This abstract of offers is for a construction project solicitation to perform ecosystem restoration work along the Lower Brule River in South Dakota. The work includes placement of 1,500 linear feet of breakwater structure, as well as associated quarried stone, spalls, and mobilization/demobilization. The base requirement is for 500 linear feet with two 500 linear foot options. The Corps of Engineers received six offers for the work from contractors including Morris Inc., HSG Park JV LLC, Young General Contracting Inc., Moltron Meyer LLC, Sharpe Enterprises, with prices ranging from $3.95 to $5.47 million. The independent government estimate was $4.52 million. The 150-day period of performance will commence upon notice to proceed.

View the file

Other files for this federal contract opportunity

Other files attached to Lower Brule Natural Resource Protection Ecosystem Restoration, newest first.
File Type Posted
Lower Brule Site Visit Sign-In Sheet 10-20-2020.pdf PDF
Pre-bid location.pdf PDF
Lower Brule Specs.pdf PDF
Lower Brule Drawings.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

7A C. D. E. F. C. D. E. F. C. D. E. F. C. D. E. F.

ITEM #

Est.

Quantity UNIT UNIT PRICE ESTIMATED AMOUNT Est.

Quantity UNIT UNIT PRICE ESTIMATED AMOUNT Est.

Quantity UNIT UNIT PRICE ESTIMATED AMOUNT Est.

Quantity UNIT UNIT PRICE ESTIMATED AMOUNT

0001 2000 LF $129.53 259,060.00$ 2000 LF $61.40 122,800.00$ 2000 LF $158.13 316,260.00$ 2000 LF $211.25 422,500.00$

0002 13320 Tons $71.17 947,984.40$ 13320 Tons $48.10 640,692.00$ 13320 Tons $96.31 1,282,849.20$ 13320 Tons $65.00 865,800.00$

0003 10600 Tons $61.12 647,872.00$ 10600 Tons $47.00 498,200.00$ 10600 Tons $96.31 1,020,886.00$ 10600 Tons $55.00 583,000.00$

0004 1 JB $149,650.00 149,650.00$ 1 JB $315,000.00 315,000.00$ 1 JB $251,562.50 251,562.50$ 1 JB $290,000.00 290,000.00$

0005 1 JB $385,900.00 385,900.00$ 1 JB $445,000.00 445,000.00$ 1 JB $704,375.00 704,375.00$ 1 JB $45,000.00 45,000.00$

0006 750 LF $123.07 92,302.50$ 750 LF $67.80 50,850.00$ 750 LF $158.13 118,597.50$ 750 LF $100.00 75,000.00$

0007 5000 Tons $71.17 355,850.00$ 5000 Tons $48.10 240,500.00$ 5000 Tons $96.31 481,550.00$ 5000 Tons $65.00 325,000.00$

0008 3975 Tons $61.12 242,952.00$ 3975 Tons $47.00 186,825.00$ 3975 Tons $96.31 382,832.25$ 3975 Tons $55.00 218,625.00$

0009 1 JB $28,200.00 28,200.00$ 1 JB $70,000.00 70,000.00$ 1 JB $35,937.50 35,937.50$ 1 JB $5,000.00 5,000.00$

0010 750 LF $123.07 92,302.50$ 750 LF $62.55 46,912.50$ 750 LF $158.13 118,597.50$ 750 LF $200.00 150,000.00$

0011 5000 Tons $71.17 355,850.00$ 5000 Tons $48.10 240,500.00$ 5000 Tons $96.31 481,550.00$ 5000 Tons $65.00 325,000.00$

0012 3975 Tons $61.12 242,952.00$ 3975 Tons $47.00 186,825.00$ 3975 Tons $96.31 382,832.25$ 3975 Tons $55.00 218,625.00$

0013 1 JB $131,100.00 131,100.00$ 1 JB $224,000.00 224,000.00$ 1 JB $201,250.00 201,250.00$ 1 JB $5,000.00 5,000.00$

0014 750 LF $123.07 92,302.50$ 750 LF $65.60 49,200.00$ 750 LF $158.13 118,597.50$ 750 LF $200.00 150,000.00$

0015 5000 Tons $71.17 355,850.00$ 5000 Tons $48.10 240,500.00$ 5000 Tons $96.31 481,550.00$ 5000 Tons $65.00 325,000.00$

0016 3975 Tons $61.12 242,952.00$ 3975 Tons $47.00 186,825.00$ 3975 Tons $96.31 382,832.25$ 3975 Tons $55.00 218,625.00$

0017 1 JB $131,100.00 131,100.00$ 1 JB $223,000.00 223,000.00$ 1 JB $201,250.00 201,250.00$ 1 JB $5,000.00 5,000.00$

0018 750 LF $123.07 92,302.50$ 750 LF $66.70 50,025.00$ 750 LF $158.13 118,597.50$ 750 LF $100.00 75,000.00$

0019 5000 Tons $71.17 355,850.00$ 5000 Tons $48.10 240,500.00$ 5000 Tons $96.31 481,550.00$ 5000 Tons $65.00 325,000.00$

0020 3975 Tons $61.12 242,952.00$ 3975 Tons $47.00 186,825.00$ 3975 Tons $96.31 382,832.25$ 3975 Tons $55.00 218,625.00$

0021 1 JB $28,200.00 28,200.00$ 1 JB $72,000.00 72,000.00$ 1 JB $50,312.50 50,312.50$ 1 JB $5,000.00 5,000.00$

5,473,484.40$ 4,516,979.50$ 7,996,601.70$ 4,850,800.00$ Total

Option 4: Spalls per specifications

Option 4: All Remaining Work

Total Total Total

Option 3: Placement of Breakwater Structure

Option 3: Quarried Stone per specifications

Option 3: Spalls per specifications

Option 3: All Remaining Work

Option 4: Placement of Breakwater Structure

Option 4: Quarried Stone per specifications

Option 1: Spalls per specifications

Option 1: All Remaining Work

Option 2: Placement of Breakwater Structure

Option 2: Quarried Stone per specifications

Option 2: Spalls per specifications

Option 2: All Remaining Work

Base -Quarried Stone per specifications

Base -Spalls per specifications

Base -Mobilizations/ De-Mobilization

Base -All Remaining Work

Option 1: Placement of Breakwater Structure

Option 1: Quarried Stone per specifications

(Including Profit)

C. REASONABLE CONTRACT

Base - Placement of Breakwater Structure

DESCRIPTION OF OFFER ITEM

A. HIRED LABOR

7B

6. NUMBER OF AMENDMENTS ISSUED

(Without Profit)

2. DATE ISSUED

NO. 1

NAME AND TITLE OF CERTIFYING OFFICIAL (Type)

LEE M MCCORMICK

10-Oct-20

DATE SIGNED

NO. 3

B. REASONABLE CONTRACT

ABSTRACT OF OFFERS - CONSTRUCTION

Independent Government EstimateShore Protection Project Lower Brule, SD Missouri River-Big Bend Reach Lyman County, SD

(Check A, B or C AND COMPLETE D, E AND F)

4. ISSUING OFFICE

5. PROJECT TITLE

1. SOLICITATION NUMBER

W9128F21B0003

I CERTIFY T HAT I HAVE OPENED, READ AND

RECORDED ON THIS ABSTRACT OF

ALL OFFERS RECEIVED IN RESPONSE TO THIS

SOLICITATION

20%

9. OFFERS

A. OFFEROR

C. AMENDMENTS ACKNOWLEDGED

B. BID SECURITY (Type & Amount) B. BID SECURITY (Type & Amount) 20%

A. OFFEROR

Morris Inc. (0ELU6)

NO. 2

A. OFFEROR

HSG Park JV LLC (8NPU9)

8. GOVERNMENT ESTIMATE

B. BID SECURITY (Type & Amount) 20%

C. AMENDMENTS ACKNOWLEDGED

US ARMY CORPS OF ENGINEERS

CONTRACTING DIVISION (CENWO-CT-C)

1616 CAPITOL AVENUE

OMAHA, NE 68102-1618

Contracting Officer

SIGNATURE

Young General Contracting Inc (1KJZ3)

C. AMENDMENTS ACKNOWLEDGED

X

7A C. D. E. F. C. D. E. F. C. D. E. F. C. D. E. F.

ITEM #

Est.

Quantity UNIT UNIT PRICE ESTIMATED AMOUNT Est.

Quantity UNIT UNIT PRICE ESTIMATED AMOUNT Est.

Quantity UNIT UNIT PRICE ESTIMATED AMOUNT Est.

Quantity UNIT UNIT PRICE ESTIMATED AMOUNT

0001 2000 LF $129.53 259,060.00$ 2000 LF $285.55 571,100.00$ 2000 LF $95.00 190,000.00$ 2000 LF

0002 13320 Tons $71.17 947,984.40$ 13320 Tons $35.00 466,200.00$ 13320 Tons $52.00 692,640.00$ 13320 Tons

0003 10600 Tons $61.12 647,872.00$ 10600 Tons $34.00 360,400.00$ 10600 Tons $52.00 551,200.00$ 10600 Tons

0004 1 JB $149,650.00 149,650.00$ 1 JB $200,000.00 200,000.00$ 1 JB $140,000.00 140,000.00$ 1 JB

0005 1 JB $385,900.00 385,900.00$ 1 JB $110,000.00 110,000.00$ 1 JB $92,000.00 92,000.00$ 1 JB

0006 750 LF $123.07 92,302.50$ 750 LF $174.44 130,830.00$ 750 LF $95.00 71,250.00$ 750 LF

0007 5000 Tons $71.17 355,850.00$ 5000 Tons $35.00 175,000.00$ 5000 Tons $52.00 260,000.00$ 5000 Tons

0008 3975 Tons $61.12 242,952.00$ 3975 Tons $34.00 135,150.00$ 3975 Tons $52.00 206,700.00$ 3975 Tons

0009 1 JB $28,200.00 28,200.00$ 1 JB $65,899.00 65,899.00$ 1 JB $20,000.00 20,000.00$ 1 JB

0010 750 LF $123.07 92,302.50$ 750 LF $333.64 250,230.00$ 750 LF $95.00 71,250.00$ 750 LF

0011 5000 Tons $71.17 355,850.00$ 5000 Tons $35.00 175,000.00$ 5000 Tons $52.00 260,000.00$ 5000 Tons

0012 3975 Tons $61.12 242,952.00$ 3975 Tons $34.00 135,150.00$ 3975 Tons $52.00 206,700.00$ 3975 Tons

0013 1 JB $131,100.00 131,100.00$ 1 JB $65,899.00 65,899.00$ 1 JB $47,000.00 47,000.00$ 1 JB

0014 750 LF $123.07 92,302.50$ 750 LF $338.93 254,197.50$ 750 LF $95.00 71,250.00$ 750 LF

0015 5000 Tons $71.17 355,850.00$ 5000 Tons $35.00 175,000.00$ 5000 Tons $52.00 260,000.00$ 5000 Tons

0016 3975 Tons $61.12 242,952.00$ 3975 Tons $34.00 135,150.00$ 3975 Tons $52.00 206,700.00$ 3975 Tons

0017 1 JB $131,100.00 131,100.00$ 1 JB $65,899.00 65,899.00$ 1 JB $47,000.00 47,000.00$ 1 JB

0018 750 LF $123.07 92,302.50$ 750 LF $133.53 100,147.50$ 750 LF $95.00 71,250.00$ 750 LF

0019 5000 Tons $71.17 355,850.00$ 5000 Tons $35.00 175,000.00$ 5000 Tons $52.00 260,000.00$ 5000 Tons

0020 3975 Tons $61.12 242,952.00$ 3975 Tons $34.00 135,150.00$ 3975 Tons $52.00 206,700.00$ 3975 Tons

0021 1 JB $28,200.00 28,200.00$ 1 JB $65,899.00 65,899.00$ 1 JB $20,000.00 20,000.00$ 1 JB

5,473,484.40$ 3,947,301.00$ 3,951,640.00$

ABSTRACT OF OFFERS - CONSTRUCTION

1. SOLICITATION NUMBER 2. DATE ISSUED

W9128F21B0003 10-Oct-20

4. ISSUING OFFICE

I CERTIFY T HAT I HAVE OPENED, READ AND

RECORDED ON THIS ABSTRACT OF

ALL OFFERS RECEIVED IN RESPONSE TO THIS

SOLICITATION

NAME AND TITLE OF CERTIFYING OFFICIAL (Type)

US ARMY CORPS OF ENGINEERS

CONTRACTING DIVISION (CENWO-CT-C)

1616 CAPITOL AVENUE

OMAHA, NE 68102-1618

LEE M MCCORMICK Contracting Officer

SIGNATURE DATE SIGNED

5. PROJECT TITLE

8. GOVERNMENT ESTIMATE 9. OFFERS

Lower Brule Restoration

(Check A, B or C AND COMPLETE D, E AND F) NO. 4 NO. 5 NO. 6

A. HIRED LABOR A. OFFEROR A. OFFEROR A. OFFEROR

Independent Government Estimate Moltron Meyer LLC (85Y90) Sharpe Enterprises (46V78) NO OTHER OFFERS

B. REASONABLE CONTRACT B. BID SECURITY (Type & Amount) B. BID SECURITY (Type & Amount) B. BID SECURITY (Type & Amount) (Without Profit) 20% 20% 20%

6. NUMBER OF AMENDMENTS ISSUED

X

C. REASONABLE CONTRACT C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED (Including Profit)

7B

DESCRIPTION OF OFFER ITEM

Base - Placement of Breakwater Structure

Base -Quarried Stone per specifications

Base -Spalls per specifications

Base -Mobilizations/ De-Mobilization

Base -All Remaining Work

Option 1: Placement of Breakwater Structure

Option 1: Quarried Stone per specifications

Option 1: Spalls per specifications

Option 1: All Remaining Work

Option 2: Placement of Breakwater Structure

Option 2: Quarried Stone per specifications

Option 2: Spalls per specifications

Option 2: All Remaining Work

Option 3: Placement of Breakwater Structure

Option 3: Quarried Stone per specifications

Total Total Total Total

Option 3: Spalls per specifications

Option 3: All Remaining Work

Option 4: Placement of Breakwater Structure

Option 4: Quarried Stone per specifications

Option 4: Spalls per specifications

Option 4: All Remaining Work

11/12/2020

PAGE 1
PAGE 2
Bid Opening Totals Summary
2020-11-12T12:23:30-0600
MCCORMICK.LEE.M.1231351694

File details come from the government source that posted it. Updated .