+Oahe_Inspect_Shale_Drains_PWS_FINAL_wOPTION.pdf
PDF 7 MB Posted
- Attached to
- Hydro Flush and Inspect Federal contract opportunity
- Solicitation number
- w9128f-17-q-0089
About this file
PWS
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Shale_Drains.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BIDDING SCHEDULE
Inspect and Clean Outlet Works Shale Drains Oahe Dam Pierre, SD
BASE CONTRACT
Item
No. Description Quantity Unit Unit Price Amount
0001. Hydro-Flush and Inspect up to 3800 Lineal Foot $_________ $____________
~3800 Lineal Feet of Shale Drain (horizontal to 2° upward)
0002. All Remaining Work for Base Contract Job LS $____________
TOTAL BASIC AMOUNT $_________________(in figures)
OPTION 1 – Clean and Inspect additional Shale Drains
0003. Hydro-Flush and Inspect up to 2500 Lineal Foot $___________ $___________ ~2500 Lineal Feet of Shale Drain (Horizontal to 2° upward)
0004. All Remaining Work – Option 1 Job LS $___________
TOTAL OPTION 1 AMOUNT $____________________________(in figures)
TOTAL AMOUNT (BASIC) $________________________________ (in figures)
Notes for Bidding Schedule:
1. Bid prices must be entered for all items of the schedule. Total amount bids submitted without bid prices being entered on individual items will be rejected. In case of variation between the lump-sum prices and the total amount, the lump-sum prices will be considered the bid. In case of variation between the unit prices and the extensions, the unit prices will be considered the bid.
2. A modification to a bid that provides for a single adjustment to the total amount bid should state the application of the adjustment to each respective lump-sum price and unit price affected. If the modification is not so apportioned, the single adjustment will be applied on a pro rata basis to all items on bid schedule.
3. The category “All Remaining Work” shall include any activities not listed as pay items, such as mobilization, de-mobilization, Contractor staging, site access, test hydro flushes and inspections, restoration of disturbed surfaces, environmental protection measures, required safety equipment, daily reports, etc.
4. Quantities for unit priced items are estimated only and the respective unit price will prevail in the event of an overrun or underrun.
5. Payment for unit price items shall be based on the unit price per lineal foot multiplied by the number of satisfactorily flushed and/or inspected lineal feet of drain according to the plans and specifications.
6. Payment for lump sum items shall be made on a progressive basis, based on the amount of work completed.
PERFORMANCE WORK STATEMENT (PWS)
Inspect and Clean Outlet Works Shale Drains US Army Corps of Engineers
Oahe Dam 28563 Power House Road, Pierre, SD 57501
PART 1
GENERAL INFORMATION
1. General:
This is a services contract to inspect and clean/flush the outlet works stilling basin shale drains at Oahe Dam, north of Pierre, South Dakota.
1.1 Description of Services/Introduction:
The contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to clean by hydro-flushing the outlet works shale drains as defined in this Performance Work Statement (PWS), except for those items specified as vernment furnished property and services. The contractor shall perform to the standards in this contract.
1.2 Background:
Flood control outlet works are located on the river’s right bank and consists of six tunnels with individual submerged intakes, dam-center control shafts, a two stage stilling basin, and a discharge channel (Photo 1). The outlet works is used to control releases from the reservoir in conjunction with releases required for power generation and were originally used to divert the river during construction. At the maximum
PWS – Oahe Dam - Inspect and Clean Outlet Works Shale Drains | USACE
P ar t 1
G en er al
In fo rm at io n operating pool of elevation 1620.0 feet, the outlet works has a discharge capacity of 111,000 cfs. The stilling basin, located approximately 1,800 feet downstream from the dam’s axis, conveys water to the discharge channel. The stilling basin structure is approximately 495 feet wide and extends 483 feet downstream from the tunnel portals (Plate 1). The stilling basin is a two stage type consisting of primary and secondary basins separated by an ogee weir. The 6 concrete tunnels are 18 feet in diameter and numbered 1 through 6 (from the riverside to the abutment side). The invert of the tunnels is at elevation 1420.0 feet. Five training piers guide water flow from the tunnel portal transition sections, down the drop section and into the primary basin.
Access to the outlet works shale drains is accomplished by entering the access manholes that are located on the west side of each tunnel (Plate 1 and Photo 2). Tunnel 1 has a manhole on the east side that is used for accessing piezometers that are not included in this work. The manhole access with covers are rectangle shaped, 2’-0” by 3’-0”, at elevation 1445.0 feet. The manholes are 6 feet by 6 feet square. From the manhole cover, there is a ladder to a landing at elevation 1431.0 feet, where there is a valve stem that operates a valve at elevation 1422.0 feet, used to drain the manhole (tunnels 2-5). There is another ladder from the landing to the bottom of the manhole at elevation 1418.0 feet. The bottom of the manhole is slightly sloped to a sump and is non-slip (Plates 2 and 3, and Photos 3 through 7).
The shale drains discharge into the manhole from the upstream wall at approximate elevation 1424.0 feet (Plate 4, Photos 8 and 9). Each manhole (tunnels 1-5) has one drain discharge visible. Tunnel 6 is unique in that it has five drain lines entering the manhole, and two ~12” diameter headers on the downstream side. One header is covered with a flange as shown in the drawings and can be seen in Photos 10 and 11.
The lower header in tunnel 6 drains the manhole and extends down the right tailrace wall to the access pit located adjacent to the weir. There is no discharge valve in tunnel 6 manhole; the valve is in the valve pit. Normal tail water elevation is approximately
1425.0 feet, so each manhole is expected to need dewatering after the valves are closed.
According to the drawing on Plate 4, it appears there are two shale drains that join in the upstream wall and discharge through one discharge pipe. These two drains are oriented in the same direction upstream, but at different angles from the horizontal. One pipe is angled approximately 2˚ upward (looking upstream) from horizontal, while the other is angled approximately 9˚ downward (looking upstream) from horizontal, as shown in Plate 4. However, as a result of an initial camera investigation done by the Lake Oahe project office, it is believed only the 2˚ upward (looking upstream) from horizontal drain actually exist. Reference plan view in drawing Plate 5, which only shows one drain extending upstream into the shale. The base contract calls for hydro-flushing and inspecting the drains angled approximately 2˚ upward (looking upstream) from horizontal in tunnels 1 through 5 and the one drain in tunnel 6 that is oriented upstream along tunnel 6. Option #1 calls for hydro-flushing and inspecting the four drains in tunnel six that radiate out form the manhole towards the right abutment. If other drains are found during the inspection it shall be documented within appropriate deliverables described in Section 1.4.
t 1
G en er al
In fo rm at
1.2.1 Project General Information:
Oahe Dam and Reservoir, one of six main stem dam projects on the Missouri River, is located in central South Dakota, approximately six miles upstream from Pierre, South Dakota in Hughes and Stanley Counties. Oahe Dam consists of an earthfill embankment, a gated concrete spillway structure with an earthcut spillway channel, a hydroelectric generating plant, flood control outlet works and a multi-purpose reservoir operated as a unit in coordination with five other mainstem dams. The mainstem system operates according to a comprehensive plan for flood control, irrigation, navigation, power development, recreation, and other uses in the Missouri River Basin. The Oahe Project is a federally owned facility. Project operation and maintenance functions are the responsibility of the Lake Oahe Project Office under the direction of Operations Division, Omaha District, North West Division, USACE.
1.3 Objectives:
The overall objective is to flush/clean and inspect the Outlet Works Shale Drains as specified in this Performance Work Statement.
1.4 Scope:
Work will consist of cleaning by hydro-flushing and inspecting the 2” diameter shale drain pipes in each manhole. Hydro-flushing and inspecting the drains angled approximately 2˚ upward (looking upstream) from horizontal in tunnels 1 through 5 and the one drain extending upstream in tunnel 6 is considered the base contract and hydro-flushing and inspecting the four drains angled approximately 2˚ upward (looking upstream) from horizontal radiating out towards the right abutment is considered option 1 to this contract. Details of the work are included in Part 5, Specific Tasks.
Initially the contractor is required to conduct test hydro-cleaning and camera inspections (before and after hydro-flushing) for up to two test section of pipe. Details are in included in Section 5.2.
Visual inspection of the drains will be done with camera equipment able to enter and record the condition of the drain, to be included in a detailed formal report that will thoroughly document the condition of these features.
The contractor shall provide daily logs (report) which describes the activities, problems/obstructions, findings etc. for each day on site and all features inspected.
Detail are included in Section 5.6.3.
Deliverables from this work will include 3 DVDs of the inspection footage and a report that summarizes the procedures, pertinent field activities, problems encountered and measures taken to alleviate these problems and findings of all inspections. The report shall also include individual inspection logs that summarize the condition of each pipe and documents the location of any significant observation(s). Details are included in Section 5.6.4.
The contractor shall perform these services as noted in this PWS. All work shall be conducted in accordance with current professional standards, Corps of Engineers policies, regulations, and procedures. The Contractor is responsible for supplying all equipment, supplies, materials and personnel necessary for the completion of this work.
t 1
G en er al
In fo rm at
1.5 Period of Performance:
The period of performance for the PWS shall be 90 days from the date of Notice to Proceed (NTP). Upon receipt of NTP, the Contractor shall submit a draft baseline schedule and Work Plan for completion of the tasks in this PWS for approval to meet the milestones as indicated below. The baseline schedule shall be based on calendar days and shall include milestones for completion of each task provided herein.
Schedule Milestones
ITEM Duration (Calendar Days)
Draft Baseline Schedule & Work Plan 14 days after NTP Final Baseline Schedule & Work Plan 21 days after NTP
Kick-Off Meeting (required) Prior to Start of Work
On-Site Field Work Start 30 days after NTP
On-Site Field Work BASE CONTRACT Complete 70 days after NTP
Draft Inspection Reports Complete 75 days after NTP
Completion of all Work 90 after NTP
1.6 General Information
1.6.1 Quality Control:
The contractor shall develop and maintain an effective quality control program to ensure services are performed in accordance with this PWS. The contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The contractor’s quality control program is the means by which he assures himself that his work complies with the requirement of the contract. A QC Plan will be included in the Work Plan submitted by the contractor, as indicated in Paragraph 1.6.4 below.
1.6.2 Quality Assurance:
The government shall evaluate the contractor’s performance under this contract in accordance with Technical Exhibit 1, Performance Requirements Summary. The contractor service requirements are summarized into performance objectives that relate directly to mission essential items. The performance threshold briefly describes the acceptable levels of service required for each requirement. These thresholds are critical to mission success. The method of surveillance describes the method that will be utilized to determine if the performance threshold has been met by the contractor. At any time during the period of performance, representatives of the Contracting Officer may review: work progress; adherence to this PWS and the subsequent Work Plan; and work quality and adequacy. This may include oversight of field operations. Such review shall not relieve the Contractor from performing all contract requirements.
1.6.3 Safety:
The Contractor shall be responsible for site safety of contractor and subcontractor employees and any visitors to the work area. The Contractor shall supply the required safety equipment and shall ensure that all contractor employees and subcontractor employees are properly equipped and trained in all safety procedures and precautions.
t 1
G en er al
In fo rm at
An Accident Prevention Plan (APP) shall be developed, maintained on-site during fieldwork and shall be available for review at any time during the period of performance.
An abbreviated APP shall be submitted as part of the Work Plan.
At a minimum, all work shall be conducted in accordance with OSHA requirements and the requirements in EM 385-1-1, (USACE, 2014). This safety manual is available at the following internet site: http://www.usace.army.mil/Safety-and-Occupational- Health/Safety-and-Health-Requirements-Manual/. All other applicable local, state and federal rules and requirements shall be adhered to.
Confined space entry will be required. All confined space entry shall be in accordance with EM 385-1-1 (USACE 2014) and OSHA requirements. The contractor shall not enter any manholes or other confined spaces without full coordination and prior approval of the Contracting Officer Representative (COR). Insects, rodents, snakes and other wildlife could be encountered in the area of the manholes and pipe entrance and exit points. The contractor shall take appropriate safety precautions and provide appropriate personnel protection equipment. The contractor shall be responsible to submit to the COR Safety Data Sheets (SDS) for any materials delivered to the work site.
1.6.3.1 Site Safety and Health Officer:
A Site Safety and Health Officer (SSHO) shall be designated at the work site at all times to assure adherence to the APP, perform safety and occupational health management, surveillance, inspections, and safety enforcement for the Contractor. The SSHO role and responsibilities may be assigned to one of the personnel working at the site.
1.6.3.2 Tailgate Safety Meetings:
A tailgate safety meeting shall be held at the beginning of the project and daily thereafter for the duration of the project or any time the hazards associated with the work change significantly; whichever is more frequent. The Contractor shall document the occurrence of the safety meeting on the Daily Log form. The Tailgate Safety Meeting documentation shall consist of the safety topics covered, date of the meeting, and printed names and signatures of all participants of the field team. In addition, emergency and Contractor POC phone numbers and the location, direction, and route to the nearest hospital shall be verified and discussed for situational awareness at the Tailgate Safety Meeting.
1.6.4 Work Plan:
The Contractor shall develop and submit a Work Plan that details the Contractor’s plan for executing this PWS to include procedures for completing tasks and gathering relevant data. Fieldwork shall not commence until the Corps of Engineers reviews and approves the Work Plan. The Contractor shall submit for acceptance a written abbreviated APP including an Activity Hazard Analysis (AHA) as part of the Work Plan.
The APP and AHA shall be in accordance with the criteria described in EM 385-1-1, with reference to this manual in the APP (USACE, 2014). At a minimum and as applicable to task(s), the following information will be provided in the Work Plan.
Project Summary Project Management Baseline Project Schedule t 1
G en er al
In fo rm at
Abbreviated Accident Prevention Plan Including Activity Hazard Analysis Quality Control Plan Procedures Points of Contact
1.6.5 Draft and Final Inspection Report:
An Inspection report shall be developed at the completion of the work. The Inspection report shall contain all documentation and results specified in Paragraph 5.6, and delivered as shown in Technical Exhibit 2 (attached). The inspection report shall also describe all pertinent field activities, problems encountered and measures taken to alleviate these problems, and all other appropriate information and data.
1.6.6 Submittals:
The following table outlines the schedule and format of submittals presented in this PWS. Any deviation from this submittal schedule shall be approved by the Contracting Officer. A draft inspection report shall be submitted to the Corps of Engineers for review within 75 days after Notice to Proceed (NTP). The Corps of Engineers will review the draft inspection reports and provide comments that the Contractor shall address in the final inspection report. The final inspection report, incorporating resolution of all comments, will be submitted to the Corps of Engineers within 90 days after NTP.
Submittal Schedule Submittal Schedule
Draft Baseline Schedule & Work Plan 14 days after NTP Final Baseline Schedule & Work Plan 21 days after NTP Daily Log / Tailgate Safety Meeting Forms Daily Field Work Documentation/Draft Inspection Reports Complete 75 days after NTP Final Inspection Report Complete/All work complete 90 days after NTP
Draft Work Plans and Draft Inspection Reports will be provided by hard copy and digital PDF format. Daily Log / Tailgate Safety Meeting Forms can be digital PDF format. One copy of each shall be provided to the Dam Safety Engineer and the Project Office POC listed in paragraph 1.6.14. Format and number of copies for the Final Inspection Report shall be as indicated in paragraph 5.6.4.
1.6.7 Recognized Holidays:
Contractors shall not be required to work on Federal Holidays as listed below:
New Year’s Day Labor Day
Martin Luther King Jr.’s Birthday Columbus Day
President’s Day Veteran’s Day
Memorial Day Thanksgiving Day
1.6.8 Hours of Operation:
The contractor is responsible for conducting business, between the hours of 0700-1700, Monday thru Friday except Federal holidays or when the Government facility is closed t 1
G en er al
In fo rm at due to local or national emergencies, administrative closings, or similar Government directed facility closings. Work on the weekend is acceptable with prior approval of the Oahe Dam POC. For other than firm fixed price contracts, the contractor will not be reimbursed when the government facility is closed for the above reasons. The Contractor must at all times maintain an adequate workforce for the uninterrupted performance of all tasks defined within this PWS when the Government facility is not closed for the above reasons.
1.6.9 Place of Performance:
The work to be performed under this contract will be performed at Oahe Dam, located approx. 7 miles north of Pierre, South Dakota.
1.6.10 Type of Contract:
The government will award a Firm Fixed Price Contract.
1.6.11 Security Requirements:
All Contractor and all associated sub-contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The Contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in Contractor security matters or processes. Directions for background checks are in paragraph 1.6.11.3.
The Contractor will be working at a high profile dam where security concerns are paramount and access is restricted to authorized personnel. The Contractor shall coordinate with the Project Office POC and provide a list of personnel and equipment that will be on-site. The Contractor and their subcontractors shall display identification placards on all vehicles when the vehicles are on the Oahe Dam site. The placards will identify them as a contractor to the Corps of Engineers and display the contractor number for this work. The placards will need to be placed on door panels or other easily identifiable locations.
1.6.11.1 List of Personnel
Submit a complete, updated and signed, list of all Contractor and subcontractor personnel, including their titles and intended working hours, who will be working on site prior to start of work. This listing shall be revised and resubmitted when personnel changes occur.
1.6.11.2 Personnel Risk Assessment
A minimum of seven days prior to engaging in work submit, to the CO or Project POC, a Personnel Risk Assessment (PRA) for each employee requiring authorized unescorted access to the Jobsite. The Contractor employee will only be allowed authorized t 1
G en er al
In fo rm at unescorted physical access after the PRA is shown to and approved by the Government.
1.6.11.3 Authorized Unescorted Access Requirements
Perform a PRA on all Contractor personnel that require authorized unescorted access to the Jobsite. Costs associated with the execution of the PRA shall be at the expense of the Contractor. The content of the PRA is defined by the requirements as follows:
a. Criminal Check - Obtain a criminal background check, completed within the last seven years, on all Contractor personnel that require authorized unescorted access to the Jobsite. A minimum of a 7-year criminal background check with the state patrol office shall be performed from all states of residence and employment, for the past seven years. The COR through the Contacting Officer will approve, disapprove, or revoke authorized unescorted access to the Jobsite as a result of the seven-year background check in accordance with Army Directive 2014-05 Enclosure 2.
b. Identity Verification - Contractor employees shall provide positive verification of individual identity prior to authorized unescorted access to the Jobsite. Acceptable forms of identity verification are documents issued by a federal Government agency that include: the individual's photograph, name, and date of birth, such as a passport or military identification (ID) card. Additionally, a state issued driver's license or ID card is acceptable for identity verification.
c. The Criminal Check and Identity Verification shall be updated at least every seven years for each employee requiring authorized unescorted access to the Jobsite.
d. Escort Requirements - Contractor personnel not cleared for authorized access to the Jobsite may be escorted by Government or Contractor personnel that have authorized unescorted access to the Jobsite. All costs related to the escorting of non-cleared personnel shall be at the expense of the Contractor. Additional burden shall not be placed upon the Government to provide these escorts. Prior to access, coordination with the Project Security Officer is required, including but not limited to:
(1) Verification of identity with photo identification
(2) Name of escorting individual and verification of unescorted status
(3) Time of entry into the Jobsite
(4) Time exiting the Jobsite.
1.6.11.4 Special Qualifications:
All Contractor employees, to include subcontractor employees, requiring access to Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. The Contractor shall submit certificates of completion for each affected Contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 5 calendar days after completion of training by all employees and subcontractor personnel. AT Level I awareness training is available at the following website: http://jko.jten.mil/courses/atl1/launch.html.
t 1
G en er al
In fo rm at
1.6.11.5 Suspicious Activity Training:
The Contractor and all associated sub-contractors shall brief all employees on the local iWATCH, Corps Watch, or See Something, Say Something program (training standards provided by the requiring activity ATO). This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 5 calendar days after contract award.
http://www.myarmyonesource.com/cmsresources/Army%20OneSource/Media/Videos/Family%2 0Programs%20and%20Services/iWatch_Program/iWATCH%2060_4streaming.wmv
1.6.11.6 OPSEC Training:
All new Contractor employees will complete Level I OPSEC training within 30 calendar days of their reporting for duty. Additionally, all Contractor employees must complete annual OPSEC awareness training. http://cdsetrain.dtic.mil/opsec/index.htm
1.6.11.7 Security Clearance:
All contract employees, including subcontractor employees who are not in possession of the appropriate security clearance, will be escorted in areas where they may be exposed to classified and/or sensitive materials and/or sensitive or restricted areas.
1.6.11.8 Facility Clarence:
The Prime Contractor Company must have (or will have) a Facility Clearance (FCL) at the appropriate level (IAW the NISPOM DOD 5220.22-M and AR 380-49) prior to the start of the contract awarded period of performance. Contractor personnel performing work under this contract must have the required security clearance, per AR 380-67, at the appropriate level at the start of the period of performance. Security Clearances and FCL requirements are required to be maintained for the life of the contract IAW the DD254 attached to the contract. If no FCL, the supporting Government Contracting Activity will sponsor the prime contract company in obtaining the FCL. This location does NOT require a Facility Clearance/FCL.
1.6.11.9 Eligibility Verification:
The Contractor must pre-screen Candidates using the E-verify Program (http://www.dhs.gov/E-Verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award. When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, with the designated Government representative. This Form will be provided to the Contracting Officer and shall become part of the official contract file.
1.6.11.10 Physical Security:
The Contractor shall be responsible for the security of all contactor equipment at all times. The Contractor shall coordinate with, and acquire approval from the Project t 1
G en er al
In fo rm at
Office POC regarding leaving vehicles or equipment at the dam site overnight or otherwise unattended. The Contractor shall also coordinate with, and acquire approval from the Project Office POC regarding acceptable staging areas for the work. The contractor shall be responsible for safeguarding any government equipment, information and property provided for contractor use. At the close of each work period, government facilities, equipment, and materials shall be secured.
1.6.11.11 Key Control:
The Contractor shall establish and implement methods of making sure all keys/key cards issued to the Contractor by the Government are not lost or misplaced and are not used by unauthorized persons. NOTE: All references to keys include key cards. No keys issued to the Contractor by the Government shall be duplicated. The Contractor shall develop procedures covering key control that shall be included in the Quality Control Plan. Such procedures shall include turn-in of any issued keys by personnel who no longer require access to locked areas. The Contractor shall immediately report any occurrences of lost or duplicate keys/key cards to the Contracting Officer.
In the event that keys, other than master keys, are lost or duplicated, the Contractor shall, upon direction of the Contracting Officer, re-key or replace the affected lock or locks; however, the Government, at its option, may replace the affected lock or locks or perform re-keying. When the replacement of locks or re-keying is performed by the Government, the total cost of re-keying or the replacement of the lock or locks shall be deducted from the monthly payment due to the Contractor. In the event a master key is lost or duplicated, all locks and keys for that system shall be replaced by the Government and the total cost deducted from the monthly payment due to the Contractor.
The Contractor shall prohibit the use of Government issued keys/key cards by any persons other than the Contractor’s employees. The Contractor shall prohibit the opening of locked areas by Contractor employees to permit entrance of persons other than Contractor employees engaged in the performance of assigned work in those areas, or personnel authorized entrance by the Contracting Officer.
1.6.11.12 Post Award Conference/Periodic Progress Meetings:
The Contractor agrees to attend any post award conference convened by the contracting activity or contract administration office in accordance with Federal Acquisition Regulation Subpart 42.5. At a minimum the contractor shall attend one kick-off meeting prior to the work commencing. The COR and other Government personnel, as appropriate, may meet periodically with the contractor to review the contractor's performance. At these meetings the contracting officer will apprise the contractor of how the Government views the contractor's performance and the contractor will apprise the Government of problems, if any, being experienced. Appropriate action shall be taken to resolve outstanding issues. These meetings shall be at no additional cost to the government. Meeting minutes shall be developed by the contactor and provided to the government.
1.6.11.13 Contracting Officer Representative (COR):
t 1
G en er al
In fo rm at
The COR will be identified by separate letter. The COR monitors all technical aspects of the contract and assists in contract administration. The COR is authorized to perform the following functions: assure that the Contractor performs the technical requirements of the contract: perform inspections necessary in connection with contract performance:
maintain written and oral communications with the Contractor concerning technical aspects of the contract: issue written interpretations of technical requirements, including Government drawings, designs, specifications: monitor Contractor's performance and notifies both the Contracting Officer and Contractor of any deficiencies; coordinate availability of government furnished property, and provide site entry of Contractor personnel. A letter of designation issued to the COR, a copy of which is sent to the Contractor, states the responsibilities and limitations of the COR, especially with regard to changes in cost or price, estimates or changes in delivery dates. The COR is not authorized to change any of the terms and conditions of the resulting order.
Government Points-of-Contact for the work are provided in the table below.
USACE Points-of-Contact Function Name Office Phone Cell Phone Address
Dam Safety Engineer
Carlie Mander (402) 995-2089 (402) 990-7317
Carlie.L.Mander@usace.army.mil or Carlie Mander, US Army COE
CENWO-ED-GB
1616 Capitol St Omaha, NE 68102
Project Office POC
Kris Cleveland (605) 945-3410 (605) 280-8006
Kris.Cleveland@usace.army.mil
US Army COE
CENWO-OD-OA
28563 Power House Road, Pierre, SD 57501
1.6.12 Key Personnel:
The following personnel are considered key personnel by the government: Contract Manager, Alternate Contract Manager, and Lead On-Site Field Representative. The contractor shall provide a contract manager who shall be responsible for the performance of the work. The name of the contract manager, alternate contract manager, and lead on-site field representative shall be designated in writing to the contracting officer. The contract manager or alternate shall have full authority to act for the contractor on all contract matters relating to daily operation of this contract. The contract manager or alternate shall be available between 0800 to 1630, Monday thru Friday, except Federal holidays or when the government facility is closed for administrative reasons. Contact information shall include office phone, cell phone, and e-mail address for each individual. In addition, the contractor shall provide a 24-hour phone number that can be utilized to contact the contractor’s POCs outside of normal business hours. The Contractor will provide the updated contact lists anytime there is a change in personnel or contact information. All employees shall possess required licenses/certificates/insurance as required by federal, state, and local authorities.
t 1
G en er al
In fo rm at
1.6.13 Identification of Contractor Employees:
All contract personnel attending meetings, answering Government telephones, and working in other situations where their contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression in the minds of members of the public that they are Government officials. They must also ensure that all documents or reports produced by contractors are suitably marked as contractor products or that contractor participation is appropriately disclosed.
1.6.14 Public Affairs:
The Contractor shall not make available to the news media or publicly disclose any data generated in the performance of this work. If approached by the news media or general public, the Contractor shall refer them to the Oahe Project Office for a response.
1.6.15 Contractor Travel:
N/A
1.6.16 Other Direct Costs:
N/A
1.6.17 Data Rights:
The Government has unlimited rights to all documents/material produced under this contract. All documents and materials, to include the source codes of any software, produced under this contract shall be Government owned and are the property of the Government with all rights and privileges of ownership/copyright belonging exclusively to the Government. These documents and materials may not be used or sold by the contractor without written permission from the Contracting Officer. All materials supplied to the Government shall be the sole property of the Government and may not be used for any other purpose. This right does not abrogate any other Government rights.
1.6.18 Organizational Conflict of Interest:
N/A
1.6.19 Phase in / Phase Out Period:
N/A t 2
D ef in iti on s an d
A cr on ym s
PART 2
DEFINITIONS & ACRONYMS
2. Definitions and Acronyms:
2.1 Definitions:
2.1.1 Contractor:
A supplier or vendor awarded a contract to provide specific supplies or service to the government. The term used in this contract refers to the prime.
2.1.2 Contracting Officer:
A person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the government. Note: The only individual who can legally bind the government.
2.1.3 Contracting Officer’s Representative (COR):
An employee of the U.S. Government appointed by the contracting officer to administer the contract. Such appointment shall be in writing and shall state the scope of authority and limitations. This individual has authority to provide technical direction to the Contractor as long as that direction is within the scope of the contract, does not constitute a change, and has no funding implications. This individual does NOT have authority to change the terms and conditions of the contract.
2.1.4 Defective Service:
A service output that does not meet the standard of performance associated with the Performance Work Statement.
2.1.5 Deliverable:
Anything that can be physically delivered. This may include non-manufactured things such as meeting minutes or reports.
2.1.6 Key Personnel:
Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the Key Personnel listed in the PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.
2.1.7 Physical Security:
Actions that prevent the loss or damage of Government property.
2.1.8 Quality Assurance:
The government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.
2.1.9 Quality Assurance Surveillance Plan (QASP):
An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.
t 2
D ef in iti on s an d
A cr on ym
2.1.10 Quality Control:
All necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet contract requirements.
2.1.11 Subcontractor:
One that enters into a contract with a prime contractor. The Government does not have privity of contract with the subcontractor.
2.1.12 Work Day:
The number of hours per day the Contractor provides services in accordance with the contract.
2.1.13 Work Week:
Monday through Friday, unless specified otherwise.
2.2. Acronyms:
AFARS Army Federal Acquisition Regulation Supplement AHA Activity Hazard Analysis APP Accident Prevention Plan AR Army Regulation CFR Code of Federal Regulations COR Contracting Officer Representative COTR Contracting Officer's Technical Representative COTS Commercial-Off-the-Shelf DA Department of the Army DOD Department of Defense EM Engineer Manual FAR Federal Acquisition Regulation KO Contracting Officer NTP Notice to Proceed OCI Organizational Conflict of Interest OCONUS Outside Continental United States (includes Alaska and Hawaii) POC Point of Contact PRS Performance Requirements Summary PWS Performance Work Statement QA Quality Assurance QASP Quality Assurance Surveillance Plan QC Quality Control SSHO Site Safety and Health Officer TE Technical Exhibit t 4
C on tr ac to r
F ur ni sh ed It em
PART 3
GOVERNMENT FURNISHED PROPERTY, EQUIPMENT, AND SERVICES
3. Government Furnished Items and Services:
3.1 Services:
N/A
3.1 Facilities:
N/A
3.2 Utilities:
N/A. Water for flushing operations may be obtained from the Project Office at the outside Maintenance Facility.
3.3 Equipment:
N/A
3.4 Materials:
t 4
C on tr ac to r
F ur ni sh ed It em
PART 4
CONTRACTOR FURNISHED ITEMS AND SERVICES
4. Contractor Furnished Items and Responsibilities:
4.1 General
The Contractor shall furnish all supplies, equipment, facilities and services required to perform work under this contract that are not listed under Section 3 of this PWS.
4.2 Secret Facility Clearance:
N/A
4.3 Supplies and Materials:
The Contractor shall provide all supplies and materials to meet the requirements under this PWS. This includes, but is not limited to, those supplies and materials necessary to collect and capture materials flushed from the drains.
4.4 Equipment:
The Contractor shall provide all equipment necessary to meet the requirements under this PWS. This includes, but is not limited to, camera equipment to be used for horizontal pipes and hydro-flushing equipment.
t 5
S pe ci fic
T as ks
PART 5
SPECIFIC TASKS
5. Specific Tasks:
5.1 Basic Services:
The contractor shall provide services to clean by hydro-flushing and inspect drains with camera equipment and produce a detailed formal report to thoroughly document the condition of these features and results of cleaning procedure. Deliverables from this work will include DVD(s) of the inspection footage and a report that summarizes the procedures and findings of all inspections and includes individual inspection logs that summarize the condition of each shale drain segment and documents the location of any significant observation.
Basic and optional work is listed below. Complete task descriptions, site-specific requirements, and other pertinent information for the Oahe Dam are provided below.
5.1.1 Base Contract:
Clean by hydro-flushing and inspecting up to approximately 3,800 lineal feet of shale drain (horizontal to 2˚ upward looking upstream) in the outlet works stilling basin.
5.1.2 Option 1:
Clean by hydro-flushing and inspecting up to approximately 2,500 lineal feet of shale drain (angled 2˚ upward looking upstream) in the outlet works stilling basin.
5.2 Base Contract – Clean by Hydro-Flushing and Inspect Drains Horizontal to 2° Upward Looking Upstream:
This work shall include hydro-flushing, performing a camera inspection and documenting the condition of up to 3,800 lineal foot of horizontal to 2˚ upward (from horizontal) 2 inch drain pipe accessed from the outlet works stilling basin manholes.
The contractor shall conduct up to two hydro-flush tests and perform camera inspections both before and after the test hydro-flush. The test pipe sections shall be a minimum of 20 feet in length with locations to be selected by the COR. During the test hydro flushing, the water pressure used shall be documented by the contractor. The condition of the test pipe section shall be documented by the contractor both before and after the test hydro-flush. Results documenting the condition of the test pipe sections shall be reviewed and approval given by the COR prior to the contractor proceeding to hydro-flushing all the drain pipes outlined in the base contract.
All hydro-flushing and inspection equipment and procedures for this work shall conform to this PWS and hydro flushing and inspections shall be inclusive of the estimated pipe length for pipes identified in Table 5-1 below, if accessible. Pipe and manhole details for the stilling basin drains are provided on drawing PLATES 1-5. Manhole designations, pipe lengths and pipe materials are summarized below in Table 5-1. NOTE: Pipe lengths were approximated from PLATE 5. All materials flushed from the drains must be captured and removed from the manholes. The Contractor’s Work Plan shall discuss their method to prevent sediment from washing into the legs of the drains that are not t 5
S pe ci fic
T scheduled for flushing. Disposal of the sediments will be coordinated with and directed by the Project POC.
The COR shall be notified immediately if any portion of pipe cannot be hydro-flushed and/or inspected, and details shall be documented on the Daily Log. Payment will not be made for drain pipe portions not hydro-flushed or inspected without prior approval from the COR.
Table 5-1 Shale drain pipe details for base contract
Pipe No.
(PLATE 5)
Location/ Manhole
Pipe Size & Material Approx. Pipe Length horizontal to 2˚ upward (feet)
21 MH 1
3" galv. Steel pipe with 2"plastic pipe inside (with gravel pack)
19 MH 2
3" galv. Steel pipe with 2"plastic pipe inside (with gravel pack)
17 MH 3
3" galv. Steel pipe with 2"plastic pipe inside (with gravel pack)
15 MH 4
3" galv. Steel pipe with 2"plastic pipe inside (with gravel pack)
13 MH 5
3" galv. Steel pipe with 2"plastic pipe inside (with gravel pack)
11 MH 6
3" galv. Steel pipe with 2"plastic pipe inside (with gravel pack)
5.3 Option 1 – Clean by Hydro-Flushing and Inspect Drains Horizontal to 2° Upward Looking Upstream near tunnel 6:
This work shall include hydro-flushing, performing a camera inspection and documenting the condition of up to 2,500 lineal foot of horizontal to 2˚ upward (from horizontal) 2 inch drain pipe accessed from the outlet works stilling basin manholes.
The contractor shall conduct up to two hydro-flush tests and perform camera inspections both before and after the test hydro-flush. The test pipe sections shall be a minimum of 20 feet in length with locations to be selected by the COR. During the test hydro flushing, the water pressure used shall be documented by the contractor. The condition of the test pipe section shall be documented by the contractor both before and after the test hydro-flush. Results documenting the condition of the test pipe sections shall be reviewed and approval given by the COR prior to the contractor proceeding to hydro-flushing all the drain pipes outlined in the base contract.
All hydro-flushing and inspection equipment and procedures for this work shall conform to this PWS and hydro flushing and inspections shall be inclusive of the estimated pipe length for pipes identified in Table 5-2 below, if accessible. Pipe and manhole details for the stilling basin drains are provided on drawing PLATES 1-5. Manhole designations, pipe lengths and pipe materials are summarized below in Table 5-2. NOTE: Pipe lengths were approximated from PLATE 5. All materials flushed from the drains must be captured and removed from the manholes. The Contractor’s Work Plan shall discuss their method to prevent sediment from washing into the legs of the drains that are not scheduled for flushing. Disposal of the sediments will be coordinated with and directed by the Project POC.
t 5
S pe ci fic
T
The COR shall be notified immediately if any portion of pipe cannot be hydro-flushed and/or inspected, and details shall be documented on the Daily Log. Payment will not be made for drain pipe portions not hydro-flushed or inspected without prior approval from the COR.
Table 5-2 Shale drain pipe details for option 1
Pipe No.
(PLATE 5)
Location/ Manhole
Pipe Size & Material Approx. Pipe Length horizontal to 2˚ upward (feet)
10a MH 6 3" galv. Steel pipe with 2"plastic pipe inside (with gravel pack)
9 MH 6
3" galv. Steel pipe with 2"plastic pipe inside (with gravel pack)
8 MH 6
3" galv. Steel pipe with 2"plastic pipe inside (with gravel pack)
7* MH 6
3" galv. Steel pipe with 2"plastic pipe inside (with gravel pack)
* MH 6 has 5 pipes of which 4 are shown on Plate 5. The 5th pipe is estimated to be the same length as “pipe 9” (450 feet) from Plate 5. Location of pipe 7 can be seen on Plate 4 in the tunnel 6 plan view.
5.4 Access Restrictions and Controls:
All access to the project site shall be fully coordinated with the Project Office POC in advance of mobilization to the site. A Contractor staging area and equipment storage area can be provided nearby. The staging areas shall be fully coordinated with the Project Office POC in advance of mobilization to the site.
5.5 Site Restoration:
The Contractor is responsible for site restoration to the satisfaction of the Project Office POC. The project site and any staging areas, access roads, haul roads, or other areas disturbed by the Contractor shall be restored to original conditions after completion of work to include removing excess materials, equipment, and repairing any rutting or other damages and seeding and disturbed areas at the dam. The Contractor shall be responsible for providing all equipment, persons, and material to complete site restoration. The Contractor shall coordinate with, and acquire approval from the Project Office POC regarding final disposition of the project site.
5.6 Inspection and Inspection Reporting Requirements:
5.6.1 Camera Equipment:
The inspection shall be performed with the use of camera equipment that may include a controlled crawler unit for horizontal pipes. All equipment shall be rugged, constructed of non-corrosive/non-hazardous material, and be designed for the intended purpose of this type of inspection work. The camera shall be equipped with high-resolution lenses capable of a clear view (subject to water clarity) of the various pipe components. The camera shall also be equipped to pan, focus, zoom and provide a variable intensity light source. Date, time, and distance readout must appear on-screen at all times. The camera equipment shall have the capability of providing continuous audio and video documentation in digital format and have the ability to capture still photos of damage or problem areas for inclusion into reports. The camera head may be capable of continually rotating 360 degrees, panning from side to side +/- 120 degrees, and t 5
S pe ci fic
T possess an automatic upright feature for image orientation. The camera equipment may have the capability of providing continuous depth/length measurements. The camera equipment must have the capability of inspecting horizontal pipe diameters and conditions specified in the site-specific requirements.
5.6.2 Field Inspection:
The field inspection shall include a detailed inspection and evaluation of all features for each drainage pipe as applicable to include, but not limited to the following:
Perforated drainage pipe (interior and exposed exterior) Non-perforated drainage pipe (interior and exposed exterior) Pipe joints (interior and exposed exterior) Pipe configuration (interior and exposed exterior) Length inspected Blockage location / description
5.6.3 Daily Log (Reports) Documentation:
The contractor shall provide complete documentation which describes the activities for each day on site and all features inspected. The Daily Log requirements include but are not limited to the following:
Date and personnel performing work Drain/manhole designation Lengths of drain pipe inspected Findings of configurations Problems/obstructions found
The daily log shall be made available to the Project POC and Dam Safety Engineer at the end of each day.
5.6.4 Reports:
The contractor shall develop and submit three (3) copies of a professionally prepared…