A.01.30_PWS_Attachment_3_-_PRS.pdf
PDF 79 KB Posted
- Attached to
- Norfork Lake Area Debris Removal Federal contract opportunity
- Solicitation number
- W9127S-17-Q-0031
About this file
PWS Attachment 3 - Performance Requirements Summary (PRS)
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| A.01.30_PWS.pdf | ||
| A.01.30_PWS_Attachment_2_D.jpg | JPG image | |
| A.01.30_PWS_Attachment_2_L.jpg | JPG image | |
| A.01.30_PWS_Attachment_2_F.jpg | JPG image | |
| A.01.30_PWS_Attachment_2_E.jpg | JPG image | |
| A.01.30_PWS_Attachment_2_G.jpg | JPG image | |
| A.01.30_PWS_Attachment_2_N.jpg | JPG image | |
| A.01.30_PWS_Attachment_2_J.jpg | JPG image | |
| A.01.30_PWS_Attachment_2_K.jpg | JPG image | |
| A.01.30_PWS_Attachment_2_A.jpg | JPG image | |
| A.04.36_Wage_Rates.pdf | ||
| A.01.30_PWS_Attachment_2_C.jpg | JPG image | |
| A.01.30_PWS_Attachment_2_P.jpg | JPG image | |
| A.01.30_PWS_Attachment_2_I.jpg | JPG image | |
| A.01.30_PWS_Attachment_2_B.jpg | JPG image | |
| A.01.30_PWS_Attachment_2_M.jpg | JPG image | |
| A.01.30_PWS_Attachment_4_-_QASP.pdf | ||
| A.01.30_PWS_Attachment_2_O.jpg | JPG image | |
| A.01.30_PWS_Attachment_1_-_Security_Requirements.pdf | ||
| A.01.30_PWS_Attachment_2_H.jpg | JPG image |
Show all 20
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT 3
Performance Requirements Summary The contractor service requirements are summarized into performance objectives that relate directly to mission essential items. The performance threshold briefly describes the minimum acceptable levels of service required for each requirement. These thresholds are critical to mission success.
Performance Objective
Standard Performance Threshold
Method of Surveillance
PRS # 1.
The contractor shall perform work according to the contract.
5.1 The contractor shall provide all
personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform debris cleanup/removal and roadway/campsite sweeping within identified parks on Norfork Lake.
1 critical
Planned Sampling
PRS # 2
The Contractor shall remove all debris according to contract.
5.1 The work consists of removing all
debris that exceeds 2” in diameter from the lake flooding within the recreation parks on Norfork Lake. Attached are park maps including the labeled area that shall receive debris clean up within the boundary limits.
The debris cleanup shall consist of removing all silt rows, sand, paper, tires, rocks, cans, glass, driftwood and other types of debris to the water’s edge in the areas specified within each park. All ditches and culverts shall be cleaned up and re-established to allow accurate drainage flow. Some handwork may be required. Contractor shall dispose of all debris types collected during cleanup operations by hauling to a legally established landfill off of government property. The specified areas shall be mow-able without any chances of flying debris by the mowing crew. Any areas that receive rutting from equipment usage, shall be restored at no additional cost. If any of the results of debris cleanup are considered to be unsatisfactory, Contractor shall re-clean the unsatisfactory areas within twenty-four (24) hours after notifications with no additional cost to the government.
The contractor shall have ninety (90) days from the Notice to Proceed (NTP) to complete the debris removal and sweeping for each line item. Contractor shall begin work only once the lake levels are within five (5) feet of their seasonal conservation pools, or when given approval by the Contracting Officer.
1 critical Planned
PRS # 3
The Contractor shall sweep roadways/campsites according to contract.
5.1 The work consists of removing all
debris within the recreation park roadways on Norfork Lake. Reference Attachment 2 titled "Park Maps" demonstrating park maps specifying the areas that shall receive roadway sweeping within the boundary limits. The roadway sweeping shall consist of removing all silt, dirt, mud, sand, paper, rocks, cans, glass, driftwood and other types of debris in the areas specified within each park. Sweeping areas shall include all main roadways, parking lots, campsite turnouts, and concrete camping pads and any other asphalt/concrete surfaces. Contractor shall make every effort to minimize streaks left by sweepers.
Any disposal of all debris types collected during sweeping operations shall be hauled to a legally established landfill off of government property. If any of the results of road sweeping cleanup are considered to be unsatisfactory, Contractor shall re-sweep the unsatisfactory areas within twenty-four (24) hours after notifications with no additional cost to the government.
The contractor shall have ninety (90) days from the Notice to Proceed (NTP) to complete the debris removal and sweeping for each line item. Contractor shall begin work only once the lake levels are within five (5) feet of their seasonal conservation pools, or when given approval by the contracting officer.
1 critical Planned