force shall first be absorbed by the barrier ramp and then transmitted to the ground. This barrier system shall be able to be sited on asphalt roadways. No excavation or sub-surface preparation is allowed. The barrier shall raise to a 45 degree angle to prohibit vehicles from passing through, similar to a phalanx type barrier. Two locations on the installation are required to have barriers; one roadway with a total width of 25ft and another roadway with a total width of 36ft. The mobile barrier shall accommodate both commercial (tractor trailer, emergency vehicles, construction equipment) and private (sedans, motorcycles, low ride-height vehicles, trucks, SUVs) automobiles. The Barricade shall be equipped with hydraulic rams which is required for deployment of barrier. During emergency conditions or power outages a manual deployment mechanism option is required. The standard system must also have a battery operated Hydraulic Power Unit charged by an Internal Battery Charger (operated on a local power source). At least two control points are required and shall be wireless with a minimum range of 250ft. The unit shall be completely self-contained, capable of withstanding weather, winter weather chemical treatments (salts), and daily barrier operation (raising and lowering barrier) to accommodate a single point of entry with vehicle traffic exceeding 300 vehicles a day. *Installation is not required*

DEPARTMENT OF THE AIR FORCE

193D SPECIAL OPERATIONS WING (AFSOC)

81 CONSTELLATION COURT

MIDDLETOWN PENNSYLVANIA

The Voice of the Quiet Professionals of AFSOC Never Seen – Always Heard

3.2 Barrier Height: Height of the Barrier shall be at least 30 inches as measured from the roadway surface to the top edge of the Barrier Ramp. The barrier when in the down position shall be low enough to allow cars and low riding vehicles to pass over top without receiving any damage.

3.3 Finish: All external surfaces of the barrier, ramps, support mechanism and transporter shall have a rust inhibiting industrial enamel surface. The Barrier must be able to withstand at least 3 years of inclement weather, snow/ice treatment chemicals, and the temperature range appropriate for the State of Pennsylvania (0-110 degrees Fahrenheit)

3.4 Barrier Ramp Locking Method: The barrier must have a manual locking mechanism in order to secure the barrier in the ‘Up/Guard’ position when not in use (or as protection posture dictates). The locking mechanism must be capable of being secured by an aftermarket lock and key system (padlock) and should include a failsafe to prevent attempted operation when barrier is locked.

4. Delivery:

120 Days ARO to 79 Mustang Aly, Middletown PA 17057.

5. Site Visit:

A site visit will be conducted on 14 August 2018 at 9:00 AM Eastern time starting in the LRS Classroom, Building 79, 193d Special Operations Wing, Middletown, PA 17057. POC for the site visit is TSgt Natonya Hill via email at natonya.r.hill.mil@mail.mil. Attendance at this site visit is not mandatory. Information provided at this site visit as well as answers to questions shall not change/qualify the terms and conditions of the solicitation and specifications. Terms remain unchanged unless solicitation is amended in writing. If an amendment is issued, normal procedure relating to the acknowledgment and receipt of solicitation amendments shall apply.