About this file

This Amendment updated the Methodology to be used while installing the Pile, the Pile material thickness requirements, and bid opening date.

View the file

Other files for this federal contract opportunity

Other files attached to Coquille River Navigation Marker, newest first.
File Type Posted
Coquille_Nav_Marker_Final_Dwg_Combined_with_ATON_Revised_x2.pdf PDF
COQUILLE_NAV_MARKERS_FINAL_DWG_COMBINED.PDF PDF
A.07.23CoquilleNavigationAmendment1.pdf PDF
A.07.23_Drawings_17-B-0010.pdf PDF
A.07.23_Coquille_Navigation_Solicitation_Package.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

PROJECT TITLE: Coquille Navigation Markers

The purpose of this modification is to:

1. Update draw ings package

2. Bid opening date extended to the date and time indicated in the continuation sheet.

All other terms and conditions remain unchanged.

POC: Brandon Lasich Email: brandon.m.lasich@usace.army.mil

1. CONTRACT ID CODE PAGE OF PAGES

J 1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 15-Jun-2017

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W9127N-17-B-0010

X 9B. DATED (SEE ITEM 11)

18-May-2017

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

15-Jun-2017

CODE

USACE PORTLAND DISTRICT

333 SW 1ST AVE

PORTLAND OR 97204-3440

W9127N 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W9127N-17-B-0010

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00010 - SOLICITATION CONTRACT FORM

The required response date/time has changed from 19-Jun-2017 02:00 PM to 29-Jun-2017 02:00 PM.

(End of Summary of Changes)

Coquille River Navigation Marker

PROJECT TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 11 13.00 25 GENERAL CONTRACT REQUIREMENTS

01 33 00 SUBMITTAL PROCEDURES

01 35 26.00 25 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

DIVISION 05 - METALS

05 05 23.00 25 WELDING - STRUCTURAL STEEL

05 14 00.00 25 WELDING - STRUCTURAL ALUMINUM

05 50 13.00 25 MISCELLANEOUS METAL FABRICATIONS

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

06 73 01.00 25 FIBERGLASS REINFORCED PLASTIC (FRP) GRATING

DIVISION 31 - EARTHWORK

31 62 16.16 25 STEEL PIPE PILES

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1

SECTION TABLE OF CONTENTS

DIVISION 31 - EARTHWORK

SECTION 31 62 16.16 25

STEEL PIPE PILES

PART 1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

PART 2 PRODUCTS

2.1 MATERIALS

PART 3 EXECUTION

3.1 INSTALLATION

-- End of Section Table of Contents --

SECTION 31 62 16.16 25 Page 1

SECTION 31 62 16.16 25

STEEL PIPE PILES

PART 1 GENERAL

Piles on this project are six steel pipe piles for installation of Navigation Hazard Markers. Piles must be installed to the embedment depth shown on the contract drawings.

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM A252 (2010) Standard Specification for Welded and Seamless Steel Pipe Piles

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-02 Shop Drawings

Pile Installation Plans; G

SD-03 Product Data

Pipe Pile Manufacturer's Mill Certificates; G

PART 2 PRODUCTS

2.1 MATERIALS

a. Pipe piles must be 18-inch diameter, 1/2-inch or greater wall thickness, 35-foot long steel pipe pile. Pile must be ASTM A252 Grade 3 with minimum Fy = 45 ksi.

b. Submit pipe pile manufacturer's mill certificates including chemistry, yield strength, and mill numbers.

PART 3 EXECUTION

3.1 INSTALLATION

a. Submit Pile Installation Plans for pile installation method. Plans must contain equipment specifications, installation methods, and temporary support structures/methods for pile installation. Plans must be sufficient to determine that methods and equipment meet the specifications and are properly suited for installation of piles. All pile driving methods must meet the requirements of the permits issued

SECTION 31 62 16.16 25 Page 2

PROJECT TABLE OF CONTENTS
DIVISION 31 - EARTHWORK
31 62 16.16 25 - STEEL PIPE PILES
31 62 16.16 25 - STEEL PIPE PILES
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
PART 2 PRODUCTS
2.1 MATERIALS
PART 3 EXECUTION
3.1 INSTALLATION
[2]: [2]