Questions_and_Answers_Set_3.doc

DOC document 24 KB Posted

Attached to
Septic System at 599 Federal contract opportunity
Solicitation number
W912GY16T0036
Issued by
Department of the Army Materiel Command Contracting Command Detroit Arsenal

View the file

Other files for this federal contract opportunity

Other files attached to Septic System at 599, newest first.
File Type Posted
QUESTIONS_AND_ANSWERS_SET_4.doc DOC document
Questions_and_Answers_Set_2.doc DOC document
QUESTIONS_AND_ANSWERS_SET_1.doc DOC document
Drawing_-_599_Septic.pdf PDF
W912GY-16-T-0036.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers Set 3

1. Is a Flow and perc test required?

ANSWER: No the tests are not required.

2. It appears the Manhole lines may require repairs.

ANSWER: Contractor shall repair sewer lines at existing manhole to insure proper flow.