B.8 Question and Answers_amended.docx
DOCX document 13 KB Posted
- Attached to
- Cardio and ACFT Equipment Federal contract opportunity
- Solicitation number
- W912J620R0014
- Issued by
- Department of the Army National Guard
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Solicitation revisions.docx | DOCX document | |
| 3 - Brand Name J and A_Redacted.pdf | ||
| 2 - Full text provisions and clauses.pdf | ||
| 1 - Purchase Description.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1) Am I reading the table correctly in that CLINs 0001-0005 will be shipping to the destination in CLIN0006, Kapolei, HI 96707. And then, CLINs 0007-0008 will be shipping there as well, (Kapolei), with the exception of a single ACFT bike that will ship to Kihie, HI 96753?
Just trying to understand the split so we can figure out shipping costs.
A: CLINs0001-0005 is FOB Destination shipping to Hilo, HI 96720 (CLIN0006).
CLINs0007 & 0008 is FOB Destination shipping to Kapolei, HI 96707, with the exception of one ACFT Bike shipping FOB Destination to Kihie, HI 96753
2) Is the expectation that all items ship at the same time from the same location to the destination(s)?
A: Invoices will not be accepted until all items have been received, inspected, and accepted.
3) Is 180 days acceptable on a lead time?
A: Delivery time is 60 days after date of contract (ADC)
4) Please note that CLINs 0004 and 0008 would be supplied with the same product. Do you want to leave the RFQ as is, or consolidate those two CLINs into a single CLIN for a quantity of 19?
A: Separate
5) Does the Portable Pull-Up Bar need to be hot dip galvanized to protect against corrosion?
The minimum requirements are those specified in the solicitation which are extracted from the ACFT IOC.
6) Is installation required on the Precor items? This would involve assembling the items and ensuring the computers are working properly upon delivery.
Installation is not required on the Precor items.
File details come from the government source that posted it. Updated .