Reefer - Questions and Answers.pdf

PDF 393 KB Posted

Attached to
JPMRC Reefer Lease Federal contract opportunity
Solicitation number
W912CN-22-Q-0055
Issued by
Department of the Army Materiel Command Army Contracting Command

View the file

Other files for this federal contract opportunity

Other files attached to JPMRC Reefer Lease, newest first.
File Type Posted
Technical Exhibit 1 Revised 8 Sep 2022.pdf PDF
W912CN22Q0055 0002 Conformed.pdf PDF
W912CN22Q0055 Amendment 0002.pdf PDF
W912CN22Q0055 0001 Conformed.pdf PDF
W912CN22Q0055 Amendment 0001.pdf PDF
Technical Exhibit 1 Revised.pdf PDF
Technical Exhibit 1.pdf PDF
W912CN22Q0055 Reefer Solicitation.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions Answers

1. What is the voltage and amperage each unite will pull?

The voltage and amperage will depend on the reefer container the vendor is supplying.

The power source just needs to be able to run the reefer whether internal or external

2. How many hours will the generator run per day? 24 hours a day

3. What is the cable length you will need?

Long enough for any kind of external generator to reach the reefer hookups that is begin provided. Not necessary if the power source is internal to the refer container.

4. Are the generators being used to power the reefers?

Yes the generators are being used to power the reefers. Some reefers have internal power sources and some require external power sources. Generator is only required if the reefer does not have built in power.

5. I would like to know if on the above if you are looking for reefer trailers or reefer containers? We prefer containers due to containers generally has internal power supply.