Solicitation amendment with Q&A from industry. No further questions will be allowed on this action.

View the file

Other files for this federal contract opportunity

Other files attached to LMA Workboat, newest first.
File Type Posted
W912EF19Q0127.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose for this amendment is to extend the due date and time to allow vendors to received questions and answ ers from the industry.

Extention is from 9/19/19 to 9/23/19.

No further questions w ill be accepted.

Please see summary of changes for additional information.

All other terms and conditions remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 19-Sep-2019

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912EF19Q0127

X 9B. DATED (SEE ITEM 11)

11-Sep-2019

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

19-Sep-2019

CODE

USAED, WALLA WALLA - CONTRACTING DIV.

LEANNE WALLING

201 N. THIRD AVENUE

WALLA WALLA WA 99362-1876

W912EF 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912EF19Q0127

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 1449 - CONTINUATION SHEET

SOLICITATION/CONTRACT FORM

The required response date/time has changed from 19-Sep-2019 04:00 PM to 23-Sep-2019 04:00 PM.

The following have been added by full text:

QUESTIONS AND ANSWERS

Questions and Answers:

1. The specification lists "26' landing craft with either a twin hull design or V-hull design with a 64" wide bow door." Would you accept a stabilized monohull? If so, can you please modify the specification and provide us with an additional week to put our bid together?

Answer: A stabilized mono-hull is considered in our definition as a v-hull. No modification to specifications will be completed. See forthcoming amendment with extension details.

2. The specification lists: "All surface areas shall be shiny, mill finish, with no grind marks, splatters, or blemishes."

This is a very broad specification, is there any way that you can provide a more detailed specification in this section? I am assuming a "yacht level" finish is not required, and that some level of scratches, blemishes and defects is acceptable. –

Answer: Yacht level is not expected. What is expected is that good shop practices will be used and the boat will be finished in a manner of good workmanship.

3. The specification lists: "At a minimum, submittals shall include manufactures catalog cuts, specification sheets, warranty information and a list of authorized service centers within a 75 mile driving radius of Kahlotus, WA 99335." Is it a hard requirement to have an authorized service center within 75 miles of Kahlotus, WA? We feel this is too restrictive and limits the companies that can respond to this RFP. Can you loosen this restriction or provide us with an additional 2 weeks to secure a service center that meets your requirements? --

Answer: This requirement stays as is. The intent is to ensure that whatever power system is used that a local service center is located within 75 miles of our location.

4. Due to the location of our company, we would need to take exception to the 120 day delivery requirement. We would need 180-240 days due to shipping times. Can you adjust this requirement? --

Answer: The Government need is to have Workboat onsite and fully operational for navlock outage Scheduled in March. Max exception will be NLT 180 day delivery date.

5. Item 3.0 #1 - We have a model that includes an engine bracket - Is the hull length 26' Length Overall including any engine brackets?

Answer: The 26' requirement is the same as the coast guard

6. It is technically considered 26" by the Coast Guard but provides more deck space because the engines are mounted on a bracket. The bracket also provides a platform for stern recovery and ease of engine maintenance. Is that an acceptable and equivalent offer?

W912EF19Q0127

Answer: Yes

7. Item 3.0 #10 - Our CVK is 1/4 X 12" instead of 3/8" X 3". I can provide engineering support that it is equally as strong if not stronger (Only Munson uses the 3/8" X 3" CVK). Is that an acceptable and equivalent offer?

Answer: Yes

8. Item 3.1 Hull Package 2.5" drains - If we supply a boat with an engine bracket it eliminates the slop well completely. Is that an acceptable and equivalent offer?

Answer: Yes

9. 3.3 Hull Outfitting - We use a flush square scupper at the stern deck that exits as pipe at the transom. This ensure maximum water egress with minimum water pooling. Is that an acceptable and equivalent offer?

Answer: Yes

10. The bid pack calls for; "Twin 150 HP four-stroke outboard engines shall be installed. Engines shall come with power trim/tilt and stainless steel propellers. The propellers shall be selected for optimized engine performance."

Currently Evinrude offers a 150hp motors in their E-Tec line that are more efficient, have cleaner emissions and have special pricing structure for government owned vessels. They are a direct injection motor, but they are not a 4-stroke as required in the specifications. Would this be a suitable option?

Answer: This motor offer of a 4-stroke is acceptable

(End of Summary of Changes)