Draft_RFP_-_W9128F18R0020_-_$95M_RDI_SB_MATOC.PDF

PDF 1 MB Posted

Attached to
DRAFT RFP RDI Small Business MATOC Federal contract opportunity
Solicitation number
W9128F-18-R-0020
Issued by
Department of the Army Corps of Engineers Engineering District Omaha

About this file

This is a draft request for proposal for a Rapid Disaster Infrastructure Small Business Multiple Award Task Order Contract. The contract will have a shared capacity of $95 million over five years, including a one-year base period and four one-year option periods. The U.S. Army Corps of Engineers seeks to award up to four contracts for time-sensitive disaster, infrastructure, and construction projects varying in size, complexity, and location within the United States. Work may include flood recovery, infrastructure repair, emergency management support, and military construction requiring mobilization within three days of notification. Offerors must be small businesses registered in the System for Award Management. The RFP includes sections for technical evaluation factors, cost/price information, and submission requirements. Technical factors cover experience, core competencies, key personnel, and past performance. Cost elements include binding labor rates, overhead caps, and profit/fee rates.

View the file

Other files for this federal contract opportunity

Other files attached to DRAFT RFP RDI Small Business MATOC, newest first.
File Type Posted
Amendment_0003.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RAPID DISASTER INFRASTRUCTURE (RDI) RESPONSE CONTRACT

INDEFINITE DELIVERY/INDEFINITE QUANTITY

SMALL BUSINESS MULTIPLE AWARD TASK ORDER CONTRACT (MATOC), CONUS, ALASKA, HAWAII, AND U.S. TERRITORIES

RETURN WITH OFFER: INFORMATION REQUIRED BY SECTION 00 11 00 (SF1442), SECTION 00 22 00, AND SECTION 00 45 00.

*BLOCK 13A. – REFER TO SECTION 00 22 00 FOR THE NUMBER OF COPIES TO BE SUBMITTED WITH THE ORIGINAL OFFER.

OTHER BONDING INFORMATION: SEE GENERAL CONDITIONS (CONTRACT CLAUSES) CLAUSE "PERFORMANCE AND PAYMENT BONDS".

THIS SOLICITATION IS SET-ASIDE FOR SMALL BUSINESSES ONLY.

GLENDA A CANTY 402-995-2059

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

03-Nov-2018

(RFP)

(IFB)

X

CALL:

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________ calendar days after receiving aw ard, X notice to proceed. This performance period is mandatory, negotiable. (See _________________________per task order

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

X YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________0 copies to perform the w ork required are due at the place specified in Item 8 by ___________ local time ______________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee is, X is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______180 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

U.S. ARMY CORPS OF ENGINEERS, OMAHA DIST

CONTRACTING OFFICE

1616 CAPITOL AVENUE

OMAHA NE 68102-4901

W9128F

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

(hour)

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

8. ADDRESS OFFER TO (If Other Than Item 7)

FAX:TEL: TEL: FAX:

W9128F18R0020 176

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

Section 00 10 00 - Solicitation

ITEM NO SUPPLIES/SERVICES MAX

QUANTITY

UNIT UNIT PRICE MAX AMOUNT

0001 95,000,000 Job RDI SB MATOC - Base Period

FFP

Cost-Plus-Fixed-Fee or Firm-Fixed Price, one (1) 1-year base with four (4) 1-year options for a total of five (5) year contract with a shared capacity of $95,000,000.00.

FOB: Destination

MAX

NET AMT

UNIT UNIT PRICE MAX AMOUNT

0002 UNDEFINED

OPTION RDI SB MATOC - Option Period 1

FFP

Cost-Plus-Fixed-Fee or Firm-Fixed Price, one (1) 1-year base with four (4) 1-year options for a total of five (5) year contract with a shared capacity of

UNIT UNIT PRICE MAX AMOUNT

0003 UNDEFINED

OPTION RDI SB MATOC - Option Period 2

FFP

Cost-Plus-Fixed-Fee or Firm-Fixed Price, one (1) 1-year base with four (4) 1-year options for a total of five (5) year contract with a shared capacity of

UNIT UNIT PRICE MAX AMOUNT

0004 UNDEFINED

OPTION RDI SB MATOC - Option Period 3

FFP

Cost-Plus-Fixed-Fee or Firm-Fixed Price, one (1) 1-year base with four (4) 1-year options for a total of five (5) year contract with a shared capacity of

UNIT UNIT PRICE MAX AMOUNT

0005 UNDEFINED

OPTION RDI SB MATOC - Option Period 4

FFP

Cost-Plus-Fixed-Fee or Firm-Fixed Price, one (1) 1-year base with four (4) 1-year options for a total of five (5) year contract with a shared capacity of

DELIVERY INFORMATION

CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

0001 N/A N/A N/A N/A

0002 N/A N/A N/A N/A

0003 N/A N/A N/A N/A

0004 N/A N/A N/A N/A

0005 N/A N/A N/A N/A

CONTRACT RATE PRICING SCHEDULE

Section 00 10 00

CONTRACT RATE PRICING

SCHEDULE

TABLE 1: Binding Labor Rates

TABLE 1: Binding Labor Rate Schedule

Labor Discipline

U n b u rd en ed

L ab o r R at e (B as e

P er io d

B u rd en ed

L ab o r R at e (B as e

P er io d

U nb ur de ne d L ab o r R at e

(O p ti o n P er io d

B u rd en ed

L ab o r R at e (O p ti o n

P er io d

U nb ur de ne d L ab o r R at e

(O p ti o n P er io d

B u rd en ed

L ab o r R at e (O p ti io d

U nb ur de ne d L ab o r R at e

(O p ti o n P er io d

B u rd en ed

L ab o r R at e (O p ti io d

U nb ur de ne d L ab o r R at e

(O p ti o n P er io d

B u rd en ed

L ab o r R at e (O p ti io d

Program Manager (Home Office)

Operations

Project

Safety

Quality Control

Accounting / Procurement / Contract Administration

Site Superintendent (Field Office)

Quality Control Specialist (Field Office)

Specialist (Field Office)

Cost Tracker (Field Office)

NOTES:

1. The hourly burdened labor rates proposed in Table 1 are binding upon contract award for the life of the MATOC for firm-fixed-price (FFP) task orders. The hourly unburdened labor rates proposed in Table 1 are binding upon contract award for the life of the MATOC for cost-plus-fixed-fee (CPFF) task orders.

2. The hourly burdened labor rates shall include direct cost, payroll taxes, insurance, benefits, and any other applicable labor costs, but shall exclude profit.

3. The binding hourly rates represent the maximum labor rates that the contractor shall use when responding to either a FFP or CPFF Request for Task Order Proposal (RTOP) issued by the Government. These binding rates shall also apply to all modifications issued against task orders. The contractor may propose a lower hourly rate for these labor disciplines when responding to the RTOP or modification request based on the tasks within the RTOP or modification requests.

4. Adherence to these rates will be reviewed through submittal of supporting documentation by the

Contractor with each FFP or CPFF task order proposal. Failure to propose the binding hourly rate or a lower rate for the listed labor disciplines may result in the Contractor’s task order proposal being rejected for award consideration.

5. If a discipline is not listed in the Binding Labor Rate Schedule and is required for the Contractor to perform a specific task order, the Contractor may propose the required labor discipline and the associated unburdened (for CPFF task orders) or fully burdened labor rate (for FFP task orders) (exclusive of profit) in the proposal submitted in response to the issued RTOP or modification request.

6. If during the Contract Period of Performance, the Contractor’s original personnel are no longer available, the Contractor shall find personnel that have the same qualifications as the previous personnel. The Contractor shall be responsible for negotiating the labor rates for those personnel that have been provided in Table 1. The rates provided in Table 1 are the maximum that will be paid by the Government for any replacement personnel.

7. The maximum rates shall be governed by the effective date of the Task Order. Task Orders will use the prices for the 12-month period effective on the date the Task Order is issued. Modifications to Task Orders will reflect the rates of the “current 12-month” binding labor rate schedule. For example, if the rate schedule changes over on 1 November of each year, and a Task Order is issue on 1 September 2019 for 12 months work, the maximum rates will be the rates that were effective on 1 November 2018. Under the same assumptions, if a modification to the Task Order is required in December 2019, the labor rates effective on 1 November 2019 will apply.

8. The Government reserves the right to request certified cost or pricing date; or information other than certified cost or pricing data from the contractor at the task order level to assess the reasonableness of the proposed task order pricing.

TABLE 2: Binding Cap Rates

Table 2 Binding Rate Cap

Base Period Option Period 1 Option Period 2 Option Period 3 Option Period 4

Home Office Overhead Rate

Field Office Overhead Rate

G&A Rate*

Other (identify):

1. The Binding Cap Rates provided in Table 2 are a breakout of the caps / markups incorporated into the Burdened Hourly Rates (Table 1). If the offeror has Binding Cap Rates that are the same for the Base Period and Option Periods 1 – 4 simply put the same number in each box. If the offeror intends to provide Binding Rate Caps that are different for any or all Option Periods 1-4 from the Base Period, the offeror must provide a justification for the changed cap rates.

2. The Binding Cap Rates represent the maximum rates that the Contractor shall use when responding to all task order request issued by the Government. These Binding Cap Rates shall also apply to all modifications. The Contractor may propose lower rates for these when responding to the task order request or modification requests.

3. Adherence to these rates will be reviewed through submittal of supporting documentation by the

Contractor with each task order proposal. Failure to propose the binding rates or a lower rates may result in the Contractor’s task order proposal being rejected for award consideration.

4. The Binding Cap Rates shall be governed by the effective date of the Task Order. Task Orders will use the prices for the 12-month period effective on the date the Task Order is issued. Modifications to Task Orders will reflect the rates of the “current 12-month” Binding Cap Rate schedule. For example, if the rate schedule changes over on 1 November of each year, and a Task Order is issue on 1 September 2018 for 12 months work, the maximum rates will be the rates that were effective on 1 November 2017. Under the same assumptions, if a modification to the Task Order is required in December 2018, the Binding Cap Rates effective on 1 November 2018 will apply.

TABLE 3: Profit / Fee

Table 3 ‐ Maximum Profit and Fee Rates

Maximum Profit Rate (Firm Fixed Price Task Orders)

Maximum Fixed Fee Rate (Cost Reimbursement Task Orders)

1. The maximum profit rate shall be binding and shall be the maximum profit rate the Contractor will be allowed to propose for all firm-fixed-price task orders issued under this contract.

2. The maximum fixed fee rate shall be binding and shall be the maximum fee rate the Contractor will be allowed to propose for all cost reimbursable task orders issued under this contract. In accordance with

FAR

15.404-4(4)(i)(C), the offeror may not propose a fixed fee above the statutory limitation of 10%.

3. The Contractor may propose a lower profit or fee rate when responding to the task order request (or subsequent modifications) based on the tasks identified in the request. Profit and fee will be negotiated on an individual Task Order and modification basis, but shall never exceed the rates identified in Table 3. The maximum profit rate is profit cap shall be binding even if the Weighted Guidelines Method would result in a higher profit. The maximum profit rate shall not be construed as a “fixed” profit percentage for all Task Order or Modification actions. If Weighted Guidelines Method calculations indicate a lower profit is merited, the lower profit percentage shall be applied.

Department of Labor Wage Rates

The appropriate Department of Labor Wage Determination will be provided for individual Task Orders issued against the contract.

Travel

The Contractor shall perform all travel and attend all meetings necessary for completion of the work required by the Task Orders. Per Diem (lodging and MI & E expenses) shall be paid at the current Government rates in accordance with the Federal Travel Regulation (FTR) per person per calendar day spent in travel status. No per diem will be paid for travel less than the number of hours per day stated in the current FTR. Per Diem rate information may be obtained at http:www.defensetravel.dod.mil/. Actual cost of transportation by public conveyance (plane, limited to coach class) shall be paid. Air travel shall (if possible) be planned in advance in order to acquire the best prices available. Privately owned vehicles shall be paid at the current Government mileage rate in accordance with the FTR. No fee or profit will be paid on travel.

SUMMARY OF WORK

Section 01 11 00

SUMMARY OF WORK

1.0 INTRODUCTION

This is a solicitation for an Indefinite Delivery, Indefinite Quantity (IDIQ) Rapid Disaster Infrastructure (RDI) Response Multiple Award Task Order Contract (MATOC) for Small Businesses (SBs). The shared contract capacity of the MATOC is $95 million for an ordering period of five (5) years: one (1) base year and four (4) one (1) year options.

2.0 BACKGROUND

This MATOC will be executed in support of the RDI Program. The RDI Program is a successor to the Security, Disaster, Infrastructure and Construction (SDIC) Program, with the exception that RDI does not include Tenant Renovations in Secure Spaces (TRSS) activities.

RDI and SDIC contracts require very similar management, planning, and execution. It is imperative that RDI contractors be capable of administering time-sensitive and cost reimbursement type projects.

3.0 SCOPE

This RDI MATOC facilitates time-sensitive disaster, infrastructure, and construction related activities in support of federally funded customers.

Projects may vary in size, complexity, and location, and will require a high degree of flexibility and adaptability. Contractors must respond quickly and effectively. The diverse scopes of work are time-sensitive, which necessitates a timely response in order to mitigate threat to life and property and/or operational impacts to the government. Examples include but are not limited to:

*Flood Recovery: flood control and water diversion projects, embankments, channel alignments and flood control structures in support of civil works missions.

*Infrastructure Recovery: restoration, repair, and demolition of facilities, utilities, real property systems, and other vital infrastructure requirements with time constraints that prohibit the use of other contract mechanisms.

*Emergency Management: response actions such as unwatering missions, debris recovery, temporary housing, and other actions to meet vital mission requirements.

*Military: construction of facilities, infrastructure, water and sanitation systems, electrical systems, natural gas and other energy systems, fences, lighting, and roads to support troop movements and other crucial military missions with time constraints that prohibit use of other contract mechanisms.

Each specific Task Order Request For Proposal will identify when the mobilization must commence; however, emergency recovery actions may require mobilization within three (3) days of Government Notification.

Projects may require incidental design and/or ecological/environmental, hazardous waste recovery, and munitions work.

This Scope also encompasses construction applications and technologies needed to support time-sensitive construction projects in various locations within the U.S. (defined as all 50 states). Individual Task Orders will further define specific project requirements once identified.

4.0 APPLICABLE DOCUMENTS

The Contractor shall comply with all applicable Federal, State, and Local requirements, codes, policies, statutes, etc. Task Orders will be performed at a variety of locations, to include civilian sites and military installations. Coordination with installation’s force protection, and other governmental entities will require the Contractor to obtain and be familiar with the appropriate and applicable documents. It is the Contractor’s responsibility to identify and comply with all applicable requirements. Applicable documents may include, but are not limited to: Unified Facility Criteria (UFC), International Building Code (IBC), National Fire Protection Association (NFPA), and the National Electric Code (NEC). When specified by Task Orders (TOs), the Contractor will also be required to follow military construction criteria.

5.0 ENVIRONMENTAL REQUIREMENTS

The Contractor shall be cognizant of all appropriate environmental laws, regulations, and guidelines. The Contractor shall ensure that all work activities performed by his personnel, subcontractors and suppliers are executed as required by these laws and regulations. Any incident of noncompliance noted by the Contractor shall immediately be brought to the attention of the Contracting Officer or Contracting Officer’s Representative (COR). A COR will be aapproved by the Contracting Officer and identified in each task order.

5.1 General

5.2 Permits/Approvals

The Contractor shall investigate requirements and obtain all applicable permits, licenses, approvals, certificates, etc., necessary to accomplish the work specified in the individual Task Orders. The Contractor shall notify the Contracting Officer or Contracting Officer’s Representative of any delay in obtaining the necessary permits or approvals.

5.3 Treatment Storage and/or Disposal of Hazardous Materials

Under this RDI MATOC, Treatment Storage and/or Disposal of Hazardous Materials must be incidental. The Contractor shall ensure on-site management, transportation, storage, treatment, and disposal of all hazardous/special waste materials complies with all applicable federal, state, and local laws and regulations.

6.0 SAFETYAND HEALTH

See Section 01 35 26 Governmental Safety Requirements. Individual Task Orders may contain additional requirements.

7.0 MANAGEMENT AND REPORTING INSTRUCTIONS

7.1 Work Plan (WP)

Immediately following Task Order award, the Contractor will submit a WP. The WP must be approved by the Government prior to start of on-site activities. Any deviation from the approved plan must be approved by the Contracting Officer or authorized representative.

The WP should fully describe activities that will be performed by the Contractor and shall contain, at a minimum, the following:

a. A Statement of work and objectives to be accomplished

b. A description of project implementation, to include the method of operation, type of equipment, personnel required, and other special considerations

c. A schedule that identifies requirements necessary to complete the required work, in addition to key milestones

d. Permits, licenses, certificates, and other pertinent compliance documents

e. An organizational chart and a roster of Key Personnel and their responsibilities

7.2 Work Breakdown Structure (WBS)

For each Task Order, the Contractor shall prepare and submit for approval a WBS compatible with the Construction Specifications Institute (CSI) format for construction activities. The approved WBS shall be used to report the cost and schedule statuses of all required tasks.

7.3 Integrated Master Schedule (IMS)

The Contractor shall prepare and submit an IMS for approval. The IMS shall be in the form of a Gantt chart and shall include a Critical Path Method (CPM) analysis. The schedule shall be resource-loaded and correlated to the approved WBS.

7.4 Contractor’s Progress, Status, and Management Report (CPSMR)

The Contractor shall prepare and submit a CPSMR. The CPSMR shall be used by the Government to review and evaluate the progress of work and to identify existing or potential problem areas. The Contractor shall report progress and document all key events on a weekly basis. The CPSMR shall include a summary of the events that occurred during the reporting period, and shall discuss performance, identifying problems and proposed solutions, corrective actions taken, and unresolved issues.

7.5 Cost Performance Report (CPR)

The Contractor shall implement and maintain a performance measurement system to support the gathering of cost and schedule data, for the purpose of determining program status. The approved WBS shall be used for reporting cost. The CPR presents the baseline against which actual cost and schedule performance is measured. Submittals shall include appropriate cost figures and related data necessary to accurately ensure daily project costs and schedule status. This report shall go beyond the usual reporting of ‘Expenditures to Date’ and ‘Estimated Cost to Complete’ by establishing earned value factors. This will ensure that the project stays on budget and schedule. From these figures the Contractor shall develop time-phased spending ccurves that correlates work progress and the rate of expenditure. The CPR shall be submitted weekly.

7.6 RDI Program Cost Reimbursement Principles and Processes

Principles:

a. An ability to accurately track all costs on a daily basis and perform reasonable forecasts is paramount to the integrity of cost reimbursable contract management.

Without this ability, there is significant damage to the viability of the program.

b. If costs are not tracked accurately or are omitted, those errors must be brought to the attention of the appropriate USACE representatives immediately for appropriate resolution.

c. Cost reimbursable contracts require procurement strategies to maintain expectations for cost, schedule, quality, and safety. For example, the prime contractor may be required to self- perform higher risk elements of work under the cost reimbursement provisions and have subcontractors perform the well-defined/low risk elements of work under firm fixed price subcontracts.

Processes:

a. Project specific coordination will be held frequently (oftentimes on a daily basis) to support timely decision making and approval. The contractor, and selected subcontractor representatives, shall participate in the coordination to support needed decision making.

b. Daily Decision Making. Daily planning and execution will be vetted and approved by appropriate representatives from USACE and frequently within on-site command posts.

Further, the project will be managed and administered through daily work authorizations, daily cost reports, daily Quality Control Reports (QCRs) daily planning documents, and other deliverables necessary to perform the mission.

c. The RDI contractor shall adhere to the following RDI processes, which are not inclusive of all contract management and administration and other contract requirements:

1. Daily Work Authorization

a) Coordination meetings occur between USACE and Contractor.

b) Contractor develops Work Authorization Documents (WADs) (reference Attachment 1) for both Home and Field offices.

c) Contractor submits WADs to USACE.

d) USACE reviews and approves/disapproves WADs.

e) Contractor executes/procures USACE approved work.

2. Change Management:

a) In-Scope differing site condition is discovered.

b) Contractor holds meeting with USACE to discuss plans and resource requirements.

c) Contractor develops plan.

d) Contractor submits to USACE.

e) USACE reviews and approves plan.

f) Contractor executes/procures change items.

3. Invoicing:

a) Contractor reconciles approved costs.

b) Contractor develops invoice.

c) Contractor submits invoice.

d) USACE reviews and approves invoice.

e) USACE makes payment.

f) Contractor manages unallowable/unreasonable costs that are billed by providing credit on subsequent invoice.

4. Cost Tracking/Forecasting:

a) Contractor establishes a USACE approved Cost Accounting System.

b) Contractor holds meetings with USACE to develop Work Breakdown Structure (WBS)/and Cost Accounting procedures.

c) Contractor develops cost report.

d) Contractor submits cost report to USACE.

e) USACE reviews and approves cost report.

f) Contractor develops cost forecast based on approved costs incurred.

g) Contractor manages cost overruns/underruns (errors) accordingly and in concurrence with USACE.

h) Personnel who are authorized to expense money on cost reimbursable contracts must be identified and authorities clearly identified so that timely decisions are made so the project is not adversely impacted. Further, the Government must be included in spending decisions since it is responsible for reimbursement of all allowable, allocable, and reasonable costs.

5. Meetings

a) The Contractor shall attend and participate in required meetings. Examples include: daily command post meetings, site visits, pre-proposal, post-award, and pre-construction conferences, in addition to other meetings the Government considers necessary to support project activities.

b) The Contractor may also be required to participate in support meetings and teleconferences for the purpose of discussing technical issues, project progress, and status.

c) The Contractor shall prepare and submit for review agendas and presentation materials for such meetings. The Contractor may be required to prepare minutes for meetings attended.

d) Specific requirements will be addressed in each Task Order.

7.7 Personnel Authorized to Expense Money

7.8 Personnel who are authorized to expense money on cost reimbursable contracts must be identified and authorities clearly identified. The Government must be included in spending decisions since it is responsible for reimbursement of all allowable, allocable, and reasonable costs.

7.9 Meetings, Required

The Contractor shall attend and participate in required meetings. Examples include: daily command post meetings, site visits, pre-proposal, post-award, and pre-construction conferences; in addition to other meetings the Government considers necessary to support project activities. The Contractor may also be required to participate in support meetings and teleconferences for the purpose of discussing technical issues, project progress, and status. The Contractor shall prepare and submit for review agendas and presentation materials for such meetings. The Contractor may be required to prepare minutes for meetings attended. Specific requirements will be addressed in each Task Order.

7.10 Plans, Required

a) Work Plan (Section 6.1)

b) Site Safety and Health Plan (Section 01 35 26 General Safety Requirements)

c) Quality Control Plan (Section 01 45 00.00 10 Quality Control)

7.11 Reports, Required

d) Design Drawings/Specifications per Task Order

e) Site/Project Summary

f) Shop Drawings and/or As-Built Drawings

g) Survey Reports per Task Order basis

h) CPSMR

i) CPR

8.0 QUALITY MANAGEMENT (QM)

Quality Management (QM) refers to the combined QC/QA effort. The specific rrequirements for Contractor QC will be identified in the project Task Order. See Section 01 45 00.00 10 Quality Control.

9.0 CONSTRUCTION WITH INCIDENTAL DESIGN

The RDI Contractor shall manage and perform construction with incidental design work as defined in the Task Order. The following are typical “construction with incidental design” Task Order requirements: work performed under design memorandums, completion of working drawings, permitting, construction management, scheduling, inspection and testing, environmental protection coordination, construction quality control, technical reach-back for applicable construction activities, and project closeout.

10. ORGANIZATIONAL STAFF/STRUCTURE

10.1 General

The Contractor shall be capable of efficiently and effectively executing all RDI Task Order requirements.

10.2 Veteran’s Employment Emphasis for USACE Contracts

In addition to complying with the requirements outlined in FAR Clause 52.222-35, Equal Employment Opportunity for Veterans, all contractors, and subcontractors at all tiers, are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract. However, no set-aside, evaluation preference, or incentive is applicable with regard to this paragraph.

The following resources are available to assist USACE contractors in their outreach efforts: Federal Veteran employment information at http://www.fedshirevets.gov/index.aspx.

Department of Labor Veterans Employment Assistance http://www.dol.gov/vets/ Department of Veterans Affairs - VOW to Hire Heroes Act http://benefits.va.gov/vow/

10.3 Operations Office

The Contractor shall establish an RDI Operations Office in which it will manage the RDI program and contract operations (see Paragraph: "Operations Manager"). The location of this office is at the discretion of the Contractor. Other functions of this office may include but are not limited to:

*Accounting and record keeping.

*Administration and management of Government-owned property acquired or operated by the Contractor under this contract.

*Quality control training and oversight necessary to ensure compliance with construction and environmental measures and RDI contract requirements.

*Billing of progress payments.

*Processing of submittals, RFP’s, and invoices.

10.4 Key Personnel/Positions

Persons identified as “Key” by the Government are mandatory positions and shall not be replaced without notifying the Contracting Officer. Should it become necessary to replace the key management personnel, the Contractor shall provide a written request stating the reasons for the change and listing the name and qualifications of the proposed replacement to the Contracting Officer for approval. The Offeror shall obtain the Contracting Officer's written consent before making any substitutions for these designated personnel. Personnel shall meet oe exceed the qualifications listed below:

Home Office (Corporate) Personnel

10.4.1 Accounting Manager

The Accounting Manager is responsible for ensuring that invoicing, billings, and related activities are performed in accordance with contract requirements, specific task order agreements, and contract management procedures (CMP’s). The Accounting Manager shall be experienced and responsible in all of the firm’s activities related to Procurement, Wage Rate Determinations, Government property, Subcontracting goals compliance, and compliance with applicable Federal, state, and local laws and regulations.

Qualifications

The Accounting Manager shall have the following minimum qualifications:

*A college degree including or supplemented by a minimum of 24 semester hours in accounting, economics, business law, procurement, or management related curriculum; or certification as a Certified Professional Contracts Manager (CPCM) by the National Contracts Management Association.

*Four (4) years of Government accounting/billing experience in a position of increasing complexity and responsibility.

*Training in Government fiscal accounting/law.

*Shall be employed directly by the Prime Contractor.

10.4.2 Construction Operations Manager (COM)

The COM is responsible for the successful and efficient construction within the RDI Contract. The COM is responsible for developing, implementing, and managing the quality control program and will ensure that Government quality and environmental requirements are achieved. The COM will manage subcontracts, manpower, equipment, and other resources, and will ensure that Safety is the number one priority at jobsites.

The COM shall be competent, experienced and knowledgeable in management of the construction-specific activities identified in this contract, and shall designate a Site Manager for each Task Order who shall be responsible for all on site management of construction duties per Task Orders. The COM may be “dual hatted” as Program Manager if the qualifications for both positions are met.

The Construction Operations Manager shall have the following minimum qualifications:

*A college degree or four (4) years equivalent experience in a technical field (e.g. engineering, construction management, geology, chemistry, or related field).

*Four (4) years-experience in Operations/Contract Management for other contracts/programs acceptable to the Government.

*A minimum of four (4) years’ work experience in Construction Project Management or in a combination of the Construction, with Incidental Design.

*Working knowledge of applicable Federal, state, and local construction laws and regulations and Federal labor laws.

*The ability to effectively communicate and manage customer expectations.

*The ability to locate, coordinate, and utilize resources.

*The ability to effectively manage subcontracts and cost reimbursable contracts.

10.4.3 Corporate Quality Control Manager (QCM)

The QCM shall have experience in development and oversight of corporate quality control programs and processes relevant to scope of work. The QCM is responsible for the development, implementation, oversight and enforcement of the firm’s Government approved QC program.

The Corporate Quality Control Manager shall have the following minimum qualifications:

*A minimum of four (4) years-experience in developing and implementing effective Quality Control programs with a construction focus.

*Expert knowledge of the USACE Quality Assurance/Control requirements and processes.

10.4.4 Corporate Safety and Health Manager (SHM)

The SHM shall be responsible for the development, implementation, oversight and enforcement of the firm’s health and safety program.

The Corporate Safety and Health Manager shall have the following minimum qualifications

*The SHM shall be an Industrial Hygienist certified by the American Board of Industrial Hygiene, or a Safety Professional certified by the Board of Certified Safety Professionals.

*A minimum of four (4) years-experience in developing and implementing safety and health programs at construction sites, operations, or equivalent.

*Documented experience: in supervising professional and technician level personnel; in developing worker exposure assessment programs and monitoring programs and techniques; in managing personal protective programs.

*Working knowledge of state and Federal occupational safety and health regulations and statutes.

*Expert knowledge of the USACE Safety and Health Requirements, EM 385-1-1 Manual, through documented experience construction operations contracted under the USACE, Naval Facilities Engineering Command, or other Department of Defense entities requiring the use of the EM 385-1-1 manual.

*Shall be employed directly by the Prime Contractor.

10.4.5 Procurement Specialist

The procurement specialist is responsible for identifying, planning, procuring, and managing equipment and materials required for each project. The Procurement Specialist will identify suppliers for materials and equipment; negotiate prices with suppliers, obtaining the best prices available, given project constraints such as geography and schedule; arrange for shipping/delivery/returns; ensure items delivered are of the type, quality, and serviceability agreed to; establish and maintain an adequate inventory of required materials; ensure invoices are complete and accurate; control equipment and materials costs and avoid waste;

additional procurement activities, as directed. Work to be performed in accordance with all applicable FAR requirements.

*A minimum of three (3) years-experience in procurement activities of the type described above, for construction projects.

*Knowledge, experience, understanding of federal procurement guidelines is a requisite *Shall be employed directly by the Prime Contractor

10.4.6 Program Manager (PgM)

The PgM shall be the corporate point of contact for the RDI Program and shall ensure that sufficient corporate resources are allocated to Task Orders to successfully execute the RDI mission. The PgM shall designate a Project Manager (PM) who shall be responsible for managing individual Task Orders. The PgM shall be accountable for the performance of all appointed Project Managers. The PgM may be “dual hatted” as the Construction Operations Manager if the qualifications for both positions are met.

The Program Manager shall have the following minimum qualifications:

*A college degree or four (4) years equivalent experience in a technical field (e.g. engineering, construction management, geology, chemistry, or related field). Further, an additional degree or experience in business administration is desirable.

*Two (2) years relevant experience in Program Management/Business Development for other contracts/programs similar in size and scope.

*The ability to effectively communicate and manage customer expectations.

*The ability to locate, coordinate, and utilize resources within his or her organization.

*The ability to effectively communicate and manage customer expectations.

*The ability to locate, coordinate, and utilize resources.

Project Manager (PM)

The PM will plan and coordinate all activities required to comply with Task Order requirements. in close coordination with USACE representatives. The PM shall promptly report all obstacles to mission achievement. The PM will also: coordinate submittals and other deliverables; provide administrative support, supervision, and management of Contractor personnel, equipment, and materials; and provide USACE with progress, financial, and other reports deemed necessary by the Government.

A Project Manager (PM) shall be appointed by the Program Manager for each RDI Task Order awarded. The Program Manager shall furnish the PM’s qualifications, experience and performance to the Contracting Officer for approval. The PM shall be the point of contact for the Task Order, and shall be responsible for the management and execution of all construction activities in exact accordance with the approved statement of work, Contractor's approved submittals and all applicable Federal, state, and local laws and regulations.

The PM shall have the following minimum qualifications:

*Four (4) years working experience as a PM in the construction industry, with emphasis on swift and time-sensitive construction related response actions.

*Working knowledge of applicable Federal, state, and local construction laws and regulations *Four (4) years’ experience related to on-site construction activities at a variety of construction projects.

*The ability to effectively communicate and to assist in management of customer expectations *Shall be directly employed by the Prime Contractor.

10.5 Field Personnel

10.5.1 Accounting/Financial Analyst

Responsible for specific Task Order financial management to include project set- up in the company accounting system, voucher preparation (with complete backup), and financial closeout. The Accounting/Financial Analyst shall be experienced in, and responsible for, all of the firm’s activities related to financial management, internal time keeping, travel and per diem, and invoicing /billing. The analyst is responsible for company compliance with Federal accounting and financial regulations.

The Accounting/Financial Analyst shall have the following minimum qualifications:

*Associates degree or two (2) years equivalent experience in accounting, economics, business law, procurement, or management related curriculum.

*Two (2) years of experience in a position of increasing complexity and responsibility including cost reimbursement requirements.

*Working knowledge of the FAR Section 01 11 00

10.5.2 Onsite Project Onsite Project Cost Tracker (PCT)

As part of site administration requirements for cost reimbursement Task Orders, the contractor may be required to provide daily on-site cost tracking. The PCT’s duties include daily tracking of all costs and maintenance of supporting documentation; utilization of schedules to project funding needs; reporting of variations once actual funding amounts are known; and reconciliation of home office and jobsite financial management records.

Qualifications

The Onsite Project Onsite Project Cost Tracker shall have the following minimum qualifications:

*Four (4) years’ work experience in the construction industry, with emphasis on project cost tracking for cost reimbursable contracts/task orders.

*Working knowledge of the FAR

11.1 PROJECT CLOSEOUT

11.2 Warranty

The Contractor shall complete all inspections and commissioning requirements prior to Final Inspection. All warranties for firm fixed price task orders shall be issued in conjunction with the Final Report. Extended warranties offered by the Contractor and its subcontractors or suppliers may be accepted at the Government’s discretion. See Section 01 78 36.00 24 Warranty of Construction.

11.3 Final Report

For Task Orders, a draft copy of the Project Final Report shall be submitted 30 days after completion of the field work for each Task Order. The report shall include a summary of the work performed and all project documentation. The exact format and requirements will be specified on a Task Order basis.

Attachment 1: Work Authorization Document (Sample)

Work Authorization Document

Primary Contractor's Name:

Contract Number:

Site Name & Location:

Report #: Delivery Order #: Date:

Subcontractor(s):

Government agencies on-scene:

INSTRUCTIONS

The contractor shall attach this form to the rapid response quality control daily report and it shall be submitted daily at the close of business to the on-site COE representative. Concurrently, the contractor shall provide electronic access to the completed forms to the COE district office and the area office.

1. Description of work to be performed by contractor(s), with an estimate of the percentage to be completed:

WORK AUTHORIZATION DOCUMENT - CONT'D.

3. Equipment and expendable materials authorized:

Item Quantity Duration Item Quantity Duration

2. Number of personnel authorized to perform work on site and off site:

Supervisors Foremen Engineers

Technicians Geologists Operators Chemists Laborers EMT

Others (specify):

4. Tests and/or inspections to be performed (indicate type and location):

5. Additional comments/remarks:

6. Certification: I CERTIFY THAT THE ABOVE WORK IS APPROVED BY THE ON-SITE COE

REPRESENTATIVE, SINCE THE WORK EFFORT IS WITHIN THE SCOPE OF THE PROJECT, IN THE

PERFORMANCE OF THE ABOVE-CITED CONTRACT.

On-site COE representative

WORK AUTHORIZATION DOCUMENT - CONT'D.

7. I ACKNOWLEDGE RECEIPT OF THIS WORK ORDER AND UNDERSTAND THAT ANY

MODIFICATION TO THE WORK ORDER MUST BE IN WRITING AND APPROVED BY THE PROPER

GOVERNMENT REPRESENTATIVE.

Contractor's representative

8. Work order amendments and modifications (include time, description, and authorizing person):

On-site COE representative Contractor's representative

Section 00 22 00 - Supplementary Instructions

SUPPLEMENTARY INSTRUCTIONS

Section 00 22 00

SUPPLEMENTARY INSTRUCTIONS

(Submission Requirements and Evaluation)

1.1 CONTRACT INFORMATION

1.2 INDEFINITE DELIVERY TYPE CONTRACTS

The Government intends to issue one solicitation and award a Multiple Award Task Order Contract (MATOC) for shared capacity of $95M to up to four (4) Small Businesses (SB). Individual Task Orders will be solicited and competed within the MATOC pool. Task Orders within the MATOC may be Cost-Plus-Fixed-Fee (CPFF), or Firm Fixed Price (FFP).

The base period for this MATOC is one (1) year. There will be four (4) one-year option periods, making the total ordering period up to five (5) years from the date of award. The Government’s decision to exercise an option will be contingent upon satisfactory contractor past performance and an informal survey of current market conditions. The minimum guarantee amount for this MATOC (to include all option periods) is $2,500.00.

1.3 TYPES OF PROJECTS

Projects will vary in size, complexity, and location, and will require a high degree of flexibility and adaptability.

The Contractor must respond quickly and effectively. All work will be time-sensitive in nature, necessitating an immediate response to mitigate threat to life and property and/or operational impacts to the government.

Previous task orders under the RDI program included: vegetation and debris removal; fuel line pigging/repair;

levee rehabilitation; and railway embankment repair.

Work contemplated under this MATOC include, but are not limited to:

Flood Recovery Flood control and water diversion projects, embankments, channel alignments and flood control structures in support of civil works missions.

Infrastructure Recovery Restoration, repair, and demolition of facilities, utilities, real property systems, and other infrastructure requirement that cannot be performed in required timeframes with normal contract mechanisms to meet vital mission requirements.

Emergency Management Response actions such as unwatering missions, debris recovery, temporary housing, and other actions to meet vital mission requirements.

Military Construction of facilities, infrastructure, water and sanitation systems, electrical systems, natural gas and other energy systems, fences, lighting, and roads to support troop movements and other crucial military missions.

NOTE: Each Task Order Request for Proposal will identify when the contractor must mobilize; however, emergency recovery actions may require mobilization within three (3) days of Government Notification.

Projects may require incidental design and/or ecological/environmental, hazardous waste recovery, and munitions work.

1.4 PROJECT LOCATIONS

Projects may occur anywhere in the United States (US). “United States” is defined as all 50 states and the District of Columbia for this contract. The Offeror shall be prepared to respond to any location within the U.S., as defined above.

1.5 TASK ORDERS

Individual Task Orders will be awarded under this MATOC using either the Tradeoff Source Selection Process (see FAR 15.101-1) or the Lowest Price Technically Acceptable (LPTA) Source Selection Process (see FAR 15.101-2). The process will be determined at the Task Order level and will be communicated in the Task Order RFPs. Task Orders will be awarded as “Firm Fixed Price” (FFP), “Cost Plus Fixed Fee (CPFF),” or a combination of each contract type. Maximum Task Order award will be $20,000,000.00.

RDI Workload History

Average Range of Task Orders Issued: $400k – $2M

Please note that the Government will conduct a cost realism analysis in accordance with FAR 15.404-1(d) on individual Cost Reimbursement task orders during task order source selection so the Contractor(s) will be required to provide adequate cost information during the task order source selection process in order to do such analysis.

2.0 WHO MAY SUBMIT

This solicitation is open to Offerors registered as a Small Business (SB) in the System for Award Management (www.sam.gov).

The Primary North American Industry Classification System (NAICS) code for this solicitation is 236220. This code has a Small Business size standard of $36.5 million dollars.

Proposals submitted must be sufficiently detailed to allow for an effective and equitable evaluation by the Government. There will be no public proposal opening. Proposals submitted will become, upon receipt, the property of the U.S. Government and will not be returned. After evaluation of proposals, electronic copies will be retained for the official paperless contract file. All other copies will be destroyed or forwarded to the Field and Areas Offices in support of their contract administration functions.

3.1 GENERAL PROPOSAL SUBMISSION INSTRUCTIONS

All Offerors shall submit electronic proposals, to include pricing information, via the AMRDEC SAFE website.

Proposals without all required content may be deemed by the Government as non-responsive and the proposal may be rendered as ineligible for award. The Government will utilize the processes described in Section 00 22 00 to evaluate proposals. The Government intends to award up to four (4) contracts under this SB Multiple Award Task Order Contract (MATOC). To be considered for award, Offerors shall submit complete and acceptable proposals prior to the date and time stated on the SF 1442.

The date and time of delivery of proposals will be established by the time of receipt of the e-mail notification to the Contract Specialist and Contracting Officer by the AMRDEC SAFE…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .