W912DR-17-T-0071.pdf
PDF 3 MB Posted
- Attached to
- INDIAN ROCK DAM HERBICIDE APPLICATION SERVICE Federal contract opportunity
- Solicitation number
- W912DR-17-T-0071
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| A10_W912DR-17-T-0071_0003.pdf | ||
| W912DR17T007100002.pdf | ||
| W912DR-17-T-0071_0001.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SEE ADDENDUM
(No Collect Calls)
W912DR-17-T-0071 09-Jun-2017
b. TELEPHONE NUMBER
410-962-4978
8. OFFER DUE DATE/LOCAL TIME
02:00 PM 23 Jun 2017
5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
STANDARD FORM 1449 (REV. 2/2012)
Prescribed by GSA – FAR (48 CFR) 53.212
(TYPE OR PRINT)
(SIGNATURE OF CONTRACTING OFFICER)
ADDENDA X ARE
26. TOTAL AWARD AMOUNT (For Gov t. Use Only )
23.
CODE 10. THIS ACQUISITION IS
SUCH ADDRESS IN OFFER
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT
BELOW IS CHECKED
TELEPHONE NO.
W912DR9. ISSUED BY
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK
7. FOR SOLICITATION
INFORMATION CALL:
a. NAME
IAN WEISS
2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER
(TYPE OR PRINT)
30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA
27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.X
25. ACCOUNTING AND APPROPRIATION DATA
1. REQUISITION NUMBER
20.
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
ARE NOT ATTACHED
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
. YOUR OFFER ON SOLICITATION
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
% FOR:SET ASIDE:UNRESTRICTED OR X
SMALL BUSINESS
17a.CONTRACTOR/ CODE FACILITY
OFFEROR CODE
U.S. ARMY CORPS OF ENGINEERS, BALTIMORE
10 S. HOWARD STREET
ROOM 7000
BALTIMORE MD 21201
18a. PAYMENT WILL BE MADE BY CODE
RATED ORDER UNDER
DPAS (15 CFR 700)
13a. THIS CONTRACT IS A
13b. RATING
CODE15. DELIVER TO CODE 16. ADMINISTERED BY
SEE SCHEDULE
12. DISCOUNT TERMS11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
14. METHOD OF SOLICITATION
RFQ IFB RFPX
FAX:
TEL: 410-962-2196
SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
8(A)
HUBZONE SMALL
BUSINESS
SIZE STANDARD:
$7.5 Million
NAICS:
115310
X
OFFER DATED
29. AWARD OF CONTRACT: REF.
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
EMAIL:
TEL:
31c. DATE SIGNED
SEE SCHEDULE
SCHEDULE OF SUPPLIES/ SERVICESITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT
24.22.21.19.
X
WOMEN-OWNED SMALL BUSINESS (WOSB)
ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
EDWOSB
32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
(CONTINUED)
PAGE 2 OF77
ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________
32a. QUANTITY IN COLUMN 21 HAS BEEN
RECEIVED INSPECTED
32b. SIGNATURE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE
37. CHECK NUMBER
FINALPARTIALCOMPLETE
36. PAYMENT35. AMOUNT VERIFIED
CORRECT FOR
34. VOUCHER NUMBER
FINAL
33. SHIP NUMBER
PARTIAL
38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT
41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE
42a. RECEIVED BY (Print)
42b. RECEIVED AT (Location)
42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS
STANDARD FORM 1449 (REV. 2/2012) BACK
Prescribed by GSA – FAR (48 CFR) 53.212
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
SEE SCHEDULE
20.
SCHEDULE OF SUPPLIES/ SERVICES
21.
QUANTITY UNIT
22. 23.
UNIT PRICE
24.
AMOUNT
19.
ITEM NO.
Section SF 30 - BLOCK 14 CONTINUATION PAGE
INSTRUCTIONS TO OFFERORS
INSTRUCTION TO OFFERORS
Quotes can be submitted via e-mail at Ian.Weiss@usace.army.mil or via mail to U.S. Army
Corps of Engineers, Contracting Division, Simplified Acquisition Branch, ATTN: Ian Weiss, 10
South Howard Street, 7th floor, Room 7200-D, Baltimore, MD 21201-2530.
All line items must be priced. Quotes providing partial pricing may be considered non-responsive.
I. EQUIPMENT, STAFFING, & WORK PLANS:
A. Submission Requirements: This information consists of the offeror’s intended approach to executing the contract. The submission for this section shall not exceed 5 pages in length, excluding resumes.
1. Equipment plan: The proposed equipment list should only include the equipment which will be used on this contract. Include size, make, model, and ownership
(owned or rented) of equipment. Proposed herbicides to be used for Area A and B treatments shall be included in this section.
2. Staffing plan: The proposed staffing plan shall include both numbers of personnel proposed and position titles. Resumes for proposed key personnel, consisting of experience and other pertinent information, inclusive of superintendents, quality control inspectors, and foremen must also be submitted.
3. Work plan: A work plan shall be submitted indicating how the work will be accomplished including the steps required and definable features of work. An anticipated schedule of work in compliance with the Statement of Work should also be provided and shall include the earliest response time from date of award.
B. Evaluation Criteria: The Government will check Offeror’s equipment, staffing, and work plans for each project for completeness and reasonableness.
A complete and reasonable equipment, staffing plan, and work plan will receive an Acceptable rating.
Incomplete or unreasonable plans will receive a rating of Unacceptable.
- Government will evaluate the clarity and strength of the overall organization and how well it is organized and structured to execute the entire scope of work.
-The Government will evaluate the capability of the firm to execute the project.
-The Government will evaluate the Contractor’s resources to determine if it has the capability to self-perform the required amount of the project, in accordance with public policy to assure adequate interest in and supervision of all work.
II. EXPERIENCE:
A. Submission Requirements: The offeror shall demonstrate recent, relevant experience on similar projects. If the offeror is a joint venture, each firm shall demonstrate experience. Submit at least 3 detailed examples of relevant work that are currently well underway or performed within the past 5 years. Work experience shall be demonstrated for at least 5 years.
B. Evaluation Criteria: The Government will evaluate how well the Offeror demonstrated their recent (within three years of the issue date of the RFQ), relevant experience with similar projects. If the Offeror is a joint venture, each entity must demonstrate qualifying experience comparable to its role on the project. The Government reserves the right to verify the experience record of cited projects or other recent projects or to interview owners or references. The Government reserves the right to check any or all cited references to verify supplied information. A rating of Not Acceptable will be given to an Offeror who cannot demonstrate a history of recent, relevant experience.
The Government will consider extent of recent experience, degree of relevance of such experience to this project, demonstrated familiarity with similar sites and local conditions. Some examples of relevancy to this project may include, but not be limited to: (1) Number, size, type work, location; (2) Dates (completion within last 10 years);
and (3) Firm's role and extent of work self-performed (subcontracting out all work is an examples of less relevant experience).
III. PAST PERFORMANCE FACTOR:
A. Submission Requirements: Past performance refers to the quality of recent project experience from the customer’s perspective. The Offeror shall arrange for the reference customer point of contact for three projects to fill out the Questionnaire, attached below, and return directly to Ian Weiss, Contract Specialist, via e-mail at
Ian.Weiss@usace.army.mil. The questionnaires must be forwarded directly by the references. The Government will not accept questionnaire forms from the Offeror at any time, in order for the Government to solicit candid, unbiased responses and comments. Three References from previously completed jobs must be submitted and include a point of contact and phone numbers. These references must be relevant to the work which will be performed in this contract. References must be recent within the past 5 years.
B. Evaluation Criteria: The Government will assess the degree of success of Offeror’s recent, relevant past performance. Owners/references will be asked to comment on items such as quality of work, timeliness, management of subcontractor work, including timely payment to subs or suppliers, safety, relations between customer and contractor, level of support for such things as correcting errors. The Government will target areas covered in the requirements of the Performance Work Statement including mailto:Ian.Weiss@usace.army.mil records conforming to quality, schedule, customer satisfaction, and problem resolution for errors and safety. The Government will give a Favorable rating to documented successful outcomes that are supported by outside source confirmation (e.g. but not limited to telephone interviews with points of contact identified in the proposal, agency performance databases, offeror furnished references, or personal knowledge).
Successful outcomes are defined as having received a rating of satisfactory or better, or the equivalent. If the Government does not obtain past performance information for the projects identified by the offeror and cannot establish a past performance record for the offeror through other sources, or if the offeror has no past performance record and cannot tie significant, relevant experience of key personnel proposed for this project to cited experience, past performance will be rated neither favorably nor unfavorably.
Additionally, entries in the Contracting Performance Assessment Reporting System may be used to evaluate Past Performance.
C. Price: Price will be evaluated in accordance with FAR 15.402. The government may require additional pricing information to assist in determining the extent to which the price is fair and reasonableness and the pricing information shall be provide if requested. The Government will evaluate quotes for award purposes by adding the total of all CLIN prices to ensure that pricing is not unbalanced.
Award will be made for the lowest-price, technically acceptable offer. The lowest-price will be evaluated for the sum of the Base and Option Years.
Questions concerning this solicitation must be submitted by email no later than 2 PM, EST,15
June 2017. This will allow responses to be posted on FBO prior to solicitation closing. Email:
Ian.Weiss@usace.army.mil
PAST PERFORMANCE SUBMISSION: (See Attached Past Performance Questionnaire)
APPENDIX D – PAST PERFORMANCE ON EXPERIENCE IN RELEVANT PROJECTS
ENCL 1
NAVFAC/USACE PAST PERFORMANCE QUESTIONNAIRE (Form PPQ-0)
CONTRACT INFORMATION (Contractor to complete Blocks 1-4)
1. Contractor Information Firm Name: CAGE Code:
Address: DUNs Number:
Phone Number:
Email Address:
Point of Contact: Contact Phone Number:
2. Work Performed as: Prime Contractor Sub Contractor Joint Venture Other (Explain) Percent of project work performed:
If subcontractor, who was the prime (Name/Phone #):
3. Contract Information Contract Number:
Delivery/Task Order Number (if applicable):
Contract Type: Firm-Fixed-Price Cost Reimbursement Other (Please specify):
Contract Title:
Contract Location:
Award Date (mm/dd/yy):
Contract Completion Date (mm/dd/yy):
Actual Completion Date (mm/dd/yy):
Explain Differences:
Original Contract Price (Award Amount):
Final Contract Price (to include all modifications, if applicable):
Explain Differences:
4. Project Description:
Complexity of Work High Med Routine
How is this project relevant to project of submission? (Please provide details such as similar equipment, requirements, conditions, etc.)
CLIENT INFORMATION (Client to complete Blocks 5-8)
5. Client Information Name:
Title:
Phone Number:
Email Address:
6. Describe the client’s role in the project:
7. Date Questionnaire was completed (mm/dd/yy):
8. Client’s Signature:
NOTE: Past performance refers to the quality of recent project experience from the customer’s perspective. The Offeror shall arrange for the reference customer point of contact for two projects to fill out the Questionnaire and return directly to Ian Weiss, Contract Specialist, e-mail at Ian.Weiss@usace.army.mil. The questionnaires must be forwarded directly by the references. The
Government will not release the questionnaire forms to the Offeror at any time, in order for the Government to solicit candid, unbiased responses and comments. Three References from previously completed jobs must be submitted and include a point of contact and phone numbers. These references must be relevant to the work which will be performed in this contract. Relevant work is defined as herbicide application services service. References must be recent within the past 3 years.
mailto:Jason.s.torzok@usace.army.mil
ADJECTIVE RATINGS AND DEFINITIONS TO BE USED TO BEST REFLECT
YOUR EVALUATION OF THE CONTRACTOR’S PERFORMANCE
RATING DEFINITION NOTE
(E) Exceptional Performance meets contractual requirements and exceeds many to the Government/Owner’s benefit.
The contractual performance of the element or sub-element being assessed was accomplished with few minor problems for which corrective actions taken by the contractor was highly effective.
An Exceptional rating is appropriate when the Contractor successfully performed multiple significant events that were of benefit to the
Government/Owner. A singular benefit, however, could be of such magnitude that it alone constitutes an Exceptional rating.
Also, there should have been NO significant weaknesses identified.
(VG) Very Good Performance meets contractual requirements and exceeds some to the Government’s/Owner’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective.
A Very Good rating is appropriate when the Contractor successfully performed a significant event that was a benefit to the
Government/Owner. There should have been no significant weaknesses identified.
(S) Satisfactory Performance meets minimum contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.
A Satisfactory rating is appropriate when there were only minor problems, or major problems that the contractor recovered from without impact to the contract.
There should have been NO significant weaknesses identified. Per DOD policy, a fundamental principle of assigning ratings is that contractors will not be assessed a rating lower than Satisfactory solely for not performing beyond the requirements of the contract.
(M) Marginal Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being assessed reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor's proposed actions appear only marginally effective or were not fully implemented.
A Marginal is appropriate when a significant event occurred that the contractor had trouble overcoming which impacted the Government/Owner.
(U)
Unsatisfactory
Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains serious problem(s) for which the contractor's corrective actions appear or were ineffective.
An Unsatisfactory rating is appropriate when multiple significant events occurred that the contractor had trouble overcoming and which impacted the
Government/Owner. A singular problem, however, could be of such serious magnitude that it alone constitutes an unsatisfactory rating.
(N) Not
Applicable
No information or did not apply to your contract Rating will be neither positive nor negative.
W912DR-17-T-0071
TO BE COMPLETED BY
CLIENT
PLEASE CIRCLE THE ADJECTIVE RATING WHICH BEST
REFLECTS
YOUR EVALUATION OF THE CONTRACTOR’S PERFORMANCE.
1. QUALITY:
a) Quality of technical data/report preparation efforts E VG S M U N
b) Ability to meet quality standards specified for technical performance
E VG S M U N
c) Timeliness/effectiveness of contract problem resolution without extensive customer guidance
d) Adequacy/effectiveness of quality control program and adherence to contract quality assurance requirements (without adverse effect on performance)
2. SCHEDULE/TIMELINESS OF PERFORMANCE:
a) Compliance with contract delivery/completion schedules including any significant intermediate milestones. (If liquidated damages were assessed or the schedule was not met, please address below)
b) Rate the contractor’s use of available resources to accomplish tasks identified in the contract
3. CUSTOMER SATISFACTION:
a) To what extent were the end users satisfied with the project? E VG S M U N
b) Contractor was reasonable and cooperative in dealing with your staff
(including the ability to successfully resolve disagreements/disputes;
responsiveness to administrative reports, businesslike and communication)
c) To what extent was the contractor cooperative, businesslike, and concerned with the interests of the customer?
d) Overall customer satisfaction E VG S M U N
4. MANAGEMENT/ PERSONNEL/LABOR
a) Effectiveness of on-site management, including management of subcontractors, suppliers, materials, and/or labor force?
b) Ability to hire, apply, and retain a qualified workforce to this effort E VG S M U N
c) Government Property Control E VG S M U N
d) Knowledge/expertise demonstrated by contractor personnel E VG S M U N
e) Utilization of Small Business concerns E VG S M U N
f) Ability to simultaneously manage multiple projects with multiple disciplines E VG S M U N
g) Ability to assimilate and incorporate changes in requirements and/or priority, including planning, execution and response to Government changes
h) Effectiveness of overall management (including ability to effectively lead, manage and control the program)
5. COST/FINANCIAL MANAGEMENT
a) Ability to meet the terms and conditions within the contractually agreed price(s)?
b) Contractor proposed innovative alternative methods/processes that reduced E VG S M U N cost, improved maintainability or other factors that benefited the client
c) If this is/was a Government cost type contract, please rate the Contractor’s timeliness and accuracy in submitting monthly invoices with appropriate back-up documentation, monthly status reports/budget variance reports, compliance with established budgets and avoidance of significant and/or unexplained variances (under runs or overruns)
d) Is the Contractor’s accounting system adequate for management and tracking of costs? If no, please explain in Remarks section.
Yes No
e) If this is/was a Government contract, has/was this contract been partially or completely terminated for default or convenience or are there any pending terminations? Indicate if show cause or cure notices were issued, or any default action in comment section below.
f) Have there been any indications that the contractor has had any financial problems? If yes, please explain below.
6. SAFETY/SECURITY
a) To what extent was the contractor able to maintain an environment of safety, adhere to its approved safety plan, and respond to safety issues?
(Includes: following the users rules, regulations, and requirements regarding housekeeping, safety, correction of noted deficiencies, etc.)
b) Contractor complied with all security requirements for the project and personnel security requirements.
7. GENERAL
a) Ability to successfully respond to emergency and/or surge situations
(including notifying COR, PM or Contracting Officer in a timely manner regarding urgent contractual issues).
b) Compliance with contractual terms/provisions (explain if specific issues) E VG S M U N
c) Would you hire or work with this firm again? (If no, please explain below) Yes No
d) In summary, provide an overall rating for the work performed by this contractor.
Please provide responses to the questions above (if applicable) and/or additional remarks. Furthermore, please provide a brief narrative addressing specific strengths, weaknesses, deficiencies, or other comments which may assist our office in evaluating performance risk (please attach additional pages if necessary):
PRICING SCHEDULE
INDIAN ROCK DAM
YORK, PENNSYLVANIA
HERBICIDE APPLICATION
BID SCHEDULE
The Contractor, as an independent Contractor and not as an agent of the Government, shall furnish all labor, supervision, materials, equipment and supplies to perform work in accordance with the specifications of the Scope of Work.
BASE
PERIOD
ITEM DESCRIPTION – See PWS for full location details
UNIT UNIT
PRICE
QTY TOTAL
AMOUNT
0001 Area A Treatment 1
Acre 8
0002 Area B Treatment 1
Acre 47
0003 Area A Treatment 2
Acre 4
0004 Area B Treatment 2
Acre 23.5
TOTAL BASE PERIOD
OPTION PERIOD I
ITEM DESCRIPTION
QTY TOTAL
1001 Area A Treatment 1
1002 Area B Treatment 1
1003 Area A Treatment 2
1004 Area B Treatment 2
TOTAL OPTION PERIOD I
OPTION PERIOD II
QTY TOTAL
2001 Area A Treatment 1
2002 Area B Treatment 1
2003 Area A Treatment 2
2004 Area B Treatment 2
TOTAL OPTION PERIOD II
OPTION PERIOD III
QTY TOTAL
3001 Area A Treatment 1
3002 Area B Treatment 1
3003 Area A Treatment 2
3004 Area B Treatment 2
TOTAL OPTION PERIOD
III
OPTION PERIOD IV
QTY TOTAL
4001 Area A Treatment 1
4002 Area B Treatment 1
4003 Area A Treatment 2
4004 Area B Treatment 2
TOTAL OPTION PERIOD
IV
TOTAL BASE PERIOD + 4 OPTION
PERIODS
PERFORMANCE WORK SCHEDULE
YORK, PENNSYLVANIA
HERBICIDE APPLICATION
PERFORMANCE WORK STATEMENT
Objective: The Contractor shall provide all labor, supervision, materials, equipment, and supplies to complete the following:
1. Summary: Apply herbicide at the following locations:
A. Indian Rock Dam, located in York County near York, PA.
B. Codorus Creek Stream Improvement Project, located in York County near York, PA.
2. Responsibilities: Contractor’s work and responsibility shall include all planning, selection of herbicides, programming, administration and management necessary to assure that a target kill rate of 100% is achieved in accordance with the contract and all applicable laws, regulations, codes and directives. The Contractor shall perform all related Contractor administrative services necessary to perform the work such as procurement, supplying, quality control, work scheduling, Contractor financial control and maintenance of accurate and complete records and files.
3. TPOC: The Technical Points of Contact (TPOCs) for this call is:
A. Steve Young at Indian Rock Dam, York, PA 17408. 717-792-0312
TECHNICAL SPECIFICATIONS
1. Selection: Herbicides to be used shall be selected by the Contractor based on vegetative growth to be eradicated or prevented, toxicity, environmental concerns and site to be treated. When selecting herbicides, the Contractor shall take into consideration that the treated areas may be used frequently by the public, that there may be fresh water lakes and or/ streams in close proximity and desirable vegetation may exist in very close proximity to the designated spray site. The Contractor shall furnish the Contracting Officer’s Representative (COR) copies of current labels, and Material Safety Data Sheets (MSDS) of any and all herbicides proposed for use. All herbicides must be approved by the COR before being order or purchased by the Contractor. The Government reserves the right to deny any herbicides that may be proposed for use by the Contractor if prohibited by Local, State, or Federal standards.
2. Area Descriptions:
Area A This includes all areas within 20 feet of bodies of water, standing water, and drainage ditches with flowing water. This is to include rip-rap areas along both sides of the intake channel, upstream and downstream rip-rap embankment of the dam, the rip-rap areas and along the spillway wall upstream of the dam, the rip areas on the south end of the spillway and along the creek bank. Where desirable vegetation is present, spraying limits shall extend no closer than 1 foot from desirable vegetation.
Area B This includes all areas more than 20 feet from bodies of water and drainage ditches with flowing water, but where there is the possibility of leeching into the bodies of water. Any areas where there may be the presence of root systems of desirable vegetation such as trees, bushes, and shrubs. All areas along the edge of all buildings, concrete structures, walks, driveways, parking lots, guardrails, fences, headwalls, gate posts, utility structures, etc., as directed by the designated government representative. All gravel roads will be sprayed. Areas will generally be sprayed 8 to 12 inches from all above mentioned objects to eliminate the need of hand trimming of grass and other vegetation growth. Some areas may require wider areas to be treated.
3. Determination of Boundaries: The exact boundaries of application areas will be defined by the TPOC or his designee. The majority of the spraying at the dam sites is on the dams and levees, but there are several other sites which include the spillways, outlet works, rip-rap areas and roadways. Formulations will be designed separately for both areas using criteria as described in Area Descriptions. All formulation shall include a surfactant, colorant and anti-drift agent.
4. Application at Indian Rock Dam: This includes around all structures, all rip-rap, drainage ditches, guardrails, fencing at residence, etc; as directed by designated government representative. Areas will generally be sprayed 8 to 12 inches from all above mentioned objects to eliminate the need for hand trimming of grass and other vegetative growth. All rip-rap areas shall have a 24 inches border sprayed. A residual herbicide will not be used in areas where there is a possibility of entering into the root system of any desired vegetation such as trees, shrubs, etc.
5. Application at Codorus Creek Levee: Spraying shall begin upstream of the weir at Richland Avenue (Station 273+69) and proceed downstream of York City Sewage Treatment Plant (Station 44+00). Tyler’s Run located between Penn Street and Grantley Street, discharging on the right embankment, shall be sprayed from the confluence of Codorus Creek to the Railroad Bridge. The area between College Avenue and the Railroad Bridge identified on the attached IRD Herbicide Exclusion Zone Location Map shall be excluded from all herbicide application. Herbicides shall be applied to rip-rap areas around all concrete structures, utility structures, headwalls, and drainage structures on both the right and left banks of the Codorus Creek in York, PA. Prior to the commencement of work, a site survey will be conducted. Areas that are not to be sprayed will be specified by the TPOC during the pre-work meeting. Under no circumstances will any public use areas be treated with herbicide.
6. Rate of Spray Coverage: The Contractor shall use spot-treatment for all areas, spraying only areas with active vegetative growth. Spray shall not exceed the manufacturer’s recommended amounts per acre. Concentration shall be on the heavy growth areas to ensure a thorough wetting of all vegetation surfaces. All vegetation foliage shall be made on a spray-to-wet basis, obtaining uniform and complete coverage. All work shall conform to the manufacturer’s recommendations. The application shall be a post emergence stage application.
7. Performance Requirements: The Contractor shall provide herbicide spraying services at the project with a target standard kill rate of 100%. The Contractor shall be allowed to deviate from the standard by 10%. The surveillance method used by the government will be 100% inspection performed by the TPOC/COR at the end of each day or the completion of each location. Should the Contractor fail to achieve a kill rate of at least 90%, follow up spraying will be conducted at no additional cost to the government to achieve the desired kill rate. Upon satisfactory completion of the Firm-Fixed-Price contract and notification by the TPOC/COR of inspection and approval, the Contractor shall submit an Invoice(s) for payment. The area of application in acres shown on the invoice shall be consistent with the Daily Quality Control Reports and the volume of herbicide applied shown on the Pesticide Application Records.
SPECIAL CONDITIONS
1. Period of Performance: All herbicides shall be applied on successive workdays (weather permitting) once the work has commenced. At least three days’ notice shall be given the TPOC/COR at each project prior to the commencement of spraying at each location.
The Contractor shall not commence spraying operations prior to receiving approval from the TPOC/COR.
A. First spray: The COR will contact the Contractor between April 1st and May 20th when the need for herbicide application arises under the Base Contract.
Successive Option Years awarded will utilize the same dates of service. The Contractor shall mobilize within 14 days of being contacted. The start date will be coordinated with the TPOC/COR.
B. Second spray: The COR will contact the Contractor between July 1st and August 31st when the need for a second herbicide application arises under the Base
Contract. Successive Option Years awarded will utilize the same dates of service.
The Contractor shall mobilize within 14 days of being contacted. The start date will be coordinated with the TPOC/COR. The second spray is estimated to cover less acreage than the first spray.
2. Performance of Work: The Contractor shall perform work only during normal Corps of Engineers duty hours (7:30 a.m. to 4:00 p.m., Monday through Friday, excluding federal holidays). Exceptions to this condition must be coordinated with and approved in advance by the Operations Manager, Susquehanna River Project.
3. Accident Prevention: In performing this contract the Contractor shall comply with all current Federal, State, and Local safety regulations, including Corps of Engineers Safety and Health Requirement Manual EM 385-1-1 and shall comply with any subsequent changes. Information regarding acquiring the Corps of Engineers Safety and Health Requirement Manual EM 385-1-1 may be found on the USACE Headquarters website at http://www.usace.army.mil/SafetyandOccupationalHealth/SafetyandHealthRequiremen tsManual.aspx Within 14 days of contract award the Contractor shall furnish the following for approval by the Government:
A. Accident Prevention Plan Section I, Article 01.A.11, EM 385-1-1, dated 15 Sep 08 B. Activity Hazard Analyses Section I, Article 01.A.13, EM 385-1-1, dated 15 Sep 08
4. Accident Reporting: In the event of an accident or injury involving Contractor personnel or equipment in performance of work the Contractor shall immediately notify the TPOC, COR, and Contracting Officer by the most expedient means feasible. The Contractor shall complete forms furnished and/or provide a written description of the incident within 24 hours of notification to do so.
5. Operations and Storage Areas: The Contractor shall confine all operations to areas authorized or approved by the TPOCs. Materials may only be stored on site in the Contractor’s vehicles or equipment. The Contractor shall coordinate with Project Personnel for the location of a designated area for mixing and preparation of herbicides and will provide for a spill containment system constructed of impervious materials or an acceptable alternative, as required. The Contractor is prohibited from using Government property to clean his equipment or to dispose of any waste.
6. Access and General Protection/Security Policy and Procedures: All contractor and all associated sub-contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation/facility access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity http://www.usace.army.mil/SafetyandOccupationalHealth/SafetyandHealthRequirementsManual.aspx http://www.usace.army.mil/SafetyandOccupationalHealth/SafetyandHealthRequirementsManual.aspx
Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any installation or facility change, the Government may require changes in contractor security matters or processes.
7. Government Escort: All contract employees, including subcontractor employees who are not in possession of the appropriate security clearance or access privileges, will be escorted in areas where they may be exposed to classified and/or sensitive materials and/or sensitive or restricted areas.
8. Pre-screen candidates using E-Verify Program: The Contractor must pre-screen
Candidates using the E-verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award.
9. Housekeeping: The Contractor shall keep the work area, including storage areas, free from accumulations of waste materials. Before completing the work, the Contractor shall remove from the work site and premises, any rubbish, tools, equipment, and materials that are not property of the Government. Upon completing the work the Contractor shall restore the work area to the original condition, to be approved by the TPOC.
10. Environmental Protection: The Contractor is required to comply with all Federal, State, and Local environmental regulations. The Contractor shall exercise care and safety in the performance of the contract and shall take necessary precautions to avoid contamination of the water, damage to private property and injury to employees and the public. The Contractor shall be liable for any and all damage to the Environment and/or public or private property, caused by equipment or chemicals. No separate payment will be made for environmental protection measures. All environmental protection matters shall be coordinated with the TPOC. The Contractor shall notify project personnel of any herbicide spills immediately and take appropriate action. Information on decontamination of emergency and non-emergency type spills may be obtained by contacting CHEMTREC toll free at 1-800-424-9300. The Contractor shall be responsible for any on or off-site damage occurring from spray operations such as over-spray, leaching, drift, etc.
11. Permits and Licenses: The Contractor shall be properly certified by the Commonwealth of Pennsylvania as a licensed applicator of herbicides within the State or Commonwealth, and must adhere to all rules and regulations relating to herbicide application. A copy of appropriate certifications shall be furnished to the TPOC prior to commencement of work. The Contractor shall, at his/her own expense, obtain any licenses or permits required to perform the contract. The Contractor shall comply with all current Federal, State and Local laws and regulations and shall comply with any subsequent changes.
12. Records and Reports: In addition to the administrative requirements dictated elsewhere, the Contractor shall complete a Daily Quality Control Report form to maintain record of contract performance, accident/injury incidence, and observance of project deficiencies.
Forms will be distributed at pre-work conference. The Contractor must provide his/her own appropriate form (Pesticide Application Record) to maintain herbicide application records. This form shall be completed and furnished to the Government Representative upon completion of each site or day. The Pesticide Application Record shall have the following information:
A. Name of applicator and Certification ID number B. Herbicide name and EPA Reg. number C. EPA Registration number D. Weather conditions E. Amount of herbicide used, date and time applied F. Amount of acreage covered G. Locations applied
13. Minimum Man-power Requirements: The Contractor shall provide an adequate number of fully qualified personnel to perform the work specified herein. The areas to be sprayed are dam embankments and areas that are not easily accessible. It is suggested but not required that a minimum of three persons are needed to apply the herbicides.
14. Superintendent: The Contractor shall act as or provide a superintendent who acts as a quality control manager whenever the work specified herein is being performed. The superintendent shall conduct overall management coordination and be the central point of contact with the Government for performance of all work under this contract. The superintendent and any individual designated to act for him/her shall have full authority to contractually commit the Contractor for prompt action on matters pertaining to the administration of the entire project. Such authorization shall be submitted in writing to the COR and contracting officer. The superintendent shall deal directly with the TPOC for normal day-to-day administration of the contract provisions. The superintendent shall attend pre-work conference(s) prior to commencing work.
15. Project Operation: The locations of work are flood control projects and the Contractor’s access to the work areas and the execution of the requirements specified herein shall not interfere with the daily operations of the government operations. The sites of work are subject to periodic flooding. The Contractor shall consider the potential for high water levels in the scheduling of work. A specific program shall be established by the Contractor to evacuate personnel, equipment, and materials as necessary in the event of high water.
It is the responsibility of the Contractor to coordinate all work with the TPOCs/COR.
DELIVERABLES
1. Required with Quote - A paper or digital copy of the following shall be submitted with the Contractor’s quote:
A. Copies of any and all application licenses and certificates B. Proposed herbicide information including current labeling information, MSDS and any other pertinent information.
2. Pre-Work Submittals – A paper or digital copy of the following shall be submitted within 14 days of award to the COR:
A. Accident Prevention Plan B. Activity Hazard Analyses
3. Post-Work Submittals – A paper or digital copy of the following shall be submitted within 14 days of award to the COR:
A. Daily Quality Control Reports B. Pesticide Application Records
INVOICES AND PAYMENT
1. Invoices: The Contractor shall submit itemized invoices no later than 15 days from the completion of the work. The invoice shall accurately reflect work completed. Each invoice at a minimum shall contain the following information:
Contractor name and address, exactly as it appears on the contract
Contract number
Date of invoice submission
Invoice or Call Order number
Invoice total
2. Corrections: Incorrect invoices will be returned to the Contractor for correction before processing payment. Corrected invoices shall be re-dated to reflect the new submission date.
QASP
Quality Assurance Surveillance Plan (QASP)
For
HERBICIDE
1. INTRODUCTION:
1.1. Purpose: The role of the government in quality assurance is to ensure contract standards are achieved. The purpose of the QASP is to identify the methods and procedures the government will use to evaluate contractor actions while performing the requirements in the contract specifications. It is designed to provide an effective surveillance method by monitoring contractor performance for each service listed in the contract specifications for the subject contract.
1.2. The QASP provides a systematic method to evaluate the services the contractor is required to provide. The QASP is based on the premise that the government desires to maintain a high quality standard for services for which it has contracted.
1.3. This QASP has been developed by the requiring activity, Susquehanna River Project. It is designed to provide direction to personnel performing “on the ground” contract administration and quality assurance. Personnel monitoring the contract terms, conditions, and specifications will periodically review the QASP throughout the life of the contract.
2. ROLES AND RESPONSIBILITIES:
2.1. Contracting Officer Representative (COR). The COR is responsible for quality assurance guidance and to ensure that contract quality requirements, specifications, standards, and thresholds are defined, practical, enforceable, necessary, and verifiable.
2.2. The COR evaluates and documents contractor performance in accordance with the QASP and contract specifications. The COR will utilize Quality Assurance Evaluators (QAE) to perform the hands on day to day quality surveillance of the contractor. QAE’s are nominated by the COR, subject to Contracting Officer approval and designation. COR’s may utilize other surveillance support personnel as authorized in AR 70-13.
2.3. The COR informs the contractor of the names, duties, and limitations of authority for all quality assurance personnel assigned to the contract.
2.4. The COR notifies the Contracting Officer of any significant performance deficiencies.
2.5. The COR maintains surveillance documentation and recommends improvements to the QASP throughout the life of the contract.
2.6. Contracting Officer (KO). The Contracting Officer is responsible to safeguard the interests of the United States in contractual relationships. Only the contracting officer is authorized to bind the government and then, only to the extent of the authority delegated to them through the issuance of a warrant.
2.7. The KO delegates authority for inspection and/or acceptance in accordance with terms of the contract.
3. DESCRIPTION OF SERVICES:
3.1. Scope of Work. The Contractor shall provide herbicide application services at Indian Rock Dam and Codorus Creek LFPP.
4. QUALITY REQUIREMENTS:
4.1. Quality Control Program. The contractor, not the government, is responsible for management and quality control actions to meet the terms of the contract.
4.2. The quality control program is the driver for quality. The contractor is required to develop a comprehensive program of inspections and monitoring actions. The first major step to ensuring a “self-correcting” contract is to ensure that the quality control program, discussed and agreed to at the beginning of the contract, provides the measures needed to lead the contractor to success.
4.3. Once the quality control program is accepted, careful application of the process and standards presented in the remainder of this document will ensure a consistent quality assurance program.
5. SURVEILLANCE:
5.1. Surveillance Schedule. The Contracting Officer Representative (COR) will work with assigned quality assurance evaluators to develop a surveillance schedule. Changes to the surveillance schedule will be discussed in advance with COR. Surveillance documentation will be kept in the official electronic contract file and/or the official hardcopy contract file.
a) Surveillance Methods. This QASP will incorporate 100% inspections as the approach to ensure the contractor complies with the contract requirements. Re-performance is the preferred method of correcting any unacceptable performance.
b) Validated Customer Complaint. This contract will be inspected for quality assurance using the validated customer complaint surveillance method. Anyone who observes unacceptable services, either incomplete or not performed, should immediately contact the COR. The COR will conduct an investigation to determine the validity of the complaint. If the COR determines the complaint to be valid, the COR will document the findings and notify the customer and the contractor. The COR will retain a copy of the written complaint for the government’s files. If the complaint is valid, the contractor will be given the opportunity to correct the defect.
c) 100% Inspection: 100% inspection will be utilized for this contract and will be noted as follows: 100% inspections will be utilized for all projects. This type of surveillance overrides periodic surveillance. However, validated customer complaints are still utilized. Under the 100% surveillance method all contract performance requirements are inspected for quality assurance at every occurrence within the contract schedule.
d) Surveillance Team. The surveillance team consists of the following key players:
Contracting Officer Representative, Contracting Officer, Contract Administrator, and Quality Assurance Evaluators.
e) Unacceptable Performance. If the number of complaints/defects exceeds the performance threshold for any requirement, the COR will determine the possible cause of this unacceptable performance. Government-caused complaints/defects shall not be counted against the contractor. The same applies to any other requirement of the contract when Government-caused complaints/defects are the cause of unacceptable contractor performance. If the contractor’s performance is judged unacceptable by the COR for any requirement, the COR will inform the contractor’s on-site representative, and request acknowledgement of the unacceptable performance. Unacceptable performance will normally result in the contractor being required to re-perform the unacceptable work. If the work is not able to be re-performed according to specification, the COR will consult with the Contracting Officer to determine the appropriate resolution. If the contractor disputes the results of surveillance, the COR must refer the contractor to the contracting officer for resolution.
f) Revisions. Revisions to this QASP are the responsibility of the requiring activity.
However as a result of partnering with the contractor, surveillance checklists may be revised jointly by COR personnel and contractor personnel. The Contracting Officer must approve any revisions that are significant enough in nature to impact the quality expectations of the contractor.
6. DOCUMENTATION REQUIREMENTS:
6.1 The COR is responsible for maintaining a Surveillance Folder at a designated location either hardcopy or electronic, which may also be a part of the COR’s official contract file.
The following information should be contained in the Surveillance Folder:
a. QASP
b. Contractor’s Quality Control Plan, if required.
c. Contract Documents, to include the contract, specifications, modifications, and delivery orders.
d. Appointment Letters and Training Certificates of the COR and other Surveillance
Personnel if applicable.
e. Surveillance Checklists/Inspection Forms.
f. Quality Assurance Surveillance Schedules, if applicable.
g. Corrective Action Notes/Log
h. Invoice and payment documents
i. Meeting Minutes/Memo’s/Miscellaneous Correspondence
7. PERFORMANCE REQUIREMENTS SUMMARY: This summary identifies critical success factors for the contract. It identifies both the performance objectives for those factors and the performance threshold required for each performance objective. The Government reserves the right to inspect all services called for in the contract to determine whether or not the performance objectives and goals were met. The Performance Requirements Summary is an integral part of the QASP.
Performance
Objective Performance Standard Performance Threshold Disincentive Incentive
Herbicide
Application
Apply herbicide at the locations required in accordance with the
PWS.
Achieve at least 90% kill rate.
20% of invoice deduction or re-performance for failing to meet the performance threshold
Full payment of invoice
Environmental
Protection
Select and use herbicides properly.
Use in accordance with
PWS, public laws, and manufacturer’s recommendations.
20% of invoice deduction or re-performance for failing to meet the performance threshold
Full payment of invoice
Report
Submittals
Required reports/invoices are submitted within designated timeframe
Required reports/invoices are submitted within designated time frame 95% of the time
5% deduction from invoice for failure to meet the performance threshold
Full payment of invoice
Safety
Maintained during operations
No accidents or incidents due to contractor’s failure to take safety precautions
No accidents or incidents due to contractor’s failure to take safety precautions
5% deduction from invoice for safety violation.
Full payment of invoice
*The absence of any contract requirement from the PRS shall not detract from its enforceability nor limit the rights or remedies of the Government under any other provision of the contract including the clauses entitled “Inspection of Services” and “Default”.*
7.1 Performance Evaluation and Re-Performance. Performance of a service will be evaluated to determine whether or not it meets the performance threshold. Re-performance is the preferred method of correcting any unacceptable performance. The contractor shall provide the Government written or verbal response why the performance threshold was not met, how performance will be returned.
PRIMARY CONTRACTING OFFER
PRIMARY CONTRACTING OFFICER
"The Primary Contracting Officer for this action is Colette B. Day, however, any Contracting
Officer holding the appropriate warrant authority in the Baltimore District can serve as the
Contracting Officer for this contract.
Also, please note that any time the primary KO changes, it will be incorporated into the contract via unilateral modification to the contract."
SUBMI…