A02_Hurley_Pipe_SOW.pdf

PDF 34 KB Posted

Attached to
Discharge Pipe Federal contract opportunity
Solicitation number
W912EQ-18-Q-0015
Issued by
Department of the Army Corps of Engineers Engineering District Memphis

About this file

Updated Specifications

View the file

Other files for this federal contract opportunity

Other files attached to Discharge Pipe, newest first.
File Type Posted
A02_Hurley_Pipe_SOW.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work

US Army Corps of Engineers Memphis District (MVM) Specifications for Steel round bar stock.

Scope: The contractor shall deliver the material listed below in table 1 to 2915 Riverport Road, Memphis, TN 38109.

Table 1.

Quantity Description Length 8 ea. 32” I.D. x 5/8” wall, rolled and welded carbon steel pipe.

40’

Note:

- All pipe shall have beveled ends, and multiple mid-welds in each length.

- Pipe shall have a minimum hardness of 180 Brinnell.

- Welds shall fully penetrate the full depth of the wall thickness.

- All pipe seams shall be electrically butt welded.

- The inside weld bead shall be ground flush and smooth.

- The outside weld bead shall rise slightly above the plate surface.

- All pipe shall be cleaned and painted with red oxide primer.

Place of Performance: All material listed in table 1 shall be delivered to EEY Plant Section.

Deliver to USACE, Ensley Engineering Yard, ATTN: Andrea Williams or Paul Lacy, 2915 Riverport Road, Memphis, TN 38109 30 days after contract award or sooner, P.O.C for questions regarding specs please contact Andrea Williams at 901-544-3937.