This solicitation requests quotations for two digital static excitation systems and power potential transformers for the Norfork Powerhouse. The U.S. Army Corps of Engineers Engineering District Little Rock is procuring these items as an unrestricted acquisition. Offerors must provide pricing for design, manufacturing, factory testing, delivery, as-built drawings, spare parts, commissioning, and training in accordance with the specifications in the five attached documents. The response due date was extended to May 18, 2020. Award will be determined by a best value tradeoff analysis of technical factors and past performance, which are substantially more important than price.

View the file

Other files for this federal contract opportunity

Other files attached to Exciter Supply, Norfork Powerhouse, newest first.
File Type Posted
A.07.24 Amendment 0001- Exciter Supply, Norfork Powerhouse.pdf PDF
A.02.01 Attachment A- Form PPQ-0.pdf PDF
A.02.01 Attachment 1- Specifications.pdf PDF
A.02.01 Attachment 2- Reference Plans.pdf PDF
A.02.01 Attachment 3- Plans.pdf PDF
A.02.01 Combined Synopsis & Solicitation.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Amendment 0002 provides Government responses to requests for information; provides a revised bid schedule, revises the submission requirments and evaluation criteria, provides changes to specifications, and extends the quotation due date to May 18, 2020.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 24

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 06-May-2020

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W9127S20Q0002

X 9B. DATED (SEE ITEM 11)

30-Mar-2020

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

06-May-2020

CODE

CONTRACTING DIVISION

USACE, LITTLE ROCK (W9127S)

700 W. CAPITOL AVE, RM 7315

LITTLE ROCK AR 72201-3225

W9127S 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W9127S20Q0002

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 1449 - CONTINUATION SHEET

SOLICITATION/CONTRACT FORM

The required response date/time has changed from 14-May-2020 01:00 PM to 18-May-

2020 01:00 PM.

The following have been added by full text:

AMENDMENT SUMMARY

Norfork Exciter Supply

SOLICITATION NO. W9127S20Q0002

Amendment 0002 Summary of Changes

Drawing E-201:

- Available area for the exciter has been changed from 9’6” x 4’6” to 9’6” x 5’6”

- Note 5 has been amended to read “Exciter cubicles shall be segmentable into sections no longer than 7 feet.

Each section shall have the smallest overall footprint length dimension not be greater than 54" (i.e. only one of the footprint dimensions is permitted to be between 54" and 84" while the other dimension must be 54" or less)."

o This is due to access and maneuverability limitations.

- The conduit entry point approximate locations for the excitation system have been removed – the entry points for the AC and DC conduit into the excitation system will be in the top of the equipment, and will be submitted for approval as part of the arrangement drawings for this Contract.

Specifications:

SECTION 01 11 00.00 26:

- Paragraph 1.1 now reads:

o “The scope of work for this contract consists of the Contractor furnishing all engineering, labor, materials, and equipment to perform the following work in strict accordance with the detailed requirements of this contract:”

Removed “supervision”, originally in place between “all” and “engineering”.

“The scope of work for this contract consists of the Contractor furnishing all supervision, engineering, labor, materials, and equipment to perform the following work in strict accordance with the detailed requirements of this contract:”

- Item (c) in Paragraph 1.1 now reads:

o “Provide recommendations for wire and cable types for all wire and cable necessary for connection between components of the excitation systems (namely, the PPTs and exciter cabinets).”

Replaced “Furnish all necessary wire, cable, and buswork” with “Provide recommendations for wire and cable types for all wire and cable”

“Furnish all necessary wire, cable, and buswork Provide recommendations for wire and cable types for all wire and cable necessary for connection between components of the excitation systems (namely, the PPTs and exciter cabinets).”

SECTION 48 19 26.00 26:

- Paragraph 1.1.1 now reads:

o “This section covers the work necessary to design; to prepare drawings, data, and installation instructions; to manufacture; to shop test; to prepare and load for shipment; and to deliver f.o.b.

destination two complete digital static excitation systems at the Norfork Powerhouse. All components, wiring, and connections within the excitation systems and the power potential transformers (PPTs) shall be provided. External connections (medium voltage supply to PPTs, wire and cable between PPT and exciter cabinets, DC leads to the slip rings, and all power, control, and communication wiring) are excluded from the supply.”

Removed “and between” between the words “within” and “the excitation systems”.

“All components, wiring, and connections within and between the excitation systems and the power potential transformers (PPTs) shall be provided.”

Added “wire and cable between PPT and exciter cabinets” to list of items excluded in the last sentence.

“External connections (medium voltage supply to PPTs, wire and cable between

PPT and exciter cabinets, DC leads to the slip rings, and all power, control, and communication wiring) are excluded from the supply.”

- Submittal Section SD-08 (Manufacturer’s Instructions):

o A new Submittal is added - “Installation Instructions; G, HDC” with a due date of no less than 30 calendar days prior to delivery.

- Paragraph 2.4.1 now reads:

o “PPTs shall be provided for each unit and be of the three-phase, 60 Hz, self-cooled, ventilated, Vacuum Pressure Impregnated (VPI) dry type, conforming to the applicable requirements of IEEE C57.12.01, with a Basic Insulation Level (BIL) on the high voltage winding of 95 kV. The winding material shall be copper. The PPTs furnished shall also conform to the recommended practice of IEEE C57.110 and shall be designed specifically for supplying a thyristor-controlled rectifier load.

The PPTs shall be of sufficient rating to deliver the required input power to the exciters under all generator operating conditions, with an average winding temperature rise by resistance not to exceed 90°C. Hottest spot winding temperature rise shall not exceed 110°C. For each unit, three suitable relaying accuracy current transformers (CTs) shall be installed on the PPT secondary. The PPTs shall be designed for floor mounting, with secondary connection to the excitation equipment.”

Added “Vacuum Pressure Impregnated (VPI)” and changed the BIL requirement from 110 kV to 95 kV in the first sentence

“PPTs shall be provided for each unit and be of the three-phase, 60 Hz, self-cooled, ventilated, Vacuum Pressure Impregnated (VPI) dry type, conforming to the applicable requirements of IEEE C57.12.01, with a Basic Insulation Level (BIL) on the high voltage winding of 110 95 kV.”

Added sentence “The winding material shall be copper.”

- Paragraph 2.4.3 now reads:

o “Three new current limiting fuses (CLFs) and holders shall be provided in the primary chamber of each potential power transformer (PPT). Submit Fuse Ratings for approval. The BIL rating for the fuse holders shall be 95 kV. The fault current available at the generator terminals is approximately 17 kA, symmetrical. The fuses shall be accessible and easily removed for maintenance purposes.”

Changed BIL requirement from 110 kV to 95 kV.

“[…] The BIL rating for the fuse holders shall be 110 95 kV. […]”

- Paragraph 2.4.5 now reads:

o “The PPTs shall be designed for floor mounting, with secondary connection to the excitation equipment provided via cable and conduit with entry into the top of the enclosure. Floor mounts with appurtenances shall be furnished for the PPT, meeting the requirements of SECTION 13 48

00.00 26 SEISMIC RESTRAINT FOR MECHANICAL AND ELECTRICAL EQUIPMENT.”

Removed “as described in paragraph 2.4.7” and added “provided via cable and conduit with entry into the top of the enclosure” in the first sentence.

The PPTs shall be designed for floor mounting, with secondary connection to the excitation equipment as described in paragraph 2.4.7 provided via cable and conduit with entry into the top of the enclosure.

- Paragraph 2.7.11 now reads:

o “Provide Ethernet over copper and Ethernet over fiber-optic ports for external communication with plant distributed control systems. Provide at least one external port allowing communication with the contractor supplied laptop for programming and troubleshooting.”

Removed “serial RS-485 serial” from first sentence.

“Provide serial RS-485 serial, Ethernet over copper and Ethernet over fiber-optic ports for external communication with plant distributed control systems.

- Paragraph 2.7.12 now reads:

o “Provide MODBUS TCP/IP communication protocol via the external communication ports.”

Removed “MODBUS serial, or” and “and DNP 3.0” from the sentence.

“Provide MODBUS serial, or MODBUS TCP/IP and DNP 3.0 communication protocol via the external communication ports.”

EDITED E-201 DRAWING

RESPONSE TO RFIS

UNCLASSIFIED\\FOR OFFICIAL USE

ONLY

Bid Inquiry Contractor Report All Inquiries

Project: Norfork Excitation System Review: RFI Review (00001) (sorted by CommentID ) Displaying 38 inquiries.

Id Discipline Sheet Detail Spec 8487440 Specifications 1 of 31 A.02.01 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

5th para: Please clarify what you mean by 'supervision', ie., during installation by others, how many days, when?

Under what line item should that be included?

On: Apr 02 2020.

Government Response. . No exciter manufacturer "supervision" during site installation is required by this solicitation. The only requirement stated in this solicitation for manufacturer personnel on site during installation phase work is for a commissioning engineer. Amended solicitation will remove the word "supervision" from this location. On: Apr 28 2020

Current Request Status: Request Closed Information for this report is procurement sensitive.

8487444 Specifications 2 of 31 A.02.01 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

You state '...When submitting your quote, be please make sure the solicitation number, W9127S20Q0002, is written in the subject line or on the outside of the envelope...' This seem to imply that we can submit the proposal via e-mail --> Please confirm.

Government Response. . We cannot accept email submissions due to file size. We will amend the solicitation to accept electronic copies only in lieu of hard copies. On: May 05 2020 Current Request Status: Request Closed

Information for this report is procurement sensitive.

8487451 Specifications 4 of 31 A.02.01 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Please note that line items listed in 'Pricing Schedule' do not match job payment items as defined as line items 001 to 010 in section 01 22 00, item 1.1 --> please clarify.

Government Response. . This pricing schedule will be revised to match the job payment items as described in Section 01 22 00 in the coming amended solicitation. On: Apr 28 2020 Current Request Status: Request Closed

Information for this report is procurement sensitive.

8487456 Specifications 11 of 31 A.02.01 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO) item II.4: Converter / AVR redundancy approach seems to be based on vendor selection. However section 48 19 26, item 2.6.1 clearly specifies the redundancy the District requires, i.e., there seems to be no choice. Please advise.

Government Response. . The contractor is required to follow requirements in the specifications regarding redundancy. Item II. 4) is intended to communicate that the Bidder is to provide the necessary information to ensure compliance with, and understanding of, specification requirements. On: Apr 28 2020

Current Request Status: Request Closed

Information for this report is procurement sensitive.

8487467 Specifications Section 01 11 00, item 1.1 c

Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

We are not clear about this item. Do you expects us to provide cables and wires between the PPT and exciter shipped loose and cut to length? This does not make much sense to us as it depends on the final location of the equipment, the cable routing etc which is not part of this solicitation. Please review.

Government Response. . This requirement will be changed and clarified in the coming amendment to the solicitation. Cables and wires between PPT and Exciter are not required to be provided in this solicitation. On: Apr 28 2020

Current Request Status: Request Closed Information for this report is procurement sensitive.

8487470 Specifications Section 01 14 00, item 1.2.1 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO) Do these work hours also apply for commissioning, start-up, training etc. Please advise.

On: Apr 02 2020.

Government Response. . Yes. Any deviation, as explained in Section 1.2.1, must be coordinated with and approved by the Contracting Officer or Contracting Officer's Representative (COR). On: Apr 28 2020

Current Request Status: Request Closed Information for this report is procurement sensitive.

8487475 Specifications Section 48 19 26, item 1.1.1 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

You state '..All components, wiring, and connections within and between the excitation systems and the power potential transformers (PPTs) shall be provided...' This does not make much sense to us as it depends on the final location of the equipment, the cable routing etc which is not part of this solicitation. Please review.

Government Response. . This requirement will be clarified in the coming amendment to the solicitation.

Providing these wires and cables is not required for this solicitation. On: Apr 28 2020 Current Request Status: Request Closed

Information for this report is procurement sensitive.

8487478 Specifications Section 48 19 26, item 1.1.4

Comment Classification: Unclassified\\For Official Use Only (U\\FOUO) Please provide generator open circuit saturation curve

On: Apr 02 2020.

Government Response. . This attachment will be provided in the coming amendment to the solicitation.

On: Apr 28 2020

Current Request Status: Request Closed Information for this report is procurement sensitive.

8487479 Specifications Section 48 19 26, item 1.1.5 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO) Please re-confirm that warranty starts after equipment delivery and not after commissioning.

On: Apr 02 2020.

Government Response. . This is confirmed. On: Apr 28 2020 Current Request Status: Request Closed

8487481 Specifications Drawing E-201

Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Note 3 states '...cables for 15 kV supply and LV from PPT to exciter...'. However section 01 11 00, item 1.1 c makes reference to buswork. Please clarify.

Also please confirm cable entries for power supply, controls and metering (top or bottom).

On: Apr 02 2020.

Government Response. . Note 3 on this drawing is correct. No buswork is to be provided in this solicitation, nor to be utilized for any of these connections during the installation phase. This language will be changed in the coming amendment to clarify this.

Cable entries for power, controls, and metering will be in the top of the cabinets. On: Apr 28 2020

Current Request Status: Request Closed Information for this report is procurement sensitive.

8490496 Specifications 2 of 31 General A.02.01 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Required Documents to Submit:

Does item 2 "Provisions" refer to the "Offeror Representations and Certifications"?

If yes, do these pages count towards the 100 page limit ?

On: Apr 03 2020.

Government Response. . Page limit will be revised and will only apply to Tab B and Tab C. On: May 06

Current Request Status: Request Closed

Information for this report is procurement sensitive.

8490542 Specifications 2 of 31 General A.02.01

Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Required Documents to Submit:

Considering the COVID-19 health crisis, many employees are currently working from home and access to printing material, binders etc and submittal of such material would create an additional exposure to the virus for both vendors and government employees. Therefore, would it be acceptable that the proposal is submitted electronically as long as it is structured according to the instructions in the solicitation. If so, please provide an email address for sending the proposal.

On: Apr 03 2020.

Government Response. . We cannot accept email submissions due to file size. We will amend the solicitation to accept electronic copies only in lieu of hard copies. On: May 05 2020 Current Request Status: Request Closed

Information for this report is procurement sensitive.

8490628 Specifications 11 of 31 Sub-factor 1.2 I.5

Comment Classification: Unclassified\\For Official Use Only (U\\FOUO) The request to list critical sub contractors is also mentioned on the same page in sub-factor 1.2 III. Please clarify.

On: Apr 03 2020.

Government Response. . Requirement for submission of subcontractor information will be removed from Subfactor 1.2. On: May 06 2020

Current Request Status: Request Closed Information for this report is procurement sensitive.

8490643 Specifications 9 of 31

1. Non-price Technical Factor

Submission

Volume 2, Tab B references an Offer Guarantee. However, the solicitation did not outline such a requirement. Also, is there a standard Form 1442 available for this procurement ?

On: Apr 03 2020.

Government Response. . An offer guarantee is not required. On: May 05 2020

8491152 Specifications 8 of 176 1.1.e SECTION 01 11 00.00 26 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Please confirm if the cost for commissioning and training shall be included in the quoted in the price sheet. If yes, please indicate days of commissioning and in which line item the cost shall be included.

Government Response. . The line items in section 01 22 00 should be referred to for these prices. The

Pricing Schedule will be modified in the coming amendment to match these items. Bidders should use typical commissioning schedule based on their experience for similar installations to determine expected days for commissioning activities for these line items. On: Apr 28 2020

Current Request Status: Request Closed Information for this report is procurement sensitive.

8491206 Specifications 8 of 176 1.1.c SECTION 01 11 00.00 26 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

The specification indicates that all interconnecting wiring and buswork between the Excitation line-up and the PPT shall be furnished. The scope for the Excitation line-up and the PPT is clear. However, if the supply contract shall also include the non-segregated AC bus duct and control wiring (125Vdc, 120Vac, PPT temp and alarm, PPT CTs etc.) we would have to make some assumptions for the non-segregated bus duct related to total length, number of elbows, wall/floor penetrations, fire stops etc as this greatly affects the price. It is also not known if additional steel supporting structure is required other than hangers from the ceiling. Seismic calculations would also need to be included for the bus duct. Please clarify if the government will accept a pricing for the buswork and control connections between the Excitation line-up and the PPT based on an estimated length and routing to be adjusted once actual measurements are available.

On: Apr 03 2020.

Government Response. . The amended solicitation will clarify the following points:

- No wiring or cables between the PPTs and Exciters is to be provided in this solicitation.

- No buswork will be required for these excitation systems. Cable and conduit will be used for all power connections. On: Apr 28 2020

Current Request Status: Request Closed Information for this report is procurement sensitive.

8491247 Specifications 8 of 176 1.1.b SECTION 01 11 00.00 26 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

The specification indicates that the following items are not included: Furnishing wire, cable, or buswork between the Excitation system and the other powerhouse equipment. We assume that means that DC cables to the collector rings are excluded and that all control wiring, PT/CT wiring, aux supply and field flashing wiring etc. is also excluded.

Would apparatus (control switches, indicating lights, meters etc.) in the unit control board also be excluded?

Government Response. . These assumptions are all correct. On: Apr 28 2020 Current Request Status: Request Closed

8491308 Specifications 100 of 176 1.2 SECTION 01 78 00

Please confirm that the close-out drawings refers to the updated reference drawings with the new excitation interfaces. As with other USACE excitation projects, we assume that the internal excitation drawings do not have to be made in Microstation format. Also, please confirm that all reference drawings that need to be updated are already in vectorized format (Microstation .dgn). Please confirm.

Government Response. . All items here are confirmed to be accurate. On: Apr 28 2020

8491318 Specifications 118 of 176 1.1 SECTION 13 48 00.00 26

Please confirm if this contract shall include seismic calculations for the Excitation line-up, PPT and non-segregated AC bus duct. Also confirm if anchor bolts and bus duct supports are excluded from this contract.

Government Response. . It is confirmed that seismic calculations for the exciter cabinets and PPT are required. No bus duct (nor bus duct supports) is required. Anchor bolts are to be provided based on specification requirements. On: Apr 28 2020

Current Request Status: Request Closed Information for this report is procurement sensitive.

8491328 Specifications 134 of 176 1.5 SECTION 26 25 00.00 26 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Please confirm if this includes arrangement drawings of the bus routing in the power house between the Excitation line-up and the PPT.

Government Response. . No bus is to be provided. This referenced section (26 25 00.00 26) will be removed as part of the coming solicitation. On: Apr 28 2020 Current Request Status: Request Closed

Information for this report is procurement sensitive.

8491336 Specifications 136 of 176 2.1.4.3 SECTION 26 25 00.00 26

Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Please confirm if the housing of the non-segregated bus duct can be made of aluminum or if it has to be made of steel.

Government Response. . No bus duct is to be provided. This referenced section (26 25 00.00 26) will be removed as part of the coming solicitation. On: Apr 28 2020 Current Request Status: Request Closed

Information for this report is procurement sensitive.

8491380 Specifications 140 of 176 1.1.1 SECTION 48 19 26.00 26

Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Installation instructions are referenced, but not included as a submittal in the submittal register. Please clarify if this contract includes removal/installation instructions for the future install contract and if this contract includes the interface engineering between the excitation system and other powerhouse equipment. Also, shall the included Arrangement drawing include the Excitation line-up, PPT and the non-segregated AC bus duct ?

Government Response. . A new submittal will be added to the submittal register in the coming amendment to the solicitation for "Installation Instructions". Interface engineering as described in SECTION 48 19 26.00 26 (especially 2.12.2.1) is required. Arrangement drawings shall meet requirements described in 2.12.1.3, and no bus duct is to be provided. On: Apr 28 2020

8491882 Specifications 148 of 176 2.5.1.3 SECTION 48 19 26.00 26 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Please clarify if this contract shall specify the suitable type of devices (control switches, indicating lights, meters etc.)

for the unit control board and if this contract also include the supply of such devices.

On: Apr 03 2020.

Government Response. . This contract will include "determination of required external items" but not the supply of such devices. On: Apr 28 2020

8491883 Specifications 161 of 176 2.7.4 SECTION 48 19 26.00 26 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

The government typically asks for one (1) remote HMI to be installed in the control room with access to all units. Will this be required for this project as well ?

Is a managed Ethernet switch required for the control room as well?

On: Apr 03 2020.

Government Response. . No remote HMI in the control room is required for this project. On: Apr 28

Current Request Status: Request Closed

Information for this report is procurement sensitive.

8492955 Specifications 147 of 176 2.4.4 SECTION 48 19 26.00 26 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Will a heater with thermostat be required to ensure that the PPT windings do not collect humidity if the unit is not operating for an extended period of time ?

On: Apr 06 2020.

Government Response. . While a heater with thermostat is not required as a part of the specifications, if one is part of a PPT manufacturer's standard design in order to meet performance and life expectancy requirements given site conditions then it should be provided. On: Apr 28 2020

Current Request Status: Request Closed Information for this report is procurement sensitive.

8499164 Contracting Quotation due date Combined Synopsis & Solicitation Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

As the US is now affected by COVID-19 outbreak and its consequences, including restrictions being put in place to mitigate its spread, suppliers are taking longer to respond to quotationa and customers are also taking longer to return the PPQs questionnaires.

In order to have reasonable period to prepare the quotation according to the requirements, we kindly ask the the Government to extend in ~30 days the original quotation due date (Updated Quotes Due date: May 29, 2020 02:00 pm CDT).

On: Apr 08 2020.

Government Response. . Due date for quotations will be extended to Monday, May 18, 2020. On: May

06 2020 Current Request Status: Request Closed

8508642 Specifications 6 of 7 E-201 Plan Drawings

Please explain the constraints of the 4'6" cabinet depth for the exciter cabinets. There does seem to be plenty of space for a larger depth, which would allow for different cubicle configurations that may reduce the length, so that more space is freed-up close to the generator. Would it be possible to have an excitation footprint smaller than 70" x 70" ?

On: Apr 13 2020.

Government Response. . The 4'6" depth requirement is due to access and equipment movement limitations. There are existing governor oil tanks which have a clearance of roughly 5' to the wall, limiting the ability to move equipment with larger dimensions than this. Please advise if the available footprint as shown on the drawings is not achievable, and if not please provide possible resolutions for Government consideration.

On: Apr 28 2020

Current Request Status: Request Closed Information for this report is procurement sensitive.

8509684 Specifications CYBERSECURITY Section 01 35 70

Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Please clarify when contractor shall execute all Cybersecurity related activities detailed in Section 01 35 70: During Factory Acceptance Tests or during Commissioning (2 years later).

On: Apr 14 2020.

Government Response. . The cybersecurity related activities are to be completed prior to delivery. On:

Apr 28 2020 Current Request Status: Request Closed

Information for this report is procurement sensitive.

8509688 Specifications Digital Exciters 48 19 26.00 26

Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Please confirm if modifications in existing drawings is part of the scope. If yes, how many drawings need to be modified?

Government Response. . Yes, approximately 10 drawings will need to be updated based on Contractor's design. These updated/revised drawings will be used in part for installation. On: Apr 28 2020 Current Request Status: Request Closed

Information for this report is procurement sensitive.

8509702 Specifications Part 2.4 48 19 20.00 26

Comment Classification: Unclassified\\For Official Use Only (U\\FOUO) Please confirm if it is acceptable to supply a cast coil PPT as the one existing.

On: Apr 14 2020.

Government Response. . A VPI type PPT will be required, and a cast coil PPT is not acceptable. This language will be clarified/included in the coming amendment. On: Apr 28 2020

Current Request Status: Request Closed Information for this report is procurement sensitive.

8509707 Specifications Part 2.4.5 48 19 26.00 26 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Paragraph 2.4.5 in Section 48 19 26.00 26 Page 8 refers to paragraph 2.4.7; however it does not exist in the specification. Please clarify if there is any requirement which has to be addressed.

Government Response. . This erroneous reference will be removed in the coming amendment. On: Apr

28 2020

8509713 Specifications Part 2.4 48 19 26.00 26

Please confirm if Aluminum will be accepted as winding material for the PPT.

On: Apr 14 2020.

Government Response. . Aluminum winding material will not be acceptable. The amended specifications will clarify this requirement On: Apr 28 2020

Current Request Status: Request Closed Information for this report is procurement sensitive.

8509719 Specifications Part 1.3.1.1 01 14 00.00 46 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Please clarify how shall bidders proceed with the Anticipated Adverse Weather Days if there is not a preliminary commissioning schedule.

Those non-working days vary from 1 to 8 depending on the month and might represent a considerable cost deviation in the quotation.

On: Apr 14 2020.

Government Response. . A commissioning schedule cannot be accurately defined at this time; however, the Government does not consider there to be any weather dependent activities related to commissioning.

Zero adverse weather days should be considered for the commissioning duration. On: May 06 2020

Current Request Status: Request Closed Information for this report is procurement sensitive.

8509721 Specifications 48 19 20.00 26 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO) Please confirm if the Excitation model validation tests will be included in the scope of supply.

On: Apr 14 2020.

Government Response. . Model validation testing will not be required in the scope of this supply contract On: Apr 28 2020

Current Request Status: Request Closed Information for this report is procurement sensitive.

8509736 Specifications part 2.7.12 48 19 26.00 26 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Please confirm that the excitation system shall Provide one of the following external communication protocols:

MODBUS (serial or TCP/IP) OR DNP 3.0.

Government Response. . MODBUS TCP/IP is desired. This requirement will be clarified in the coming amendment. On: Apr 28 2020 Current Request Status: Request Closed

Information for this report is procurement sensitive.

8517388 Contracting Quotation Deadline Combined Synopsis & Solicitation

Comment Classification: Unclassified\\For Official Use Only (U\\FOUO) Would the Government consider extending the Closing Date (Thursday, April 30, 2020) to May 29, 2020?

On: Apr 16 2020.

Government Response. . Due date for quotations will be extended to Monday, May 18, 2020. On: May 06 2020

Current Request Status: Request Closed

8518679 Contracting 2 of 31 A.02.01

We respectfully ask for a bid due date extension until May 29, 2020 as no answers have been provided to the questions posted. We require 30 days to prepare a thorough proposal after all questions have been answered.

On: Apr 17 2020.

Government Response. . Due date for quotations will be extended to Monday, May 18, 2020. On: May

06 2020 Current Request Status: Request Closed

Information for this report is procurement sensitive.

8539877 Contracting 8 of 176 Section 01 11 00, item 1.1

Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Two paragraphs are in direct contradiction of each other. One states that wire, cable and buswork between exciter and PPT is included.

The other states that furnishing wire, cable and buswork between excitation system equipment is not included.

Please clarify.

On: Apr 27 2020.

Government Response. . Wire and cable between PPT and Exciter is not required. No buswork external to the excitation system is required. Forthcoming amendment will clarify these items. On: May 05 2020 Current Request Status: Request Closed

Report Complete

UNCLASSIFIED\\FOR OFFICIAL USE

ONLY

Patent 11/892,984 ProjNet property of ERDC since 2004.

REVISED BID SCHEDULE

Line Item No.

Description

Estimated Quantity

Unit Measure

Unit Price

Amount

BASE BID

0001 Design Excitation Systems and Power Potential Transformers (PPTs) as Specified

1 Job XXX $

0002 Manufacture, Factory Test, and Deliver Excitation System and Required Appurtenances

2 Each $ $

0003 Manufacture, Factory Test, and Deliver Power Potential Transformer

2 Each $ $

0004 Perform Excitation System Special Factory Tests 1 Job $ $

0005 Perform Power Potential Transformer Special Factory Tests 1 Job $ $

0006 As-Built Drawings and O&M Manuals 1 Job XXX $

0007 Spare Parts/Special Tools 1 Job XXX $

0008 Testing and Commissioning of Unit 1 Excitation System 1 Job XXX $

0009 Testing and Commissioning of Unit 2 Excitation System 1 Job XXX $

0010 Training 1 Job XXX $

TOTAL BASE BID $

The following have been modified:

52.212-2 EVALUATION--COMMERCIAL ITEMS (OCT 2014)

(a) The Government will award a contract resulting from this solicitation to the responsible offeror whose offer conforming to the solicitation will be most advantageous to the Government, price and other factors considered. The following factors shall be used to evaluate offers:

1. NON-PRICE TECHNICAL FACTOR SUBMISSION REQUIREMENTS:

COVER SHEET & TABLE OF CONTENTS. The offeror’s technical factor submission shall consist of two (2) volumes. A cover sheet identifying the Offeror (name, address, point of contact) and solicitation number shall be provided. The second sheet shall be a table of contents. The submission shall contain a detailed table of contents.

Offers that violate these rules unnecessarily delay the evaluation process and may be rejected by the Government after the initial evaluation without receiving any further consideration. Neither the cover sheet nor the table of contents count toward the page limitations.

TABS. Written materials shall be submitted in standard three ring loose-leaf binders. Offers shall be tabbed and labeled as specified in a manner to afford easy identification from a Table of Contents.

Offerors shall submit their quotes in accordance with the following:

VOLUME 1:

TAB A – Request for Quotation Cover Page. Quote must include offeror’s telephone number, FAX number, email address, and DUNS number. DUNS number will be used to access CPARS Data.

TAB B - Factor 1 – Technical Subfactor 1.1 – Design and Manufacturing Experience Subfactor 1.2 – Technical Data and Approach TAB C – Factor 2 - Past Performance

VOLUME 2:

TAB A - Price Schedule TAB B - Offer Guarantee

FONT SIZE. Shall not be less than 10 point. Pages will be double-sided and each page shall be identified with the appropriate page number centered at the bottom of the page.

SHEET SIZE. Shall be 8-1/2 inches x 11 inches; however, if drawings, charts, or other graphics are submitted, sheets no larger than 11 inches x 17 inches and folded to 8-1/2 inches x 11 inches shall be used. Sheets that are 11 x 17 inch will be counted as two 8-1/2 inch x 11-inch sheets. All sheets shall be dated and numbered.

NUMBER OF COPIES. Offerors shall submit an original and four (4) hard electronic copies of their non-price quotation (Volume 1) with a matching number of electronic copies; and an original and one (1) hard electronic copy of their price quotation (Volume 2). Electronic format shall be CD/DVD disc.

PAGE LIMIT. The number of pages for Tab B and Tab C submission is limited to 100 20 pages for Subfactor 1.1;

30 pages for Subfactor 1.2; and 18 pages for not including the past performance information.

2. EVALUATION FACTORS, EVALUATION CRITERIA, AND BASIS OF AWARD

FACTOR 1 - TECHNICAL (VOL 1, TAB B)

Sub-factor 1.1: Design and Manufacturing Experience

SUBMISSION REQUIREMENTS:

Offerors shall submit the following for Sub-factor 1.1:

I. Offerors shall submit design and manufacturing experience by providing a minimum of three (3) examples that collectively address each of the elements identified below performed within the past five (5) years.

1) Project examples must be 100% complete (all units commissioned) at the time of submission.

2) Designed and manufactured static excitation systems for hydrogenerators rated at or greater than 20 MVA.

3) Project experience shall include adequate detail such as configuration, dimensions, ratings, and other salient design features to demonstrate the relevancy of the scope of work for comparison to that required in this solicitation.

II. Sub-Contractor Identification:

1) Offerors should clearly identify the firm(s) that will be utilized during performance of the contract or work that will be self-performed. Ensure the submission is clear as to which function the Offeror or subcontractor will be performing. If the prime contractor proposes to use a subcontractor for design and manufacturing, the offeror must submit a signed Letter of Commitment from the subcontractor with the quotation for that subcontractor’s experience to be evaluated.

EVALUATION CRITERIA – Offeror’s quotation will be evaluated to determine the extent to which it:

-Demonstrates the offeror’s design and manufacturing experience working with the hydropower industry and adhering to industry standards for timely results.

-Demonstrates the offeror’s understanding of exciter electrical design and manufacturing.

-Demonstrates the offeror has a formal process in place to uphold quality and safety standards.

-Demonstrates experience working with the proposed subcontractor or joint venture partner.

Sub-factor 1.2: Technical Data and Approach

SUBMISSION REQUIREMENTS:

Offerors shall submit the following for Sub-factor 1.2:

I. Work Plan / Schedule

1) Work plan / Schedule should reflect the planned activities, order of major tasks identified, task dependencies and durations proposed to successfully accomplish the entire project from notice to proceed. Any assumptions made by the offeror shall be clearly illustrated in the quotation. At a minimum, the schedule must include the following:

a. Submittal of design drawings and equipment information, including consideration of time for Government review

b. Manufacturing Facility Inspection

c. Factory Testing

d. Delivery of exciters and ancillary equipment onsite

2) Discuss how work to complete one task may impact or be impacted by work to complete other tasks.

3) Identify any critical assumptions and uncertainties that may impact the completion of work and identify methods to check assumptions and address uncertainties.

4) List any specialty work crews, trades and crafts, or individuals required to complete unique or special tasks.

5) List all critical subcontractors with their respective role and responsibility to complete all major tasks.

II. Technical Data

1) Offerors shall provide documentation showing the exciter continuous current rating, DC field lead ampacity rating, exciter ceiling voltage, and exciter transformer (PPT) kVA and voltage ratings as well as basis/calculations for PPT ratings. Design details shall meet the minimum specification requirements.

2) The Offeror shall provide a drawing showing a plan view of the new equipment arrangement.

This drawing shows dimensions for the new exciter and exciter transformer cabinets, and this new equipment fits within the space limitations indicated in contract drawings.

3) Descriptive literature is required to establish, for the purpose of evaluation and award, details of the excitation system offered that are specified elsewhere in the solicitation and pertain to significant elements. Information not related to the major excitation system to be supplied will not be used for evaluating the offer. Cut-sheets and brochures for the proposed excitation system shall be provided. Where cut-sheets are provided with multiple models, the proposed model number or information shall be circled with all unnecessary models crossed out.

4) Identify redundant components (i.e. redundant bridges, controls etc.) and clearly describe the redundancy approach utilized (i.e. can each redundant controller operate each redundant bridge, etc.).

5) Provide information on technical support services which are available for the proposed system.

Included information shall include physical location(s), phone number(s), and hours of availability.

III. Sub-Contractor Identification:

Offerors should clearly identify the firm(s) that will be utilized during performance of the contract or work that will be self-performed. Ensure the submission is clear as to which function the Offeror or subcontractor will be performing. If the prime contractor proposes to use a subcontractor for the fabrication, the offeror must submit a signed Letter of Commitment from the subcontractor with the quotation for that subcontractor’s experience to be evaluated.

EVALUATION CRITERIA – Offeror’s quotation will be evaluated to determine the extent to which it:

-Demonstrate the ability to perform a work plan and schedule for excitation systems installation above 20 MVA.

-Demonstrates the offeror’s understanding of exciter electrical ratings, equipment arrangement, descriptive literature, redundancy, and technical support services for of excitation systems.

-Demonstrates experience working with the proposed subcontractor or joint venture partner.

FACTOR 2 – PAST PERFORMANCE (VOL 1, TAB C)

SUBMISSION REQUIREMENT: Page Limit – Eighteen (18) Pages. Submit completed Past Performance Questionnaires (Form PPQ-O) (Attachment A) from at least three (3) customers demonstrating past performance completed within the past five (5) years. The Government will use the information to determine the Offeror’s probability of successfully performing the scope of work described in this solicitation.

NOTE: Teaming arrangements and Joint Ventures. Provide a copy of the teaming/joint venture agreement. Offerors may submit experience of an affiliated entity where that affiliated entity has made a firm commitment to participate meaningfully in the performance of the contract. If required, JV approval must be obtained in accordance with Small Business Administration policy.

EVALUATION CRITERIA:

There are two aspects to the past performance evaluation. The first is to evaluate the Offerors past performance to determine how relevant a recent effort accomplished by the offeror is to the effort to be acquired through the source selection. Common aspects of relevancy include similarity of service in scope and price. The second aspect of the past performance evaluation is to determine how well the contractor performed on the contracts.

1. Past Performance Relevancy Ratings (Adjectival) -- Past performance analysis provides insight into an Offerors probability of successfully completing the solicitation requirements based on the Offerors performance record on similar contract efforts.

Rating Definition

Very Relevant Present/past performance effort involved essentially the same scope and magnitude of effort and complexities this solicitation requires.

Relevant Present/past performance effort involved similar scope and magnitude of effort and complexities this solicitation requires.

Somewhat Relevant

Present/past performance effort involved some of the scope and magnitude of effort and complexities this solicitation requires.

Not Relevant Present/past performance effort involved little or none of the scope and magnitude of effort and complexities this solicitation requires.

2. Past Performance Confidence Assessment - Performance confidence is the confidence associated with an Offeror’s likelihood of success in performing the solicitation's requirements as indicated by that Offeror’s record of current or past performance. Performance Confidence Assessment: In conducting a performance confidence assessment, each offeror shall be assigned one of the ratings in accordance with the table below.

Rating Description

Substantial Confidence

Based on the Offeror’s recent/relevant performance record, the Government has a high expectation that the offeror will successfully perform the required effort.

Satisfactory Confidence

Based on the Offeror’s recent/relevant performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort.

Limited Confidence

Based on the Offeror’s recent/relevant performance record, the Government has a low expectation that the offeror will successfully perform the required effort.

No Confidence Based on the Offeror’s recent/relevant performance record, the Government has no expectation that the offeror will be able to successfully perform the required effort.

Unknown Confidence (Neutral)

No recent/relevant performance record is available or the Offerors performance record is so sparse that no meaningful confidence assessment rating can be reasonably assigned.

PRICE SCHEDULE (VOL 2, TAB A)

SUBMISSION REQUIREMENT: Submit the required Price Schedule

EVALUATION CRITERIA: The Government will perform a price analysis after completion of technical evaluations. Price analysis will be performed in accordance with FAR 15.404-1, to determine completeness, reasonableness, and understanding of the work. The evaluation will determine the adequacy of the offer in fulfilling the requirements of the solicitation. Completeness addresses the extent to which the elements of the price quote are consistent with the requirements of the RFP. Reasonableness will be established using historical price information, price competition information, the IGE, and any other pricing tools necessary. A clear audit trail must be evident as to the conversion of costs to the coefficients to accomplish the tasks described herein. Price will not be rated, but will be a factor in making the final best value determination for award.

BASIS OF AWARD

Rating Adjectives:

Outstanding Quote meets requirements and indicates an exceptional approach and understanding of the requirements. Strengths far outweigh any weaknesses. Risk of unsuccessful performance is very low.

Good Quote meets requirements and indicates a thorough approach and understanding of the requirements. Quotation contains strengths which outweigh any weaknesses.

Risk of unsuccessful performance is low.

Acceptable Quote meets requirements and indicates an adequate approach and understanding of the requirements. Strengths and weaknesses are offsetting or will have little or no impact on contract performance. Risk of unsuccessful performance is no worse than moderate.

Marginal Quote does not clearly meet requirements and has not demonstrated an adequate approach and understanding of the requirements. The quotation has one or more weaknesses which are not offset by strengths. Risk of unsuccessful performance is high.

Unacceptable Quote does not meet requirements and contains one or more deficiencies.

Quotation is un-awardable.

Technical Evaluation Weights:

Factor/Subfactor Location Description Relative Importance

FACTOR 1 Tab B Technical Equal in importance to Factor 2

Subfactor 1.1 Tab B Design and Manufacturing Experience Equal in importance to Subfactor 1.2

Subfactor 1.2 Tab B Technical Data and Approach Equal in importance to Subfactor 1.1

FACTOR 2 Tab C Past Performance Equal in importance to Factor 1

Award will be based on a Best Value Decision, Tradeoff process, and will be made to the best overall offer that is determined to be the most advantageous to the Government. The non-price technical and past performance factors, when combined, are substantially more important than price.

(b) A written notice of award or acceptance of an offer, mailed or otherwise furnished to the successful offeror within the time for acceptance specified in the offer, shall result in a…

This is the start of the file's text. The full file is on GovTribe.