A02.02-Site_Visit_Q&A.pdf

PDF 185 KB Posted

Attached to
PL84-99 Levee System 0561 (North) Levee Improvement Construction Project Federal contract opportunity
Solicitation number
W9123818R0027
Issued by
Department of the Army Corps of Engineers Engineering District Sacramento

About this file

Site Visit Questions and Responses. Note that all other questions (i.e., bidder inquiries) must be submitted as stated in the solicitation - via ProjNET.

View the file

Other files for this federal contract opportunity

Other files attached to PL84-99 Levee System 0561 (North) Levee Improvement Construction Project, newest first.
File Type Posted
A07.02-Atch_02_Specifications_5Jul18.pdf PDF
A07.02-18R0027_AMD_01.pdf PDF
A07.01.3-Atch_3_Wage_Determination.pdf PDF
A02.02-Site_Visit_Attendance.pdf PDF
A07.01-Atch_1_Plans.pdf PDF
A07.01-Atch_3_Wage_Determination.pdf PDF
A07.01-Solicitation_31May18.pdf PDF
A07.01-Atch_2_Specifications.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Memorandum for Record

7 June 2018

SUBJECT: 0561 North Sites 11 and 35 Site Visit Questions/Answers

Question 1: What is the impact to the property owner’s trees along the levee?

Government Response: See CLIN 0005 under Site 0561-35 on the Schedule of Items will be revised to remove the estimated quantity of 28 trees to “job.” This CLIN would then no longer be subject to the

Variations in Estimated Quantities clause.

Question 2: Note 1 of Drawing C-310 indicates that trees are to be “relocated.” Where are they being relocated?

Government Response: A forthcoming amendment will revise this note to delete “relocated” and replace with “remove and dispose of.”

Question 3: Is the property owner aware of the project?

Government Response: The property owner whose property is adjacent to the construction activity is different from the property owner whose property is adjacent to the staging area. Both owners are aware and supportive of the project.

Question 4: Can the Government share the property owner’s information with the contractor?

Government Response: The landowner’s contact information will be provided upon contract award.

Question 5: Can prospective offerors be provided with CAD files?

Government Response: AutoCAD files will not be provided for this solicitation.

---------------------------------END OF QUESTIONS AND RESPONSES----------------------------------------------------