SF30 W912BU21R0001 Amendment 0004.pdf
PDF 237 KB Posted
- Attached to
- Medium Class Hopper Dredge (MCHD) Federal contract opportunity
- Solicitation number
- W912BU21R0001
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SF30 W912BU21R0001 Amendment 0005 with Drawings.pdf | ||
| SF30 W912BU21R0001 Amendment 0003.pdf | ||
| Past Performance Questionnaire.pdf | ||
| SF30 W912BU21R0001 Amendment 0002.pdf | ||
| Attachment 1 QA Amendment 0002.pdf | ||
| Amendment 1 - W912BU21R0001 MCHD.pdf | ||
| B.08.05 W912BU21R0001 3010 MCHD Solicitation (final).pdf | ||
| DOD_SAFE_User_Guide v0_2d1.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W912BU21R0001
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Amendment 0004 hereby incorporates changes to section H6 as described in the SF 30 continuation sheet and extends the solicitation due date to 16 april 2021.
All other terms and conditions remain unchanged.
Only a w arranted Contracting Officer (either a Procuring Contracting Officer (PCO) or an Administrative Contracting Officer (ACO)), acting w ithin their appointed limits, has the authority to issue modif ications or otherw ise change the terms and conditions of this contract. If an individual other than the Contracting Officer attempts to make changes to the terms and conditions of this contract, you shall not proceed w ith the change and shall immediately notify the Contracting Officer. Proceeding w ith any w ork not authorized by the Contracting Officer w ill be at the Contractor’s ow n risk.
Extend solicitation due date to 16 April 2021
1. CONTRACT ID CODE PAGE OF PAGES
J 1 9
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 22-Mar-2021
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912BU21R0001
X 9B. DATED (SEE ITEM 11)
18-Dec-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
22-Mar-2021
CODE
US ARMY ENGINEER DISTRICT, PHILADELPHIA
CONTRACTING DIVISION
WANAMAKER BUILDING
100 PENN SQUARE EAST
PHILADELPHIA PA 19107-3390
W912BU 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AMENDSMENT 0004
H06 CONSTRUCTION PLAN
After receipt of the Notice to Proceed with Phase 0001AA, the Contractor shall develop and submit to the Contracting Officer’s Representative (COR) the Contractor’s proposed plan for the design, construction, testing, and delivery of the MCHD.
The proposed plan shall consist of a Master, Design, Production, Outfitting, Outsourcing, Integration, Risk Management, and Earned Value Management plan to the extent to which it shall result in the design and production of a high quality MCHD. The Government will evaluate the maturity and comprehensiveness of the plans including areas like engineering, material purchasing, production, resource allocation, and testing. The Government will review the planned approaches to assess the extent to which completion of the proposed effort can be accomplished within the four phases of this contract.
Master Plan: At a minimum, the Master Plan shall contain an executive summary, comprehensive overview of the project strategy across all supporting plans, a shipyard facility overview, and an overview of the MCHD production flow model in conjunction with site layout. The plan shall include completion dates of key milestones in the shipbuilding project, such as keel laying, launching, and delivery.
Design & Engineering Plan: At a minimum, this plan shall contain an all-inclusive summary of engineering management, design change management, design quality control, and supporting data for the critical path Integrated Master Schedule of the planned approach, addressing the different vessel design stages and planned reviews with the Government. Design areas to address include:
• Concept
• Functional Design
• Detailed Design
• ABS Review
Production Plan: At a minimum, the production plan shall contain a comprehensive overview of production management, production change management, quality control, resourcing, and supporting data for the critical path Integrated Master Schedule of the planned approach addressing the various production areas of the hull and superstructure. For example, items to highlight may include:
• Panel Construction
• Section Assembly
• Block Building
• Erection
• Launching
Outfitting Plan: The outfitting plan shall contain a detailed summary of outfitting management, outfitting change management, quality control, resources, and supporting data for the critical path Integrated Master Schedule of the planned approach addressing the various outfitting areas of the vessel. For example, items to address may include:
• Pre-outfitting
• Painting
• Slipway Outfitting
• Quay Outfitting
Outsourcing Plan: The outsourcing plan shall contain a comprehensive overview and planned approach to outsourcing from the shipyard to subcontractors. Outsourcing should be addressed in the critical path Integrated Master Schedule. For example, the plan may address items like:
• Total outsourcing
• Peak outsourcing
• Long lead time items
Integration Plan: The Integration plan shall contain a comprehensive overview and planned approach to integration from the shipyard to subcontracted and internal integration teams. The integration plan shall be included in the critical path Integrated Master Schedule. The plan shall address areas like:
• Automation
• Dredging System & Components
• Electrical System
Risk Management Plan: The Contractor shall establish and execute a Risk Management Plan describing the Contractor’s management strategy and processes for identifying, analyzing, and mitigating program risks and opportunities. The Contractor shall develop and maintain a Risk Database that documents each risk, the assessment results, recommended risk severity, the risk mitigation plans, and the progress against the mitigation plans.
Milestones associated with approved risk mitigation plans shall be reflected in the Integrated Master Schedule. The Contractor shall integrate risk management efforts and elements into new or revised design deliverables, including referencing and addressing project moderate and high risks, including associated mitigation actions, into contract deliverables.
Earned Value Management System: In the performance of this contract the Contractor shall establish, maintain, and use an integrated performance management system. Central to this integrated system, the contractor shall use an Earned Value Management System (EVMS) that uses an approach generally consistent with the intent of Electronic Industries Alliance document EIA-748 Earned Value Management Systems. This specification is structured to define the goals and objectives of the EVMS approach to address cost and schedule performance, while attempting to maximize contractor flexibility to develop their own approach to best match their internal business processes. As a result, this specification shall focus on the outputs from the Contractor’s EVMS system that the Government requires to surveil, monitor, and react to contractor performance.
The goal and objective of the Government is to ensure that adequate tools are in place to allow both the contractor and the Government to monitor progress, foresee any issues that are arising early on, and to provide meaningful reporting that allows all stakeholders to assess project status.
The EVMS shall be coordinated with the scheduling requirement in this contract so that all scheduled activities and all contractor costs are included in the EVMS. A baseline submittal shall be prepared and submitted.
The Contractor shall provide output reports from their EVMS system monthly. Submittals shall be coordinated with payment requests so that EVMS results can be reflected in progress payments.
Monthly Outputs:
EVMS monthly reporting shall include the following:
o An overview narrative discussing progress since the previous reporting period o A discussion of the critical path and progress on all critical path activities, including risks/concerns o A tabular status-ing of all activities
A plotted S curve showing:
The baseline Actual Cost of Work Performed (ACWP) Budgeted Cost of Work Performed (BCWP) or (EV) Budgeted Cost of Work Scheduled (BCWS)
Budget at Completion (BAC) Estimate at Completion (EAC)
Calculated Variances:
Cost Variance (CV) - BCWP-ACWP Schedule Variance (SV) – BCWP-BCWS Cost Variance percent - (BCWP—ACWP)/BCWP Schedule Variance percent – (BCWP-BCWS)/ Variance at Completion BAC-EAC BCWS
Performance Indices:
Cost Performance Index (CPI) – BCWP/ACWP Schedule Performance Index (SPI) – BCWP/BCWS
Overall Status:
Percent Scheduled – BCWScum /BAC Percent complete - BCWPcum/BAC Percent budget spent – ACWPcum/BAC Work Remaining (WR) - BAC-BCWPcum
Assessing Progress:
Activities with a firm milestone at the end may be progressed up to 100% Activities that do not have a firm milestone at end shall be limited to 95% Significant subcontractors and suppliers or ones on the critical path shall be contacted at least weekly
Initial Discussions: The contractor shall schedule a meeting at their facility within 60 days after award of contract.
The purpose of this meeting shall be for Contractor and Government representatives to discuss the Contractor’s proposed approach to this EVMS requirement so that when the EVMS process is implemented both the Contractor’s and the Government’s needs shall be met. It is not intended for the Contractor to produce their EVMS system at that time.
MASTER SCHEDULE DETAILED REQUIREMENTS:
The Master Schedule shall be prepared as a critical path Master schedule using Primavera. This contract shall use a total of four types of Master schedules: 1) Preliminary, 2) Initial, 3) Baseline, & 4) Updates
Qualifications: Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of reports. The authorized representative must have a minimum of 2 years’ experience scheduling vessel construction projects similar in size and nature to this project with scheduling software that meets the requirements of this specification. Representative must have a comprehensive knowledge of critical path method (CPM) scheduling principles and application.
General requirements: Prepare, for approval, a Project Schedule as specified herein. Show in the schedule the sequence in which the Contractor proposes to perform the work and dates on which the Contractor contemplates starting and completing all schedule activities. The scheduling of the entire project, including the design and construction sequences, is required. The scheduling of construction is the responsibility of the Contractor.
Contractor management personnel shall actively participate in its development. Subcontractors and suppliers working on the project shall also contribute in developing and maintaining an accurate Project Schedule. The schedule must be a forward planning, as well as, a project monitoring tool. Ensure the schedule captures ABS reviews, testing, and inspections during all phases of the contract.
Critical Path Method: Use the Critical Path Method (CPM) of network calculation to generate the Project Schedule.
Activity Durations: The time estimate of the duration of the activities shall be logical and consistent with the Contract Documents and shall be based on realistic and available resources (manpower, materials, tools, and equipment, etc.), of the Contractor. The unit time for measuring the duration of activities is the "Day." Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods.
Procurement Activities: The schedule must include activities associated with the submittal, approval, procurement, fabrication and delivery of long lead materials, equipment, fabricated assemblies, and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over ninety calendar days. A typical procurement sequence includes the string of activities: submit, approve, procure, fabricate, and deliver.
Contract Changes/Requests for Equitable Adjustment (REA) Coding: Assign Activity code to any activity or sequence of activities added to the schedule because of a Contract Modification, when approved by the Contracting Officer, with a Contract Changes/REA Code. Key all Code values to the Government's modification numbering system (i.e. P0001, P0002, etc.). Any activity or sequence of activities added to the schedule because of alleged constructive changes made by the Government may be added to a copy of the current schedule, subject to the approval of the Contracting Officer. Assign Activity codes for these activities with a Contract Changes/REA Code (i.e. REA0001, REA0002). Approval to add these activities does not necessarily mean the Government accepts responsibility and therefore liability for such activities and any associated impacts to the schedule, but rather the Government recognizes such activities are appropriately added to the schedule for the purposes of maintaining a realistic and meaningful schedule. Such activities shall not be Responsibility Coded to the Government unless approved. An activity shall not have more than one Contract Changes/REA Code.
Schedule Constraints and Open-Ended Logic: Constrain completion of the last activity in the schedule by the contract completion date. Schedule calculations shall result in a negative float when the calculated early finish date of the last activity is later than the contract completion date. Include as the last activity in the project schedule an activity called "End Project". The "End Project" activity shall have a "LF" constraint date equal to the contract completion date for the project, and with a zero-day duration or by using the "project must finish by" date in the scheduling software. The schedule shall have no constrained dates other than those specified in the contract. The use of artificial float constraints such as "zero free float" or "zero total float" are prohibited. There shall only be two open ended activities: Start Project (or NTP) with no predecessor logic and End Project with no successor logic.
Under this contract the project owns the float. Float of the master schedule gets used on a first come first served basis as issues arise.
Out-of-Sequence Progress: Activities that have progressed before all preceding logic has been satisfied (Out-of- Sequence Progress) shall be allowed only on a case-by-case basis. Propose logic corrections to eliminate all out of sequence progress or justify not changing the sequencing for approval prior to submitting an updated project schedule. Correct out of sequence progress that continues for more than two update cycles by logic revision, as approved by the Contracting Officer.
Integrated Master Schedule submissions: Provide the submissions as described below.
Preliminary Integrated Master Schedule Submission:
• Due within 30 calendar days of phase one NTP
• Contains detail for phases I and II of the contract
• Contains summary activities for the remaining phases.
• 1 activity per level 2 WBS structure
• Used for payment purposes
• Afterwards only Govt. approved updated Initial Schedule shall be used.
Initial Integrated Master Schedule Submission:
• Detailed schedule for the entire project.
• Submitted within 60 days of phase I NTP
• Shall be appropriate level of detail for the complexity of the project
• Shall address all supporting plans (engineering, production, outfitting, outsourcing, testing, and integration).
• A planning document shall be submitted with the initial schedule identifying all schedule development assumptions, constraints, limitations, and applicable notes.
• Activities represent work activities under each WBS through the entire project
• Activities shall be resourced (i.e. material, labor, and equipment resources and costs). Resource data such as cost and required codes must be entered for activities. The schedule data can be ordered in different sorts and compiled into specific reports for management purposes. Actual progress must be entered once work commences. Based on this progress with actual start dates, actual finish dates, percent complete, and remaining duration recorded, progress payments can be calculated.
• Activities shall correspond and be synched with the submittal, materials, and equipment schedule.
• The schedule shall be used as a primary planning and event progressing tool. It shall show and logically connect critical milestone events and accomplishments for both the prime and subcontractors through the last required delivery or end of the contract performance period, whichever is later.
• The schedule shall be integrated with and used for EVMS calculations and reporting.
• Subsidiary plans and schedules required herein shall be integrated with the Master Plan and Master
Schedule.
• The schedule shall show the order in which the contractor proposed to do the work, the start date on the salient features (including procurement of materials, plant, and equipment) and contemplated dates for completing the same.
• Progress on the contract must be shown. Progress shall show dollar amounts for various phases of work that directly relate to those items on the payment estimate. The Master Schedule and its support documents shall include a list of pay activities that the Contractor shall develop in conjunction with the construction schedule. The sum of all pay activities shall be equal to the total contract amount, including modifications.
Pay activities shall be grouped by Contract Line Item Number (CLIN), and the sum of the activities shall equal the amount of each CLIN. The total of all CLINs equals the Contract Amount.
• The Government has 28 days for approval.
Baseline Integrated Master Schedule:
• All percent complete =0
• Approved at the end of phase one
• Signed by contractor and COR
Integrated Master Schedule Updates:
• The schedule must be updated and submitted monthly with the Progress Payment Request.
• **Only additional time approved through modification (KO approved) can be added to the schedule update.
Every Integrated Master Schedule Submission requires: (This includes schedule updates each month)
• Narrative
• Activity description along the two most critical paths
• Descriptions of current & anticipated problem areas
• Description of delaying factors
• All known Impacts
• Explanations of corrective actions in maintaining or regaining schedule. If there are project schedule changes in the schedule submission that have not been previously approved, there shall be a pending approval version of the schedule and the currently approved schedule.
• The Narrative Report shall specifically reference, on an activity by activity basis, all changes made since the previous period and relate each change to documented, approved schedule changes.
• S-Curve
• Earned Value Management Metrics shall be provided with S-Curve
• Precedence Diagram Method (PDM) Diagram
• Activity/WBS Progress Report
• Float Report
• Logic Report
• 1 Electronic PDF file of schedule
• 1 Electronic native file of schedule
• Schedule Reports: Typically reports shall contain: Activity Numbers, Activity Description, Original
Duration, Remaining Duration, Early Start Date, Early Finish Date, Late Start Date, Late Finish Date, Total
Float, Actual Start Date, Actual Finish Date, and Percent Complete. The following lists typical reports that shall be requested.
The Master critical path schedule shall capture the Contractor’s proposed starting date, duration in calendar days, ending date, and percentage completion (both as planned and as achieved) for all of the major activities of the contract. The plan shall also show the amount of the total bid price (percent and actual dollars) associated with each activity. The plan shall also have the progress “S” curve plotted (both as planned and as achieved).
The activities shown on the chart shall be developed by the Contractor and shall include, as a minimum, the following respective line items:
• All WBS items as identified in Section C (Levels 1, 2, & 3)
• Planning & Support
• Bonding
• Scheduling
• ABS Fees (Engineering Review, Inspection, Surveys, Testing, Vessel & Material Certificates)
• Launch – Labor & Material
• Pre-Trial Tests – Labor & Material
• Builder’s Dock Trials – Labor & Material
• Dock Trials & Crane Tests – Labor & Material
• Delivery
• Final Acceptance Demonstrations – Labor & Material
• Overhead & Profit
In addition, the following milestone events shall be marked on the schedule:
• Award of Contract
• Notice to Proceed with Planning and Scheduling (Phase 0001AA)
• Notice to Proceed with Engineering (Phase 0001AB)
• Notice to Proceed with Construct & Test (Phase 0001AC)
• Notice to Proceed with Test, Sea Trials, & Deliver (Phase 0001AD)
• Launch
• Tests and Trials
• Provisional Acceptance
• Final Acceptance
• Delivery
Periodic Schedule Update Meetings: Conduct periodic schedule update meetings for the purposes of reviewing the Contractor's proposed out of sequence corrections, determining causes for delay, correcting logic, maintaining schedule accuracy, and determining earned value. Meetings shall occur at least monthly within five calendar days of the proposed schedule data date and after the Contractor has updated the schedule with Government concurrence respecting actual start dates, actual finish dates, remaining durations and percent complete for each activity it intend to status. The meeting shall be a working interactive exchange which shall allow the Government and the Contractor the opportunity to review the updated schedule on a real time and interactive basis. The Contractor's Project Manager and/or the Authorized Scheduler shall attend the meeting.
Requests for Time Extensions: In the event the Contractor believes it is entitled to an extension of the contract performance period, completion date, or any interim milestone date, furnish the following for a determination by the Contracting Officer: written justification, project schedule data, and supporting evidence as the Contracting Officer may deem necessary. Submission of proof of excusable delay, based on revised activity logic, duration, and costs (updated to the specific date that the delay occurred) is a condition precedent to any approvals by the Government.
In response to each Request for Proposal issued by the Government, the Contractor shall submit a schedule impact analysis demonstrating whether or not the change contemplated by the Government impacts the critical path.
Justification of Delay: The project schedule shall clearly display that the Contractor has used, in full, all the float time available for the work involved with this request. The Contracting Officer's determination as to the number of allowable days of contract extension shall be based upon the project schedule updates in effect for the time period in question, and other factual information. Actual delays that are found to be caused by the Contractor's own actions, which result in a calculated schedule delay, shall not be a cause for an extension to the performance period, completion date, or any interim milestone date.
Payment: No separate payment shall be made for work under this section and all costs shall be included in the overall contract price.
SECTION SF 1449 - CONTINUATION SHEET
SOLICITATION/CONTRACT FORM
The required response date/time has changed from 02-Apr-2021 04:30 PM to 16-Apr-2021 04:30 PM.
The following have been deleted:
SPECIAL CONTRACT REQUIREMENTS
(End of Summary of Changes)