W68SBV31912520
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
TITLE: Dw orshak Roadw ay Maintenance
The purpose of this amendment is to add the technical specif ications and to remove the Special Contract Requirement titled "Contractor Supply and Use of Electronic Softw are for Processing Davis-Bacon Act Certif ied Labor Payrolls," and to update the Wage Determination.
Quote due date of September 12, 2013 at 3:00 p.m. remains unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
1 12
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 30-Aug-2013
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912EF-13-Q-0198
X 9B. DATED (SEE ITEM 11)
29-Aug-2013
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
30-Aug-2013
CODE
USAED, WALLA WALLA - CONTRACTING DIV.
JANI C. LONG
201 N. THIRD AVENUE
WALLA WALLA WA 99362-1876
W912EF 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:509-527-7209TEL:
JANI C LONG / CONTRACTING OFFICER
W912EF-13-Q-0198
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
The following has been modified:
The solicitation is 100 percent set-aside for small business concerns.
Award will be made on the basis of lowest evaluated total price.
Quotation is due no later than 3:00pm, local time, on Thursday, 12 September 2013.
(This instruction overrides the statement in Block Number 10 of Standard Form 18.)
Quotation may be emailed (preferred) to: Caroline.B.Mueller@usace.army.mil Quotation may be hand-delivered or mailed to: US Army Corps of Engineers, Attention: Contracting Division, Caroline Mueller, 201 N. Third Avenue, Walla Walla, WA 99362.
The resulting purchase order will be FOB Destination. Quoted price must include all shipping to destination and all Federal, State, and local taxes. Inspection and acceptance will be at destination.
All work shall be in accordance with the specifications, attachments, and all other terms and conditions herein.
This work is considered a construction project in excess of $2,000. The Davis Bacon Act applies. No laborer or mechanic employed directly upon the site of the work shall receive less than the prevailing wage rates as determined by the Secretary of Labor. Wage Decision Number ID130068, dated 08/30/2013, is attached hereto and incorporated herein.
WAGE DETERMINATION
General Decision Number: ID130068 08/30/2013 ID68
Superseded General Decision Number: ID20120073
State: Idaho
Construction Type: Heavy HEAVY CONSTRUCTION, Including water and sewer line construction and heavy construction projects on treatment plants and industrial (power plants, manufacturing plants, processing plants, etc.) sites
Counties: Benewah, Clearwater and Latah Counties in Idaho.
Modification Number Publication Date 0 01/04/2013 1 02/22/2013 2 04/05/2013 3 06/21/2013 4 07/26/2013 5 08/30/2013
CARP0001-045 06/01/2012
mailto:Caroline.B.Mueller@usace.army.mil
Rates Fringes
CARPENTER (Form Work Only).......$ 30.30 12.62
ELEC0073-011 07/01/2013
Rates Fringes
ELECTRICIAN......................$ 29.07 16.15
ENGI0370-035 06/01/2012
Rates Fringes
POWER EQUIPMENT OPERATOR:
Backhoe (45,000 gw & under), Cranes (25 tons & under), Drill (8 in bit and over
GROUP 5....................$ 26.46 12.60
Backhoe (45,000-110,000 gw), Crane (25-45 tons), Bulldozer (D-6 and over), Grader/Blade, Front-End Loader(4-8 yds), Paver, Scrapers (all)
GROUP 6....................$ 26.74 12.60
Backhoe (over 110,000 gw), Cranes (45-85 tons), Heavy Duty Mechanic, Front End Loader (8-10 yds)
GROUP 7....................$ 27.01 12.60
Bulldozer (up to D-6)
GROUP 3....................$ 26.14 12.60
Cranes (85 tons & over), Front End Loader (10 yds & over)
GROUP 8....................$ 28.11 12.60
Front End Loader (under 4 yds)
GROUP 4....................$ 26.30 12.60
Rollers (all)
GROUP 1....................$ 25.21 12.60
ZONE PAY:
ZONE CENTERS: SPOKANE, PASCO, LEWISTON
ZONE 1: 0-45 Miles: Free ZONE 2: 45 Miles & Over: $2.00
BOOM PAY (ALL CRANES):
(A): 180'-250': $.50 over scale (B): over 250': $.80 over scale
IRON0014-006 07/01/2013
Rates Fringes
IRONWORKER, REINFORCING AND
STRUCTURAL.......................$ 31.60 21.35
LABO0238-028 02/01/2012
Rates Fringes
LABORER (PIPELINE ONLY)
COMMON......................$ 24.69 9.95
LABO0238-031 06/01/2013
Rates Fringes
LABORER
Asphalt Includes Raker, Shoveler, Spreader, and Distributor Group 4....................$ 24.34 10.65 Flagger Group 1A...................$ 22.70 10.65
Zone Differential (Add to Zone 1 rates): Zone 2 - $2.00
BASE POINTS: Spokane
Zone 1: 0-45 radius miles from the main post office.
Zone 2: 45 radius miles and over from the main post office
PLAS0072-003 06/01/2013
BENEWAH, BONNER, BOUNDARY, CLEARWATER, IDAHO (NORTH OF THE 46TH
PARALLEL), KOOTENAI, LATAH, LEWIS AND NEZ PERCE AND SHOSHONE
COUNTIES
ZONE 1:
Rates Fringes
CEMENT MASON/CONCRETE FINISHER...$ 26.01 12.14
Zone Differential (Add to Zone 1 rate): Zone 2 - $2.00
BASE POINTS: Spokane, Pasco, Lewiston, Wenatchee
Zone 1: 0-45 radius miles from the main post office
Zone 2: Over 45 radius miles from the main post office
PLUM0044-015 06/01/2012
Rates Fringes
PLUMBER
Zone 1......................$ 31.41 15.67
* TEAM0690-002 01/01/2013
Rates Fringes
TRUCK DRIVER (DUMP)
6 yds and under.............$ 22.94 14.44 over 6 yds..................$ 23.38 14.44
SUID2010-058 08/08/2012
Rates Fringes
CARPENTER, Excludes Form Work....$ 29.92 5.20
LABORER: Common or General......$ 23.75 8.98
LABORER: Landscape..............$ 22.13 11.13
LABORER: Pipelayer..............$ 17.67 7.26
OPERATOR: Bobcat/Skid Steer/Skid Loader................$ 20.97 0.00
OPERATOR: Concrete Batch Plant............................$ 24.94 11.96
OPERATOR: Forklift..............$ 21.20 0.00
TRUCK DRIVER: Lowboy Truck......$ 21.00 12.10
TRUCK DRIVER: Water Truck.......$ 24.48 11.67
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).
The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is union or non-union.
Union Identifiers
An identifier enclosed in dotted lines beginning with characters other than "SU" denotes that the union classification and rate have found to be prevailing for that classification. Example: PLUM0198-005 07/01/2011. The first four letters , PLUM, indicate the international union and the four-digit number, 0198, that follows indicates the local union number or district council number where applicable , i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination.
The date, 07/01/2011, following these characters is the effective date of the most current negotiated rate/collective bargaining agreement which would be July 1, 2011 in the above example.
Union prevailing wage rates will be updated to reflect any changes in the collective bargaining agreements governing the rates.
0000/9999: weighted union wage rates will be published annually each January.
Non-Union Identifiers
Classifications listed under an "SU" identifier were derived from survey data by computing average rates and are not union rates; however, the data used in computing these rates may include both union and non-union data. Example: SULA2004-007 5/13/2010. SU indicates the rates are not union majority rates, LA indicates the State of Louisiana; 2004 is the year of the survey; and 007 is an internal number used in producing the wage determination. A 1993 or later date, 5/13/2010, indicates the classifications and rates under that identifier were issued as a General Wage Determination on that date.
Survey wage rates will remain in effect and will not change until a new survey is conducted.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)
and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISION
(End of Summary of Changes)
Dworshak Roadway Maintenance W912EF-13-Q-0198
SECTION 32 15 01 Page 1
SECTION 32 15 01
DWORSHAK ROADWAY MAINTENANCE
PART 1 GENERAL
1.1 DESCRIPTION OF WORK
This Section specifies requirements for performing roadway maintenance on roads located in the vicinity of Grandad Bridge which crosses Dworshak Dam reservoir approximately 50 miles upstream from the dam. The work includes grading and compacting of 8.6 miles of gravel roadway, cleaning of 1/2 mile of roadway ditch, cleaning of five (5) culverts located along Grandad Bridge Road and one (1) located on Benton Creek Road, replacement of three
(3) culverts, and relocation of 18 boulders currently located in the area adjacent to Grandad Bridge and Breakfast Creek Roads.
1.2 LOCATION OF WORK ACTIVITIES
Work activities to be performed are shown in Attachment 1 (Map Package) at the end of this specification. Work Activities are sequentially numbered and shown at the correct location for the work. Each work activity will be field marked by the Government and will be indentified in a pre-work site visit.
1.3 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE) EM 385-1-1 (2008; Errata 1-2010;
Changes 1-3 2010; Changes 4-6 2011) Safety and Health Requirements Manual
Website for the safety manual is:
http://publications.usace.army.mil/publications/eng-manuals/EM_385-1- 1_languages/EM_385-1-1_English_2008/toc.html
1.4 SUBMITTALS
The Contractor shall bring all pre-work submittals to the Pre-Work meeting.
The Pre-Work meeting shall take place at the Dworshak Resource Maintenance Building, 1682 A Road, Ahsahka, Idaho. Contractor and Government staff will review and annotate changes to submittals at the meeting. All required changes shall be made prior to commencement of on-site work activities.
Required submittals are as follows:
PRE-WORK SUBMITTALS
Project Schedule Equipment List
Accident Prevention Plan
Activity Hazards Analysis http://publications.usace.army.mil/publications/eng-manuals/EM_385-1-1_languages http://publications.usace.army.mil/publications/eng-manuals/EM_385-1-1_languages
SECTION 32 15 01 Page 2
Traffic Control Plan
SSHO Personnel Qualifications
1.5 PRE-WORK MEETING
The Contractor shall meet with the Contracting Officer's Representative (COR) and the Government's Quality Assurance Representative (QAR) at least five working days prior to the beginning of work. The date of the meeting shall be coordinated with the COR. The purpose of this meeting is to discuss and develop general and technical aspects of the work, including safety, scheduling of work, and environmental protection provisions of the contract.
1.6 SAFETY
1.6.1 Accident Prevention Plan
The Contractor shall submit an Accident Prevention Plan for the COR's review and acceptance. Requirements and guidelines for preparation of accident prevention plans are specified in EM 385-1-1, paragraph 01.A.11 and Appendix A.
1.6.2 Activity Hazards Analysis
The Contractor shall prepare an Activity Hazards Analysis (AHA) for each work activity in accordance with paragraph 01.A.13 of EM 385-1-1. A sample AHA form is attached to the end of this section (see Attachment 2, Sample Activity Hazards Analysis).
1.6.3 Site Safety and Health Officer (SSHO)
Site Safety and Health Officer (SSHO) shall be employed by the Prime Contractor and shall be at the work site at all times to perform safety and occupational health management, surveillance, inspections, and safety enforcement for the Contractor. The SSHO can be assigned other duties on this project. The SSHO shall have at least the following qualifications:
Level 2:
* A minimum of three (3) years safety work on similar project.
* 30-hour OSHA construction safety class or equivalent within last three (3) years.
* Competent person training as needed.
1.6.4 Subcontractors
Compliance with the accident prevention and safety requirements by subcontractors will be the responsibility of the Contractor.
1.6.5 Equipment
All vehicles (except pickups and personal vehicles) and machinery used to perform the work shall be equipped with warning devices such as 4-way or top mounted flashing amber lights or rotary beacons. The warning devices shall be turned on whenever equipment is being used to perform the work.
All self-propelled equipment in excess of 8000 pounds shall be equipped with backup alarms which shall be turned on whenever the equipment is
SECTION 32 15 01 Page 3 being used to perform the work. When not in operation, vehicles and equipment shall be parked off the traveled roadway at approved locations to minimize interference with the normal use of the road. Tracked vehicles shall not be operated on paved surfaces without approval of the QAR. The Contractor shall provide protection for paved surfaces whenever tracked equipment is operated on paved surfaces. Equipment shall not be operated on project lands outside the roadway without written approval of the QAR.
1.7 CONTRACTOR QUALITY CONTROL
The Contractor shall perform Quality Control for all work performed under this contract. Contractor Quality Control (CQC) is the means by which the Contractor ensures that the services provided, to include that of subcontractors and suppliers, complies with the requirements of the contract. The controls shall be adequate to cover all work performed, and shall be keyed to the proposed work sequence.
1.7.1 Organization
The Contractor shall identify one primary individual and one backup within its organization who will be responsible for overall management of CQC and who will have the authority to act in all CQC matters for the Contractor, including stoppage of work and re-performance of non-complying work. The CQC Manager shall have at least three years experience on similar projects and shall be on-site at all times during performance of the work.
1.7.2 Documentation
The Contractor shall maintain current records of quality control operations, activities, and tests performed, including the work of subcontractors and suppliers. These records shall be prepared on form WWD- QCR PO, Daily Construction Quality Control Report (see Attachment 3, Sample Quality Control Report), or accepted equivalent,, and shall include factual evidence that required quality control activities and/or tests have been performed, including but not limited to the following:
a. Contractor/subcontractor and their area of responsibility.
b. Operating plant/equipment with hours worked, idle, or down for repair.
c. Test and/or control activities performed with results and references to specifications/plan requirements. List deficiencies noted along with corrective action.
d. Job safety evaluations stating what was checked, results, and instructions or corrective actions.
e. List instructions given/received and conflicts in plans and/or specifications.
f. Contractor's verification statement.
g. Work performed today, giving location, description, and by whom.
h. Material received with statement as to its acceptability and storage.
SECTION 32 15 01 Page 4
i. Identify submittals reviewed, with contract reference, by whom, and action taken.
j. Description of trades working on the project; the number of personnel working; weather conditions encountered; and any delays encountered.
k. Description of conforming and deficient features.
l. Contractor’s statement(s) that equipment and materials incorporated in the work and workmanship comply with the contract.
These records shall be prepared daily on each day work is performed, and the original and one copy shall be furnished to the Government not later than each Monday for the seven days preceding. Reports need not be submitted for days on which no work is performed. Reports shall include copies of reports prepared by all subordinate quality control personnel and shall be signed and dated by the CQC system manager.
1.7.3 Notification of Noncompliance
The Contracting Officer will notify the Contractor of any detected noncompliance with the foregoing requirements. The Contractor shall, after receipt of such notice, immediately take corrective action. Such notice, when delivered to the Contractor at the site of the work, shall be deemed sufficient for the purpose of notification. If the Contractor fails or refuses to comply promptly, the Contracting Officer may issue an order suspending or stopping all or part of the work until satisfactory corrective action has been taken.
1.8 TRAFFIC CONTROL AND PUBLIC ACCESS
The roads being worked on under this contract are open to the public and shall remain open during performance of the work to the maximum extent possible. During the work, the Contractor shall limit access to the immediate vicinity of the equipment by placing barricades and/or signage to keep the public at a safe distance from the work. When required for performance of the work (such as culvert replacement), the Contractor may close the roadway for up to four (4) hours at a time. Closures shall be scheduled a minimum of 48 hours in advance with the COR to allow for public notification of the closure. The Contractor shall remain vigilant during the work and shall take measures to ensure the public's safety and shall notify the COR of all incidences of unauthorized public access.
The Contractor shall prepare a Traffic Control Plan in compliance with the Manual of Uniform Traffic Control Devices (MUTCD) and shall implement the plan including traffic signs, barricades, and other traffic control devices at all times when on site work is being performed.
1.9 PROTECTION AND RESTORATION OF EXISTING FACILITIES
The Contractor shall take precautions to prevent damage to existing facilities while performing work under this contract. Upon completion of the work, all the existing facilities not included as a portion of the work shall be left in a condition better than or equal to the condition existing at time of contract award. Costs for maintenance, repair and
SECTION 32 15 01 Page 5 restoration of the facilities shall be considered incidental to and included in the price of the work.
1.10 PRE-WORK AND POST WORK SURVEYS
The Contractor shall conduct a pre-work survey and a post-work survey, of the work site. The surveys shall be performed in the presence of the COR or QAR. The surveys shall be documented with digital photographs and descriptive narrative reports with emphasis on identifying any damage to the facilities. A color copy of the survey photographs and a narrative report shall be submitted to the COR.
1.11 ENVIRONMENTAL PROTECTION
1.11.1 General
Environmental protection is defined as the retention of the environment in its natural or preconstruction state to the greatest possible extent during project operations and to restore or enhance the natural or preconstruction appearance in its final condition. In order to prevent environmental degradation, the Contractor and subcontractors in the performance of this contract shall comply with all applicable Federal, State, and local laws and regulations.
1.11.2 Protection of Land Resources
The land resources within the project boundaries and outside the limits of work areas/zones performed under this contract shall be preserved in their present condition or be restored to a condition after completion of work that will appear to be natural and not detract from the appearance of the project. The Contractor shall limit activities to the areas indicated.
1.11.3 Protection of Water Resources
The Contractor shall not pollute streams, lakes, or reservoirs with fuels, oils, bitumens, concrete materials, calcium chloride, acids, herbicides, or other harmful materials. The Contractor shall comply with all applicable Federal, State, county, and local laws and regulations concerning pollution of surface or subsurface waters.
1.11.4 Erosion Control
When performing road grading, ditch cleaning, culvert cleaning, and culvert replacement, the Contractor shall use best management practices to prevent sediment from entering waterways. Active controls such as silt fences or other approved means shall be installed as needed near waterways for the duration of each work activity.
1.11.5 Spillage
Special measures shall be taken to prevent chemicals, fuels, oils, greases, bituminous materials, and waste washings from entering surface and subsurface waters. All prevention/cleanup materials shall comply with all Federal, State, county, and local laws and regulations. The Contractor shall provide and utilize the following prevention/cleanup materials:
a. Fuel dispensing vehicles shall carry a tanker fueling berm spill kit
SECTION 32 15 01 Page 6 on board at all times.
b. An emergency spill response kit shall be carried on board each piece of equipment performing work.
c. Storage of more than 200 gallons of petroleum products at the work site shall be in conformance with the State of Idaho Forest Practices Act (IDAPA 20.02.01).
d. Oil from crankcases or gear boxes, equipment waste, spilled or excess fuel shall all be placed in containers and removed from the work site and disposed in accordance with Federal, State and local laws.
e. Fuels and/or oil storage containers greater than 200 gallons shall be sited within a constructed dike of sufficient size to contain 125% of the volume of petroleum products stored in the tanks. Containment areas shall be lined with an impermeable membrane.
f. Storage areas shall be located more than 300 feet from any existing stream courses. Fueling of equipment shall be done in a manner to eliminate potential spills.
g. Transfer trucks shall be limited to no more than 200 gallons.
Fueling of equipment shall take place a minimum of 300 feet from the Ordinary High Water Mark of any stream course or other body of water.
If this requirement cannot be met, a written spill plan must be submitted and accepted by the QAR.
h. All spills shall be reported to the COR as soon as practicable.
Spills over 25 gallons shall also be reported to the Idaho Department of Environmental Quality.
1.11.6 NOXIOUS WEED CONTROL
In order to prevent the potential spread of noxious weeds into work areas, the Contractor shall clean all maintenance equipment prior to entry to the work area. This cleaning shall remove all dirt and plant parts and material that could carry noxious weed seeds into the work area. Only maintenance equipment so cleaned and inspected by the COR or QAR will be allowed to operate within the work area. All subsequent move-ins of construction equipment shall be treated in the same manner as initial move-in. Prior to initial move-in, and all subsequent move-ins, the Contractor shall make all maintenance equipment available for inspection by the COR or QAR at an agreed upon location. The Contractor shall give the COR or QAR at least 24 hours advance notification when equipment is ready for inspection. Pickup trucks and personal vehicles will not be included in this requirement.
1.11.7 Disposal
Disposal of any materials, wastes, effluents, trash, garbage, oil, grease, chemicals, etc., in areas adjacent to streams will not be permitted. If any waste material is dumped in unauthorized areas, the Contractor shall remove the material and restore the area to the original condition before being disturbed. If necessary, contaminated ground shall be excavated, disposed of in accordance with Federal, State, county, and local laws and regulations, and replaced with suitable fill material, compacted and
SECTION 32 15 01 Page 7 finished with topsoil and planted as required to re-establish vegetation.
The legal removal and disposal of any of the above materials shall be the responsibility of the Contractor.
1.11.8 Protection of Fish and Wildlife
The Contractor shall at all times perform all work and take such steps required to minimize interference with or disturbance to fish and wildlife. The Contractor will not be permitted to alter waterflows or otherwise disturb native habitat adjacent to the project work areas/zones which, in the opinion of the Contracting Officer, are critical to fish or wildlife.
1.12 FIRE CONTROL
1.12.1 Responsibility for Fires
The Contractor shall be responsible for all Contractor-caused fires. The Contractor shall immediately extinguish all fires on or in the vicinity of the project which are caused by Contractor's employees or equipment, whether set directly or indirectly as a result of Contractor operations.
The Contractor may be held liable for all damages and costs of additional labor, subsistence, equipment, supplies, and transportation resulting from fires set or caused by the Contractor's employees or from contract operations.
1.12.2 Fire Protection Requirements
At all times during the closed fire season period, as specified by Idaho State law, the Contractor shall comply with each of the following provisions to the extent applicable to his operation under the contract.
1.12.2.1 Fire Extinguishers and Tools on Mobile or Stationary Equipment
Each unit of powered equipment used to perform work under this contract, including automobiles, trucks, tractors, etc., shall be equipped with serviceable tools and fire extinguishers as follows:
a. One (1) fire extinguisher, dry chemical type of not less than 2-1/2 pound capacity with 4 BC or higher rating.
b. One (1) shovel.
c. One (1) ax, two (2) pounds or over, 26-inch minimum length, or one
(1) Pulaski.
d. One (1) water container (at least 1-gallon capacity), not required with stationary equipment.
1.12.2.2 Spark Arresters
Each internal combustion engine shall be provided with a spark arrester or spark arresting device.
1.12.2.3 Smoking
Smoking is not permitted within the contract area except on surfaced or
SECTION 32 15 01 Page 8 dirt roads, within closed vehicles, in camps.
1.12.2.4 Storage of Petroleum and Other Highly Flammable Products
Gasoline, oil, grease, or other highly flammable material shall be stored either in a separate building used exclusively for such storage, at a site where all combustible debris and vegetation is cleared away within a radius of 25 feet or in a vehicle that is designated and placarded in accordance with Idaho state and federal laws for such use. Fire extinguishers and/or sand barrels may be required at such locations specified by the COR or QAR when unusually hazardous conditions exist.
1.12.2.5 Welding
Welding or use of cutting torches will be permitted only in areas that have been cleared or are free of all flammable material. Flammable debris and vegetation shall be removed from within a minimum of 10 feet radius of all welding and cutting torch operations. A shovel and a 5-gallon container of water shall be available for immediate use in the event of a fire start.
1.13 SANITATION FACILITIES
The Contractor may use the Government's restrooms located at Grandad Campground during performance of the work or may provide portable sanitation facilities at the work site as required by EM-385-1-1.
1.14 CLEANUP AND DISPOSAL OF WASTES
The Contractor shall perform daily cleanup and legally dispose of all garbage, rubbish, and solid or liquid wastes generated from its work activities and overnight camping if applicable. The project work site and campgrounds, if used, shall be left neat and clean to the satisfaction of the QAR at completion of the work.
1.15 USE OF GOVERNMENT CAMPGROUNDS
Due to the remote location of this work, the Contractor may use Grandad Campground or mini camps located on the reservoir on a space available basis. Alternatively, an open space along the roadway, approximately 1/2 mile from Grandad Campground may be used by the Contractor for parking camp trailers. The Contractor shall apply for a special use permit from the Dworshak Natural Resources Staff for use of this alternative camp space.
1.16 MEASUREMENT AND PAYMENT
In each instance, the contract price for an item shall constitute full compensation for furnishing all plant, labor, equipment, and materials, and for performing all operations required to complete the work included in the item as herein specified, or as otherwise approved.
1.16.1 Roadway Grading and Compaction
Grading and compacting of roads will be measured for payment as a complete job. Payment will be made at the lump sum (LS) price for CLIN 0001, "Roadway Grading and Compaction," which price and payment shall be full compensation
SECTION 32 15 01 Page 9 for all work required to grade and compact roads, complete, as specified and approved.
1.16.2 Drainage Ditch and Culvert Maintenance
Drainage ditch and culvert maintenance will be measured for payment as a complete job. Payment will be made at the lump sum (LS) price for CLIN 0002, "Drainage Ditch and Culvert Maintenance," which price and payment shall be full compensation for all work required to perform maintenance on roadway ditches and culverts, complete, as specified and approved.
1.16.3 Culvert Replacement
Replacement of existing culverts will be measured for payment as a complete job. Payment will be made at the lump sum (LS) price for CLIN 0003, "Culvert Replacement," which price and payment shall be full compensation for all work required to replace existing culverts including disposal of old culvert pipe, complete, as specified and approved.
1.16.4 Boulder Relocation
Relocation of boulders will be measured for payment as a complete job.
Payment will be made at the lump sum (LS) price for CLIN 0004, "Boulder Relocation," which price and payment shall be full compensation for all work required to relocate existing boulders, complete, as specified and approved.
PART 2 PRODUCTS
2.1 PIPE FOR CULVERTS
Pipe for culverts shall be corrugated steel pipe meeting the requirements of ASTM A760/A760M, zinc or aluminum (Type 2) coated pipe and shall be Type I pipe with annular or helical 2-2/3 by 1/2 inch corrugations.
2.2 GRAVEL
Gravel for use in culvert replacement may be from the Government-furnished stockpile located approximately 1/2 mile east of the junction of Breakfast Creek and Camp X roads. This gravel will be provided at no cost to the contractor.
2.3 ROCK FOR SPLASHPADS
Rock for constructing splashpads shall be 6-inch dense, angular rock.
2.4 GRASS SEED
Grass seed for use in culvert replacement will be Government-furnished and will be delivered to the Contractor at the work site.
2.5 BOULDERS
Eighteen existing 3-foot diameter boulders for relocation by the Contractor are currently located at Sites 8 and 9, as indicated in Attachment 1, Map Package.
2.6 WATER
SECTION 32 15 01 Page 10
Water for use in compacting the roadway may be obtained from two sites identified by the Government. One site will be the Grandad Boat Ramp. The other site is along the Camp X Road as identified in Attachment 1, Map Package. The Contractor shall provide its own pumping facilities to fill water trucks. Contractor’s pumping equipment must have fish screens in place.
PART 3 EXECUTION
3.1 ROADWAY GRADING AND COMPACTION
3.1.1 Roads to be Graded
The Contractor shall perform maintenance grading for approximately
8.6 miles of road in the vicinity of Grandad Campground as shown on the attached maps (see Attachment 1, Map Package) and as listed in TABLE 1.
TABLE 1
ROAD NAME
LENGTH
(miles)
ROADWAY WIDTH
(feet)shoulder to shoulder
Grandad Bridge Road 1.80 20
Grandad Campground Road 0.50 23
Breakfast Creek Road 3.40 20
Camp X Road 1.10 18
Silver Creek Road 1.80 18
3.1.2 Grading Operations
The Contractor shall perform roadway maintenance grading for the roads specified to produce a finished surface that is smooth, tightly compacted, and without segregation of the surface gravels. Grading on graveled roads shall be performed to minimize disturbance to the subgrade, and to prevent loss of surface gravels in ditches or over the road shoulders. Grading of un-graveled roads shall be performed so that no base material is lost.
Surface material shall be graded commencing at the outside edges of the roadway and proceeding to the centerline creating a berm which shall then be spread evenly over the roadway being careful to prevent segregation of gravels. If surface gravels become segregated, additional grading and mixing will be required to produce an unsegregated surface. Grading operations shall not undercut road backslopes at roadway sections without ditches.
3.1.3 Repairs and Shaping
3.1.3.1 Ruts, Chuckholes, Washboards, and Washes
The Contractor shall repair ruts, chuckholes, washboards, and washes in
SECTION 32 15 01 Page 11 the road surface by scarifying or cutting to the bottom of such defects to provide for uniform compaction of roadbed material. Large rock or organic material (as defined in section 3.1.6 below) removed from drainage facilities during the cleaning process shall not be used as fill. High blading, or any method which merely fills depressions with loose material, does not eliminate the defect or provide for uniform compaction, and is therefore not acceptable.
3.1.3.2 Settlement Areas
The Contractor shall repair sections of the roadway that have settled by grading the roadbed at each end of the settled area to provide a smooth transition down into and back out of the settled area. The Contractor will not be required to import fill material to repair settled areas.
3.1.3.3 Drainage Dips
The Contractor shall clean existing drainage dips and restore the outslope grade to equal or exceed the cross slope of the adjacent roadway.
3.1.3.4 Insloping/Outsloping (Crowning)
Sections of roads constructed without a roadside ditch shall be uniformly insloped or outsloped the entire width of the roadbed (i.e. crowning). The inslope or outslope grade shall be a minimum of 2% and a maximum of 6%.
The existing roadway cross slopes are within this range and will not require substantial grading to change the cross slopes.
3.1.4 Soil Moisture
Grading operations shall only be conducted when soil moisture is within an acceptable range for dust control and compaction of the roadway. At the beginning of each work day when grading operations will be conducted, the Contractor and the QAR shall meet to determine if soil moisture is within the acceptable range for the section of roadway to be graded. If additional moisture is required, the amount of water to be added will be determined and agreed upon prior to commencement of work that day.
Throughout the work day, if sufficient drying occurs, additional water shall be applied to the roadway to maintain acceptable soil moisture.
3.1.5 Finishing
At the completion of grading operations for each section of roadway, the road surface shall be smooth, tightly compacted, with appropriate cross slope for drainage, free of hollows, depressions, or projections above the road surface, and no berms or ridges shall remain. Work shall be sequenced so that ditch cleaning, culvert cleaning, or culvert replacement will not damage the finished surface.
3.1.6 Compaction
Completed sections will be compacted using a self-propelled vibratory roller compactor with a minimum drum width of 84 inches. The compactor shall be run over the entire running surface of the road after grading is completed. A minimum of six overlapping passes with the appropriate machine shall be accomplished on each completed road section each day of operation.
Compaction shall be done concurrent with grading operations and prior to
SECTION 32 15 01 Page 12 the loss of the appropriate moisture content as specified in section 3.1.3 above.
3.1.7 Debris Removal
The Contractor shall remove wood, rocks, and other debris, as defined below, that have been deposited on the road surface or any drainage facility, whether pre-existing or resulting from grading activities.
3.1.7.1 Organic Debris
The Contractor shall remove and scatter outside the roadway all fallen trees, limbs, or brush in excess of one (1) inch in diameter or two (2) feet in length on the road surface or within two (2) feet of any cross drain culvert inlet.
3.1.7.2 Large Rocks
The Contractor shall remove and scatter outside the roadway all rocks greater than three (3) inches in greatest dimension on the road surface, or greater than six (6) inches in greatest dimension occurring within two
(2) feet of any cross drain culvert inlet.
3.1.7.3 Disposal
Debris shall be sidecast on stable fill slopes or natural ground out of streambeds, streams, or other waterways directly adjacent to the current work site. No sidecasting will be permitted on roads paralleling streams where the ground slope from the outside road shoulder to the stream edge is steeper than 2:1 and the road surface is less than 100 feet from the stream bank.
3.1.8 Existing Culverts
The Contractor shall restore, reshape, and compact existing ditch dikes as needed for effective drainage through existing cross drain culverts. The Contractor will be required to repair, at the Contractor’s expense, any culvert that is unreasonably damaged by the Contractor or their employees during the completion of grading activities.
3.2 DRAINAGE DITCH MAINTENANCE
The Contractor shall perform maintenance on approximately 0.70 miles of roadside drainage ditches located within the 8.6 miles of roads being graded under this contract. 0.5 miles of maintenance are located along the Grandad Bridge Road and 0.2 miles are located along the Breakfast Creek Road near the junction with the Camp X Road, as indicated in Attachment 1, Map Package. The exact location of ditch maintenance will be marked by the Government prior to commencement of work. Drainage ditch maintenance will include the following:
a. Remove and dispose of all trees and branches in excess of one (1) inch in diameter or two (2) feet in length within two (2) feet of any cross drain culvert inlet.
b. Remove and dispose of all woody vegetation.
SECTION 32 15 01 Page 13
c. Remove and dispose of all rocks larger than three (3) inches in greatest dimension from the ditch line, or greater than six (6) inches in greatest dimension occurring within two (2) feet of any cross drain culvert inlet.
d. Remove and dispose of sediment and sloughing from backslopes.
e. Remove and dispose of all trash, debris and all other items which would restrict free flow of water in the drainage ditches.
f. Perform ditch shaping to make a smooth continuous ditch profile and cross section conducive to free flow of water. Ditch cross sections shall have slopes no steeper than 1V:3H unless otherwise approved by the QAR or COR. Backslopes shall not be undercut during ditch shaping.
Ditch shaping shall be performed by tractor with specialty ditch cleaning bucket or other approved equipment that can produce a smooth ditch surface.
Trees, branches, rocks and sediment removed from drainage ditches may be disposed of on-site at locations approved by the QAR. Trash, debris and all other items shall be removed from Government property and disposed of in a legal manner.
3.3 CULVERT MAINTENANCE
The Contractor shall perform maintenance on six (6) culverts, as indicated in Attachment 1, Map Package. Five (5) culverts (map reference numbers 3-7) are located along the Grandad Bridge Road in the location of the first Drainage Ditch Maintenance work site. The last culvert (map reference #11) is located on the Benton Creek Road approximately 300 feet north of the culvert replacement site. Culvert site #11 will also require approximately 250 feet of drainage ditch maintenance work near to inlet between CMP #10 and #11. Maintenance work shall be accomplished to ensure an unobstructed flow of water into and through the culverts.
Maintenance activities shall include the following:
a. Remove and dispose of all sediment, rocks, woody debris, or other items occurring within three (3) feet of the inlets or blocking outlets.
b. Remove and dispose of all sediment and debris from inside culverts for the full length of the pipe. The contractor shall coordinate the method of removal and disposal with the COR or QAR in advance of the work.
c. Shape culvert inlet basins to ensure smooth flow of water into the culvert. Shape the inlet basin to prevent water from flowing past or around the culvert adding a ditch dike where necessary. Compact all surfaces to minimize erosion of the basin surfaces.
d. Trees, branches, rocks, and sediment removed from culverts may be disposed of on-site at locations approved by the QAR. Trash, debris, and all other items shall be removed from Government property and disposed of in a legal manner.
SECTION 32 15 01 Page 14
3.4 CULVERT REPLACEMENT
The Contractor shall replace three (3) existing corrugated metal pipe (CMP) culverts listed in Table 2.
TABLE 2
3.4.1 Replacement of Existing Culverts
Culvert replacement shall include the following:
a. Remove and dispose of existing CMP.
b. Furnish and install Class B bedding material to provide a minimum of six (6) inches below the pipe and up to the spring line on the sides of the culvert, full width of the trench.
c. Furnish and install new CMP as specified with all connecting bands and hardware required for a complete installation.
d. Compact and backfill the trench back to finish grade and finish the roadway with gravel from the Government stockpile where gravel already existed.
e. Shape inlet basin and ditch to provide unobstructed flow of water into the culvert.
f. Place Government-furnished grass seed on all exposed disturbed mineral soil outside the roadway.
g. Construct splash pads where specified.
3.4.1.1 Excavation
The width of the pipe trench shall be sufficient to permit satisfactory jointing of the pipe and thorough tamping of the bedding material under and around the pipe. All excavated material shall be utilized as backfill
CULVERT
LOCATION
(corresponding map #)
CULVERT
DIAMETER
(Inches)
CULVERT
LENGTH
(Feet) REMARKS
1 18 40
At start of side road off Grandad Bridge Road at approximately mile 14.5; gravel road surface over top of pipe.
2 24 40
Across Grandad Bridge Road at approximately mile 14.5; construct splashpad at outlet, re-gravel road surface as necessary
10 36 60
Across Benton Creek Road 400 ft south of Log Dump; construct catch basin to ensure all drainage from draw is captured; construct splashpad
SECTION 32 15 01 Page 15 for new culverts. If additional fill is required, the QAR will make a borrow source available in the vicinity of the culvert being installed.
3.4.1.2 Foundation preparation
Bedding for the culvert shall conform to the requirements of Class B bedding. Bedding shall be constructed by placing the culvert in a trench cut in road bed to a depth of six inches below the bottom of the existing pipe. The pipe shall be bedded on a 6-inch thickness of material and sufficient additional bedding accurately shaped to fit the lower part of the pipe exterior for at least 10% of its overall height. Bedding material shall then be compacted in layers not over 6" in loose thickness around the pipe to the spring line of the pipe.
3.4.1.3 Backfilling
After the bedding has been prepared and the culvert set in place, the trench shall be backfilled with bedding material and soil from excavation.
The backfill shall be brought up evenly on both sides of the pipe in layers not over 6" in loose depth. Each layer shall be moistened (or dried if necessary) to near optimum moisture content and thoroughly compacted with mechanical tampers. Special care shall be taken to compact thoroughly the material under the haunches of the pipe and ensure that the backfill material is in intimate contact with the pipe. The backfill shall be brought up evenly on both sides of the pipe for the full length of the pipe.
3.4.1.4 Finishing
Where culverts are installed in existing gravel surfaced roads, gravel surfacing shall be replaced in kind and graded to make a smooth running surface and compacted with a minimum of six passes with a self-propelled vibratory single drum roller with a minimum drum width of 84 inches.
Gravel for this use is currently located near the Long Creek Camp site and labeled on the attached maps.
3.5 BOULDER RELOCATION
The Contractor shall relocate eighteen existing 3-foot diameter boulders.
The boulders are currently located as shown in Attachment 1, Map Package.
The boulders shall be relocated to Sites 8 and 9 and placed adjacent to the two gates. The exact placement of the boulders adjacent to the gates will be marked by the QAR. The existing boulders are used to delineate the edge of the roadway or cleared area. Following removal of each boulder to be relocated, the remaining boulders shall be re-spaced to leave an evenly spaced row of boulders.
-- End of Section –-
| 03_DWA Gravel Roads Maint - Spec (8-29-13).pdf |
| 1.16.1 Roadway Grading and Compaction |
| 1.16.2 Drainage Ditch and Culvert Maintenance |
| 1.16.3 Culvert Replacement |
| 1.16.4 Boulder Relocation |