A07D-SPECS.pdf
PDF 622 KB Posted
- Attached to
- Levee Gravel Resurfacing Federal contract opportunity
- Solicitation number
- W912EQ-17-B-0006
About this file
Specifications
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bid_Abstract_Levee_Gravel_Resurfacing.pdf | ||
| A07D-PLANS.pdf | ||
| A07D-Solicitation.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
St Francis Basin Levee Gravel Resurfacing SFBGRAVEL
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00.00 11 SUMMARY OF WORK
01 22 00.00 11 MEASUREMENT AND PAYMENT
01 33 00 SUBMITTAL PROCEDURES
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 02.00 11 QUALITY CONTROL SYSTEM (QCS)
01 45 04.00 11 CONTRACTOR QUALITY CONTROL
01 57 20.00 11 ENVIRONMENTAL PROTECTION
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 15 00.00 11 AGGREGATE SURFACE COURSE
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
FOR SOLICITATION
SECTION 01 11 00.00 11
SUMMARY OF WORK
PART 1 GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
1.1.1 Project Description
The work consists of furnishing all plant, labor and materials for levee crown resurfacing and any incidental related work according to the specifications and plans. The project limits are as shown on the plans.
The estimated value of the work is between $1,000,000 and $5,000,000
1.1.2 Location
Work performed for this contract shall progress starting with the Base Bid and then to each subsequent option. Work required under options shall be performed after the base bid work if the options are exercised by the Contracting Officer. Each option shall commence with the approval of the Contracting Officer.
1.2 EXISTING WORK
In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.
1.3 LOCATION OF UNDERGROUND FACILITIES
Verify the elevations of existing piping, utilities, and any type of underground obstruction not indicated to be installed or removed, but indicated or discovered during work to be conducted or installed. For further instructions and details, see the paragraph entitled, "OBSTRUCTIONS" in Section 00 80 00.00 11 SPECIAL CONTRACT REQUIREMENTS.
1.4 UAI SUBPART 22.13 - EQUAL OPPORTUNITY FOR VETERANS (NOV 2014)
In addition to complying with the requirements outlined in FAR Part 22.13, FAR Provision 52.222-38, FAR Clause 52.222-35, FAR Clause 52.222-37, DFARS
222.13 and Department of Labor Regulations, U.S. Army Corps of Engineers (USACE) contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract. While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract, SECTION 01 11 00.00 11 Page 2
USACE contractors are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are available to assist USACE contractors in their outreach efforts:
Federal Veteran employment information-https://www.fedshirevets.gov/index.aspx
Department of Labor Veterans Employment Assistance http://www.dol.gov/vets/
Department of Veterans Affairs-VOW to Hire Heroes Act http://benefits.va.gov/vow/
Army Wounded Warrior Program http://wtc.army.mil/modules/employers/index.html
U.S. Chamber of Commerce Foundation-Hiring Our Heroes https://www.uschamberfoundation.org/hiring-our-heroes
Guide to Hiring Veterans - Reference Material https://www.whitehouse.gov/sites/default/files/docs/white_house_business_council_-_guide_
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION (Not Used)
-- End of Section --
SECTION 01 11 00.00 11 Page 3
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00.00 11
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 LUMP SUM PAYMENT ITEMS
1.1.1 Mobilization and Demobilization
1.1.2 Environmental Protection
1.2 UNIT PRICE PAYMENT ITEMS
1.2.1 Gravel Resurfacing
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION (Not Used)
-- End of Section Table of Contents --
SECTION 01 22 00.00 11 Page 1
SECTION 01 22 00.00 11
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 LUMP SUM PAYMENT ITEMS
Payment items for the work of this contract for which contract lump sum payments will be made are listed in the BIDDING SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular lump sum or unit price payment item, shall be included in the listed lump sum item most closely associated with the work involved. The lump sum price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
1.1.1 Mobilization and Demobilization
a. Payment
Payment will be made for costs associated with mobilization and demobilization, as defined in Contract Clauses PAYMENT FOR MOBILIZATION
AND DEMOBILIZATION.
b. Unit of measure, Job: JA
1.1.2 Environmental Protection
a. Measurement
No measurement will be made for Environmental Protection.
b. Payment
Payment will be made for costs associated with operations necessary for environmental protection as specified in the National Pollution Discharge Elimination System (NPDES) and State Laws. This price and payment shall be considered full compensation for furnishing all plant, labor, materials, and equipment and for performing all operations necessary for "Environmental Protection." The Contractor shall be responsible for payment of fees associated with environmental permits, application, and/or notices obtained by the Contractor. The Contractor shall be responsible for payment of all fines/fees arriving from violation or non-compliance with Federal, State, Regional, and local laws or regulations. The Government will not provide any compensation for payments of fines/fees, in the event that fines/fees are incurred by the Contractor.
c. Unit of measure, Job: JA
SECTION 01 22 00.00 11 Page 2
1.2 UNIT PRICE PAYMENT ITEMS
Payment items for the work of this contract on which the contract progress payments will be based are listed in Section 00 41 00.00 11 - BIDDING SCHEDULE and are described below. The unit price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests, and reports, and for performing all work required for each of the unit price items.
Payment items for the work of this contract for which unit price payments will be made are listed in the BIDDING SCHEDULE and described below. The unit price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, meeting safety requirements, tests and reports, and for performing all related work required for which separate payment is not otherwise provided.
1.2.1 Gravel Resurfacing
a. Measurement
All materials will be measured for payment by the ton (2,000 lbs) by weighing each truckload to the nearest 0.1 ton, and the final quantity of the whole sum for each type of material will be rounded to the nearest whole ton. When the gravel resurfacing is delivered by truck, the material will be measured for payment, in the presence of a Government Inspector, unless the Contracting Officer waives such right, by being weighed on approved, accurately calibrated scales furnished by and at the expense of the Contractor. Scales shall be sufficient length to permit simultaneous weighing of all axle loads and shall be inspected, tested and sealed as directed to ensure the accuracy within
0.5 percent throughout the range of the scales. Scales shall be checked and certified before any material hauling; also, rechecked and re-certified whenever a variance is suspected. Individual weight tickets for each truckload of aggregate resurfacing shall be furnished to the Government Inspector at the time of delivery. As a minimum, all weight tickets shall have the contract number or project name, the gross weight, the vehicle identity and empty weight, and the net load weight. Scales that produce this information printed on the weight tickets are prefered. Weight certificates furnished by a Public Weightmaster, where available, will be acceptable, when authorized by the Contracting Officer. The Contractor has the option to use certified, and otherwise acceptable, scales that are Contractor furnished, quarry/supplier furnished, or commercial/public facilities.
b. Payment for
Payment for gravel surfacing will be made at the applicable contract unit price per ton for "Aggregate Resurfacing" which price and payment shall include all costs of furnishing, hauling, handling, stockpiling, reworking, placing, compacting, and maintaining the aggregate resurfacing: all as specified in Section 35 15 00.00 11 and in accordance with the contract drawings. The preparation of subgrade, including the stripping, disking, drying, regrading, and compacting of existing subgrade material in preparation for placement of aggregate surface course shall be incidental to Gravel Resurfacing.
SECTION 01 22 00.00 11 Page 3
c. Unit of measure: ton: TON
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION (Not Used)
-- End of Section --
SECTION 01 22 00.00 11 Page 4
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 33 00
SUBMITTAL PROCEDURES
PART 1 GENERAL
1.1 DEFINITIONS
1.1.1 Submittal
1.1.2 Submittal Descriptions (SD)
1.1.3 Approving Authority
1.1.4 Work
1.2 SUBMITTALS
1.3 SUBMITTAL REGISTER
1.4 CONTRACTOR USE OF SUBMITTAL REGISTER
1.5 APPROVING AUTHORITY USE OF SUBMITTAL REGISTER
1.6 COPIES DELIVERED TO THE GOVERNMENT
1.7 PROCEDURES FOR SUBMITTALS
1.7.1 Reviewing, Certifying, Approving Authority
1.7.2 Constraints
1.7.3 Scheduling
1.7.4 Variations
1.7.4.1 Considering Variations
1.7.4.2 Proposing Variations
1.7.4.3 Warranting That Variations Are Compatible
1.7.4.4 Review Schedule Is Modified
1.8 CONTRACTOR'S RESPONSIBILITIES
1.9 GOVERNMENT'S RESPONSIBILITIES
1.10 FORMAT OF SUBMITTALS
1.10.1 Transmittal Sheet
1.10.2 Identifying Submittals
1.11 SUBMISSION AND CONTROL OF SUBMITTALS
1.11.1 Submittals Required from the Contractor
1.11.1.1 Submittal Procedures and Deviations
1.11.1.2 Control of Submittals
1.11.1.3 O&M Data
1.12 SUBMITTAL CLASSIFICATION
1.12.1 Government Approved
1.12.2 Information Only
1.13 APPROVED SUBMITTALS
1.14 DISAPPROVED SUBMITTALS
1.15 WITHHOLDING OF PAYMENT
1.16 GENERAL
1.17 SUBMITTAL REGISTER
1.18 SCHEDULING
1.19 TRANSMITTAL SHEET (ENG FORM 4025)
1.20 GOVERNMENT APPROVED SUBMITTALS
1.21 INFORMATION ONLY SUBMITTALS
1.22 STAMPS
PART 2 PRODUCTS (Not Used)
SECTION 01 33 00 Page 1
PART 3 EXECUTION (Not Used)
-- End of Section Table of Contents --
SECTION 01 33 00 Page 2
SECTION 01 33 00
SUBMITTAL PROCEDURES
PART 1 GENERAL
1.1 DEFINITIONS
1.1.1 Submittal
Contract Clauses "FAR 52.236-5, Material and Workmanship," paragraph (b) and "FAR 52.236-21, Specifications and Drawings for Construction," paragraphs (d), (e), and (f) apply to all "submittals."
1.1.2 Submittal Descriptions (SD)
Submittals requirements are specified in the technical sections.
Submittals are identified by SD numbers and titles as follows.
SD-01 Preconstruction Submittals
Certificates of Insurance.
Surety Bonds.
Construction Progress Schedule.
Work Plan.
Submittal Register.
Schedule of Prices.
Accident Prevention Program.
Quality Control Plan.
Environmental Protection Plan.
List of Proposed Subcontractors.
List of Proposed Products.
List of Barges.
SD-02 Shop Drawings
Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.
Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project.
Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.
SD-03 Product Data
Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials or equipment for some portion of the work.
SECTION 01 33 00 Page 3
Samples of warranty language when the contract requires extended product warranties.
SD-04 Samples
Physical examples of materials, equipment or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged.
Color samples from the manufacturer's standard line (or custom color samples if specified) to be used in selecting or approving colors for the project.
Field samples and mock-ups constructed on the project site establish standards by which the ensuring work can be judged. Includes assemblies or portions of assemblies which are to be incorporated into the project and those which will be removed at conclusion of the work.
SD-06 Test Reports
Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accordance with specified requirements. (Testing must have been within three years of date of contract award for the project.)
Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.
Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.
Investigation reports.
Daily checklists.
Final acceptance test and operational test procedure.
SD-07 Certificates
Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that product, system or material meets specification requirements. Must be dated after award of project contract and clearly name the project.
Document required of Contractor, or of a supplier, installer or subcontractor through Contractor, the purpose of which is to further quality of orderly progression of a portion of the work by documenting procedures, acceptability of methods or personnel qualifications.
Text of posted operating instructions.
SD-11 Closeout Submittals
Documentation to record compliance with technical or administrative
SECTION 01 33 00 Page 4 requirements or to establish an administrative mechanism.
1.1.3 Approving Authority
Approving authority rests with the Contracting Officer and his/her Authorized Representative(s). Approval actions and correspondence with the Contractor shall be made through the Caruthersville Area Office.
1.1.4 Work
As used in this section, on-site and off-site construction required by contract documents, including labor necessary to produce submittals, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction.
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only or as otherwise designated. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section
01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Submittal register.; G
1.3 SUBMITTAL REGISTER
Submit the submittal register at least seven days prior to the prework conference. Verify that all submittals required for the project are listed and add any missing submittals. Complete the following on the register:
Column (g) Contractor Submit Date: Scheduled date for approving authority to receive submittals.
Column (h) Contractor Approval Date: Date Contractor needs approval of submittal.
1.4 CONTRACTOR USE OF SUBMITTAL REGISTER
Update the following fields.
Column (b) Transmittal Number: Contractor assigned list of consecutive numbers.
Column (j) Action Code (k): Date of action used to record Contractor's review when forwarding submittals to Area Engineer.
Column (l) List date of submittal transmission.
Column (q) List date approval received.
1.5 APPROVING AUTHORITY USE OF SUBMITTAL REGISTER
Update the following fields.
Column (b).
SECTION 01 33 00 Page 5
Column (l) List date of submittal receipt.
Column (m) through (p).
Column (q) List date returned to Contractor.
1.6 COPIES DELIVERED TO THE GOVERNMENT
Deliver one copy of submittal register updated by Contractor to Government with each invoice request.
1.7 PROCEDURES FOR SUBMITTALS
1.7.1 Reviewing, Certifying, Approving Authority
The Contractor Quality Control (CQC) organization shall be responsible for reviewing and certifying that submittals are in compliance with contract requirements. Approving authority on submittals ultimately rests with the Contracting Officer, and his/her Authorized Representative(s). Approval of all submittals will be made through the Caruthersville Area Office.
1.7.2 Constraints
a. Submittals listed or specified in this contract shall conform to provisions of this section, unless explicitly stated otherwise.
b. Submittals shall be complete for each definable feature of work;
components of definable feature interrelated as a system shall be submitted at same time.
c. When acceptability of a submittal is dependent on conditions, items, or materials included in separate subsequent submittals, submittal will be returned without review.
d. Approval of a separate material, product, or component does not imply approval of assembly in which item functions.
1.7.3 Scheduling
a. Coordinate scheduling, sequencing, preparing and processing of submittals with performance of work so that work will not be delayed by submittal processing. Allow for potential requirements to resubmit.
b. Except as specified otherwise, allow review period, beginning with receipt by approving authority, that includes at least 15 working days for submittals for Contracting Officer's Authorized Representative approval and 20 working days for submittals for Contracting Officer approval. Period of review for submittals with Contracting Officer approval begins when Government receives submittal from CQC organization. Period of review for each resubmittal is the same as for initial submittal.
1.7.4 Variations
Variations from contract requirements require Government approval pursuant to contract Clause entitled "FAR 52.236-21, Specifications and Drawings for Construction" and will be considered where advantageous to Government.
SECTION 01 33 00 Page 6
1.7.4.1 Considering Variations
Discussion with Caruthersville Area Office prior to submission, will help ensure functional and quality requirements are met and minimize rejections and resubmittals. When contemplating a variation which results in lower cost, consider submission of the variation as a Value Engineering Change Proposal (VECP).
1.7.4.2 Proposing Variations
When proposing variation, deliver written request to the Contracting Officer, with documentation of the nature and features of the variation and why the variation is desirable and beneficial to Government. If lower cost is a benefit, also include an estimate of the cost saving. In addition to documentation required for variation, include the submittals required for the item. Clearly mark the proposed variation in all documentation.
1.7.4.3 Warranting That Variations Are Compatible
When delivering a variation for approval, Contractor warrants that this contract has been reviewed to establish that the variation, if incorporated, will be compatible with other elements of work.
1.7.4.4 Review Schedule Is Modified
In addition to normal submittal review period, a period of 15 working days will be allowed for consideration by the Government of submittals with variations.
1.8 CONTRACTOR'S RESPONSIBILITIES
a. Determine and verify field measurements, materials, field construction criteria; review each submittal; and check and coordinate each submittal with requirements of the work and contract documents.
b. Transmit submittals to the Government in accordance with the approved Submittal Register. To prevent delays in the work, delays to Government, or delays to separate Contractors transmit submittals using ENG FORM 4025 (Transmittal Sheet).
c. Stamp submittal data to certify that the submittal meets contract requirements.
d. Advise Contracting Officer of variation, as required by paragraph entitled "Variations."
e. Correct and resubmit submittal as directed by approving authority. When resubmitting disapproved transmittals or transmittals noted for resubmittal, the Contractor shall provide copy of that previously submitted transmittal including all reviewer comments for use by approving authority. Direct specific attention in writing or on resubmitted submittal, to revisions not requested by approving authority on previous submissions.
f. Furnish additional copies of submittal when requested by Contracting Officer, to a limit of 20 copies per submittal.
SECTION 01 33 00 Page 7
g. Complete work which must be accomplished as basis of a submittal in time to allow submittal to occur as scheduled.
h. Ensure no work has begun until submittals for that work have been returned as "Approved as submitted" or "Approved, except as noted...", except to the extent that a portion of work must be accomplished as basis of submittal.
1.9 GOVERNMENT'S RESPONSIBILITIES
a. Note date on which submittal was received from Contractor on each submittal.
b. Review each submittal; and check and coordinate each submittal with requirements of work and contract documents.
c. Review submittals for conformance with project design concepts and compliance with contract documents.
d. Act on submittals, determining appropriate action.
(1) When the Contracting Officer's Authorized Representative is the approving authority, take appropriate action on submittal.
(2) When Contracting Officer is approving authority or when variation has been proposed, forward submittal to Memphis District Office, care of the Construction Branch, with the necessary certifying statement.
e. Ensure that material is clearly legible.
f. When approving authority is Contracting Officer, Caruthersville Area Office will certify submittals forwarded to Contracting Officer with the following certifying statement:
"I hereby certify that the (equipment) (material) (article) shown and marked in this submittal is that proposed to be incorporated with contract No. W912EQ-__-C-____, is in compliance with the contract drawings and specification, can be installed in the allocated spaces, and is submitted for Contracting Officer approval.
Certified by Submittal Reviewer _____________________, Date _______ (Signature when applicable)
Certified by Area Engineer __________________________, Date ______" (Signature)
Stamp each sheet of each submittal with certifying statement, except that data submitted in bound volume or on one sheet printed on two sides may be stamped on the front of the first sheet only.
g. When approving authority is the Contracting Officer's Authorized Representative, the Area Engineer will take approval action on ENG FORM 4025 (Transmittal Sheet).
h. Sign certifying statement or ENG FORM 4025 (Transmittal Sheet).
i. Update submittal register as submittal actions occur and maintain
SECTION 01 33 00 Page 8 the submittal register at project site until final acceptance of all work by Contracting Officer.
j. Retain a copy of approved submittals at project site, including Contractor's copy of approved samples.
k. When approving authority is Contracting Officer, the Government will:
(1) Note date on which submittal was received by Contracting Officer, on each submittal for which the Contracting Officer is approving authority.
(2) Review submittals for approval within scheduling period specified and only for conformance with project design concepts and compliance with contract documents.
(3) Returned submittals with appropriate action indicated.
1.10 FORMAT OF SUBMITTALS
1.10.1 Transmittal Sheet
Transmit each submittal, except sample installations and sample panels, to office of approving authority. Transmit submittals on ENG FORM 4025 (Transmittal Sheet) located at the following website:
http://www.mvm.usace.army.mil/BusinessWithUs/Contracting/Forms.aspx. The transmittal sheet shall identify Contractor, indicate date of submittal, and include information prescribed by transmittal sheet and required in paragraph entitled "Identifying Submittals." Process transmittal sheets to record actions regarding sample panels and sample installations.
1.10.2 Identifying Submittals
Identify submittals, except sample panel and sample installation, with the following information permanently adhered to or noted on each separate component of each submittal and noted on transmittal sheet. Mark each copy of each submittal identically, with the following:
a. Project title and location.
b. Construction contract number.
c. Section number of the specification section by which submittal is required.
d. Submittal description (SD) number of each component of submittal.
e. When a resubmission, add alphabetic suffix on submittal description, for example, SD-10A, to indicate resubmission.
f. Name, address, and telephone number of subcontractor, supplier, manufacturer and any other second tier Contractor associated with submittal.
g. Product identification and location in project.
SECTION 01 33 00 Page 9
1.11 SUBMISSION AND CONTROL OF SUBMITTALS
1.11.1 Submittals Required from the Contractor
Within 15 calendar days after receipt of notice to proceed, the Contractor shall complete and submit to Mr. Jack Ratliff, Area Engineer, Caruthersville Area Office, 706 Harry S. Truman Blvd., Caruthersville, Missouri 63830-1268 submittals required in the technical sections of this specification, including shop drawings, product data and samples.
1.11.1.1 Submittal Procedures and Deviations
The Government will further discuss detailed submittal procedures with the Contractor at the Preconstruction Conference. For submittals which include proposed deviations requested by the Contractor, the column "variation" of ENG Form 4025 shall be checked. The Contractor shall set forth in writing the reason for any deviations and annotate such deviations on the submittal. The Government reserves the right to rescind inadvertent approval of submittals containing unnoted deviations.
1.11.1.2 Control of Submittals
The Contractor shall carefully control his procurement operations to ensure that each individual submittal is made on or before the Contractor scheduled submittal date shown on the approved "Submittal Register."
1.11.1.3 O&M Data
Contracting Officer will review and approve the O&M Data to verify the submittals comply with the contract requirements; submit data specified for a given item within 30 calendar days after the item is delivered to the contract site. In the event the Contractor fails to deliver O&M Data within the time limits specified, the Contracting Officer may withhold from progress payments 50 percent of the price of the item with which such O&M Data are applicable.
1.12 SUBMITTAL CLASSIFICATION
Submittals are classified as follows:
1.12.1 Government Approved
Government approval is required for extensions of design, critical materials, deviations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Contracting Officer.
Within the terms of the Contract Clause entitled "Specifications and Drawings for Construction," they are considered to be "shop drawings."
1.12.2 Information Only
All submittals not requiring Government approval will be for information only. They are not considered to be "shop drawings" within the terms of the Contract Clause referred to above.
1.13 APPROVED SUBMITTALS
The Contracting Officer's approval of submittals shall not be construed as a complete check, but will indicate only that the general method of construction, materials, detailing and other information are satisfactory.
SECTION 01 33 00 Page 10
Approval will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor under the CQC requirements of this contract is responsible for design, dimensions, all design extensions, such as the design of adequate connections and details, etc., and the satisfactory construction of all work. After submittals have been approved by the Contracting Officer, no resubmittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is necessary.
1.14 DISAPPROVED SUBMITTALS
The Contractor shall make all corrections required by the Contracting Officer and promptly furnish a corrected submittal in the form and number of copies specified for the initial submittal. If the Contractor considers any correction indicated on the submittals to constitute a change to the contract, a notice in accordance with the Contract Clause "Changes" shall be given promptly to the Contracting Officer.
1.15 WITHHOLDING OF PAYMENT
Payment for materials incorporated in the work will not be made if required approvals have not been obtained.
1.16 GENERAL
The Contractor shall make submittals as required by the specifications.
The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections. Units of weights and measures used on all submittals shall be the same as those used in the contract drawings. Each submittal shall be complete and in sufficient detail to allow ready determination of compliance with contract requirements. Prior to submittal, all items shall be checked and approved by the CQC System Manager and each item shall be stamped, signed, and dated by the CQC System Manager indicating action taken. Proposed deviations from the contract requirements shall be clearly identified. Submittals shall include items such as: Contractor's, manufacturer's, or fabricator's drawings;
descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders;
samples; O&M manuals (including parts list); certifications; warranties;
and other such required submittals. Submittals requiring Government approval shall be scheduled and made prior to the acquisition of the material or equipment covered thereby. Samples remaining upon completion of the work shall be picked up and disposed of in accordance with manufacturer's Material Safety Data Sheets (MSDS) and in compliance with existing laws and regulations.
1.17 SUBMITTAL REGISTER
At the end of this section is a submittal register showing items of equipment and materials for which submittals are required by the specifications; this list may not be all inclusive and additional submittals may be required. The Government will provide the initial submittal register in electronic format. Thereafter, the Contractor shall maintain a complete list of all submittals, including completion of all data columns. Dates on which submittals are received and returned by the Government will be tracked. The Contractor shall monitor the progress of all submittals.
SECTION 01 33 00 Page 11
1.18 SCHEDULING
Submittals covering component items forming a system or items that are interrelated shall be scheduled to be coordinated and submitted concurrently. Certifications to be submitted with the pertinent drawings shall be so scheduled. Adequate time (a minimum of 21 calendar days exclusive of mailing time) shall be allowed and shown on the register for review and approval. No delay damages or time extensions will be allowed for time lost in late submittals.
1.19 TRANSMITTAL SHEET (ENG FORM 4025)
A sample transmittal sheet (ENG Form 4025), which can be found at http://www.mvm.usace.army.mil/BusinessWithUs/Contracting/Forms.aspx shall be used for submitting both Government approved and information only submittals in accordance with the instructions on the reverse side of the form. Additionally, these forms are included in the QCS software that is available for Contractor use. The transmittal sheet shall be properly completed by filling out all the heading blank spaces and identifying each item submitted. Special care shall be exercised to ensure proper listing of the specification paragraph and/or sheet number of the contract drawings pertinent to the data submitted for each item.
1.20 GOVERNMENT APPROVED SUBMITTALS
Upon completion of review of submittals requiring Government approval, the submittals will be identified as having received approval by being so stamped and dated. Three copies of the submittal will be retained by the Contracting Officer and three copies of the submittal will be returned to the Contractor.
1.21 INFORMATION ONLY SUBMITTALS
Normally submittals for information only will not be returned. Approval of the Contracting Officer is not required on information only submittals.
The Government reserves the right to require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the Contracting Officer from requiring removal and replacement of nonconforming material incorporated in the work;
and does not relieve the Contractor of the requirement to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical specifications so prescribe.
1.22 STAMPS
Stamps used by the Contractor on the submittal data to certify that the submittal meets contract requirements shall be similar to the following:
SECTION 01 33 00 Page 12
| CONTRACTOR |
| (Firm Name) | | _____ Approved | | _____ Approved with corrections as noted on submittal data and/or | | attached sheets(s). |
| SIGNATURE: __________________________________________________________ |
| TITLE: ______________________________________________________________ |
| DATE: _______________________________________________________________ |
Stamps used by the Contracting Officer's Authorized Representative on the submittal data to certify that the submittal meets contract requirements shall be similar to the following:
| I hereby certify that the (equipment)(material)(article)shown | | and marked in this submittal is that proposed to be incorporated | | with contract No. W912EQ-__-C-____, is in compliance with the | | contract drawings and specification, can be installed in the | | allocated spaces, and is submitted for Contracting Officer approval. | | Certified by Submittal Reviewer ____________________, Date _______ | | (Signature when applicable) | | Certified by Area Engineer _________________________, Date ______ | | (Signature) |
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION (Not Used)
-- End of Section --
SECTION 01 33 00 Page 13
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 1 OF 2 PAGES
St Francis Basin Levee Gravel Resurfacing
00 70 00.00 11 SD-07 Certificates GCertificate or Written Evidence of
Insurance GField Notes and All Other
Records Relating to the Survey 00 80 00.00 11 SD-01 Preconstruction Submittals
1.7 GActivity Hazard Analysis
1.7 GAccident Prevention Program
1.7 GHazard Communication Program
1.24 GList of all Personnel, Vehicles
and Equipment SD-02 Shop Drawings
1.10Shop Drawings SD-03 Product Data
1.7Material Safety Data Sheets of Each Substance
SD-11 Closeout Submittals
1.11 GFinal As-Built Drawings
1.7Findings of the Accident
Investigation 01 45 02.00 11 SD-01 Preconstruction Submittals
1.7.3 GContractor Quality Control (CQC)
Plan
1.7.1.1Contractor Administrative Data SD-07 Certificates
1.7.2.2Payment Requests
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P H
C L A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 2 OF 2 PAGES
St Francis Basin Levee Gravel Resurfacing
01 45 02.00 11 1.10Payment Requests 1.10Schedule Updates
01 45 04.00 11 SD-01 Preconstruction Submittals
3.2 GContractor Quality Control (CQC)
Plan 01 57 20.00 11 SD-01 Preconstruction Submittals
1.6 G CAOEnvironmental Protection Plan
32 15 00.00 11 SD-03 Product Data
1.4Equipment SD-04 Samples
1.6 GRepresentative Sample of the
Aggregate Surfacing
SD-06 Test Reports 1.6Sampling and Testing 1.3Records and Tests
Testing
1.6.2.1 GGradation Test
SD-07 Certificates Testing
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P H
C L A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 42 00
SOURCES FOR REFERENCE PUBLICATIONS
PART 1 GENERAL
1.1 REFERENCES
1.2 ORDERING INFORMATION
-- End of Section Table of Contents --
SECTION 01 42 00 Page 1
SECTION 01 42 00
SOURCES FOR REFERENCE PUBLICATIONS
PART 1 GENERAL
1.1 REFERENCES
Various publications are referenced in other sections of the specifications to establish requirements for the work. These references are identified in each section by document number, date and title. The document number used in the citation is the number assigned by the standards producing organization, (e.g. ASTM B 564 Nickel Alloy Forgings). However, when the standards producing organization has not assigned a number to a document, an identifying number has been assigned for reference purposes.
1.2 ORDERING INFORMATION
The addresses of the standards publishing organizations whose documents are referenced in other sections of these specifications are listed below, and if the source of the publications is different from the address of the sponsoring organization, that information is also provided. Documents listed in the specifications with numbers which were not assigned by the standards producing organization should be ordered from the source by title rather than by number.
ASTM INTERNATIONAL (ASTM)
100 Barr Harbor Drive, P.O. Box C700 West Conshohocken, PA 19428-2959 Ph: 610-832-9500 Fax: 610-832-9555 E-mail: service@astm.org Internet: http://www.astm.org
U.S. ARMY CORPS OF ENGINEERS (USACE)
Order CRD-C DOCUMENTS from:
U.S. Army Engineer Waterways Experiment Station ATTN: Technical Report Distribution Section, Services Branch, TIC 3909 Halls Ferry Road Vicksburg, MS 39180-6199 Ph: 601-634-2664 Fax: 601-634-2388 E-mail: mtc-info@erdc.usace.army.mil Internet: http://www.wes.army.mil/SL/MTC/handbook.htm
Order Other Documents from:
USACE Publications Depot Attn: CEHEC-IM-PD 2803 52nd Avenue Hyattsville, MD 20781-1102 Ph: 301-394-0081 Fax: 301-394-0084 E-mail: pubs-army@usace.army.mil Internet:http://www.publications.usace.army.mil/Home.aspx or
SECTION 01 42 00 Page 2 http://www.hnc.usace.army.mil/Missions/Engineering/TECHINFO.aspx
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
8601 Adelphi Road College Park, MD 20740-6001 Ph: 866-272-6272 Fax: 301-837-0483 Internet: http://www.archives.gov
Order documents from:
Superintendent of Documents U.S.Government Printing Office (GPO) 732 North Capitol Street, NW Washington, DC 20401 Ph: 202-512-1800 Fax: 202-512-2104 E-mail: contactcenter@gpo.gov Internet: http://www.gpoaccess.gov
-- End of Section --
SECTION 01 42 00 Page 3
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 45 02.00 11
QUALITY CONTROL SYSTEM (QCS)
PART 1 GENERAL
1.1 SUBMITTALS
1.2 CONTRACT ADMINISTRATION
1.2.1 Correspondence and Electronic Communications
1.2.2 Other Factors
1.3 QCS SOFTWARE
1.4 SYSTEM REQUIREMENTS
1.5 RELATED INFORMATION
1.5.1 QCS User Guide
1.5.2 Contractor Quality Control (CQC) Training
1.6 CONTRACT DATABASE
1.7 DATABASE MAINTENANCE
1.7.1 Administration
1.7.1.1 Contractor Information
1.7.1.2 Subcontractor Information
1.7.1.3 Correspondence
1.7.1.4 Equipment
1.7.1.5 Management Reporting
1.7.1.6 Request For Information (RFI)
1.7.2 Finances
1.7.2.1 Pay Activity Data
1.7.2.2 Payment Requests
1.7.3 Quality Control (QC)
1.7.3.1 Daily Contractor Quality Control (CQC) Reports.
1.7.3.2 Deficiency Tracking.
1.7.3.3 QC Requirements
1.7.3.4 Three-Phase Control Meetings
1.7.3.5 Labor and Equipment Hours
1.7.3.6 Accident/Safety Reporting
1.7.3.7 Features of Work
1.7.4 Submittal Management
1.7.5 Schedule
1.7.6 Import/Export of Data
1.8 IMPLEMENTATION
1.9 DATA SUBMISSION VIA CD-ROM
1.9.1 File Medium
1.9.2 CD-ROM Labels
1.9.3 File Names
1.10 MONTHLY COORDINATION MEETING
1.11 NOTIFICATION OF NONCOMPLIANCE
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION (Not Used)
SECTION 01 45 02.00 11 Page 1
-- End of Section Table of Contents --
SECTION 01 45 02.00 11 Page 2
SECTION 01 45 02.00 11
QUALITY CONTROL SYSTEM (QCS)
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Contractor Quality Control (CQC) Plan; G Contractor Administrative Data
SD-07 Certificates
Payment Requests Schedule Updates
1.2 CONTRACT ADMINISTRATION
The Government will use the Resident Management System for Windows (RMS) to assist in its monitoring and administration of this contract. The Contractor shall use the Government-furnished Construction Contractor Module of RMS, referred to as QCS, to record, maintain, and submit various information throughout the contract period. The Contractor module, user manuals, updates, and training information can be downloaded from the RMS web site (http://rms.usace.army.mil/). This joint Government-Contractor use of RMS and QCS will facilitate electronic exchange of information and overall management of the contract. QCS provides the means for the Contractor to input, track, and electronically share information with the Government in the following areas:
a. Administration
b. Finances
c. Quality Control
d. Submittal Monitoring
e. Scheduling
f. Import/Export of Data
1.2.1 Correspondence and Electronic Communications
For ease and speed of communications, both Government and Contractor will, to the maximum extent feasible, exchange correspondence and other documents in electronic format. Correspondence, pay requests and other documents comprising the official contract record shall also be provided in paper format, with signatures and dates where necessary. Paper documents will govern, in the event of discrepancy with the electronic version.
SECTION 01 45 02.00 11 Page 3
1.2.2 Other Factors
Particular attention is directed to Contract Clause, "Schedules for Construction Contracts", Contract Clause, "Payments", Section 01 33 00, SUBMITTAL PROCEDURES, and Section 01 45 04.00 10, CONTRACTOR QUALITY CONTROL, which have a direct relationship to the reporting to be accomplished through QCS. Also, there is no separate payment for establishing and maintaining the QCS database; all costs associated therewith shall be included in the contract pricing for the work.
1.3 QCS SOFTWARE
QCS is a Windows-based program that can be run on a stand-alone personal computer or on a network. The Government will make available the QCS software to the Contractor after award of the construction contract. Prior to the Pre-Construction Conference, the Contractor shall be responsible to download, install and use the latest version of the QCS software from the Government's RMS Internet Website (http://rms.usace.army.mil/). Upon specific justification and request by the Contractor, the Government can provide QCS on CD-ROM. Any program updates of QCS will be made available to the Contractor via the Government RMS Website as they become available.
1.4 SYSTEM REQUIREMENTS
The following is the minimum system configuration that the Contractor shall have to run QCS:
QCS System
Hardware
IBM-compatible PC with 1000 MHz Pentium or higher processor
256+ MB RAM for workstation / 512+ MB RAM for server
1 GB hard drive disk space for sole use by the QCS system
3 1/2 inch high-density floppy drive
Compact Disk (CD) Reader 8x speed or higher
SVGA or higher resolution monitor (1024x768, 256 colors)
Mouse or other pointing device
Windows compatible printer. (Laser printer must have 4 MB+ of RAM)
Connection to the Internet, minimum 56k BPS
Software
MS Windows 2000 or higher
QAS-Word Processing software: MS Word 2000 or newer
Latest version of: Netscape Navigator, Microsoft Internet Explorer, or other browser that supports HTML 4.0 or higher
Electronic mail (E-mail) MAPI compatible
SECTION 01 45 02.00 11 Page 4
Virus protection software that is regularly upgraded with all issued manufacturer's updates
1.5 RELATED INFORMATION
1.5.1 QCS User Guide
After contract award, the Contractor shall download instructions for the installation and use of QCS from the Government RMS Internet Website ( http://rms.usace.army.mil/); the Contractor can obtain the current address from the Government. In case of justifiable difficulties, the Government will provide the Contractor with a CD-ROM containing these instructions.
1.5.2 Contractor Quality Control (CQC) Training
The use of QCS will be discussed with the Contractor's QC System Manager during the mandatory CQC Training class.
1.6 CONTRACT DATABASE
Prior to the pre-construction conference, the Government shall provide the Contractor with basic contract award data to use for QCS. The Government will provide data updates to the Contractor as needed, generally by files attached by e-mail. These updates will generally consist of submittal reviews, correspondence status, QA comments, and other administrative and QA data.
1.7 DATABASE MAINTENANCE
The Contractor shall establish, maintain, and update data for the contract in the QCS database throughout the duration of the contract. The Contractor shall establish and maintain the QCS database at the Contractor's site office. Data updates to the Government shall be submitted by e-mail with file attachments (e.g., daily reports, submittals, RFI's, schedule updates, payment requests, etc.). If permitted by the Contracting Officer, e-mail or CD-ROM may be used instead of E-mail (see Paragraph DATA SUBMISSION VIA CD-ROM).
1.7.1 Administration
1.7.1.1 Contractor Information
The database shall contain the Contractor's name, address, telephone numbers, management staff, and other required items. Within 14 calendar days of receipt of QCS software from the Government, deliver Contractor Administrative Data in electronic format.
1.7.1.2 Subcontractor Information
The database shall contain the name, trade, address, phone numbers, and other required information for all subcontractors. A subcontractor must be listed separately for each trade to be performed. Each subcontractor/trade shall be assigned a unique Responsibility Code, provided in QCS. Within 14 calendar days of receipt of QCS software from the Government, the contractor shall deliver subcontractor administrative data in electronic format via e-mail.
SECTION 01 45 02.00 11 Page 5
1.7.1.3 Correspondence
All Contractor correspondence to the Government shall be identified with a serial number. Correspondence initiated by the Contractor's site office shall be prefixed with an "S". Letters initiated by the Contractor's home (main) office shall be prefixed with an "H". Letters shall be numbered starting from 0001 (e.g., H-0001 or S-0001). The Government's letters to the Contractor will be prefixed with "C".
1.7.1.4 Equipment
The Contractor's QCS database shall contain a current list of equipment planned for use or being used on the jobsite, including the most recent and planned equipment inspection dates.
1.7.1.5 Management Reporting
QCS includes a number of reports that Contractor management can use to track the status of the project. The value of these reports is reflective of the quality of the data input, and is maintained in the various sections of QCS. Among these reports are: Progress Payment Request worksheet, QA/QC comments, Submittal Register Status, and Three-Phase Inspection checklists.
1.7.1.6 Request For Information (RFI)
The Contractor shall exchange all Requests For Information (RFI) using the Built-in RFI generator and tracker in QCS.
1.7.2 Finances
1.7.2.1 Pay Activity Data
The QCS database shall include a list of pay activities that the Contractor shall develop in conjunction with the construction schedule. The sum of all pay activities shall be equal to the total contract amount, including modifications. Pay activities shall be grouped by Contract Line Item Number (CLIN); the sum of the activities shall equal the amount of each CLIN. The total of all CLINs equals the Contract Amount.
1.7.2.2 Payment Requests
All progress payment requests shall be prepared using QCS. The Contractor shall complete the payment request worksheet and include it with the payment request. The work completed under the contract, measured as percent or as specific quantities, shall be updated at least monthly.
After the update, the Contractor shall generate a payment request report using QCS. The Contractor shall submit the Payment Requests with supporting data by e-mail with file attachment(s). If permitted by the Contracting Officer, a CD-ROM may be used instead of e-mail.