Amendment to Solicitation W9128F-15-B-0026 Attachment to SF30
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 15-B-0026_Bid_Abstract.pdf | ||
| W9128F-15-B-0026_AMD0001.pdf | ||
| Old_Fort_Thompson_Specs.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Am #0001 - 1
DEPARTMENT OF THE ARMY
Omaha District, Corps of Engineers
1616 Capitol Avenue Omaha, Nebraska 68102-4901
:NOTICE: Failure to acknowledge : Solicitation No. W9128F 15 B 0026 :all amendments may cause rejec- :
:tion of the bid. See FAR : Date of Issue: 18 August 2015 :52.214-3 of Section 00 21 00 : Date of Opening: 17 September 2015
Amendment No. 0001 24 August 2015
SUBJECT: Amendment No. 0001 to Specifications and Drawings for Construction of Bank Stabilization – Old Fort Thompson – Phase 2, Big Bend Dam, SD.
Solicitation No. W9128F 15 B 0026.
TO: Prospective Bidders and Others Concerned
1. The specifications and drawings for subject project are hereby modified as follows (revise all specification indices, attachment lists, and drawing indices accordingly).
a. Specifications. (Descriptive Changes.)
(1) Section 00 21 00 Page 10, paragraph 1.17, delete:
“(b) Contractors interested in inspecting the site of the proposed work need to make reservations by emailing Michael J. Trumm., US Army Corps of Engineers, Big Bend Project, at Michael.J.Trumm@usace.army.mil. The site visit is scheduled for Friday, 23 August 2013 at 10:00 am. Contractors are to meet at the Big Bend Administrative Building.”
and substitute:
“(b) Contractors interested in inspecting the site of the proposed work need to make reservations by emailing Colby Brakke, US Army Corps of Engineers, Big Bend Project, at Colby.T.Brakke@usace.army.mil, 605-245-1825.
The site visit is scheduled for Tuesday September 1, 2015 at 1:00 pm.
Contractors are to meet at the Big Bend Administrative Building.”
(2) Section 00 21 00 Page 12, paragraph 1.21, delete “(402) 995- 2091” and substitute “(402) 995-2085”.
(3) Section 00 21 00 Page 15, paragraph 1.31, delete the following:
“Contractual Matters: Polina Poluektova Polina.A.Poluektova@usace.army.mil
(402) 995-2091
(402) 995-2081” and substitute:
“Contractual Matters: Aleasha Cotton Aleasha.D.Cotton@usace.army.mil
(402) 995-2085
(402) 995-2081”
Attachment, dated 24 August 2015; 5 pages
Am #0001 - 2
(4) Section 01 57 20.00 10 Page 3, see Attachments, delete:
"Army Corps of Engineers Regional General Permit 00-05, Application No. NWO- 2012-1002" and add “Time Extension Memo for Regional General Permit". Delete the attachment pages that follow section 01 57 20.00 10 (37 pages) and substitute the attachment pages (3 pages) included with this amendment.
(5) Section 01 57 20.00 10 Page 10, delete paragraph 3.1.1 and substitute the following:
"3.1.1 US Army Corps of Engineers Regional General Permit 00-05
The Army Corps of Engineers is currently issuing coverage for this work under A Regional General Permit 00-05. The current permit will expire on September 21, 2015. The US Army Corps of Engineers is obtained an extension to this permit. A copy of the extension is attached. The Contractor is required to be in compliance with the Regional General Permit 00-05"
2. This amendment is a part of the bidding papers and its receipt shall be acknowledged on the [new] Standard Form 1442. All other conditions and requirements of the specifications remain unchanged. If the bids have been mailed prior to receiving this amendment, you will notify the office where bids are opened, in the specified manner, immediately of its receipt and of any changes in your bid occasioned thereby.
a. Hand-Carried Bids shall be delivered to the U.S. Army Corps of Engineers, Omaha District, Contracting Division, 1616 Capitol Avenue, Omaha, Nebraska 68102-4901.
b. Mailed Bids shall be addressed as noted in Item 8 on Page 00 10 00-1 of Standard Form 1442.
3. Bids will be received until 2:00 p.m., local time at place of bid opening, 17 September 2015.
Attachments: Spec Pages listed in 1.a. above
U.S. Army Engineer District, Omaha Corps of Engineers 1616 Capitol Avenue Omaha, Nebraska 68102-4901
24 Aug 2015
MFS/2184
Section 01 57 20.00 10 Attachment Page 1
Specifications for Contractors Concerning Prevention of Spread of Dreissena from Infested to Uninfested Waterways
Background
Zebra mussels and quagga mussels (Dreissena polymorpha and D. bugensis) are black and white striped freshwater mussels that live attached to virtually any hard surface and clog power plants, industrial and drinking water intakes, foul boat hulls, and disrupt ecosystems. Their economic and ecological impacts are serious. Prevention of their spread when boats and other equipment are moved from a potentially infested to uninfested waterway is necessary.
The Contractor must certify that all equipment associated with the construction project that will be used within the reach of the Missouri River designated as the Missouri National Recreational River (MNRR) is free of zebra mussels (Dreissena polymorpha) or zebra mussel larvae prior to entering the MNRR. If any construction equipment has been in zebra mussel infested waters, which includes but not limited to of the Great Lakes as well as the Mississippi, the Arkansas, the Ohio, the Illinois, the Tennessee, the Susquehanna and the Hudson rivers, the following checks and possible subsequent decontaminations must be completed prior to equipment entering the MNRR.
Step 1. Inspection
All waterborne vessels will be pulled out of the Missouri River at or downriver of Sioux City, Nebraska/Iowa. At the location where the boats are pulled out, thoroughly inspect hulls, drive units, trim and trolling plates, props and prop guards, transducers, anchors, ropes, and chains, trailers and any other equipment that has been kept wet.
All bilge water, live wells, engine cooling water, and any other water associated with the equipment should be drained at least one quarter mile from the river and it must be ensured that discarded water does not flow into the river.
Aquatic vegetation clinging to equipment or vessel should be removed and discarded.
Any attached mussels must be scraped off and thrown in the trash. Likewise, bait and bait bucket water must be similarly discarded.
Should zebra mussels be found during this inspection, or if the vessel has been in contaminated waters, one of the following two methods must be taken to prevent their spread.
Step 2. Cleaning
Option 1. Hot Water Rinses
Hot Water Rinses may be used to decontaminate vessels and equipment. This acts to kill the mussels and remove them from equipment. A high-pressure, hot water (120°F) washer should be used. These rinses are required for hulls, drive units, props and guards, Am 0001
Section 01 57 20.00 10 Attachment Page 2 trim and trolling plates, anchor chains and ropes, bilge and live wells, trailers and engine cooling systems.
Option 2. Aerial Exposure
Equipment and vessels must left in the open, not in the shade, for at least 5 full days (120 hours). In addition, equipment and vessels must be completely dry for 2 full days (48 hours) prior to re-entering the Missouri River at the project site.
Step 3: Documentation
All inspection and cleanings must take place under the supervision of the contracting officer’s representative (COR). The COR must be given at least two business days notice prior to inspection. Written certification that equipment is free of zebra mussel contamination shall be presented to the COR prior to mobilizing the equipment into the MNRR. This is to include a list of checks performed, findings and decontamination activities.
| am_0001 |
| 01 57 20.00 10 ATT |
| 01 57 20.00 10 ATT |
| zebespec_Construction project |
Old Fort RGP Extension