Technical Specifications
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bid_Opening_Abstract_W912EF19B0012.pdf | ||
| B.08.03_19B0012_AMEND-004_PLANS.pdf | ||
| B.08.03_W912EF19B0012_Amendment_0004.pdf | ||
| B.08.03_W912EF19B0012_Drawings_Amend-0003.pdf | ||
| B.08.03_W912EF19B0012_Amendment_0003.pdf | ||
| B.08.03_W912EF19B0012_Amendment_0002.pdf | ||
| B.08.03_W912EF19B0012_Tech_Specs_Amend-0002.pdf | ||
| B.08.03_W912EF19B0012_Amend-0001_Tech_Spec.pdf | ||
| B.08.03_W912EF19B0012_Amendment_0001.pdf | ||
| LMA_-_Diffuser_Grating_Replacement_Site_Visit_Attendees.pdf | ||
| B.08.02_Solicitation_W912EF19B0012.pdf | ||
| 19B0012_Plans.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Lower Monumental NS Fish Ladder Diffuser Grating Replacement W912EF19B0012
PROJECT TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 01 15.00 28 LIST OF DRAWINGS
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00.00 28 GENERAL REQUIREMENTS
01 11 01.00 28 SUPPLEMENTARY REQUIREMENTS
01 14 00.10 28 PROJECT SITE RESTRICTIONS
01 14 00.90 28 INTEGRATING ANTITERRORISM (AT) AND OPERATIONS SECURITY
(OPSEC)
01 22 00.00 28 MEASUREMENT AND PAYMENT
01 33 00 SUBMITTAL PROCEDURES
01 35 29.10 28 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.01 28 CONTRACTOR QUALITY CONTROL (SHORT FORM)
01 45 01.00 28 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 51 00.00 28 TEMPORARY UTILITIES
01 55 10.00 28 CONTRACTOR WORK, ACCESS AND STORAGE AREAS
01 57 20.00 28 ENVIRONMENTAL PROTECTION
01 78 00.00 28 CLOSEOUT SUBMITTALS
DIVISION 02 - EXISTING CONDITIONS
02 41 00.10 28 DEMOLITION
DIVISION 05 - METALS
05 50 03.00 28 METALWORK FABRICATION, MACHINE WORK, MISCELLANEOUS
PROVISIONS
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS
SECTION TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
SECTION 00 01 15.00 28
LIST OF DRAWINGS
PART 1 GENERAL
1.1 SUMMARY
1.2 CONTRACT DRAWINGS
1.2.1 Use Of Government Prepared Contract CAD Electronic Files
1.3 FOR RESOURCE DRAWINGS (R)
-- End of Section Table of Contents --
DOCUMENT 00 01 15.00 28
SECTION 00 01 15.00 28
LIST OF DRAWINGS
PART 1 GENERAL
1.1 SUMMARY
This section lists the drawings for the project pursuant to contract clause "DFARS 252.236-7001, Contract Drawings, Maps and Specifications."
1.2 CONTRACT DRAWINGS
Contract drawings are as follows:
FILE NUMBER SHEET
NUMBER
DESCRIPTION REVISION
NUMBER
DATE
G-001 COVER SHEET AND LOCATION MAPS
G-002 INDEX SHEET
G-101 SITE KEY PLAN
G-102 NEW WORK KEY PLAN
S-101 DIFFUSERS 2A, 3, 4 & 5 AND
DIFFUSER 6 PLANS
S-501 DIFFUSER GRATING AND SUPPORTS
SECTIONS AND DETAILS
1.2.1 Use Of Government Prepared Contract CAD Electronic Files
a. No For Information Only drawings are available on CAD.
b. The Contractor assumes all risks associated in using electronic CAD drawings.
c. Electronic copies of CAD drawings are only available in Bentley DGN format.
d. The contract drawings shall govern if there are any discrepancies between the electronic copy and the contract drawing. The Contractor shall promptly notify the Contracting Officer of any discrepancies.
The Government will not be responsible to correct the electronic CAD drawing.
1.3 FOR RESOURCE DRAWINGS (R)
These R drawings are included with the drawings for information. The Government does not warrant the accuracy of the R drawings. The Government recommends that the Contractor verify the accuracy of R drawings.
Resource (R) drawings are as follows:
FILE NUMBER SHEET NUMBER DESCRIPTION
LMF-1-4-2/1 R-001 NORTH ABUTMENT NORTH SHORE FISH LADDER
PLAN
LMF-1-4-2/2 R-002 NORTH ABUTMENT NORTH SHORE FISH LADDER
SECTIONS I
LMF-1-4-2/3 R-003 NORTH ABUTMENT NORTH SHORE FISH LADDER
SECTIONS II
LMF-1-4-2/4 R-004 NORTH ABUTMENT NORTH SHORE FISH LADDER
SECTIONS 1 & 2 - PLAN AND SECTIONS
LMF-1-4-2/24 R-005 NORTH ABUTMENT NORTH SHORE FISH
LADDER SECTIONS 7 & 8 - PLAN AND
SECTIONS
LMF-1-4-2/25 R-006 NORTH ABUTMENT NORTH SHORE FISH LADDER
SECTIONS 7 & 8 - SECTIONS & DETAILS
LMF-1-4-2/10 R-007 NORTH ABUTMENT NORTH SHORE FISH LADDER
SECTIONS 3 & 4 - PLAN AND SECTIONS
LMF-1-5-2/3 R-008 NORTH ABUTMENT NORTH SHORE FISH LADDER
DETAILS III
LMF-1-5-2/4 R-009 NORTH ABUTMENT NORTH SHORE FISH LADDER
DETAILS IV
LMP-1-4-4/1 R-010 POWERHOUSE - NORTH SHORE FISH ENT
CONCRETE OUTLINE PLAN - EL 460
LMP-1-4-4/6 R-011 POWERHOUSE - NORTH SHORE FISH ENT
CONCRETE OUTLINE SECTIONS - SHEET 2
LMP-1-4-4/2 R-012 POWERHOUSE - NORTH SHORE FISH ENT
CONCRETE OUTLINE PLAN - EL 432
LMP-1-4-4/5 R-013 POWERHOUSE - NORTH SHORE FISH ENT
CONCRETE OUTLINE SECTIONS - SHEET 1
LMP-1-5-0/14 R-014 POWERHOUSE - MISCELLANEOUS METAL
GRATINGS, SUPPORTS, ARMOR ANGLES AND
ANCHOR BOLTS
LMP-1-5-0/15 R-015 POWERHOUSE - MISCELLANEOUS METAL FISH
ENTRANCE CHANNEL GRATINGS AND
MISCELLANEOUS DETAILS
-- End of Document --
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 00 00.00 28
GENERAL REQUIREMENTS
PART 1 GENERAL
1.1 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS
CONTRACTS
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
-- End of Section Table of Contents --
SECTION 01 00 00.00 28
GENERAL REQUIREMENTS
PART 1 GENERAL
1.1 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS CONTRACTS
In addition to complying with the requirements outlined in FAR Part 22.13, FAR Provision 52.222-38, FAR Clause 52.222-35, FAR Clause 52.222-37, DFARS
222.13 and Department of Labor regulations, U.S. Army Corps of Engineers (USACE) contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract. While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract, USACE contractors are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are available to assist USACE contractors in their outreach efforts:
Federal Veteran Employment Information http://www.fedshirevets.gov/index.aspx
Department of Labor Veterans Employment Assistance http://www.dol.gov/vets/
Department of Veterans Affairs-VOW to Hire Heroes Act http://benefits.va.gov/vow/
Army Wounded Warrior Program -http://wtc.army.mil/modules/employers/index.html
U.S. Chamber of Commerce Foundation-Hiring Our Heroes http://www.hiringourheroes.org/
Guide to Hiring Veterans - Reference Material https://obamawhitehouse.archives.gov/sites/default/files/docs/white_house_business_c
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
-- End of Section --
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 01.00 28
SUPPLEMENTARY REQUIREMENTS
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 FIELD VERIFICATION OF SITE CONDITIONS
1.4 PROJECT SCHEDULE
1.5 REGULAR CLEANUP AND DEBRIS DISPOSAL
1.6 COMMUNICATIONS
1.7 GOVERNMENT ISSUED ITEMS
1.8 EQUIPMENT LIST
1.9 TESTING OF EQUIPMENT
1.10 DISPOSITION OF REMOVED MATERIALS AND EQUIPMENT
1.11 PROTECTION AND RESTORATION OF EXISTING FACILITIES
1.12 PRE-WORK AND POST WORK SURVEYS
1.13 PROJECT SUPERINTENDENT
1.14 KEY PERSONNEL SUBSTITUTION
1.15 POST AWARD MEETINGS
1.15.1 Pre-Work Meeting
1.15.2 Pre-Construction Meeting
1.15.2.1 Minutes
1.15.2.2 Demobilizing And Remobilizing
1.16 WEEKLY PRODUCTION MEETINGS
1.16.1 Minutes
1.17 ADDITIONAL MEETINGS
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION (Not Used)
ATTACHMENTS:
Weekly Meeting Agenda
-- End of Section Table of Contents --
SECTION 01 11 01.00 28
SUPPLEMENTARY REQUIREMENTS
PART 1 GENERAL
The work covered by this section of the specifications consists of work common to more than one section of these TECHNICAL SPECIFICATIONS.
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 Safety and Health Requirements Manual
Comply with the current edition and all changes posted on the web as of the effective date of this solicitation.
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals having an "I" designation are for information only. Designation following the "G" or "I" designation identifies the office that will review the submittal for the Government. Submit in accordance with SECTION
01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Project Schedule; G C
Equipment List; I C
Pre-Work Survey Photos And Report; I C
Project Superintendent; I C
SD-07 Certificates
Key Personnel Substitution; G C
SD-11 Closeout Submittals
Post-Work Survey Photos And Report; I C
Government Issued Items; G C
1.3 FIELD VERIFICATION OF SITE CONDITIONS
Field verify all elevations, dimensions, and coordinates of existing features indicated on the contract drawings that affect new construction.
Any deviations shall be updated as per SECTION 01 78 00.00 28, CLOSEOUT
SUBMITTALS, paragraphs WORKING AS-BUILT DRAWINGS.
1.4 PROJECT SCHEDULE
a. Furnish a schedule for the complete project in accordance with Clause 52.236-15 Schedules for Construction Contracts within 15 days after receipt of Notice to Proceed.
b. Email an electronic copy of the schedule, in the original format the schedule was developed in (e.g. .xer, .xls., .mpp, etc.), to the Contracting Officer. See SECTION 01 33 00 SUBMITTAL PROCEDURES paragraph "Electronic Copies" for email address.
1.5 REGULAR CLEANUP AND DEBRIS DISPOSAL
With the exception of materials specifically indicated or specified to be salvaged for reuse in construction, or turned over to the Government, all wastes and demolished materials shall become the property of the Contractor and shall be removed from the job site daily in accordance with Federal, State, and local regulations. The Contractor shall furnish waste containers. All small waste containers provided by the contractor shall be emptied daily, large bin containers shall be emptied when full or once a week.
Remove all grating, supports, bolts and all other appertances from the project site and dispose of in a legal manner.
1.6 COMMUNICATIONS
Provide a radio communications system between the Tailrace Deck and the work area in the collection channel. Radio shall be capable of transmitting and receiving on all frequencies that the Contractor will be using during the contract period. Radio shall also operate on 156,700 mHz. The Government representative shall be provided use of the communication system at any time upon request.
1.7 GOVERNMENT ISSUED ITEMS
Return to the Government all items issued to the Contractor from the Government, including but not limited to the following: keys, ID and security badges, radios, pagers, and excess/unused Government Furnished Property/Equipment. Submit documentation signed by the Contractor and Contracting Officer indicating items have been returned or fully accounted for. Format of submittal will be discussed and agreed upon at the Pre-Work Meeting.
1.8 EQUIPMENT LIST
Furnish a complete list of all equipment to be used on the Project 30 days prior to commencement of on-site work. Submit a revised list in the event of change of equipment. Lists shall include rented equipment as well as lease-purchase or sale-leaseback equipment. The initial list and the revised lists shall indicate dates equipment is assigned to or removed from the Project and adequate identification or description of each item of equipment including manufacturer's name (abbreviated), model number, manufacturer's serial number, year of manufacture, and Contractor's assigned serial or record number.
1.9 TESTING OF EQUIPMENT
Before any machinery or mechanized equipment is put to use on the job, it shall be inspected and tested by a qualified person and determined to be in safe operating condition. Cranes or derricks shall be tested by the Contractor or a qualified testing agency in accordance with EM 385-1-1.
Equipment shall be large enough to safely handle proposed picks or tasks without exceeding the crane rating established by these tests.
1.10 DISPOSITION OF REMOVED MATERIALS AND EQUIPMENT
Unless otherwise specified in other sections of the specifications, all existing equipment removed and not reinstalled shall become the property of the Contractor, removed from the Project site, and disposed of in a legal manner. Materials that cannot be removed daily may be temporarily stored on-site at an approved area. Salvaged materials shall not be sold on the project site.
1.11 PROTECTION AND RESTORATION OF EXISTING FACILITIES
Reference FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (Apr 1984).
1.12 PRE-WORK AND POST WORK SURVEYS
Conduct a pre-work survey prior to start of on-site work and a post-work survey during project closeout, with the Contracting Officer Representative, of the Government facilities at the work areas. The results of the surveys shall be documented by digital photographs and descriptive narrative reports. A color copy of the survey photographs and narrative reports shall be submitted to the Contracting Officer within five
(5) days after survey has been completed.
1.13 PROJECT SUPERINTENDENT
The Contractor's Project Superintendent shall be on the worksite during performance of work on this contract. The Project Superintendent is required on the worksite, at all times work is being performed, until work on this contract is completed and accepted. Assign a competent superintendent as per FAR Clause 52.236-6 "Superintendence by the Contractor". Submit Superintendent name and contact information prior to start of on-site construction.
1.14 KEY PERSONNEL SUBSTITUTION
If the Contractor plans on replacing any Key personnel (Project Superintendent, CQC System Manager, or CQC staff Members) they must have the approval of the Contracting Officer. Personnel shall possess the qualifications that meet or exceed those stated in this contract for the position of the individual they are replacing. Submit qualifications of new personnel at least 15 calendar days in advance of date of replacement.
1.15 POST AWARD MEETINGS
1.15.1 Pre-Work Meeting
Within 15 calendar days after receipt of Notice to Proceed, attend a Pre-Work Meeting. Senior Level members of the Contractor's staff involved with this contract shall participate in this meeting to discuss the overall contract requirements. The Government will lead this meeting and take the meeting minutes.
1.15.2 Pre-Construction Meeting
Coordinate with the Contracting Officer and establish the date of the Pre-Construction Meeting. The meeting will be held at the Project site at least one (1) week prior to mobilizing to the job site. Lead the Pre-Construction Meeting discussing the Contractor's plan on executing the work at the project site, schedule, required clearances and timeframe for them, and plan for implementing safety and quality control. The Government will have key members from the Project staff to discuss environmental and clearance issues. Key members of the contractor staff shall attend this meeting including the Quality Control (QC) System Manager, Site Safety and Health Officer (SSHO) and any other members determined by the Government to be required.
1.15.2.1 Minutes
Contractor is responsible for taking the meeting minutes and shall send them electronically within 48 hours of the meeting to the Government's Project Engineer, Quality Assurance Representative, and Resident Engineer.
1.15.2.2 Demobilizing And Remobilizing
Anytime the Contractor demobilizes from the site and remobilizes at a later date, another Pre-Construction Meeting shall be held and shall follow the requirements listed above.
1.16 WEEKLY PRODUCTION MEETINGS
During all fabrication and onsite construction work, hold a weekly production meeting to brief the Government on the status of the project.
a. Use the attached "Weekly Meeting Agenda" and discuss all elements of this agenda.
b. Provide a three (3) week 'look ahead'.
1. Describe all planned construction activities, on-site and off-site over the next three (3) weeks.
2. ENSURE these activities align to the overall construction SCHEDULE submitted under SECTION 01 11 01.00 28 SUPPLEMENTARY REQUIREMENTS, paragraph PROJECT SCHEDULE.
3. RECORD any changes to the Project Schedule AND INCLUDE IN the next scheduled update.
c. Key members of the Contractor's staff including the Quality Control System Manager and the SITE SAFETY AND HEALTH OFFICER shall attend.
d. The Quality Control System Manager shall discuss all QC aspects outlined in SECTION 01 45 00.01 28 CONTRACTOR QUALITY CONTROL.
e. The Government reserves the right to require any person from the Contractor's staff such as the Project Manager, Engineer, Scheduler or Key Subcontractor Personnel to attend the meeting.
f. Submit each meeting agenda to the COR 24 hours prior to the meeting.
1.16.1 Minutes
The Contractor shall be responsible for taking the meeting minutes and shall send them electronically within 24 hours of the meeting to the Government's Project Engineer, Quality Assurance Representative, and Resident Engineer.
1.17 ADDITIONAL MEETINGS
Record the minutes of all meetings, including all conference calls, that occur between the Contractor and Government. Send minutes electronically within 24 hours of the meeting to the Contracting Officer for concurrence.
E-mail subject line shall include project name and meeting topic.
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION (Not Used)
-- End of Section --
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 14 00.10 28
PROJECT SITE RESTRICTIONS
PART 1 GENERAL
1.1 REFERENCES
1.2 SITE CONDITIONS AND OPERATIONAL RESTRICTIONS
1.3 PROJECT SECURITY
1.3.1 Contractor Vehicle Access
1.3.2 Identification of Employees
1.3.2.1 Project Security Notification Pagers
1.4 DELIVERY OF EQUIPMENT
1.5 FACILITY OCCUPANCY CLOSURE
1.5.1 Vehicle Access along Tailrace Deck
1.6 WORK SCHEDULES
1.6.1 Contractor's Work Schedule
1.6.2 Government's Work Schedule
1.7 USE OF WALLA WALLA DISTRICT PARKS
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION (Not Used)
ATTACHMENTS:
Security Badge Form
-- End of Section Table of Contents --
SECTION 01 14 00.10 28
PROJECT SITE RESTRICTIONS
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 Safety and Health Requirements Manual
Contractor shall be responsible for complying with the current edition and all changes posted on the web as of the effective date of this solicitation.
1.2 SITE CONDITIONS AND OPERATIONAL RESTRICTIONS
The following information is provided:
1. The Government will install the bulkheads and dewater the work area and remove any fish from the area. The water level in the dewatered area will be less than six (6) inches.
2. The Government will maintain this dewatered level. No supplemental pumping will be necessary.
3. All tailrace deck grating is built to meet HS-20 loading requirements. Assume that the Diffuser Grating has no structural strength.
4. The Government does not warrant the load carrying capacity of the existing diffuser grating. The Contractor assumes all risk associated with using the existing grating in performing the work.
1.3 PROJECT SECURITY
The Project site is a secured area and access onto the Project is restricted. The security measures affect all of the Contractor's vehicles and personnel. There will be delays when entering Projects due to locked gates, vehicle inspections, and personnel checks. Inspections and checks may include inspection of tool boxes, brief cases, lunch boxes, and other containers.
1.3.1 Contractor Vehicle Access
Project access roads on both sides of the dams are secured with locked gates. All vehicles that pass through the locked gates will be subject to being searched. No privately owned vehicles (POV's) will be allowed through locked gates. Only Contractor's work vehicles and equipment that are essential to the conduct of the work will be allowed in the work areas. All Contractor vehicles shall display suitable permanent or temporary identification.
1.3.2 Identification of Employees
Government Project personnel will provide the Contractor's personnel with identification badges as they arrive on site. The Contractor shall be responsible for furnishing the Security Badge Form(attached to the end of this SECTION) and initial identification (driver's license) for each employee five (5) business days prior to the employee arriving to work on the Project site, and upon issuance of official badges, for requiring each employee engaged on the work to display identification at all times.
Ensure each employee's full name with middle initial is included with the initial identification. All prescribed identification shall immediately be delivered to the Quality Assurance Representative for cancellation upon the release of the employee or project completion. If required by the Contracting Officer, employees will be photographed by the Government.
Employees who fail to submit to photographing will not be allowed on the project site.
Every Contractor employee (prime or subcontractor) shall have a hard hat meeting the requirements of EM 385-1-1. Hardhats shall display the Prime Contractor name, subcontractor name, and the employee's name. Contractor employee hardhats shall not be white with red markings. It shall be the responsibility of the Project Superintendent to enforce this requirement.
1.3.2.1 Project Security Notification Pagers
The Government (Project personnel) will issue the Contractor's SSHO and/or Project Superintendent with pagers to be carried at all times while on-site to receive Project Security Notifications. All pagers shall immediately be delivered to the Quality Assurance Representative upon the release of the employee or project completion.
1.4 DELIVERY OF EQUIPMENT
Contractor shall be responsible for delivery and receipt of all materials and equipment. Government personnel will not be available to assist the Contractor in these activities. To the maximum extent possible, deliveries shall arrive on the same side of the river as the Contractor's work area.
Delivery vehicles will be allowed to cross the river over the dam only with Government approval. Delivery vehicles arriving on the opposite side of the river as the work area shall be unloaded outside the locked gate, equipment shall be loaded onto Contractor's vehicles, and Contractor's vehicles will then be allowed to cross the dam to the work area.
1.5 FACILITY OCCUPANCY CLOSURE
Streets, walks, and other facilities occupied and used by the Government shall not be closed or obstructed without written permission from the Contracting Officer.
1.5.1 Vehicle Access along Tailrace Deck
Maintain an open vehicular path in the work area at all times unless specified. Short term blockage may be permitted as coordinated with the Contracting Officer.
1.6 WORK SCHEDULES
1.6.1 Contractor's Work Schedule
At the Pre-Work Meeting, furnish a schedule of number of working days per week, shifts per day, and hours per shift for contract work. Furnish notification of any change of schedule of regular work hours, overtime work hours, and shifts of work crews and personnel at the site. This notification shall be provided a minimum of 48 hours prior to any schedule change to allow suitable scheduling of Government personnel and inspection. Exception to this requirement may be allowed in case of schedule change due to emergency conditions.
1.6.2 Government's Work Schedule
a. The maintenance crews at the dam work from 6:30 a.m. to 5:00 p.m., Monday through Thursday. Crews and staff do not work on weekends and Federal holidays. If a Federal holiday falls on a Friday, the crews and staff do not work on the preceding Thursday. A powerhouse operator is at the site 24 hours a day, 7 days a week, including Federal holidays but is not available to assist the Contractor.
b. If the Contractor requires Government support or assistance outside of normal work hours, the Contractor must make a formal written request to the Contracting Officer at least one week prior to the date that support/assistance is needed. The Government will review this request, but there is no guarantee that Government support or assistance can be provided.
1.7 USE OF WALLA WALLA DISTRICT PARKS
Special consideration for the use of the Walla Walla District Camping Grounds will not be given to the Contractor if camping at these sites.
The Contractor's crew may not use Government parking lots near the Lower Monumental Lock and Dam for RV parking.
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION (Not Used) -- End of Section --
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 14 00.90 28
INTEGRATING ANTITERRORISM (AT) AND OPERATIONS SECURITY (OPSEC)
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 Biographical Information Submittal
1.4 AT LEVEL 1 TRAINING
1.5 ACCESS AND GENERAL PROTECTION/SECURITY POLICY AND PROCEDURES
1.6 SUSPICIOUS ACTIVITY REPORTING TRAINING (iWATCH, CORPS Watch, or See
Something, Say Something)
1.7 CONTRACTS THAT REQUIRE OPSEC TRAINING
1.8 PRE-SCREEN CANDIDATES USING E-VERIFY PROGRAM
1.9 THREAT AWARENESS REPORTING PROGRAM
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
-- End of Section Table of Contents --
SECTION 01 14 00.90 28
INTEGRATING ANTITERRORISM (AT) AND OPERATIONS SECURITY (OPSEC)
PART 1 GENERAL
The work covered by this section of the specifications consists of work common to more than one section of these TECHNICAL SPECIFICATIONS. This contract does not require access to or handling of classified material.
This contract requires access to secured and restricted areas, sensitive information, or equipment. Secured area is considered any location where on-site work is performed by Contractor employees. The restricted areas, sensitive information, or equipment consists of everything inside the security fence at the project.
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY (DA)
AR 381-12 (2010) Threat Awareness and Reporting Program
Federal Acquisition Regulation (FAR)
FAR 52.204-9 (2015) Personal Identity Verification of Contractor Personnel
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals having an "I" designation are for information only. The designation following the "G" or "I" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with SECTION 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Anti Terrorism (AT) Level 1; I, SLE iWATCH, CORPS Watch, or See Something, Say Something; I, C
Level 1 OPSEC training; I, C
Pre-Screen Candidates Using E-Verify Program; I, SLE
Biographical Information; G, C
1.3 Biographical Information Submittal
Submit Biographical Information to the COR via email as a password protected pdf file or submitted as one hard copy to the address below for all personnel requiring unescorted access or requiring access to government information systems. See paragraph "ACCESS AND GENERAL PROTECTION/SECURITY POLICY AND PROCEDURES" for additional information and details on items to submit.
District Commander
ATTN: CENWW-EC-C
Walla Walla District Corps of Engineers 201 North Third Avenue Walla Walla, WA 99362-1876
1.4 AT LEVEL 1 TRAINING
All contractor employees, including all associated sub-contractor employees, requiring access to government facilities and controlled access areas shall complete Anti Terrorism (AT) Level 1 awareness training within 30 days after Notice to Proceed, and annually thereafter until project completion. Submit certificates of completion for each employee to the contracting officer representative (COR) or to the contracting officer (if a COR is not assigned), within 5 calendar days after initial completion of training or annual refresher.
The contractor shall retain employee training certificates for the duration of the contract and maintain a current roster. The roster shall contain the names of employees who have completed the training along with their most recent training completion date. The contractor shall update the roster and resubmit to the contracting officer no later than 5 calendar days after completion of refresher training or a new employee completes certification.
AT Level I awareness training can be completed in approximately two (2) hours and is available at the following website:
http://jko.jten.mil/courses/atl1/launch.html
1.5 ACCESS AND GENERAL PROTECTION/SECURITY POLICY AND PROCEDURES
All contractor employees, including all associated sub-contractor employees, shall comply with all applicable facility access and security policies and procedures. Local facility policies and procedures shall be provided by a government representative.
The contractor shall provide all information required for background checks to meet facility access requirements. Background checks will be performed by Walla Walla District Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR 52.204-9, Personal Identity Verification of Contractor Personnel:
http://www.ecfr.gov/cgi-bin/text-idx?rgn=div8&node=48:2.0.1.1.1.2.1.28) as directed by DOD and/or local policy.
For each individual that will be working at this site needing unescorted access, submit a copy of their driver's license to satisfy the information required to conduct the background check. Background check must be approved for an individual before they can access the site.
In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any facility change, the Government may require changes in contractor security matters or processes.
1.6 SUSPICIOUS ACTIVITY REPORTING TRAINING (iWATCH, CORPS Watch, or See Something, Say Something)
The contractor employees, including all associated sub-contractor employees, shall take one of the following trainings on the suspicious activity reporting program; iWATCH, CORPS WATCH, SEE SOMETHING, SAY SOMETHING. These trainings are available on the internet and the links to the training sites are shown below.
This training is to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the security representative. This training shall be completed within 30 calendar days of Notice to Proceed and within 30 calendar days of new employees commencing performance with the results reported to the COR or to the contracting officer (if a COR is not assigned), NLT 5 calendar days after the completion of the training.
a. iWATCH\ Website: http:://www.myarmyonesource.com/familyprogramsandservices/ iwatchprogram/default.aspx
b. CORPS WATCH Website:
http://www.spa.usace.army.mil/Missions/CivilWorks/Recreation/CorpsWatch.aspx
c. SEE SOMETHING, SAY SOMETHING Website: https://www.dhs.gov/see-something-say-something
1.7 CONTRACTS THAT REQUIRE OPSEC TRAINING
All new contractor employees, including all associated sub-contractor employees, will complete Level I OPSEC Training within 30 calendar days of their reporting for duty. Additionally, all employees must complete annual OPSEC awareness training until project completion. The contractor shall submit Level 1 OPSEC training certificates of completion for each affected employee, to the COR or to the contracting officer (if a COR is not assigned), within 5 calendar days after completion of training.
OPSEC awareness training is available at the following website:
https://securityawareness.usalearning.gov/opsec/index.htm or it can be provided by the OPSEC Officer in presentation form which will be documented via memorandum.
1.8 PRE-SCREEN CANDIDATES USING E-VERIFY PROGRAM
The Contractor must pre-screen Candidates using the E-verify Program ( http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system.
Additional time may be required for foreign nationals to pre-screen.
An initial list of verified/eligible Candidates must be provided to the contracting officer, no later than 30 business days after receipt of receipt of Notice to Proceed.
*When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, with the designated Government representative. This Form will be provided to the Contracting Officer and shall become part of the official contract file.
Submit pre-screening results to the COR via email as a password protected pdf file or submitted as one hard copy to the address below:
District Commander
ATTN: CENWW-EC-C
Walla Walla District Corps of Engineers 201 North Third Avenue Walla Walla, WA 99362-1876
1.9 THREAT AWARENESS REPORTING PROGRAM
All new contractor employees, including all associated sub-contractor employees, will complete annual Threat Awareness and Reporting Program (TARP) Training provided by the Army, go to website www.huachuca.army.mil for the training, as required by IAW AR 381-12.
The contractor shall submit certificates of completion for each affected employee or a memorandum for the record, to the COR or to the contracting officer (if a COR is not assigned), within 5 calendar days after completion of training. Authorized web-based TARP training for CAC card holders is available at the following website:
https://www.us.army.mil/suite/page/655474
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
-- End of Section --
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00.00 28
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 RETAINAGE OF PAYMENT
1.2 CLIN 0001 GRATING REPLACEMENT - GRATING SECTIONS 3, 4 and 5
1.3 CLIN 0002 GRATING REPLACEMENT - GRATING SECTION 6
1.4 CLIN 0003 GRATING REPLACEMENT - GRATING SECTION 2A (OPTIONAL)
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
-- End of Section Table of Contents --
SECTION 01 22 00.00 28
MEASUREMENT AND PAYMENT
PART 1 GENERAL
In each instance, the contract price for an item shall constitute full compensation for furnishing all plant, labor, equipment, and materials, and for performing all operations required to complete the work included in the item as herein specified, or as otherwise approved.
1.1 RETAINAGE OF PAYMENT
Retainage in the amount of 10 percent of original contract award amount will be withheld until the final submittals, listed below, have been approved by the Government. The 10 percent retainage for final submittals will be held until such time as the Contractor has earned 90 percent of the original contract value. See SECTION 01 78 00.00 28 "CLOSEOUT SUBMITTALS" for additional information.
a. Final Shop Drawings.
b. Final As-built Drawings.
c. Final Record Drawings.
d. Return of Government Issued Items.
BASE CLINS
1.2 CLIN 0001 GRATING REPLACEMENT - GRATING SECTIONS 3, 4 and 5
Grating Replacement - Grating Sections 3, 4 and 5 will be measured for payment as a complete pay item (JOB). Payment will be made at the lump sum price for CLIN No. 0001, "GRATING REPLACEMENT - GRATING SECTIONS 3, 4 AND 5", which price and payment shall be full compensation for all work required to replace this grating, complete, as specified and approved.
Features included with this item will include, but not be limited to:
a. Remove existing grating
b. Install new grating
c. Remove and dispose of removed grating, appurtenances and debris.
1.3 CLIN 0002 GRATING REPLACEMENT - GRATING SECTION 6
Grating Replacement - Grating Section 6 will be measured for payment as a complete pay item (JOB). Payment will be made at the lump sum price for CLIN No. 0002, "GRATING REPLACEMENT - GRATING SECTION 6", which price and payment shall be full compensation for all work required to replace this grating, as specified and approved. Features included with this item will include, but not be limited to:
a. Remove existing grating
b. Install new grating
c. Remove and dispose of removed grating, appurtenances and debris.
OPTIONAL CLINS
1.4 CLIN 0003 GRATING REPLACEMENT - GRATING SECTION 2A (OPTIONAL)
Grating Replacement - Grating Section 2A will be measured for payment as a complete pay item (JOB). Payment will be made at the lump sum price for CLIN No. 0003, "GRATING REPLACEMENT - GRATING SECTION 2A", which price and payment shall be full compensation for all work required to replace this grating, complete, as specified and approved. Features included with this item will include, but not be limited to:
a. Remove existing grating
b. Install new grating
c. Remove and dispose of removed grating, appurtenances and debris.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
-- End of Section --
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 33 00
SUBMITTAL PROCEDURES
PART 1 GENERAL
1.1 REFERENCES
1.2 DEFINITIONS
1.2.1 Submittal Descriptions (SD)
1.2.2 Reviewing Authority
1.2.2.1 Action Elements for Submittal Review
1.2.3 Work
1.3 SUBMITTAL CLASSIFICATION
1.3.1 Government Approved (G)
1.3.2 Information Only (I)
1.4 CAD FILE REQUIREMENTS
1.4.1 USACE CAD/BIM Technology Center
1.5 PREPARATION
1.5.1 Transmittal Form
1.5.2 Identifying Submittals
1.5.3 Format For Electronic Submittals
1.5.4 Format for SD-02 Shop Drawings
1.5.4.1 Shop Drawing File Numbers
1.5.4.2 Shop Drawing Submittals
1.5.5 Format of SD-03 Product Data and SD-08 Manufacturer's
Instructions
1.5.6 Format of SD-04 Samples
1.5.7 Format of SD-05 Design Data and SD-07 Certificates
1.5.8 Format of SD-06 Test Reports and SD-09 Manufacturer's Field
Reports
1.5.9 Format of SD-01 Preconstruction Submittals and SD-11 Closeout
Submittals
1.6 QUANTITY OF SUBMITTALS
1.6.1 Electronic Copies
1.6.2 Hard Copies (HC)
1.6.2.1 Hard Copy Submittals
1.6.3 Official Receipt of Transmittals
1.6.4 Number of Samples SD-04 Samples
1.6.5 Number of Copies of SD-10 Operation and Maintenance Data
1.7 INFORMATION ONLY SUBMITTALS
1.8 VARIATIONS REQUESTS
1.8.1 Considering Variations
1.8.2 Proposing Variations
1.8.3 Warranting That Variations Are Compatible
1.8.4 Review Schedule Is Modified
1.9 SUBMITTAL REGISTER
1.9.1 Use Of Submittal Register
1.9.2 Contractor Use of Submittal Register
1.9.3 Approving Authority Use of Submittal Register
1.9.4 Contractor Action Code and Action Code
SECTION 01 33 00
1.9.5 Copies Delivered to the Government
1.10 SCHEDULING
1.11 GOVERNMENT APPROVING AUTHORITY
1.11.1 Review Notations
1.12 DISAPPROVED OR REJECTED SUBMITTALS
1.13 APPROVED/ACCEPTED SUBMITTALS
1.14 APPROVED SAMPLES
1.15 WITHHOLDING OF PAYMENT
1.16 STAMPS
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
ATTACHMENTS:
ENG Form 4025-R
Submittal Register
-- End of Section Table of Contents --
SUBMITTAL PROCEDURES
PART 1 GENERAL
The Contracting Officer (KO) may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections. Make certain that each submittal is complete and in sufficient detail to easily determine contract compliance.
a. Use the same units of weights and measures as the contract drawings.
b. Contractor's Quality Control (CQC) System Manager shall check and approve all items prior to submittal and stamp, sign, and date indicating action taken.
c. Clearly identify any proposed variations from the contract requirements.
d. Include drawings; literature (catalog cuts, diagrams, operating charts or curves); test reports; samples; O&M manuals (including parts list); certifications; warranties; and other necessary information.
e. Obtain submittal approval prior to acquiring the covered material or equipment.
1.1 REFERENCES
The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
ERDC/ITL TR-12-1 (2015) A/E/C Graphics Standard, Release 2.0
ERDC/ITL TR-12-6 (2015) A/E/C CAD Standard - Release 6.0
1.2 DEFINITIONS
1.2.1 Submittal Descriptions (SD)
Submittals requirements are specified in the technical sections.
Submittals are identified by Submittal Description (SD) numbers and titles as follows:
SD-01 Preconstruction Submittals
Submittals which are required prior to commencing work on site.
Submittals required prior to the start of the next major phase of the construction on a multi-phase contract. Schedules or tabular list of data or tabular list including location, features, or other pertinent information regarding products, materials, equipment, or components to be used in the work.
Construction Progress Schedule
SD-03 Product Data
Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.
Samples of warranty language when the contract requires extended product warranties.
SD-06 Test Reports
Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. (Unless otherwise specified testing must have been completed within three (3) years of date of contract award for the project.)
Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.
Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.
Investigation reports.
Daily logs and checklists.
Final acceptance test and operational test procedure.
SD-07 Certificates
Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that product, system or material meets specification requirements. Must be dated after award of project contract and clearly name the project.
Document required of Contractor, or of a manufacturer, supplier, installer or subcontractor through Contractor, the purpose of which is to further quality of orderly progression of a portion of the work by documenting procedures, acceptability of methods or personnel qualifications.
Confined space entry permits.
Text of posted operating instructions.
SD-11 Closeout Submittals
Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.
Special requirements necessary to properly close out a construction contract. For example, Record Drawings and as-built drawings. Also, submittal requirements necessary to properly close out a major phase of construction on a multi-phase contract.
1.2.2 Reviewing Authority
Office or designated person to review submittal.
1.2.2.1 Action Elements for Submittal Review
C Engineering & Construction Division, Construction Branch ECC Operation's Division, Environmental Compliance Coordinator ST Engineering & Construction Division, Structural Design SO Safety Office SLE Security Law Enforcement Officer EOC Engineering Design, Project Operations and Construction
1.2.3 Work
As used in this SECTION, on- and off-site construction required by contract documents, including labor necessary to produce submittals, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction.
1.3 SUBMITTAL CLASSIFICATION
Submittals are classified as follows:
G - This code is for submittals requiring government approval that were listed in the original government-generated specs
I - This code is used for both government-generated submittals and contractor-generated submittals. This code is reserved for submittals that don't require approval, e.g. test reports.
1.3.1 Government Approved (G)
Government approval is required for extensions of design, critical materials, variations, equipment whose compatibility with the entire system must be checked, and other items as designated by the KO. Government approval is required for any variations from the Solicitation or Accepted Proposal and other items as designated by the KO. Within the terms of the Contract Clause entitled "Specifications and Drawings for Construction," they are considered to be "shop drawings."
1.3.2 Information Only (I)
Submittals not requiring Government approval will be for information only.
1.4 CAD FILE REQUIREMENTS
The following applies to all CAD File submittals for this Contract, unless otherwise noted:
a. Furnish CAD files in the latest version of Bentley DGN format, for all CAD Files submitted by the Contractor in performance of this contract.
b. Unless otherwise noted, all CAD Files shall meet A/E/C CAD and Graphic Standards, as follows:
1. Compliant with the A/E/C CAD Standard ERDC/ITL TR-12-6, A/E/C Graphics Standard ERDC/ITL TR-12-1 and Section 01 33 00 SUBMITTAL
PROCEDURES.
c. CAD Files shall have presentation graphics which can be edited by Bentley software (with the exception of photographs). Presentation graphics typically consist of drawing elements such as lines, arcs, shapes, text, and their attributes (e.g., color, width, line style).
d. If CAD files are developed in a format other than the specified Bentley software, furnish the following:
1. The original CAD files in their native file format.
2. The converted CAD files in Bentley DGN format, in compliance with all specified CAD file requirements.
e. In addition to CAD files, submit an ADOBE .pdf of each CAD File.
The pdfs and the CAD files shall be identical.
f. Submit files using the Safe Access File Exchange website as directed by the Contracting Officer.
1.4.1 USACE CAD/BIM Technology Center
The USACE CAD/BIM Technology Center hosts all standard content for USACE.
This content can be accessed through the CAD/BIM Technology Center website, https://cadbimcenter.erdc.dren.mil.
1.5 PREPARATION
1.5.1 Transmittal Form
The attached sample transmittal form (ENG Form 4025-R) is in RMS and shall be completed in RMS 3.0 Contractor Mode. Use ENG Form 4025-R for submitting both Government approved and information only submittals in accordance with the instructions on the reverse side of the form.
Properly complete this form by filling out all the heading blank spaces and identifying each item submitted. Exercise special care to ensure proper listing of the specification paragraph and sheet number of the contract drawings pertinent to the data submitted for each item.
1.5.2 Identifying Submittals
When submittals are provided by either the Prime Contractor or subcontractor, the Prime Contractor is responsible to prepare, review and stamp with Contractor's approval all specified submittals prior to submitting for Government approval.
Identify submittals, except sample installations and sample panels, with the following information permanently adhered to or noted on each separate component of each submittal and noted on transmittal form. Mark each copy of each submittal identically, with the following:
a. Project title, location, and date.
b. Contract number.
c. Date of the drawings and revisions.
d. Name, address, and telephone number of subcontractor, supplier, manufacturer and any other second tier Contractor associated with submittal.
e. Section number of the specification section by which submittal is required.
f. Submittal description (SD) number of each component of submittal.
g. When a resubmission, add a number suffix on submittal description, for example, submittal 18 would become 18.1, to indicate the resubmission.
h. Product identification and location in project.
The sequence of submission of drawings shall be such that all information is available for checking each drawing when it is received. Contract number and project shall be shown directly above the revision space on all drawings submitted. Drawing details and notes shall be of such quality and clarity and of sufficient definition and line weight as to permit sharp and totally legible scanning. All items shall be adequately identified to show where they will be used, and shall be referenced to applicable contract drawings and specification section.
All shop drawings submitted on a single transmittal (ENG form 4025-R) shall pertain to only one (1) specification section. Computed weights of all items shall be indicated on the shop drawings. Where drawings are submitted for either (1) assemblies consisting of more than one (1) piece of equipment, or (2) systems consisting of numerous components dependent one on the other for matching or compatible characteristics, complete information shall be submitted on all such related components at the same time.
1.5.3 Format For Electronic Submittals
The PDF file name of all submittals shall include the contract and transmittal number.
a. example: 17-C-0005_Trans 01 35 29.10 28-1 Item 1, 5
b. re-submittal example: 17-C-0005_Trans 01 35 29.10 28-1.1 Item 1, 5
All electronic submittals shall be in color and digitally searchable. All pages in the file shall be oriented so that no rotation or manipulation to view is needed.
1.5.4 Format for SD-02 Shop Drawings
All shop drawings prepared by the Contractor for this contract shall be formatted to American National Standards Institute (ANSI D).
a. All shop drawings shall have a title block and a revision block.
b. Title block shall include project title, sheet description, sheet number, contract number and issue date.
c. Revision block shall contain revision mark, revision description, date of revision.
d. Each Sheet shall have a unique number. See paragraph "Shop Drawing File Numbers" below.
e. Each sheet shall have the Contractor Firm name on it.
f. CAD requirements for Shop Drawings include the following:
1. CAD file(s) meeting requirements of paragraph "CAD File Requirements" in this SECTION.
2. An Adobe .pdf copy of the corresponding CAD file(s). The pdfs and CAD files shall be identical.
3. Shop drawing format does not need to comply with A/E/C CAD and Graphic Standards.
1.5.4.1 Shop Drawing File Numbers
All Shop Drawings shall have a unique File Number placed in the Title Block. A specific File Number format is only required for Shop Drawings referenced from a Contract Drawing. In this case use one of the following formats for File Numbers, and coordinate Final Shop Drawing File Numbers with the Contracting Officer prior to submitting drawings:
a. The File Number on the Contract Drawing, appended with a unique Shop Drawing Sheet Identification number.
b. The Contract Number appended with a unique Shop Drawing Sheet Identification number, or similar.
1.5.4.2 Shop Drawing Submittals
Shop Drawing Submittals are required as follows:
1. As shown and specified in the plans and specifications during design and Construction.
2. As specified in SECTION 01 78 00.00 28 CLOSEOUT SUBMITTALS, paragraph FINAL SHOP DRAWINGS.
1.5.5 Format of SD-03 Product Data and SD-08 Manufacturer's Instructions
a. Present product data submittals for each section as required.
Include table of contents, listing page and catalog item numbers for product…