W912BU18B0012.pdf
PDF 790 KB Posted
- Attached to
- 3128 MVP Deck Material Barges Federal contract opportunity
- Solicitation number
- W912BU18B0012
About this file
Solicitation
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bid_Abstract_W912BU18B0012.pdf | ||
| W912BU18B0012_0002.pdf | ||
| W912BU18B0012_0001.pdf | ||
| Drawing_844-A398-01.pdf | ||
| W912BU18B0012.pdf | ||
| 806-D420-01.pdf | ||
| 844-C406-01_MDC_STANDARD_FLOATING_PLANT_PAINT_SCHEDULE_.pdf | ||
| 806-D309-01.pdf | ||
| 844-B000-01_TITLE.pdf | ||
| 806-D170-01.pdf | ||
| 806-D460-01.pdf | ||
| 806-D105-01.pdf | ||
| 844-B405-01_CATHODIC_PROTECTION.pdf | ||
| 806-D307-01.pdf | ||
| 806-D205-01.pdf | ||
| 806-D415-01.pdf | ||
| 806-D427-01.pdf | ||
| 806-D307-02.pdf | ||
| 806-D311-01.pdf |
Show all 19
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CODE
(Hour)
PAGE(S)
until 02:00 PM local time 31 Aug 2018
A X B X C X D
EX
X
G F 64 - 86
87 - 88 X H 89 kecia.m.blackwell@usace.army.mil
RATING PAGE OF PAGES
7. ISSUED BY
(Date)
IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.
Previous Edition is Unusable 33-134 STANDARD FORM 33 (REV. 9-97)
Prescribed by GSA FAR (48 CFR) 53.214(c)
1 89
(If other than Item 7)
15A. NAME 16. NAME AND TITLE OF PERSON AUTHORIZED TO
AND
ADDRESS
SIGN OFFER (Type or print)
OF
OFFEROR
AMENDMENT NO. DATE
15B. TELEPHONE NO (Include area code) 17. SIGNATURE15C. CHECK IF REMITTANCE ADDRESS
IS DIFFERENT FROM ABOVE - ENTER
SUCH ADDRESS IN SCHEDULE.
18. OFFER DATE
1. THIS CONTRACT IS A RATED ORDER
UNDER DPAS (15 CFR 700)
2. CONTRACT NO.
W912BU 8. ADDRESS OFFER TO
See Item 7
9. Sealed offers in original and 1 copies for furnishing the supplies or services in the Schedule will be received at the place specified in Item 8, or if handcarried, in the depository located in
CAUTION - LATE Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and conditions contained in this solicitation.
10. FOR INFORMATION
CALL:
A. NAME (NO COLLECT CALLS)
KECIA M BLACKWELL 215-656-6894
11. TABLE OF CONTENTS
SOLICITATION/ CONTRACT FORM
SUPPLIES OR SERVICES AND PRICES/ COSTS
2 - 3
X I CONTRACT CLAUSES
DESCRIPTION/ SPECS./ WORK STATEMENT X
PACKAGING AND MARKING
4 - 18
J LIST OF ATTACHMENTS
INSPECTION AND ACCEPTANCE
DELIVERIES OR PERFORMANCE
20 - 29 30 - 32
X K
REPRESENTATIONS, CERTIFICATIONS AND
OTHER STATEMENTS OF OFFERORS
CONTRACT ADMINISTRATION DATA X
SPECIAL CONTRACT REQUIREMENTS
OFFER (Must be fully completed by offeror) 33 - 43 X M
L INSTRS., CONDS., AND NOTICES TO OFFERORS
EVALUATION FACTORS FOR AWARD
NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.
is inserted by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the designated point(s), within the time specified in the schedule.
13. DISCOUNT FOR PROMPT PAYMENT
(See Section I, Clause No. 52.232-8)
14. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments
AMENDMENT NO. DATE
to the SOLICITATION for offerors and related documents numbered and dated):
FACILITY
12. In compliance with the above, the undersigned agrees, if this offer is accepted within calendar days (60 calendar days unless a different period
SOLICITATION, OFFER AND AWARD
X
(X) SEC. DESCRIPTION (X) SEC. DESCRIPTION PAGE(S)
PART I - THE SCHEDULE
26. NAME OF CONTRACTING OFFICER (Type or print) 27. UNITED STATES OF AMERICA 28. AWARD DATE
EMAIL:TEL: (Signature of Contracting Officer)
CODE CODE
B. TELEPHONE (Include area code) C. E-MAIL ADDRESS
AWARD (To be completed by Government)
19. ACCEPTED AS TO ITEMS NUMBERED 20. AMOUNT 21. ACCOUNTING AND APPROPRIATION
22. AUTHORITY FOR USING OTHER THAN FULL AND OPEN COMPETITION:
10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( ) (4 copies unless otherwise specified)
23. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
24. ADMINISTERED BY (If other than Item 7) CODE 25. PAYMENT WILL BE MADE BY CODE
PART IV - REPRESENTATIONS AND INSTRUCTIONS
PART III - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
44 - 60
PART II - CONTRACT CLAUSES
US ARMY ENGINEER DISTRICT, PHILADELPHIA
CONTRACTING DIVISION
WANAMAKER BUILDING
100 PENN SQUARE EAST
PHILADELPHIA PA 19107-3390
FAX:
TEL:
FAX:
TEL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SOLICITATION
61 - 63
6. REQUISITION/PURCHASE NO.5. DATE ISSUED
01 Aug 2018
4. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
[ X ]
3. SOLICITATION NO.
W912BU18B0012
Section B - Supplies or Services and Prices
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Deck Material Barges
FFP
Design, construct, and test two Deck Material Barges for the Corps of Engineers, St. Paul District for use in support of its maintenance mission on the inland river navigation system, in accordance with the attached specifications.
NET AMT
0001AA 1 Job
PLANNING, SCHEDULING, AND ENGINEERING
FFP
Two Deck Material Barges (The submittals required for Planning and Scheduling are listed in contract Clause H02.). This item is initiated only by a Notice To Proceed issued by the Contracting Officer.
FOB: Destination
0001AB 1 Job
CONSTRUCT, TEST, AND DELIVER
FFP
Two Deck Material Barges (The submittals for “Construct, Test, and Deliver” are listed in contract Clause H02.). This item is initiated only by a Notice To Proceed issued by the Contracting Officer. The Contractor may not start this item until he receives a Notice To Proceed for this item.
Section C - Descriptions and Specifications
SCOPE OF WORK
C000 GENERAL
C001 PROJECT DESCRIPTION
The Marine Design Center (MDC) of the U.S. Army Corps of Engineers (USACE) has issued this Invitation for Bid (IFB), to acquire two welded steel barges. The barges will be used in support of the civil works maintenance and repair mission of the St. Paul District.
C002 PRINCIPAL CHARACTERISTICS
The principal dimensions of each barge shall be as follows:
Length Overall .......................................................................................................... 120'- 0" Beam (Overall) ........................................................................................................... 30'- 0" Depth (Molded at Centerline) ....................................................................................... 7’-0” Depth (Molded at Side) ................................................................................................ 6’-9” Bow ............................................................................................................................ Raked Stern ........................................................................................................................... Raked Design Deck Loading ........................................................................................... 2,000 PSF
C003 DESIGN STANDARDS
The barges shall be designed and constructed in accordance with the contract drawings, and the latest edition and interpretations of the rules, regulations, requirements and standards of the Legislation, Regulatory Agencies and technical organizations listed below. The contractor is required to incorporate into the barges any revisions to the rules and regulations listed below as well as those stipulated in the respective specification clauses.
U.S. Army Corps of Engineers, Publication No. EM 385-1-1; “Safety and Health Requirements Manual.”
American Bureau of Shipping (ABS) "Rules for Building and Classing Steel Vessels for Service on
Rivers and Intracoastal Waterways."
American Bureau of Shipping “Guide For Shipbuilding And Repair Quality Standard For Hull Structure During Construction.”
American Welding Society “Guide For Steel Hull Welding”, ANSI/AWS D3.5-85.
U.S. Coast Guard Regulation 46 CFR, Subchapter S – “Subdivision and Stability”.
C004 CLASSIFICATION & CERTIFICATION
A. ABS CLASSIFICATION
The Contractor shall be responsible obtaining necessary regulatory body reviews and approvals, obtaining necessary inspections and surveys during construction and for the certification and classing of the barges as follows:
ABS classification for “Maltese Cross ✠A-1 Intra-Coastal Waterway, River Service”, with “Reinforcement B” notation.
ABS shall class the barges for a 2000 PSF design deck load, except in way of the manholes.
All expenses associated with the acquisition of the required reviews, inspections, construction support, classing and certification shall be borne by the contractor.
The contract drawings are the as-built drawings for the U.S. Army Corps of Engineers, New Orleans District, Barges CE-1501 and CE-1502, Marine Design Center Hull Numbers 806 and 807. These barges will be identical with the following exceptions:
a 30” high cargo box installed on the main deck the manholes will all be raised 12” above the deck the barge “names” will be as directed by the COR
The previous completed barges were built in 2016 by Basic Marine, Inc. of Escanaba, MI. The shipyard hull numbers were 227 and 228. The ABS Class Numbers were 16268158 and 16268159. This information should be used when contacting ABS for review and certification of these vessels.
The Contractor shall update the contract drawings in accordance with these specifications and submit them directly to ABS for approval. The recommended ABS point of contact is Mr. Rich Delpizzo (Program Manager, ABS Government Operations), who can be reached by phone, email or mail, at: (703) 519-9233, RDelpizzo@eagle.org.
The contractor is responsible for submission of these drawings to ABS for approval of the engineering by ABS. All drawing related coordination with ABS on this project shall be handled directly by the Contractor.
The contractor shall contract for and be directly responsible for obtaining engineering drawing reviews, necessary inspections, surveys, testing, vessel and material certificates, during construction, as required by ABS for the barges’ certification and classification as stated above. All costs for construction related support by ABS shall be to the contractor’s account.
The contractor shall be financially responsible for any additional ABS review costs incurred due to contractor request for deviation from approved drawings, where the Government allows the deviation.
If the Contractor intends to launch, test, operate or tow the barges “out of class”, the Contractor must specifically advise ABS of such intent and incorporate any and all modifications required by that agency for such operation at no additional cost to the Government and at no additional contract time. Any such modifications which, in the opinion of the COR, affects the arrangements, operability, or suitability of the barges shall be removed from the barges by the Contractor at no additional cost or time and the barges returned to new condition prior to Final
B. ABS ONSITE INSPECTION
When steel construction commences, the Contractor shall coordinate with ABS to ensure the frequency of onsite inspections are not less than once every two weeks. The Contractor shall provide a schedule for the ABS Onsite Inspections. The schedule shall include the scheduled inspection date(s), actual inspection date(s), and signature blocks for the ABS Inspector and Contractor, and notes for what inspection(s) were conducted. This report shall be kept current and upon request be made available to the COR.
C. VESSEL OWNER AND ADDRESS
For the ABS certificate of classification, the owner shall be listed as “U.S. Army Corps of Engineers, St. Paul District”.
The owner’s address of record shall be listed as:
US ARMY CORPS OF ENGINEERS –SAINT PAUL DISTRICT
CEMVP-XX-XX
180 5th St. East, Ste. 700 St. Paul, MN 55101
D. ABS ENGINEERING MANAGER ACCESS & DISCLOSURE
The Marine Design Center (CEMDC) will be the “Owner’s Representative” on this project and all correspondence with ABS shall be made available to the COR. In order to facilitate the communication process and reduce the paperwork burden on all parties, the Contractor, and all sub-contractors, shall utilize the ABS Eagle Construct Engineering Manager Portal (02E) for all drawing submittals and correspondence. The Contractor and all sub-contractors shall make the necessary arrangements with ABS to ensure that the Marine Design Center is granted the following Oversight Permissions for this Contract:
View project and drawing status View comments View transmittals Download approved drawings and review letters E-Mail notification of approval E-Mail notification of transmittal Status Disclaimer
The Marine Design Center’s ID/WCN number is 615255 and the point of contact with respect to the ABS Coordination/Engineering Manager Portal (02E) is Mr. Tim Keyser, Timothy.J.Keyser@usace.army.mil, phone: (215) 656-6171.
The Contractor shall ensure that, as a part of its contract with ABS the Contractor authorizes ABS to disclose to and discuss with the Army Corps of Engineers any Rule or certification criteria issues, design assumptions and their impact on classification and certification, and any other technical considerations on which classification is to be based or which may affect future classification or certification of the barges.
The Contractor shall authorize ABS to provide the Army Corps of Engineers at its request with a copy of all correspondence related to classification, statutory certification or other compliance verification for which ABS is responsible as it is promulgated and initially distributed. This is to include drawings and other engineering work requiring ABS approval as well as correspondence generated which relates to such approvals, including all such correspondence dealing with vendors.
In addition, the Contractor shall copy the Army Corps of Engineers with correspondence regarding classification, statutory certification and other compliance verification for which ABS is responsible. The Contractor shall also authorize ABS to establish and maintain contact with other certification, verification and compliance agents involved on the barges being built.
Upon request by the COR, the Contractor shall request ABS to furnish the Government with the project comment list.
The list shall include open and closed technical and surveyor comments. The surveyor comments shall not only include comments generated during the drawing review process, but also comments generated by the ABS Surveyor during construction inspections. The comment list shall be sent directly from ABS to the COR via email as a .pdf file.
At the completion of the ABS review process, the Contractor shall download all ABS “Eagle Stamped” drawings and provide them on a CD or DVD to the Government in .pdf format.
C005 VESSEL IDENTIFICATION
The barges to be acquired through this solicitation have been assigned the following Marine Design Center project number, names and hull numbers:
MDC Project Number MDC Hull Numbers .......................................................................... 844, 845 Vessel Names .......................................................................................... TBD
For the purposes of document and drawing preparation, the title "CEMVP DECK CARGO BARGES, 120’ x 30’ x 7’" and the MDC hull numbers 844 & 845 shall be used on all documents and drawings.
C006 SCOPE OF WORK
A. CONTRACTOR’S RESPONSIBILITY
The contract consists of two phases:
Phase I ........................... Planning, Scheduling and Engineering Phase II .......................................... Construct, Test and Deliver
In accordance with the two phases, the contractor assumes complete responsibility for obtaining ABS classification and certification, and constructing, testing and delivering the barge to meet the requirements of the contract. Should the contractor determine at any time that he is unable to fulfill those responsibilities, he shall notify the COR immediately of the problem experienced and his proposed manner of correction.
B. CONTRACT INTENT
It is intended that the contractor will be able to bid, and perform further design development of the barges from the contract drawings provided in the solicitation.
C. DRAWING CHANGES
The plans and specifications of this contract have been prepared in accordance with the referenced design standards.
The plans issued as part of this solicitation are based on the as-built drawings for the previously built barges.
All members, plating and welds have been defined. The contractor shall not deviate from the hull principal characteristics, subdivision and general arrangements, scantlings and welds as shown on these plans.
It should be expected that a contractor could bid and build the barges with only such engineering and additional design effort as is necessary to modify the design to incorporate the required design change and to suit the individual construction and business practices of the shipyard.
D. DRAWINGS PROVIDED & REQUIRED
1. Contract Drawings
The contract drawings are listed in Section J, Clause J01, Contract Drawings & Documents for CLIN 0001. The contract drawings are provided with these specifications for bid and construction purposes.
2. As-Built Drawing Requirements
The requirements for the “As-Built” drawings are defined in Section H, Clause H14, As-Built Drawings.
C010 DEFINITIONS
The following definitions are applicable to phrases and acronyms used throughout this contract:
COR - Contracting Officer’s Representative - a member of the contract management and quality assurance team authorized by the Contracting Officer to perform certain administrative and managerial duties. A copy of the COR’s authority letter is furnished to the contractor.
K.O. - Contracting Officer - A person with the authority to enter into, administer and/or terminate contracts and make related determinations and findings.
MDC – Acronym for the Marine Design Center.
QC - Quality Control - Quality Control is a function of the contractor. Refer to clause E03. Quality Assurance (QA) is a function of the Government.
USACE – Acronym for United States Army Corps of Engineers.
C025 CONTRACTOR QUALITY STANDARDS
The contractor shall be responsible for the construction of complete and functioning barges. The contractor shall utilize the specified components so as to meet specification requirements utilizing construction and testing methods to ensure that the completed barges conforms to the intended design.
Inspection by the Marine Design Center is for the purpose of verifying the proper function of the contractor’s quality control measures and is not to be used as a substitute for control of quality by the contractor.
Every effort shall be made during production planning to construct the vessel in an efficient sequence minimizing re-work and repair. Care shall be taken to assure the latest revisions of the Final Design plans are being used.
A. STRUCTURAL MATERIALS
Unless otherwise specified or noted on the contract drawings, all structural hull material shall be in accordance with the following specifications:
American Bureau of Shipping (ABS), “Rules for Building and Classing Steel Vessels” and “Rules for
Building and Classing Steel Vessels for Service on Rivers and Intracoastal Waterways”.
Welding Materials - ABS “Approved Welding Electrodes, Wire-Flux and Wire Gas Combination.”
B. STANDARD PARTS & MATERIALS
All articles, fittings, equipment, machinery, supplies, and materials used in the construction and outfitting of the barges shall be the highest grade, free from defects and imperfections, unused and, be the standard product of reputable manufacturers, to the maximum extent practicable. Any material not specified shall be the best of their kind for the purpose intended.
Materials specified herein to meet the requirements of standard specifications published by national authorities shall conform to the respective editions, including amendments, specified. No salvage materials shall be used in the work.
C. WORKMANSHIP
All labor shall be especially skilled for each kind of work and under competent direction.
In engaging one kind of work with another, marring or damage of previously acceptable construction shall be cause for rejection. All parts of the barges intended to join or bear upon other parts shall have complete and solid contact and shall fit together without excessive cold work during erection. Shims or liners shall not be used for the purpose of overcoming a bad fit. Lightening holes may be punched or flame-cut and all edges shall have burrs removed. Holes in members having sharp curvature shall be avoided.
D. WELDERS
All welding under this contract shall be done only by welders who have successfully passed qualification tests accepted by the American Bureau of Shipping or other regulatory bodies acceptable to ABS.
The contractor shall bear the expense of conducting these tests and shall certify, by name to the Contracting Officer, welders who have successfully passed the prescribed tests and hold current, valid certifications.
The contractor shall require any welder to repeat these tests when in the opinion of the Contracting Officer, the work of the welder indicates a reasonable doubt of his proficiency. In such cases the welder shall be re-certified as above if he successfully passed the retest; otherwise, he shall be disqualified until he has successfully passed the retest.
The contractor shall maintain records of each welder’s certification during the course of the contract. The records are to be available for examination upon request of the Contracting Officer.
E. WELDING
All welding shall be in accordance with the current rules and Quality Standards of the American Bureau of Shipping and ANSI/AWS D3.5-85. All welding equipment used on the work shall be of a modern type subject to close control.
The electrodes used throughout the work shall be suitable for use with the parent metal at each weld, and be approved by ABS.
Welding procedures, as to direction, length, numbers, and sequence of beads, shall be carefully planned to minimize lock-up stresses. Care shall be exercised to produce smooth even beads, especially on all exposed plating and fittings.
Beads shall be chipped and ground where directed by the COR.
The contractor shall employ appropriate welding procedures and grounding connections to preclude the possibility of anodic erosion of the hull after launching
F. INSTALLATION
Materials and equipment shall be installed in accordance with the approved recommendations of the manufacturer, and in compliance with the contract documents. The installation shall be accomplished by workmen skilled in this type of work.
G. FAIRNESS & CONSTRUCTION TOLERANCES
Steel plating and structure shall be installed using proper welding procedures and sequences to insure fair, undistorted plating panels. The use of filler materials to surface unfair areas is not acceptable.
Maximum allowable construction distortion and tolerances are defined in the ABS “Guide For Shipbuilding And Repair Quality Standard For Hull Structure During Construction”. Distortion shall not exceed the amounts in this guide.
H. CONSTRUCTION STANDARDS
All material and equipment shall be new, of current manufacture and suitable for the marine service intended. Spare parts and service shall be readily obtainable.
All material, unless otherwise specified in these specifications or in the drawings, shall be of commercial quality to ASTM, ANSI, or SAE specifications.
During construction and before delivery, the contractor shall be responsible for protection of all material, equipment, etc., intended for the barges.
The overweight tolerance of members shall be within the limits defined by the specifications of the American Society for Testing and Materials (ASTM).
All materials shall be free of imperfections due to manufacturing processes and from defects which adversely affect appearance or serviceability.
All sharp edges or projections which constitute a personnel hazard shall be removed or ground smooth. All notches shall have a radius to prevent stress concentrations.
C100 SCIENTIFIC
C105 HULL GEOMETRY
A. CONTRACT DRAWING
806-D105-01 HULL LINES
B. GENERAL
The hull geometry for each barge is as shown on the contract drawing.
C115 LIGHTWEIGHT SURVEY
Upon completion of all work, with the barges in the lightship condition, a lightweight survey shall be conducted on each completed barge. The lightweight survey shall be carried out in accordance with ASTM F1321-14. Along with the four draft mark readings, five (5) freeboard readings shall be taken on each side to determine the vessel’s displacement. The contractor shall provide a lightship survey report, which gives the "lightship" load condition displacement.
Within 10 business days after completion of the lightship survey, the contractor shall submit the results to the Government. The report will be 844-D115-02 LIGHTWEIGHT SURVEY REPORT.
The Government will prepare all stability related documents.
C185 TEST & TRIALS
The barges and their component parts shall undergo tests and trials in accordance with Section E, Clause E05, Tests, Trials, & Demonstrations.
C200 ARRANGEMENTS
C215 GENERAL ARRANGEMENTS
806-D205-01 OUTBOARD PROFILE & GENERAL ARRANGEMENT
The configuration of the hull and deck arrangement, and the bulkheads and subdivisions within the hull shall be as shown on the contract drawing, with the following exceptions.
The Contractor shall design, fabricate and install a 30” cargo box on the main deck. The interior of the cargo box shall be approximately 100’ long by 23’ wide. See Section C398 for addition details.
All of the manholes shall be raise to extend 12” above the main deck. See Section C415 for additional details.
The Contractor shall revise the contract drawing (re-title 844-C205-01) and submit to the Government for review within 60 days after NTP for Phase I.
C300 STRUCTURE
C305 HULL STRUCTURE
A. CONTRACT DRAWINGS
806-D307-01 SHELL PLATING AND FRAMING
806-D307-02 DECK PLATING AND FRAMING
806-D309-01 TRANSVERSE FRAMING AND BULKHEADS
806-D311-01 LONGITUDINAL FRAMING – RAKE & TOWKNEE DETAILS
806-D420-01 DECK FITTINGS
The hull steel plate shall be ABS Grade A Steel. The steel structural shapes, stiffeners, and angles shall be ASTM A36 steel.
All welding and weld sizes shall be in accordance with ABS rules. Any area of welding not defined in the contract drawings shall be developed by the barge contractor and approved by ABS as required. All welding shall be performed in accordance with AWS and ABS specifications and procedures.
The shell and main deck plating shall be constructed of longitudinal strakes of lengths consistent with accepted practice for hulls. All seams shall be connected with full penetration welds, except the bilge radius and the deck edge, which shall be lap joints, joined with 100% weld, inside and out. Seams shall not be aligned directly over bulkhead plating or over the webs of stiffeners and transverses.
Deck structure shall meet ABS requirements for loading of 2000 psf. Note that manholes are not required to support 2000 psf loading.
C398 DECK CARGO BOX
The Contractor shall design, fabricate and install a 30” high cargo box on the main deck. The interior of the cargo box shall be approximately 100’ long by 23’ wide. Pipe bollards shall be provided for the removable gate installation at each end.
The removable ends shall be all-welded steel structure, 18’ in length and fitted with pipe sections at the ends of the sections. The pipe ends slide over the top of pipe bollards to secure the gates closed. The ends shall be fitting with lifting eyes. Each eye shall be designed in accordance with ASME B30.23 (Below the Hook Lifting Devices) to support the weight of the gate by itself. The safe working load (SWL) of each lifting eye shall be stenciled in yellow paint on (or near) the lifting eye. The Contractor shall obtain the certified weight of each gate the value in yellow paint on the inside of the gate.
Each cargo box shall be provided with two hinged gates to provide for access through a 30” clear opening. One opening shall be at the forward end on the port side; and one opening at the aft end on the starboard side. Each gate shall swing inward and be provided with a hasp and padlock.
Each cargo box shall be provided a grab rail along the length of the cargo box on both side. A cap rail shall be installed around the perimeter of the box. Freeing ports shall be provided along the side to allow water to drain.
Steel “alignment bars” shall be welded to the deck plate. The alignment bars shall be installed after installation of the removable end gates on the barge. The alignment bars shall be located so that they are close to the bottom horizontal stiffener on the outboard side of the cargo box end gate structure.
The box shall be properly designed and reinforced to support rock and gravel pile loads.
C400 OUTFIT
C405 CATHODIC PROTECTION
844-B405-01 CATHODIC PROTECTION
B. GENERAL
The contractor shall provide and install 100-lbs (10 qty x 10-lbs) MIL-SPEC Aluminum Alloy Anodes. The anodes shall be manufactured and installed in accordance with MIL-SPEC MIL-A-24779. The anodes shall be designed for use on hulls of ships, tugs, barges, etc. All anodes shall be faired or tapered to minimize turbulence. The anodes shall be manufactured with steel core straps and welded to the hull after paint is applied to the hull. The paint on the hull (exterior and interior) shall be restored after installation. The anodes shall not be painted.
Two anodes shall be provided on the forward rake, evenly spaced transversely apart, between frame 6 and 11. Two anodes shall be provided on the bottom, evenly spaced transversely apart off centerline, between frame 21 and 26.
Two anodes shall be provided on the bottom, evenly spaced transversely apart off centerline, between frame 37 and
43. Two anodes shall be provided on the bottom, evenly spaced transversely apart off centerline, near frame 60. Two anodes shall be provided on the bottom, evenly spaced transversely apart off centerline, between frame 77 and 83.
Two anodes shall be provided on the bottom, evenly spaced transversely apart off centerline, between frame 94 and
95. Two anodes shall be provided on the aft rake, evenly spaced transversely apart, between frame 109 and 114.
Documentation certifying the anodes were manufacturer in accordance with MIL-A-24779 shall be provided.
C406 COATING SYSTEM
844-C406-01 MDC STANDARD FLOATING PLANT PAINT SCHEDULE
B. SURFACE PREPARATION
Surface preparation for all structural steel shall be in accordance with Steel Structures Painting Council Standards SSPC-SP10-85 (Near White Metal Blast) throughout. Profile blasting shall be in accordance with the primer manufacturer’s requirements. All mill scale, weld spatter, dirt, oil and grease shall be removed.
Immediately upon completion of surface preparation, all steel shall be coated with the coating system described in the following.
The contractor can use either pre-construction primer or limit initial coating to base coat only. If initial coating with base coat is selected, prior to application of subsequent coats, all steel shall be sand swept clean (light blast) or water blasted and any damaged areas repaired prior to application of the remainder of the system. All areas needing repair shall be cleaned to bare metal, spot blasted to restore profile and re-coated with the base coat.
C. PAINT REQUIREMENTS
Paint shall be delivered in sealed containers with labels to indicate manufacturer, date of manufacture, contents, and any special instructions. Paints and painting materials shall be stored under cover and protected from extreme temperatures.
Paints shall not be used if they have exceeded the closed shelf or pot life, recommended by the manufacturer.
Additionally, paints shall not be applied in weather or humidity conditions not recommended by the manufacturer.
D. APPLICATION OF COATINGS
Surface preparation and paint application shall be in strict compliance with the coating manufacturer’s recommendations. The contractor shall take particular care to ensure that coating system requirements are met in all areas, especially those difficult to coat, such as flange undersides. All painting on both the interior and exterior surfaces below the deck shall be accomplished prior to launching the barges.
E. COATING SYSTEM
The system is composed of the following coating types:
Self priming epoxy base coat Abrasion resistant epoxy barrier coat Fade resistant urethane top coat
Additionally, in specified spaces/compartments the coating system may include an “Insulation Coating.”
F. PRE-QUALIFIED COATINGS
Coating systems from PPG Amercoat, International Paint, Sherwin-Williams, Carboline, and Jotun have been reviewed and are pre-qualified to meet the coating requirements of this section. The contractor may select any of these systems at his discretion. However, the systems may not be “mixed”. The specific coating designations to be used are listed on Contract Drawing.
If a pre-construction primer is used, only the pre-construction primers compatible with the pre-qualified coating system chosen will be accepted. The pre-construction primer shall be “weldable” and the coating thickness recommended by the paint manufacturer shall be strictly followed.
G. NUMBER OF COATS & PAINT SCHEDULE
The number of coats is not specified. The contractor is required to provide the number of coats necessary to attain the DFT thicknesses in accordance with the Contract Drawing. Thickness applied per coat may not exceed the manufacturer’s recommended maximum thickness.
The contractor shall develop and submit a Paint Schedule listing each coat to be applied to each area of each barge, the paint manufacturer they have elected to use, the color to be applied and corresponding FS595 number, wet mils, dry mils, overcoat time, thinner, method of application, and tip size, shall be listed in the Paint Schedule. Include any appropriate General Notes for painting.
H. COATING “TYPE” AND DFT SCHEDULE
The coating types and DFT for all areas of the barges shall be in accordance with the Contract Drawing.
I. COATING COLOR SCHEDULE
Colors shall conform to Federal Standard No. 595B Colors Identification Numbers. The color book as well as individual paint chips (3” x 5”) may be procured from the General Services Administration/Federal Supply Service as follows:
E-Mail: www.fss.gsa.gov/pub/fedspecs/
GSA/Federal Supply Service FSS Product Acquisition Center Supply Standards Division (FLAS) Arlington, VA 22202
Phone: (703) 605-2567
FAX: (703) 605-9856
The coloring schedule shall be as follows:
AREA COLOR/FS595 NUMBER
Hull Exterior and Cargo Box Black/17038 Including Removable Cargo Box Ends and Handrails Towknee Exterior
Hull & Draft Markings White/27880
Deck Fittings, including Pipe Bollard Yellow/13655
Members supporting removable Cargo box ends and end gate “alignment bar”
Hull Interior White/27880
Main Deck Deck Red/10076
The “under coats” of all multiple coat applications (except the hull interior) shall be “contrast tinted” to ensure complete coverage of successive coats.
All top coating shall be thick enough to provide complete opaque color coverage. Thickness increased over the DFT minimums required above shall be provided if required for opaque color coverage.
Painted surfaces damaged in handling and installation shall be repainted.
J. FINAL INSPECTION OF PAINTING
The contractor is responsible for delivering the barges with all painted surfaces in sound condition, and in accordance with this specification.
Prior to launching of the barges, all interior and exterior painting shall be thoroughly inspected. Notice shall be given to the COR, 7 days in advance of the scheduled launching for this purpose. If there are any defects or damage in the coating of the barges, the contractor shall repair the coating to restore the integrity of the paint system, and to meet the requirements of this specification. All damage shall be cleaned to bare metal, spot blasted to restore profile, and re-coated with the entire system schedule.
The barges shall not be launched until:
The painting documentation as required in paragraph K below has been provided to the COR. The documentation must show compliance with this specification in all areas, and all readings taken.
The painting has been inspected by an MDC representative and approved by the COR. Contractor must provide documentation prior to MDC inspection.
If outfitting is required after launching, all interior and exterior painting shall be re-inspected prior to Provisional Acceptance, and any damaged areas of the coating shall be repaired by the contractor as necessary to restore the integrity of the paint system.
Any additional painting required as a result of the Final Inspection shall be done as required to meet this specification at no additional cost to the Government.
K. DOCUMENTATION & WARRANTY
1. Documentation
The contractor shall provide a written, signed statement from the paint manufacturer certifying that all coating application and surface preparation is in accordance with the coating system manufacturer’s requirements for each barges, and that the coating application meets all requirements in this specification.
The contractor shall provide documentation logs for each coating applied. The logs shall include the following parameters:
a. Coating (per specification) type.
b. Coating manufacturer’s requirements for preparation, environmental conditions and application.
c. Date and time of preparation and application.
d. Extent and location of area coated.
e. Surface: preparation, condition at time of coating, temperature at time of coating, dew point at time of coating.
f. DFT measurements for each applied coating type. Measurements shall be taken as follows:
all flat surfaces, one reading per every 200 square feet, uniformly distributed, but a minimum of once per frame, per surface.
undersides of all flanges, one reading per every 50 linear feet of flange, uniformly distributed, but a minimum of two readings per surface, per compartment.
all free standing structural members, i.e. stanchions, truss diagonals, etc., one reading per 50 linear feet of length each surface, but a minimum of two readings per surface.
Wet film measurements may be taken and converted to DFT as an alternative to direct DFT. In areas where multiple coating types are required, the above DFT requirements are applied to each coating type.
g. Services provided by paint manufacturer’s representative (i.e. DFT readings, dew points, etc.) if present during the application.
h. Signature of paint manufacturer’s representative on site, if present.
2. Warranty
For the barges, the Contractor shall warranty the coating system for one calendar year, commencing at Final Acceptance. The Contractor shall repair any coating failures during this time period at his cost.
L. SAFETY & HEALTH STANDARDS
The U.S. Occupational Safety and Health Administration Regulations (OSHA) for shipyard employees engaged in surface preparation and coatings application shall be in accordance with the OSHA regulations stated in 29 CFR, subpart C.
These regulations require the contractor to have access to a “competent person” to test compartment atmosphere quality. The “competent person” shall be in accordance with OSHA regulations, stated in 29 CFR, subpart A, 1915.7.
The regulations also require that frequent testing of the atmosphere shall be made in compartments being coated or preserved (or prepared for coating or preservation) by paints and coatings dissolved in highly volatile, toxic and flammable solvents (29 CFR, subpart C, 1915.35(b)), to ensure the atmosphere is not hazardous.
Each compartment inspection and test shall be logged in accordance with OSHA regulations stated in 29 CFR, subpart A, 1915.7(d), with instructions on how to maintain a safe atmosphere in these spaces until the completion of the contract.
On 24-hours notice of any Government inspection, and before any representative of the U.S. Government boards the barges for inspection, each enclosed or confined space to be inspected shall be labeled “Safe for Workers” in accordance with the OSHA regulations stated in 29 CFR 1915.31-36. The initial certificate shall be issued by a National Fire Protection Association (NFPA) certified Marine Chemist. A competent person may re-certify daily provided that the conditions have been maintained.
This means that in all spaces so designated:
The oxygen content of the atmosphere is at least 19.5 percent and below 22 percent by volume;
The concentration of flammable vapors is below 10 percent of the lower explosive limit (LEL);
Any toxic materials in the atmosphere are within permissible concentrations;
Any residues or materials associated with any work in the space will not produce uncontrolled release of toxic materials under existing atmospheric conditions while maintained as directed.
The contractor shall notify the Government when this certificate has been issued for each compartment. The barges will not be inspected and accepted by the Government without a NFPA Marine Chemist certificate for each compartment designated “Safe for Workers.”
C410 HULL OUTFIT
806-D205-01 OUTBOARD PROFILE AND GENERAL ARRANGEMENT
806-D307-01 SHELL PLATING AND FRAMING
806-D311-01 LONGITUDINAL FRAMING – RAKE & TOWKNEE DETAILS
806-D460-01 HULL MARKINGS & MISCELLANEOUS DETAILS
B. TOWKNEES
Towknees shall be provided and installed in accordance with the contract drawings.
Each towknee shall be provided with towknee pusher plates for the entire height of each towknee.
C. RUB BARS
Rub bars shall be provided, located and installed as shown on the contract drawings. Ends shall be chamfered the same as the edges. Jogging strakes to avoid weld seams is not acceptable.
Rub bars shall be continuous seal welded to hull plate all around. Rub bars shall be located such that the draft marks are centered on the strakes.
C415 MANHOLES
806-D205-01 OUTBOARD PROFILE AND GENERAL ARRANGEMENT
806-D307-02 DECK PLATING AND FRAMING
806-D415-01 MANHOLES
B. MANHOLES
A 12” high coaming (not shown on the contract drawings) shall be provided for each manhole. Single bolt galvanized steel manholes with hatches, shall be furnished and installed in the locations shown on the contract drawings on the coamings. Each hatch shall be provided with a gasket, galvanized steel retaining chain, and T-handle wrench. The hatches shall be similar to NABRICO Model DF-430-18, Part No. 6335 (Galvanized).
The Contractor shall revise the contract drawing (re-title 844-C415-01) to include the coaming and installation details and submit to the Government for review within 60 days after NTP for Phase I.
C420 DECK FITTINGS
806-D205-01 OUTBOARD PROFILE AND GENERAL ARRANGEMENT
806-D307-02 DECK PLATING AND FRAMING
806-D420-01 DECK FITTINGS
B. KEVELS
The contractor shall provide and install six (6) 48” kevels, similar to NABRICO Model DF-484, on the main deck of each barge as shown on the contract drawings.
C. BITTS
Four (4) 8” double bitts with horns, similar to NABRICO DF-2A, shall be provided and installed on each barge as shown on the contract drawings.
C427 VERTICAL & INCLINED LADDERS
806-D205-01 OUTBOARD PROFILE AND GENERAL ARRANGEMENT
806-D309-01 TRANSVERSE FRAMING AND BULKHEADS
806-D427-01 VERTICAL LADDERS
B. VERTICAL LADDERS
A vertical ladder shall be constructed and installed as shown on the contract drawings for each manhole. With the addition of the 12” coaming, ladder rung(s) and/or grabs will be required for the coaming section. The Contractor shall revise the contract drawing (re-title 844-C427-01) to include the coaming and rung/grab details and submit to the Government for review within 60 days after NTP for Phase I.
C460 DRAFT MARKS, HULL MARKINGS & NOTICES
806-D205-01 OUTBOARD PROFILE AND GENERAL ARRANGEMENT
806-D307-01 SHELL PLATING AND FRAMING
806-D460-01 HULL MARKINGS AND MISCELLANEOUS DETAILS
B. GENERAL
All hull markings shall be Arabic numerals, and block type letters cut from 1/4 inch steel plate, and shall be attached to the hull with continuous welds. Hull markings shall be located as shown on the contract drawings.
Draft marks shall be 6 inches high, located on the hull sides, forward and aft. The draft marks shall indicate each foot of draft from the 1-foot water line to the 6-foot water line and be measured from the underside of the bottom plating projected to the bottom of each numeral.
Owner markings, in 8 inch high letters, consisting of the words “CORPS OF ENGINEERS – U.S. ARMY” shall be located on hull sides, amidships, above the upper rubbing bar, port and starboard.
Name markings in 8 inch high numbers, consisting of the barge number, shall be located on the side shell forward and aft, on both sides, near each barge corner, as shown on the contact drawings. The barge numbers on the contract drawings are from the previous project and are not to be used. The COR will provide the official barge numbers during construction.
C. NOTICES
Confined space markings shall be stenciled on all entrances and shall read as follows:
DANGER
PERMIT REQUIRED
CONFINED SPACE
DO NOT ENTER
Section D - Packaging and Marking
D01 PACKAGING
All spare parts shall be packaged by the Contractor for delivery and storage.
All spare parts shall be placed aboard the vessel, or loaded on contractor-furnished trucks by the contractor after they have been packaged and marked by the contractor in accordance with the requirements of this section.
Spare parts and materials are divided into two types based on their manner of long-term storage. All spares and materials shall be packaged for long term “protected” storage.
“Consumables” such as bulbs, filters, paint and hardware shall be stored aboard the vessel and do not need to be marked in accordance with Clause D02.
“PROTECTED” Storage spare parts are intended to be stored for extended (two to five years) periods of time in unheated warehouses.
“PROTECTED” Storage spare parts shall be coated with paint and other preservative coating systems as recommended by the manufacturer and acceptable to the COR and packaged for mechanical and physical protection as accepted by the Contracting Officer’s Representative.
D02 MARKING
All spare parts and materials shall be marked or labeled by the Contractor.
All “PROTECTED” spare parts and equipment shall be fitted with a plastic nametag, engraved plastic nameplate or other device acceptable to the Contracting Officer’s Representative with the following information completed by the Contractor:
NAME OF PART & PART NUMBER
VESSEL NAME
CONTRACT NUMBER
NAME OF EQUIPMENT OF WHICH ITEM IS A PART
DRAWING REFERENCE
MANUFACTURER
YEAR OF MANUFACTURE
OTHER IDENTIFYING INFORMATION
In addition, where individual spare parts are packaged in crates or other containers, the crate or container shall be labeled with a stencil, in paint of a contrasting color, on at least three sides. The stenciled labels shall provide the same information as the part identification tag.
Where multiple spare parts are packaged in a crate or container, the requirement for stenciling the crate as stated in the previous paragraph shall apply, but, in addition, the crate shall contain an inventory card affixed to the inside cover of the container. The inventory card shall list each item in the container, including all information on the individual item tags.
Section E - Inspection and Acceptance
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0001 N/A N/A N/A N/A 0001AA Destination Government Destination Government 0001AB Destination Government Destination Government
CLAUSES INCORPORATED BY REFERENCE
52.246-2 Inspection Of Supplies--Fixed Price AUG 1996 52.246-16 Responsibility For Supplies APR 1984
SECTION E
E01 INSPECTION
The contract will be managed by the Marine Design Center (MDC) of the U.S. Army Corps of Engineers (USACE) and is subject to inspection by its appointed representatives to ensure strict compliance with the terms of the contract. No Government Representative, except the Contracting Officer, is authorized to change any provision of the specifications, nor shall the presence or absence of a Government Representative relieve the Contractor from any requirements of the contract.
The contractor shall provide “Safe for Workers” labels, in accordance with the OSHA regulations stated in 29 CFR 1915.11-12, for all confined and enclosed spaces prior to permitting entrance for work or inspection. This procedure shall be reflected in the contractor’s Safety Plan (see Section H, clause H07).
Entry shall not be permitted to any confined or enclosed space that does not have a current “Safe for Workers” label.
E02 LAUNCHING
The contractor shall be responsible for the satisfactory launching of the barges at the times and dates selected and mutually agreed upon by the contractor and the COR.
The contractor shall provide a written notice to the COR 7 calendar days prior to the launching of any barge. Prior to launching any barge, all painting below the main deck (interior and exterior) must be completed. The contractor shall schedule 3 days between hull inspection and launching to allow any new paint on the hull interior and exterior to cure properly.
E03 QUALITY CONTROL & INSPECTION
A. GENERAL
After Notice To Proceed with "PLANNING, SCHEDULING AND ENGINEERING" the contractor shall develop a Contractor Quality Control (CQC) and Inspection Program for the work required in this contract. This program shall:
a. Define contractor tests and inspections to be accomplished for each work item of the contract.
b. Be commensurate with the complexity of the work in the specification and adequate to assure the contractor that the product or sub-product offered conforms to the requirements of the contract.
c. Be available to the Contracting Officer’s Representative at all times and contain recorded data of all contractor conducted inspections and tests conducted to date.
d. List by name and title, the contractor’s representatives who are authorized to witness or perform and sign for each test and inspection.
The following are the minimum requirements for data to be recorded:
a. Type of inspection or test (e.g., visual, mechanical, liquid penetrant, radiographic), accept/reject criteria, and a statement as to whether the inspection was satisfactory or unsatisfactory.
b. Number and type of deficiencies of material or workmanship found in the product or sub-product inspected and corrective action taken to correct the deficiencies and, for repetitive deficiencies, to preclude recurrence.
c. Date and signature of the Authorized Contractor Representative who witnessed or performed the test or inspection.
Responsible authorized personnel shall inspect the work in progress and all completed work, conduct necessary tests and record the data required. An Authorized Contractor Representative shall sign the records attesting to the validity of the information.