W912DR-13-R-0053_Amendment_0003.pdf
PDF 71 KB Posted
- Attached to
- East Campus Building- Marine Corps Federal contract opportunity
- Solicitation number
- W912DR-13-R-0053
About this file
The attached solicitation is hereby amended to provide responses to Requests for Information (RFI).
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| W912DR-13-R-0053_Amendment_2.pdf | ||
| W912DR-13-R-0053_Amendment_1.pdf | ||
| W912DR-13-R-0053_ECB-MC_Solicitation.pdf | ||
| Contractor_Format_for_RFIs.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to provide responses to RFI Questions. Please note, the contact number for Brandi Fialek, Contract
Specialist has changed to 443-654-7238.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 24-Oct-2013
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DR-13-R-0053
X 9B. DATED (SEE ITEM 11)
30-Sep-2013
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
24-Oct-2013
CODE
USACE, BALTIMORE
10 S. HOWARD STREET, ROOM 7000
CONTRACTING DIVISION
BALTIMORE MD 21201
W912DR 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912DR-13-R-0053
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00100 - BIDDING SCHEDULE/INSTRUCTIONS TO BIDDERS
The following have been added by full text:
AMENDMENT 3 RFI Q&A
Q42: Within Section 5.1 Factor 1: Past performance of Relevant projects, it states "The projects submitted must be completed at the time of submission, meaning that 100% of the PHYSICAL construction is complete". Please provide further clarification of the definition of 100% physical construction completion.
Will USACE consider projects for past performance that are essentially 100% construction complete for all major aspects of the project, but may still have punch list, commissioning/testing, or other closeout related activities?
A: Yes. However, demonstrating that a project is working as intended may be difficult if commissioning and testing activities are not complete and/or the project has not been accepted by the Government/Owner.
Q50: Reference is made to Ammendment 1, responsed to questions Q2 and Q3. The responses to these questions contradict in that Q2 states that "For Design only projects, 100% of the design must be complete" and Q3 states "for ongoing projects….100% of the design and 75% of the major construction milestones must be completed". Please clarify
A: Please see Amendment 2; Answer to RFI Question 3 has been updated.
Q51: Reference is made to item 52.236-4 (b) on page 52 of the solicitation. Please provide a site plan for where this project will be built. We do not have access to the JOC project drawings referenced in the solicitation.
A: Technical information will not be provided in Phase 1.
Q52: Per Amendment 1 RFI Question 3 and 6 - We have a question relative to the application of designer of record for design build projects. If the AE prepared bridging documents (35-65% complete) for a design build project and then provided title II services for the same project (reviewing submissions, making site visits and participating in project meetings) can the corresponding project be considered as relevant in the event the construction work is 75% or more complete within the solicitation requirements. The preparer of these documents are required to be experts in Design Build Contracts, Engineering and the Design of the corresponding building type.
A: No; Please reference the Amended Solicitation regarding Factor 3.
Q53: Please confirm if East Campus Building Marine Corps (ECB-MC) project includes a basement as stated in the 1391 document, the RFP makes no mention of it.
A: Please reference Solicitation page 5, Project Description :"The facility itself will consist of multiple stories and full sized basement with raised flooring in all above grade floors used for technical support and administrative space."
Q54: Please confirm if concrete frame is mandatory or will other types of structural frames be considered.
A: Technical information will not be provided in Phase 1.
W912DR-13-R-0053
Q55: As a follow up to RFI 33:
1) Can respondents recreate the Attachment B and C forms for construction and design project experience in an MS Word format? This will facilitate the respondent's ability to professionally add the required text and photos in each cell of the form.
2) Would there be any page limitation on the MS Word version of the form as long is the respondent agrees to be concise with the information provided?
A: Yes to recreating the attachments. Per the solicitation there is no page limit or page total and the page count is at the discretion of the contractor."
(End of Summary of Changes)