RFI__1_DTD_5_Apr_17.docx

DOCX document 14 KB Posted

Attached to
Project Manager - Construction Federal contract opportunity
Solicitation number
W912K6-17-R-0003
Issued by
Department of the Army Maryland Army National Guard

About this file

RFI #1 Dated 5 Apr 17

View the file

Other files for this federal contract opportunity

Other files attached to Project Manager - Construction, newest first.
File Type Posted
PWS_Project_Manager.pdf PDF
W912K6-17-R-0003.pdf PDF
EXHIBIT_F_-_Proposal_Inquiry_Format.docx DOCX document
EXHIBIT_B_-_Information_and_Consent_Form.doc DOC document
EXHIBIT_C_-_Package_Information_and_Forms.doc DOC document
EXHIBIT_A_-_Performance_Relevancy_Questionnaire.doc DOC document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

What is the expected workload for the Project Manager? (ie. How many concurrent projects?)

1 – 15 Contracts can be expected

Will the PM be a part of a team of other PMs in the Squadron, Branch, Division, etc…?

No

Will the PM have responsibilities for other locations outside of Warfield ANGB? If so, what locations?

No What is the expected dollar value range for the construction projects?

All actions above $2000

What type of construction projects will the PM manage? (ie. Office Space renovations, cubicle reconfigurations, facility engineering, new construction, air field repairs, hangar renovations, etc…?

Renovations and New Construction

Who is the incumbent?

Position currently not filled

What was the previous contract value?

Previous value for one person at 9 months was $117,268.00

What Government Furnished Equipment (GFE) is provided?

General office equipment, computer, desk phone, copier/scanner

PWS-1.4.5.4. I see an experience requirement for building SCIFs and a possible requirement for obtaining a Secret Security Clearance. But I don’t see a requirement for the Vendor to hold a Facility Clearance (FC). If a FC is not required, can you please clarify how the clearance process will work? (ie. who will hold the clearance if a Secret Clearance is required?) Will the Key Personnel have to have a current Secret (or higher) Clearance prior to contract award? Will the ANGB sponsor a Vendor for a Secret Facility Clearance if required?

The person will be required to have or obtain a favorable background check. Secret Clearance not required at this time.

Solicitation Pg. 27 of 41. For Vendors that have not operated as a Prime Vendor, will Subcontractor past performance count as the same weight as Prime Vendor past performance?

If using the subcontractor’s past performance and is the key personnel that will be assigned to the contract, Exhibit B must be used and will be weighed the same.

Page 8, “Key Personnel,” says, “The personnel listed below are considered essential to the work performed hereunder.” On page 9, on top of the page, it states, “Name Position/Labor Category.” Please confirm you are asking the proposed Contractor to include the name of the Key Personnel, along with their position title and labor category under their GSA contract in response to this statement and to include this information as part of their proposal response.

The key personnel that will be assigned to the project will be listed.

Page 15, second paragraph, notes that only an electronic copy of proposals are required. Please confirm hard copies are not required; only electronic emailed proposals.

Send in proposals per the solicitation via the SAFE website. https://safe.amrdec.army.mil/safe/

Page 38, second to last paragraph, states, “Prepare not more than 3 of these documents.” This is in reference to Exhibit A, Part I. On the Exhibit A, Part I form, it states, “Prepare not more than five (5) of these documents.” Please clarify if we are to respond with preparing 3 or 5 of Exhibit A, Part I.

The proposal should not have more than 3 documents.

Exhibit A, Part II, lists items to address in proposer’s response – 2A, 2B, 2C, 2D and then it skips to 2F. Please confirm that there isn’t a 2E section and that 2F should in fact be 2E.

The section should read 2E. There is not a 2F.