Bid Abstract - W9128F22B0007 - Signed 16 Aug 2022.pdf

PDF 442 KB Posted

Attached to
Old Fort Thompson Bank Stabilization Federal contract opportunity
Solicitation number
W9128F22B0007
Issued by
Department of the Army Corps of Engineers Engineering District Omaha

About this file

This abstract of offers summarizes bids received in response to Solicitation Number W9128F22B0007 issued by the U.S. Army Corps of Engineers Omaha District for the Old Fort Thompson Bank Stabilization project located in Buffalo County, South Dakota. The solicitation closed on August 16, 2022 and sought bids from small businesses for bank and slope protection of approximately 700 linear feet of shoreline along Lake Sharpe/Big Bend Dam. The work includes cutting, grading, compacting the existing bank, and placement of geotextile fabric and riprap stone. The project must be completed by March 17, 2023 on frozen ground during winter draw down. Six bids were received ranging from $342,391.93 to $497,652.00. The apparent low bidder is Jeremy Thomas Construction at $342,391.93.

View the file

Other files for this federal contract opportunity

Other files attached to Old Fort Thompson Bank Stabilization, newest first.
File Type Posted
Solicitation - W9128F22B0007 - Old Fort Thompson Bank Stabilization.pdf PDF
Specifications - W9128F22B0007 - Old Fort Thompson Slump Repair 2022 .pdf PDF
Drawings - W9128F22B0007 - Old Fort Thompson Slump Repair 2022 .pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

2. DATE ISSUED 3. DATE OPENED

16-Aug-22

I CERTIFY THAT I HAVE OPENED, READ AND

AND RECORDED ON THIS ABSTRACT

ALL OFFERS RECEIVED IN RESPONSE DATE SIGNED

16-Aug-22

Old Fort Thompson Bank Stabilization Buffalo County, South Dakota D. OFFEROR D. OFFEROR D. OFFEROR

Kovilic Construction Company, Inc.

Franklin Park, IL 60131

C. REASONABLE CONTRACT Bid Security 20% Yes Bid Security 20% Yes Bid Security 20% Yes C. AMENDMENTS ACKNOWLEDGED: C. AMENDMENTS ACKNOWLEDGED: C. AMENDMENTS ACKNOWLEDGED:

7A 7B 7C D. E. F.

ITEM # DESCRIPTION OF OFFER ITEM EST. QUANTITY UNIT UNIT PRICE AMOUNT

Entire work, complete to supply and install Class "C" Sioux Quartzite Riprap to the Old Fort Thompson site as designated on the design cross section.

2,739 Tons $83.02 $227,391.78

Entire work, complete to remove and reinstall existing Sioux quartzite riprap at the Old Fort Thompson site as designated on the design cross section.

3,477 Tons $14.74 $51,250.98

Entire work, complete to install existing on-site Sioux quartzite riprap from the stockpile at the Old Fort Thompson site as designated on the drawings.

1,745 Tons $18.03 $31,462.35

Entire work, complete to supply and install random fill as needed for design cross-section at the Old Fort Thompson site.

1,408 Cubic Yards $27.45 $38,649.60

Entire work, complete to supply and install geotextile as needed for design cross-section at the Old Fort Thompson site.

Lineal feet of Shoreline $49.64 $34,748.00

Entire work, complete to excavate and stockpile random fill from toe as needed for design cross-section at the Old Fort Thompson Site.

276 Cubic Yards $11.25 $3,105.00

All other work, including, but not limited to tree removal, site preparation, site restoration/seeding, mobilization and demobilization. This excludes all other Basic Items.

1 Job $41,900.00 $41,900.00

TOTAL $428,507.71

NO. 6

$47,743.20

Sharpe Enterprises

1908 N Garfield

Pierre, SD 57501

3721 N. Carnation Street

NO. 4 NO. 5

$438,532.53 $342,391.93 $396,585.00 $783,327.00 $485,520.10

$18,105.60 $3,005.64 $5,520.00 $20,700.00 $5,520.00

$38,926.00 $44,659.82 $55,000.00 $112,000.00 $63,900.00

$66,119.68 $17,388.80 $35,200.00 $105,600.00 $63,500.80

$22,372.00 $4,208.75 $14,700.00 $39,900.00 $10,500.00

Morris, Inc

PO Box 1162

Pierre, SD 57501

AMOUNT

$186,252.00

$139,080.00

UNIT PRICE UNIT PRICE UNIT PRICE UNIT PRICE

$62,820.00

$35,200.00

$22,400.00

$6,900.00

$45,000.00

$497,652.00

UNIT PRICE

$186,991.53 $157,434.16 $164,340.00 $249,249.00 $194,879.85

$58,274.52 $83,674.01 $86,925.00 $170,373.00 $109,003.95

$32,020.75 $34,900.00 $85,505.00 $38,215.50

OMAHA, NE 68102-1618

1616 CAPITOL AVENUE

CONTRACTING DIVISION (CENWO-CT)

US ARMY CORPS OF ENGINEERS

l PAGES

9. OFFERS

TO THIS SOLICITATION

SIGNATURE

NAME AND TITLE OF CERTIFYING OFFICIAL (Type) Clinton Russell

NO. 1 NO. 2

ABSTRACT OF OFFERS - CONSTRUCTION

1. SOLICITATION NUMBER

W9128F22B0007

4. ISSUING OFFICE

8. GOVERNMENT ESTIMATE

(Check A, B or C AND COMPLETE D, E AND F)

5. PROJECT TITLE

A. OFFEROR B. OFFEROR

205 N 4th Ave 201 NE 135th St.

A. HIRED LABOR

IGE R P & H, Inc. KEU Inc

Reliance, SD 57569 Vancouver, WA 98685

B. REASONABLE CONTRACT

6. NUMBER OF AMENDMENTS ISSUED Bid Security 20% Yes

C. AMENDMENTS ACKNOWLEDGED : 0

Bid Security 20% Yes

C. AMENDMENTS ACKNOWLEDGED :

(Without Profit)

(Including Profit) Bid Security 20% Yes

C. AMENDMENTS ACKNOWLEDGED:

NO. 3

C. OFFEROR

Jeremy Thomas Construction

32131 Lyman Rd.

Reliance, SD 57569

2022-08-16T15:59:37-0500
Clinton Russell

File details come from the government source that posted it. Updated .