AMENDMENT_0002-SPECS.pdf

PDF 582 KB Posted

Attached to
Mound City South Culvert Federal contract opportunity
Solicitation number
W912EQ-17-B-0002
Issued by
Department of the Army Corps of Engineers Engineering District Memphis

About this file

SPECS

View the file

Other files for this federal contract opportunity

Other files attached to Mound City South Culvert, newest first.
File Type Posted
ABSTRACT.pdf PDF
AMENDMENT_0002.pdf PDF
AMENDMENT_0002-PLANS.pdf PDF
AMENDMENT_0001.pdf PDF
A07D-PLANS_20170613-Part_2_of_2.pdf PDF
A07D-SPECS_20170613.pdf PDF
A07D-Solicitation-W912EQ-17-B-0002.pdf PDF
A07D-PLANS_20170613-Part_1_of_2.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Mound City South Culvert Repair MCSCR

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 22 00.00 11

MEASUREMENT AND PAYMENT

1/10/08

PART 1 GENERAL

1.1 JOB PAYMENT ITEMS

1.1.1 Mobilization and Demobilization - Item 0001

1.1.2 Environmental Protection - Item 0002

1.1.3 1.1.3 Demolition - Item 0003

1.1.4 Modify Storm water Pollution Prevention Plan (SWPPP) - Item

0004A

1.2 UNIT PRICE PAYMENT ITEMS

1.2.1 Storm Water Pollution Prevention - Item 0004

1.2.1.1 Straw Wattle - Item 0004B

1.2.1.2 Silt Fence - Item 0004C

1.2.1.3 Construction Exit - ITEM No. 0004D

1.2.1.4 Concrete Washout - ITEM No. 0004E

1.2.2 Excavation - Item 0005

1.2.3 Embankment - Item 0006

1.2.4 Stone Products - Item 0007A through 0007C

1.2.5 Geotextile - Item 0008

1.2.6 Concrete Grout - Items 0009A and 0009B

1.2.7 18" Dia. Ductile Iron Pipe - Item 0010

1.2.8 48" Dia. Reinforced Concrete Pipe - Item 0011

1.2.9 18" Dia. Outlet Structure with Flapgate - Item 0012

1.2.10 48" Dia. Outlet Structure with Flapgate - Item 0013

1.2.11 Gatewell Structure with Sluice Gate - Item 0014

1.2.12 Precast 48" Dia. Flared End Section - Item 0015

1.2.13 8" Steel Bollard - Item 0016

PART 2 PRODUCTS (Not Used)

PART 3 EXECUTION (Not Used)

-- End of Section Table of Contents --

SECTION 01 22 00.00 11 Page 1

AMENDMENT 002

SECTION 01 22 00.00 11

MEASUREMENT AND PAYMENT

1/10/08

PART 1 GENERAL

1.1 JOB PAYMENT ITEMS

Payment items for the work of this contract for which contract lump sum payments will be made are listed in the BIDDING SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job item or unit price payment item, shall be included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.

1.1.1 Mobilization and Demobilization - Item 0001

a. Measurement

No measurement will be made for Mobilization and Demobilization.

b. Payment

Payment will be made for costs associated with mobilization and demobilization, as defined in Contract Clauses PAYMENT FOR MOBILIZATION

AND DEMOBILIZATION.

c. Unit of measure, Job: JA

1.1.2 Environmental Protection - Item 0002

a. Measurement

No measurement will be made for Environmental Protection.

b. Payment

Payment will be made for costs associated with operations necessary for environmental protection as specified in Section 01 57 20.00 11 ENVIRONMENTAL PROTECTION. This price and payment shall be considered full compensation for furnishing all plant, labor, materials, and equipment and for performing all operations necessary for "Environmental Protection." This price and payment does not include those items covered under "Storm Water Pollution Prevention;" however, it does include items incidental thereto. The Contractor shall be responsible for payment of fees associated with environmental permits, application, and/or notices obtained by the Contractor. The Contractor shall be responsible for payment of all fines/fees arriving from violation or non-compliance with Federal, State, Regional, and local

SECTION 01 22 00.00 11 Page 2 laws or regulations. The Government will not provide any compensation for payments of fines/fees, in the event that fines/fees are incurred by the Contractor.

c. Unit of measure, Job: JA.

1.1.3 1.1.3 Demolition - Item 0003

a. Measurement

No measurement will be made for Demolition.

b. Payment

Payment will be made for costs associated with operations necessary for demolition on the items indicated and as specified in Section 02 41 00 DEMOLITION. This price and payment shall be considered full compensation for furnishing all plant, labor, materials, and equipment and for performing all operations necessary for "Demolition." Payment for this item shall include demolition of those portions of pipe, gate, and concrete structures as indicated on the contract drawings as well as the satisfactory disposal of waste materials generated therefrom.

Any clearing, geotextile and pervious fill shall be be considered incidental to "Demolition". Concrete grout, pipe, and outlet structure will be paid under separate lines.

c. Unit of measure, Job: JA

1.1.4 Modify Storm water Pollution Prevention Plan (SWPPP) - Item 0004A

a. Measurement

No measurement will be made for Modify Stormwater Pollution Prevention Plan.

b. Payment

Payment for "Modify Stormwater Pollution Prevention Plan" will be made at the contract job price for "Modify Stormwater Pollution Prevention Plan" which includes all labor, materials, fees and incidentals necessary to Modify Stormwater Pollution Prevention Plan to the satisfaction and approval of the appropriate state governing agency.

c. Unit of measure, Job: JA

1.2 UNIT PRICE PAYMENT ITEMS

Payment items for the work of this contract on which the contract progress payments will be based are listed in Section 00 41 00.00 11 - BIDDING SCHEDULE and are described below. The unit price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests, and reports, and for performing all work required for each of the unit price items.

1.2.1 Storm Water Pollution Prevention - Item 0004

No separate measurement or payment will be made for the work "Storm Water

SECTION 01 22 00.00 11 Page 3

Pollution Prevention" required by Section 01 57 25.00 11 STORM WATER POLLUTION PREVENTION PLAN (SWPPP) except as described in the paragraphs SILT FENCE, STRAW WATTLE, AND CONSTRUCTION EXIT below. Any additional costs associated with Storm Water Pollution Prevention, other than these listed, shall be included in the contract price under Environmental Protection. The Government will pay all costs for the "Storm Water Pollution Prevention" at the contract unit price for each sub-item list below as follows:

(1) Sixty percent of the unit price upon completion of the installation.

(2) The remaining 40 percent throughout the contract life, with a maximum of 20 percent being retained until final removal and cleanup of the premises.

The Contracting Officer will require the Contractor to furnish cost data to calculate the exact percentage to be paid upon installation.

1.2.1.1 Straw Wattle - Item 0004B

a. Measurement

Measurement for Straw Wattle satisfactorily placed will be made by the linear foot.

b. Payment

Payment for Straw Wattle as specified herein will be made at the contract unit price per linear foot for "Straw Wattle". Price and payment shall constitute full compensation for furnishing all plant, labor, materials and equipment, and performing all operations necessary for the placement and maintenance of straw wattle throughout the contract period, including final dressing and cleanup.

c. Unit of measure, Linear Foot: LF.

1.2.1.2 Silt Fence - Item 0004C

a. Measurement

Measurement for Silt Fence satisfactorily placed will be made by the linear foot.

b. Payment

Payment for Silt Fence as specified herein will be made at the contract unit price per linear foot for "Silt Fence". Price and payment shall constitute full compensation for furnishing all plant, labor, materials and equipment, including geotextile fabric, and performing all operations necessary for the placement and maintenance of silt fence throughout the contract period, including final dressing and cleanup.

c. Unit of measure, Linear Foot: LF.

1.2.1.3 Construction Exit - ITEM No. 0004D

a. Measurement

SECTION 01 22 00.00 11 Page 4

Measurement for "construction exit" satisfactorily designed, constructed and maintained by the Contractor will be per each placed.

b. Payment

Payment for the temporary "construction exit", including its maintenance and removal, will be made at the contract unit price per construction exit for "Construction Exit" as broken down by the percentages in the "sub-item list" above. Price and payment shall constitute full compensation for furnishing the design and all plant, labor, equipment, mechanical street sweeper and material to complete the work as specified herein and as indicated.

c. Unit of measure, each: EA

1.2.1.4 Concrete Washout - ITEM No. 0004E

a. Measurement

Measurement for "concrete washout" satisfactorily designed, constructed and maintained by the Contractor will be per each placed.

b. Payment

Payment for the temporary "concrete washout", including its maintenance and removal, will be made at the contract unit price per item installed for "concrete washout" as broken down by the percentages in the "sub-item list" above. Price and payment shall constitute full compensation for furnishing the design and all plant, labor, equipment, mechanical street sweeper and material to complete the work as specified herein and as indicated.

c. Unit of measure, each: EA

1.2.2 Excavation - Item 0005

a. Measurement

"Excavation" will be measured for payment by the cubic yard as computed by the volume of difference between the cleared existing ground and the theoretical excavation surface. The basis of measurement will be a digital terrain model survey of the area after clearing and prior to excavation, and a second survey of the same area after the completion of the excavation. Surveys will be as specified in Section 00 80 00.00 11 - SPECIAL CONTRACT REQUIREMENTS, Paragraph 1.5 "Layout of Work", subparagraph d. "Quantity Surveys". The quantity of excavation to be paid for will be computed between the before construction survey ground surface, and the theoretical grades and slope lines shown on the contract drawings. No allowance or payment will be made for over-depth excavation, or for the removal of any material outside the required theoretical sections unless required by the Contracting Officer. Slides caused by fault of the Contractor or excavation performed for the convenience of the Contractor shall not be measured for payment.

b. Payment

Payment for excavation will be made at the contract unit price for "Excavation", which price includes all labor and equipment necessary to

SECTION 01 22 00.00 11 Page 5 perform excavation necessary to construct to the lines and grades shown in the Contract Drawings. Topsoil stripping and spreading will not be measured separately but will be considered incidental to "Excavation".

Payment will include all equipment and labor necessary for excavation to achieve lines and grades indicated. Excavation shall be performed in accordance with section 31 23 00.00 12 - EXCAVATION. This includes all other operations incidental thereto, to include disposal of excess material. Any clearing required for excavation, and any establishment of turf required, shall be incidental to "Excavation", and shall be performed in accordance with sections 31 11 00.00 11 - CLEARING and 32 92 32.01 11 - ESTABLISHMENT OF TURF, respectively. Cofferdam installation, maintenance, and removal will not be paid under this line, but shall be incidental to "Gatewell Structure with Sluice Gate" below.

c. Unit of measure: cubic yard: CY.

1.2.3 Embankment - Item 0006

a. Measurement

"Embankment" will be measured for payment by the cubic yard as computed by the volume difference between the theoretical excavation surface to the theoretical design surface, as confirmed with an as-built survey.

The basis of measurement will be a survey of the area after clearing and excavation and prior to placement of the "Embankment", and a second survey of the same area after the completion of the "Embankment" placement and compaction. For areas where lines and grades are shown on the drawings, measurement will be limited to those lines and grades.

b. Payment

Payment for embankment will be made at the contract unit price per cubic yard for "Embankment", which price and payment shall constitute full compensation for furnishing all materials and equipment and performing all labor necessary for placing the fill, transporting the material within the project location, stripping of top soil, and all other operations incidental thereto, all as specified in SECTION 31 24 00.00 12 - EMBANKMENT. Borrow pit opening, maintenance (including but not limited to removal of rainfall, runoff, groundwater, and other seepage), closing, and transport of material from the borrow pit to the job shall be considered incidental. This includes all other operations incidental thereto, including clearing required, and any establishment of turf required, shall be incidental to "Embankment", and shall be performed in accordance with sections 31 11 00.00 11 - CLEARING and 32 92 32.01 11 - ESTABLISHMENT OF TURF, respectively. Cofferdam installation, maintenance, and removal will not be paid under this line, but shall be incidental to "Gatewell Structure with Sluice Gate" below.

c. Unit of measure: cubic yard: CY.

1.2.4 Stone Products - Item 0007A through 0007C

a. Measurement

Measurement for all stone products, including R200 Riprap, Bedding Material, and Aggregate Surface Course shall be made by the ton.

Measurement will be made by weighing each truckload to the nearest 0.1

SECTION 01 22 00.00 11 Page 6

AMENDMENT 002

B1SL9JEK

Highlight

B1SL9JEK

Highlight ton, and the final quantity of the whole sum for each sub-item will be rounded to the nearest ton. When stone is delivered by truck, the material will be measured for payment, in the presence of a Government Inspector, unless the Contracting Officer waives such right, by being weighed on approved, accurately calibrated scales furnished by and at the expense of the Contractor. Scales shall be of sufficient length to permit simultaneous weighing of all axle loads and shall be inspected, tested and sealed as directed to assure accuracy within 0.5 percent throughout the range of the scales. Scales shall be checked and certified before any material hauling; also, rechecked and re-certified whenever a variance is suspected. Individual weight tickets for each truckload of riprap shall be furnished to the Government Inspector at the time of delivery. At a minimum, all weight tickets shall have the contract number or project name, the gross weight, the vehicle identity and empty weight, and the net load weight. Scales that produce this information printed on the weight tickets are preferred. Weight certificates furnished by a Public Weighmaster, where available, will be acceptable, when authorized by the Contracting Officer. The Contractor has the option to use certified, and otherwise acceptable, scales that are Contractor furnished, quarry/supplier furnished, or commercial/public facilities.

Salvaged stone products shall be measured as the difference between a pre- and post-installation survey, and converting the volume to a weight at a rate of 1.5 tons per cubic yard measured. Salvaged stone must be placed and measured prior to the addition of any material from off site.

b. Payment

Payment for all stone products, including R200 Riprap, Bedding Material, and Aggregate Surface Course, as specified in this section and described in sections 35 31 19.00 11 - STONE PROTECTION will be made at the contract unit price per ton for the appropriate subitem, which price and payment shall constitute full compensation for furnishing, hauling, handling, placing, stabilizing, and maintenance as required. This includes all other operations incidental thereto, to include on-site storage and double-handling of material, if required.

Any clearing necessary for the placement of stone products will be performed in accordance with Section 31 11 00.00 11 - CLEARING and will be considered incidental to "Stone Products".

c. Unit of measure: ton: TN.

1.2.5 Geotextile - Item 0008

a. Measurement

Installed geotextiles will be measured for payment in place to the nearest square yard of protected area as indicated in the drawings.

Preparation of the base will not be measured for payment. Geotextile associated with structures and pipe shall be incidental to those items and will not be separately measured or paid under "Geotextile".

b. Payment

Payment will be made at the contract unit price and will constitute full compensation to the contractor for providing all plant, labor, material, and equipment and performing all operations necessary for the

SECTION 01 22 00.00 11 Page 7 complete and satisfactory installation of the geotextile all in accordance with SECTION 31 05 19 - GEOTEXTILE. The following items are included in the contract unit price for Geotextiles and will not be counted a second time in the process of determining the extent of geotextile placed: Material and associated equipment and operation used in laps, seams, or extra length; securing pins and associated material, equipment, and operations; and material and associated equipment and operations used to provide cushioning layer of sand or gravel or both to permit increase in allowable drop height of stone.

No payment will be made for geotextiles replaced because of waste, contamination, damage, repair, or due to contractor fault or negligence. Preparation of the base will not be paid for separately and all costs incidental thereto shall be included in contract prices for other items for which payment will be made.

c. Unit of Measure: square yard: SY.

1.2.6 Concrete Grout - Items 0009A and 0009B

a. Measurement

"Grout for stone protection" and "Grout for Culvert Demolition" will be measured for payment based upon the volume determined from the calculated batch volume and the number of mixed batches delivered to the site and acceptably placed in the work.

b.Payment

Payment for concrete grout will be made at the contract unit price for "Grout for stone protection" and "Grout for Culvert Demolition", which includes full compensation for furnishing all plant, labor, material, equipment and other items necessary and incidental to the completion of the work as described in Section 35 31 19.00 11 - STONE PROTECTION.

c. Unit of Measure: cubic yard: CY

1.2.7 18" Dia. Ductile Iron Pipe - Item 0010

a. Measurement

"18" Dia. Ductile Iron Pipe" will be measured for payment by the linear foot of pipe installed in accordance with the contract drawings and as specified herein.

b. Payment

Payment for 18" Dia. Ductile Iron Pipe will be made at the contract unit price for "18" Dia. Ductile Iron Pipe", which includes all equipment, labor, materials, connections, bedding or backfill material, placement, and backfilling of pipe. All pipe shall be installed to the lines and grades indicated. Payment shall include final clean up and incidental items for completion of the work as defined in Section

33 34 00 - FORCE MAINS.

c. Unit of Measure: linear foot: LF

1.2.8 48" Dia. Reinforced Concrete Pipe - Item 0011

a. Measurement

SECTION 01 22 00.00 11 Page 8

48" Dia. Reinforced Concrete Pipe will be measured for payment by the linear foot of pipe installed in accordance with the contract drawings and as specified herein.

b. Payment

Payment for 48" Dia. Reinforced Concrete Pipe will be made at the contract unit price for "48" Dia. Reinforced Concrete Pipe", which includes all equipment, labor, materials, connections, bedding or backfill material, geotextile, placement, and backfilling of pipe. All pipe shall be installed to the lines and grades indicated. Payment shall include final clean up and incidental items for completion of the work as defined in Section 33 40 00 - STORM DRAINAGE UTILITIES.

c. Unit of Measure: linear foot: LF

1.2.9 18" Dia. Outlet Structure with Flapgate - Item 0012

a. Measurement

18" Dia. Outlet Structure with Flapgate will be measured for payment by each structure installed.

b. Payment

Payment for 18" Dia. Outlet Structure with Flapgate will be made at the contract unit price for "18" Dia. Outlet Structure with Flapgate", which includes all equipment, labor, materials, bedding, geotextile, placement, and backfilling. Payment shall include final clean up and incidental items for completion of the work as defined in Section

33 40 00 - STORM DRAINAGE UTILITIES.

c. Unit of Measure: each: EA

1.2.10 48" Dia. Outlet Structure with Flapgate - Item 0013

a. Measurement

48" Dia. Outlet Structure with Flapgate will be measured for payment by each structure installed.

b. Payment

Payment for 48" Dia. Outlet Structure with Flapgate will be made at the contract unit price for "48" Dia. Outlet Structure with Flapgate", which includes all equipment, labor, materials, bedding, geotextile, placement, and backfilling. Payment shall include final clean up and incidental items for completion of the work as defined in Section

33 40 00 - STORM DRAINAGE UTILITIES.

c. Unit of Measure: each: EA

1.2.11 Gatewell Structure with Sluice Gate - Item 0014

a. Measurement

Gatewell Structure with Sluice Gate will be measured for payment by each structure installed.

SECTION 01 22 00.00 11 Page 9

b. Payment

Payment for Gatewell Structure with Sluice Gate will be made at the contract unit price for "Gatewell Structure with Sluice Gate", which includes all equipment, labor, materials, bedding, placement, backfilling, operator, security fence, and any other equipment required for operation of the sluice gate as indicated. Payment shall include final clean up and incidental items for completion of the work as defined in Section 33 40 00 - STORM DRAINAGE UTILITIES. Cofferdam installation, maintenance, and removal (approx. 3,500 CY) shall be considered incidental to this line item.

c. Unit of Measure: each: EA

1.2.12 Precast 48" Dia. Flared End Section - Item 0015

a. Measurement

Precast 48" Dia. Flared End Section will be measured for payment by each structure installed.

b. Payment

Payment for Precast 48" Dia. Flared End Section will be made at the contract unit price for "Precast 48" Dia. Flared End Section", which includes all equipment, labor, materials, bedding, placement, and backfilling. Also included is any regrading of the sump to ensure proper drainage to the Precast 48" Dia. Flared End Section. Payment shall include final clean up and incidental items for completion of the work as defined in Section 33 40 00 - STORM DRAINAGE UTILITIES.

c. Unit of Measure: each: EA

1.2.13 8" Steel Bollard - Item 0016

a. Measurement

8" Steel Bollard will be measured by the individual item installed.

b. Payment

Payment for 8" Steel Bollard will be made at the contract unit price for "8" Steel Bollard", which includes all equipment, labor, materials, and placement.

c. Unit of Measure: each: EA

PART 2 PRODUCTS (Not Used)

PART 3 EXECUTION (Not Used)

-- End of Section --

SECTION 01 22 00.00 11 Page 10

AMENDMENT 002

SECTION TABLE OF CONTENTS

DIVISION 33 - UTILITIES

SECTION 33 40 00

STORM DRAINAGE UTILITIES

02/10

PART 1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

1.3 DELIVERY, STORAGE, AND HANDLING

1.3.1 Delivery and Storage

1.3.2 Handling

PART 2 PRODUCTS

2.1 PIPE FOR CULVERTS AND STORM DRAINS

2.1.1 Concrete Pipe

2.2 DRAINAGE STRUCTURES

2.2.1 Flared End Sections

2.2.2 Gatewell Structure

2.2.3 Outlet structures

2.3 MISCELLANEOUS MATERIALS

2.3.1 Concrete

2.3.2 Joints

2.3.2.1 Flexible Watertight, Gasketed Joints

2.3.2.2 Steel Reinforced Polyethylene (SRPE) Pipe

2.4 RESILIENT CONNECTORS

2.5 HYDROSTATIC TEST ON WATERTIGHT JOINTS

2.5.1 Concrete Pipe

PART 3 EXECUTION

3.1 EXCAVATION FOR PIPE CULVERTS, STORM DRAINS, AND DRAINAGE STRUCTURES

3.1.1 Removal of Unstable Material

3.2 BEDDING

3.2.1 Concrete Pipe Requirements

3.3 PLACING PIPE

3.3.1 Concrete Pipe

3.4 JOINTING

3.4.1 Concrete Pipe

3.4.1.1 Flexible Watertight Joints

3.4.1.2 External Sealing Band

3.5 DRAINAGE STRUCTURES

3.5.1 Gatewell

3.5.2 Flared End Sections and Headwalls

3.6 BACKFILLING

3.6.1 Backfilling Pipe in Fill Sections

3.6.2 Movement of Construction Machinery

3.6.3 Compaction

3.6.3.1 General Requirements

3.6.3.2 Minimum Density

SECTION 33 40 00 Page 1

3.6.4 Determination of Density

3.7 PIPELINE TESTING

3.7.1 Leakage Tests

3.7.2 Deflection Testing

3.7.3 Post-Installation Inspection

-- End of Section Table of Contents --

SECTION 33 40 00 Page 2

SECTION 33 40 00

STORM DRAINAGE UTILITIES

02/10

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM C1103 (2003; R 2009) Standard Practice for Joint Acceptance Testing of Installed Precast Concrete Pipe Sewer Lines

ASTM C231/C231M (2014) Standard Test Method for Air Content of Freshly Mixed Concrete by the Pressure Method

ASTM C443 (2011) Standard Specification for Joints for Concrete Pipe and Manholes, Using Rubber Gaskets

ASTM C76 (2014) Standard Specification for Reinforced Concrete Culvert, Storm Drain, and Sewer Pipe

ASTM C877 (2008) External Sealing Bands for Concrete Pipe, Manholes, and Precast Box Sections

ASTM C923 (2008; R 2013) Standard Specification for Resilient Connectors Between Reinforced Concrete Manhole Structures, Pipes and Laterals

ASTM C969 (2002; R 2009) Standard Practice for Infiltration and Exfiltration Acceptance Testing of Installed Precast Concrete Pipe Sewer Lines

ASTM C990 (2009; R 2014) Standard Specification for Joints for Concrete Pipe, Manholes and Precast Box Sections Using Preformed Flexible Joint Sealants

ASTM D1557 (2012) Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Modified Effort (56,000 ft-lbf/ft3) (2700 kN-m/m3)

ASTM D1751 (2004; E 2013; R 2013) Standard Specification for Preformed Expansion

SECTION 33 40 00 Page 3

Joint Filler for Concrete Paving and Structural Construction (Nonextruding and Resilient Bituminous Types)

ASTM D1752 (2004a; R 2013) Standard Specification for Preformed Sponge Rubber Cork and Recycled PVC Expansion

ASTM D2167 (2008) Density and Unit Weight of Soil in Place by the Rubber Balloon Method

ASTM D6938 (2015) Standard Test Method for In-Place Density and Water Content of Soil and Soil-Aggregate by Nuclear Methods (Shallow Depth)

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-03 Product Data

Placing Pipe

Submit printed copies of the manufacturer's recommendations for installation procedures of the material being placed, prior to installation.

SD-04 Samples

Pipe for Culverts and Storm Drains; G, EC-D

SD-07 Certificates

Resin Certification Pipeline Testing Hydrostatic Test on Watertight Joints Determination of Density Frame and Cover for Gratings

1.3 DELIVERY, STORAGE, AND HANDLING

1.3.1 Delivery and Storage

Materials delivered to site shall be inspected for damage, unloaded, and stored with a minimum of handling. Materials shall not be stored directly on the ground. The inside of pipes and fittings shall be kept free of dirt and debris. Before, during, and after installation, plastic pipe and fittings shall be protected from any environment that would result in damage or deterioration to the material. Keep a copy of the manufacturer's instructions available at the construction site at all times and follow these instructions unless directed otherwise by the Contracting Officer.

Solvents, solvent compounds, lubricants, elastomeric gaskets, and any similar materials required to install plastic pipe shall be stored in accordance with the manufacturer's recommendations and shall be discarded

SECTION 33 40 00 Page 4 if the storage period exceeds the recommended shelf life. Solvents in use shall be discarded when the recommended pot life is exceeded.

1.3.2 Handling

Materials shall be handled in a manner that ensures delivery to the trench in sound, undamaged condition. Pipe shall be carried to the trench, not dragged.

PART 2 PRODUCTS

2.1 PIPE FOR CULVERTS AND STORM DRAINS

Pipe for culverts and storm drains shall be of the sizes indicated and shall conform to the requirements specified.

2.1.1 Concrete Pipe

Manufactured in accordance with and conforming to ASTM C76, Class V. Pipe shall be provided in 8' sections.

2.2 DRAINAGE STRUCTURES

2.2.1 Flared End Sections

Sections shall be of a standard design pre-cast in concrete meeting the requirements herein and of Illinois Department of Transportation. Concrete shall have a minimum strength of 2,500 psi. Install per manufacturer recommendations.

2.2.2 Gatewell Structure

Cast-in-place gatewell will be constructed as indicated.

2.2.3 Outlet structures

Outlet structures shall be cast-in-place as indicated.

2.3 MISCELLANEOUS MATERIALS

2.3.1 Concrete

Unless otherwise specified, concrete and reinforced concrete shall conform to the requirements for 4,500 psi concrete under Section 03 31 01.00 10 - CAST-IN-PLACE CONCRETE FOR CIVIL WORKS. The concrete mixture shall have air content by volume of concrete, based on measurements made immediately after discharge from the mixer, of 5 to 7 percent when maximum size of coarse aggregate exceeds 1-1/2 inches. Air content shall be determined in accordance with ASTM C231/C231M. The concrete covering over steel reinforcing shall not be less than 1 inch thick for covers and not less than 1-1/2 inches thick for walls and flooring. Concrete covering deposited directly against the ground shall have a thickness of at least 3 inches between steel and ground. Expansion-joint filler material shall conform to ASTM D1751, or ASTM D1752, or shall be resin-impregnated fiberboard conforming to the physical requirements of ASTM D1752.

SECTION 33 40 00 Page 5

2.3.2 Joints

2.3.2.1 Flexible Watertight, Gasketed Joints

a. Gaskets: Gasketed joints shall be used and shall meet the requirements of ASTM C990 or ASTM C443. Preformed flexible joint sealants shall conform to ASTM C990, Type B.

b. External Sealing Bands: External sealing bands shall be used on all RCP joints and shall meet the requirements of ASTM C877, Type I (Rubber and Mastic Bands) or Type II (Plastic Film and Mesh Reinforced Mastic Bands). Watertight joints shall be tested and shall meet the test requirements of paragraph HYDROSTATIC TEST ON WATERTIGHT JOINTS.

2.3.2.2 Steel Reinforced Polyethylene (SRPE) Pipe

[DELETED]

2.4 RESILIENT CONNECTORS

Flexible, watertight connectors used for connecting pipe to manholes and inlets shall conform to ASTM C923.

2.5 HYDROSTATIC TEST ON WATERTIGHT JOINTS

2.5.1 Concrete Pipe

A hydrostatic test shall be made on the watertight joint types as proposed. Only one sample joint of each type needs testing; however, if the sample joint fails because of faulty design or workmanship, an additional sample joint may be tested. During the test period, gaskets or other jointing material shall be protected from extreme temperatures which might adversely affect the performance of such materials. Performance requirements for joints in reinforced and nonreinforced concrete pipe shall conform to ASTM C990 or ASTM C443.

PART 3 EXECUTION

3.1 EXCAVATION FOR PIPE CULVERTS, STORM DRAINS, AND DRAINAGE STRUCTURES

Excavation of trenches, and for appurtenances and backfilling for culverts and storm drains, shall be in accordance with the applicable portions of Section 31 23 00.00 12 - EXCAVATION and the requirements specified below.

3.1.1 Removal of Unstable Material

Where wet or otherwise unstable soil incapable of properly supporting the pipe, as determined by the Contracting Officer, is unexpectedly encountered in the bottom of a trench, such material shall be removed to the depth required and replaced to the proper grade with select granular material, compacted as provided in paragraph BACKFILLING. When removal of unstable material is due to the fault or neglect of the Contractor while performing shoring and sheeting, water removal, or other specified requirements, such removal and replacement shall be performed at no additional cost to the Government.

3.2 BEDDING

The bedding surface for the pipe shall provide a firm foundation of uniform

SECTION 33 40 00 Page 6

AMENDMENT 002

B1SL9JEK

Highlight

B1SL9JEK

Highlight density throughout the entire length of the pipe.

3.2.1 Concrete Pipe Requirements

The middle third of the bedding shall be loosely placed. Bell holes and depressions for joints shall be removed and formed so entire barrel of pipe is uniformly supported. The bell hole and depressions for the joints shall be not more than the length, depth, and width required for properly making the particular type of joint.

3.3 PLACING PIPE

Each pipe shall be thoroughly examined before being laid; defective or damaged pipe shall not be used. Pipelines shall be laid to the grades and alignment indicated. Proper facilities shall be provided for lowering sections of pipe into trenches. Lifting lugs in vertically elongated metal pipe shall be placed in the same vertical plane as the major axis of the pipe. Pipe shall not be laid in water, and pipe shall not be laid when trench conditions or weather are unsuitable for such work. Diversion of drainage or dewatering of trenches during construction shall be provided as necessary. Deflection of installed flexible pipe shall not exceed the following limits:

TYPE OF PIPE MAXIMUM ALLOWABLE

DEFLECTION (percent)

48" RCP 2.0%

Note post installation requirements of paragraph DEFLECTION TESTING in PART 3 of this specification for all pipe products including deflection testing requirements for flexible pipe.

3.3.1 Concrete Pipe

Laying shall proceed upgrade with spigot ends of bell-and-spigot pipe and tongue ends of tongue-and-groove pipe pointing in the direction of the flow.

3.4 JOINTING

3.4.1 Concrete Pipe

3.4.1.1 Flexible Watertight Joints

Gaskets and jointing materials shall be as recommended by the particular manufacturer in regard to use of lubricants, cements, adhesives, and other special installation requirements. Surfaces to receive lubricants, cements, or adhesives shall be clean and dry. Gaskets and jointing materials shall be affixed to the pipe not more than 24 hours prior to the installation of the pipe, and shall be protected from the sun, blowing dust, and other deleterious agents at all times. Gaskets and jointing materials shall be inspected before installing the pipe; any loose or improperly affixed gaskets and jointing materials shall be removed and replaced. The pipe shall be aligned with the previously installed pipe, SECTION 33 40 00 Page 7 and the joint pushed home. If, while the joint is being made the gasket becomes visibly dislocated the pipe shall be removed and the joint remade.

3.4.1.2 External Sealing Band

Surfaces to receive sealing bands shall be dry and clean. Bands shall be installed in accordance with manufacturer's recommendations.

3.5 DRAINAGE STRUCTURES

3.5.1 Gatewell

Construction shall be as indicated.

3.5.2 Flared End Sections and Headwalls

Construction shall be as indicated.

3.6 BACKFILLING

3.6.1 Backfilling Pipe in Fill Sections

For pipe placed in fill sections, backfill material and the placement and compaction procedures shall be as specified below. The fill material shall be uniformly spread in layers longitudinally on both sides of the pipe, not exceeding 6 inches in compacted depth, and shall be compacted by rolling parallel with pipe or by mechanical tamping or ramming. Prior to commencing normal filling operations, the crown width of the fill at a height of 12 inches above the top of the pipe shall extend a distance of not less than twice the outside pipe diameter on each side of the pipe or 12 feet, whichever is less. After the backfill has reached at least 12 inches above the top of the pipe, the remainder of the fill shall be placed and thoroughly compacted in layers not exceeding 12 inches. Use pervious fill as indicated, and compacted impervious fill for the remainder of the pipe.

3.6.2 Movement of Construction Machinery

When compacting by rolling or operating heavy equipment parallel with the pipe, displacement of or injury to the pipe shall be avoided. Movement of construction machinery over a culvert or storm drain at any stage of construction shall be at the Contractor's risk. Any damaged pipe shall be repaired or replaced.

3.6.3 Compaction

3.6.3.1 General Requirements

Cohesionless materials include gravels, gravel-sand mixtures, sands, and gravelly sands. Cohesive materials include clayey and silty gravels, gravel-silt mixtures, clayey and silty sands, sand-clay mixtures, clays, silts, and very fine sands. When results of compaction tests for moisture-density relations are recorded on graphs, cohesionless soils will show straight lines or reverse-shaped moisture-density curves, and cohesive soils will show normal moisture-density curves.

3.6.3.2 Minimum Density

Backfill over and around the pipe and backfill around and adjacent to

SECTION 33 40 00 Page 8

AMENDMENT 002

drainage structures shall be compacted at the approved moisture content to the following applicable minimum density, which will be determined as specified below.

a. Under airfield and heliport pavements, paved roads, streets, parking areas, and similar-use pavements including adjacent shoulder areas, the density shall be not less than 90 percent of maximum density for cohesive material and 95 percent of maximum density for cohesionless material, up to the elevation where requirements for pavement subgrade materials and compaction shall control.

b. Under unpaved or turfed traffic areas, density shall not be less than 90 percent of maximum density for cohesive material and 95 percent of maximum density for cohesionless material.

c. Under nontraffic areas, density shall be not less than that of the surrounding material.

3.6.4 Determination of Density

Testing is the responsibility of the Contractor and performed at no additional cost to the Government. Testing shall be performed by an approved commercial testing laboratory or by the Contractor subject to approval. Tests shall be performed in sufficient number to ensure that specified density is being obtained. Laboratory tests for moisture-density relations shall be made in accordance with ASTM D1557 except that mechanical tampers may be used provided the results are correlated with those obtained with the specified hand tamper. Field density tests shall be determined in accordance with ASTM D2167 or ASTM D6938. When ASTM D6938 is used, the calibration curves shall be checked and adjusted, if necessary, using the sand cone method as described in paragraph Calibration of the referenced publications. ASTM D6938 results in a wet unit weight of soil and ASTM D6938 shall be used to determine the moisture content of the soil. The calibration curves furnished with the moisture gauges shall be checked along with density calibration checks as described in ASTM D6938.

Test results shall be furnished the Contracting Officer. The calibration checks of both the density and moisture gauges shall be made at the beginning of a job on each different type of material encountered and at intervals as directed.

3.7 PIPELINE TESTING

3.7.1 Leakage Tests

Lines shall be tested for leakage by low pressure air or water testing or exfiltration tests, as appropriate. Low pressure air testing for concrete pipes shall conform to ASTM C969. Testing of individual joints for leakage by low pressure air or water shall conform to ASTM C1103. Prior to exfiltration tests, the trench shall be backfilled up to at least the lower half of the pipe. If required, sufficient additional backfill shall be placed to prevent pipe movement during testing, leaving the joints uncovered to permit inspection. Visible leaks encountered shall be corrected regardless of leakage test results. When the water table is 2 feet or more above the top of the pipe at the upper end of the pipeline section to be tested, infiltration shall be measured using a suitable weir or other device acceptable to the Contracting Officer. An exfiltration test shall be made by filling the line to be tested with water so that a head of at least 2 feet is provided above both the water table and the top of the pipe at the upper end of the pipeline to be tested. The filled line

SECTION 33 40 00 Page 9 shall be allowed to stand until the pipe has reached its maximum absorption, but not less than 4 hours. After absorption, the head shall be reestablished. The amount of water required to maintain this water level during a 2-hour test period shall be measured. Leakage as measured by the exfiltration test shall not exceed 0.2 gallons per inch in diameter per 100 feet of pipeline per hour. When leakage exceeds the maximum amount specified, satisfactory correction shall be made and retesting accomplished.

3.7.2 Deflection Testing

No sooner than 30 days after completion of installation and final backfill, an initial post installation inspection shall be accomplished. Clean or flush all lines prior to inspection. Perform a deflection test on entire length of installed flexible pipeline on completion of work adjacent to and over the pipeline, including leakage tests, backfilling, placement of fill, grading, paving, concreting, and any other superimposed loads. Deflection of pipe in the installed pipeline under external loads shall not exceed limits in paragraph PLACING PIPE above as percent of the average inside diameter of pipe. Determine whether the allowable deflection has been exceeded by use of a laser profiler or mandrel.

a. Laser Profiler Inspection: If deflection readings in excess of the allowable deflection of average inside diameter of pipe are obtained, remove pipe which has excessive deflection, and replace with new pipe.

Initial post installation inspections of the pipe interior with laser profiling equipment shall utilize low barrel distortion video equipment for pipe sizes 48 inches or less. Use a camera with lighting suitable to allow a clear picture of the entire periphery of the pipe interior.

Center the camera in the pipe both vertically and horizontally and be able to pan and tilt to a 90 degree angle with the axis of the pipe rotating 360 degrees. Use equipment to move the camera through the pipe that will not obstruct the camera's view or interfere with proper documentation of the pipe's condition. The video image shall be clear, focused, and relatively free from roll static or other image distortion qualities that would prevent the reviewer from evaluating the condition of the pipe. For initial post installation inspections for pipe sizes larger than 48 inches, visual inspection shall be completed of the pipe interior.

b. Pull-Through Device Inspection: Pass the pull-through device through each run of pipe by pulling it by hand. If deflection readings in excess of the allowable deflection of average inside diameter of pipe are obtained, retest pipe by a run from the opposite direction. If retest continues to show excess allowable deflections of the average inside diameter of pipe, remove pipe which has excessive deflection, replace with new pipe, and completely retest in same manner and under same conditions. Pull-through device: The mandrel shall be rigid, nonadjustable having a minimum of 9 fins, including pulling rings at each end, engraved with the nominal pipe size and mandrel outside diameter. The mandrel shall be 5 percent less than the certified-actual pipe diameter for Plastic Pipe, 5 percent less than the certified-actual pipe diameter for Corrugated Steel and Aluminum Alloy, 3 percent less than the certified-actual pipe diameter for Concrete-Lined Corrugated Steel and Ductile Iron Culvert provided by manufacturer. When mandrels are utilized to verify deflection of flexible pipe products, the Government will verify the mandrel OD through the use of proving rings that are manufactured with an opening that is certified to be as shown above.

SECTION 33 40 00 Page 10

c. Deflection measuring device: Shall be approved by the Contracting Officer prior to use.

d. Warranty period test: Pipe found to have a deflection of greater than allowable deflection in paragraph PLACING PIPE above, just prior to end of one-year warranty period shall be replaced with new pipe and tested as specified for leakage and deflection. Inspect 100 percent of all pipe systems under the travel lanes, including curb and gutter. Random inspections of the remaining pipe system outside of the travel lanes shall represent at least 10 percent of the total pipe footage of each pipe size. Inspections shall be made, depending on the pipe size, with video camera or visual observations. In addition, for flexible pipe installations, perform deflection testing on 100 percent of all pipes under the travel lanes, including curb and gutter, with either a laser profiler or 9-fin mandrel. For flexible pipe, random deflection inspections of the pipe system outside of the travel lanes shall represent at least 10 percent of the total pipe footage of each pipe size. When mandrels are utilized to verify deflection of flexible pipe products during the final post installation inspection, the Government will verify the mandrel OD through the use of proving rings.

3.7.3 Post-Installation Inspection

Check each reinforced concrete pipe installation for joint separations, soil migration through the joint, cracks greater than 0.01 inches, settlement and alignment. Check each flexible pipe (HDPE, PVC, CMP, PP) for rips, tears, joint separations, soil migration through the joint, cracks, localized bucking, bulges, settlement and alignment.

a. Replace pipes having cracks greater than 0.1 inches in width or deflection greater than 5 percent deflection. An engineer shall evaluate all pipes with cracks greater than 0.01 inches but less than

0.10 inches to determine if any remediation or repair is required. RCP with crack width less than 0.10 inches and located in a non-corrosive environment (pH 5.5) are generally acceptable. Repair or replace any pipe with crack exhibiting displacement across the crack, exhibiting bulges, creases, tears, spalls, or delamination.

b. Reports: The deflection results and final post installation inspection report shall include: a copy of all video taken, pipe location identification, equipment used for inspection, inspector name, deviation from design, grade, deviation from line, deflection and deformation of flexible pipe systems, inspector notes, condition of joints, condition of pipe wall (e.g. distress, cracking, wall damage dents, bulges, creases, tears, holes, etc.).

-- End of Section --

SECTION 33 40 00 Page 11