A.02.16_SOW.docx
DOCX document 2 MB Posted
- Attached to
- North Fork of Pound Lake Elevator Rehabilitation Federal contract opportunity
- Solicitation number
- W9123719Q0028
About this file
Attachment 1-Scope of Work
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| W9123719Q0028.pdf | ||
| A.03.09_Exhibit_2-_Reference_Drawings.pdf | ||
| A.03.09_Exhibit_1-_Photo_log_&_photo_attachments_of_project.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
North Fork of Pound Lake Elevator Rehabilitation Specification and Scope of Work Pound, VA - August 2019
ATTACHMENT 1
Table of Contents
| 0 | Table of Contents | 2 |
| 1 | Project Information | 5 |
| 1.1 | Project Site Location | 5 |
| 1.2 | Project Point of Contact | 5 |
| 2 | Project Scope | 5 |
| 2.1 | Recent Maintenance | 8 |
| 3 | References | 9 |
| 4 | System Description | 9 |
| 4.1 | Purpose | 9 |
| 4.2 | Existing Elevator Schedule | 9 |
| 4.3 | Standard Products | 11 |
| 4.4 | Name Plates | 12 |
| 4.5 | Environmental Conditions | 12 |
| 5 | Submittals | 12 |
| 5.1 | Accident Prevention Plan (G-SO) | 12 |
| 5.2 | Shop Drawings and Product Data (G-EC) | 12 |
| 5.3 | Testing (G-EC) | 12 |
| 5.4 | Elevator Mechanics (FIO) | 13 |
| 5.5 | Operation and Maintenance Manuals (G-EC) | 13 |
| 6 | Qualifications | 13 |
| 7 | Project Site Conditions | 13 |
| 8 | Training | 13 |
| 9 | Equipment Specifications | 14 |
| 9.1 | Elevator Hoistway Entrances | 14 |
| 9.2 | Call Buttons | 14 |
| 9.3 | Car Operating Panel (COP) | 14 |
| 9.4 | Hall Call Station | 14 |
| 9.5 | Power Outage Operation | 14 |
| 9.6 | Elevator Operation | 15 |
| 9.7 | Fire Service | 15 |
| 9.8 | Leveling Devices | 15 |
| 9.9 | Hoisting Machine | 16 |
| 9.10 | Hoist Motor | 16 |
| 9.11 | Brake Assembly | 16 |
| 9.12 | Controller | 16 |
| 9.13 | Transient Protection | 19 |
| 9.14 | Motor Controller (VFD) | 19 |
| 9.15 | Conduit/Raceway | 19 |
| 9.16 | Wiring | 19 |
| 10 | Installation | 20 |
| 10.1 | Wiring | 20 |
| 10.2 | Traveling Cables | 20 |
| 10.3 | Installation | 20 |
| 10.4 | Adjustments | 21 |
| 10.5 | During Warranty Period | 21 |
| 10.6 | Testing | 21 |
| 10.7 | Test Period | 21 |
| 10.8 | Speed Load Tests | 21 |
| 10.9 | Car Levelling Tests | 22 |
| 10.10 | Brake Test | 22 |
| 10.11 | Insulation Resistance Tests | 22 |
| 10.12 | Operational Check | 22 |
| 10.13 | Over-speed Test | 22 |
| 10.14 | Warranty | 22 |
| 10.15 | Site Clean Up | 22 |
| 10.16 | Safety | 23 |
| 10.17 | Initial Maintenance | 23 |
| 11 | Inspection and Acceptance | 23 |
| 11.1 | Inspection | 23 |
| 11.2 | Final Tests and Acceptance | 23 |
| 12 | Performance | 23 |
| 13 | Delivery | 24 |
| 14 | Omissions from the Contract Specification | 24 |
| 15 | Shop Drawings | 24 |
| 16 | Security Requirements | 25 |
| 17 | AT-OPSEC Security Requirements……………………………………………………………………………………………..27 |
17.1 Access & General Protection/Security Policy and Procedures…………………………………………………25
17.2 IWatch and/or CorpsWatch Training……………………………………………………………………………….………27
17.3 Pre-Screen Candidates using E-Verify Program…………………………………………………………………….…27 18 Contractor Accident Prevention Plan………………………………………………………………………………………27
Figure 1: Existing Motor Controller Figure 2: Existing Controller Data Sheet Figure 3: Car Lighting Diagram
Exhibit 1: PHOTO LOG AND PHOTO ATTACHMENTS OF PROJECT Exhibit 2: REFERENCE DRAWINGS
1. Project Information
Project Site Location
North Fork of Pound Lake Reservoir 7530 Old North Fork Rd Pound, VA Decimal degrees: 37.124271, -82.630334
Project Point of Contact
Project Operations Contact:
Harold “Chip” Miller
(C) (276) 223-8207
(P) (276) 835-9544 X 8970 Harold.E.Miller@usace.army.mil
Project Scope The Contractor shall furnish and install all equipment and materials and perform all tasks and operations necessary for the complete replacement of the electromechanical elevator system, components, and/or subsystem described in this document.
The Contractor shall be responsible for removing the existing control equipment, materials, and associated components that will be replaced in this contract. The equipment removed shall either be scrapped by the Contractor or remain the property of the Government. For the purposes of this quote the Contractor should assume all material will be scrapped. Any equipment to remain shall be delivered in good condition to the Resource Manager of the project unless otherwise noted in writing. The Contractor shall be responsible for transporting said equipment to an on-site location at the Resources Manager’s discretion.
It is recommended that offerors visit the project site before preparing their quote in order to most accurately ascertain the scope of the work with regard to existing equipment condition, accessibility, working conditions, and specific working and system design parameters. Offerors can make a site visit by contacting:
Harold “Chip” Miller
(C) (276) 223-8207
(P) (276) 835-9544 X 8970 Harold.E.Miller@usace.army.mil The work to be accomplished and equipment and material to be furnished and installed shall include, but not be limited to the following:
1) New Controller & Motor. Furnish and install a new microprocessor based controller used in conjunction with a new Variable Frequency Drive (VFD) with compatible traction control motor per NEMA MG1. New drive motor shall be compatible with new VFD. This task shall also include the demolition and removal of all unnecessary existing equipment. The existing controller is pictured below (Figure 1).
Figure 1 Existing Elevator Motor Controller
2) Brake, Machine, & Mechanical Interfaces. The Contractor shall furnish and install a new electric brake, gearbox assembly, and interface components which meet the operating and location requirements of existing elevator system. It shall include all required braking and ancillary functions necessary. It shall also include the demolition and removal of all unnecessary existing equipment.
3) Position Detection System & Limit Switches. The Contractor shall also furnish a new position detection system and new elevator limit switches for the car and new car leveling control system, including all wiring and raceways required for the leveling controls for correct operation post modifications, as well as new top and bottom limit switches. Detection system and limit switches shall conform to ASME 17.1. It shall also include the demolition and removal of all unnecessary existing equipment.
4) Elevator System Wiring Harness, Conduit, and Associated Conductors. The Contractor shall furnish and install all new wiring for the elevator control system and within the car as necessary. The wiring is located between the new controller and existing limit switches, hall call stations, car position lights in the hall stations, stop switches in the hoistway pit and any other elevator controls or indicators. The Contractor may install a new raceway or may reuse the existing raceway. New raceway shall be submitted for approval. Raceway shall be galvanized steel.
All metallic conduit shall be replaced in kind per UL 6. All other conduit may be replaced or reused as needed. Include the demolition and removal of all unnecessary existing equipment.
The Contractor shall furnish and install a new elevator car traveling cable and any conduit required (between controller and termination junction box on car). Include the demolition and removal of all unnecessary existing equipment.
5) Car Fixtures. The Contractor shall furnish and install new fixtures within the car as required by NFPA 70. Include the demolition and removal of all unnecessary existing equipment.
6) Car Operating Panel (COP). The Contractor shall furnish and install a new car operating panel. Include the demolition and removal of all unnecessary existing equipment.
7) Hall Call Stations (HCS). The Contractor shall furnish and install new HSCs on each floor. Include the demolition and removal of all unnecessary existing equipment.
The preceding list is not intended to be fully descriptive, but rather a highlight of each task. Detailed specifications are provided throughout this document.
Deficiencies:
The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises. If the Contractor does not promptly replace or correct rejected work, the Government may –
(1) By contract or otherwise, replace or correct the work and charge the cost to the Contractor OR
(2) Terminate for default the Contractor’s right to proceed.
Pre-Construction Conference:
The Contractor shall attend a pre-construction conference, prior to the initiation of work under this contract. The Contractor's Accident Prevention Plan and all other required items must be accepted prior to this meeting.
Damage Reports:
All instances where Government materials, supplies, property, and/or equipment are damaged shall be reported immediately to the Contracting Officer. When the damage is caused by contract employees, a written report of the incident and extent of such damage shall be submitted to the Project Supervisor, Within 2 work days (less weekends and holidays) of occurrence. For property damage Accidents of $2,000 or more, the Contractor will complete and submit to the Resource Manager a copy of ENG 3394.
Insurance Verification:
Contractor shall provide Contracting Officer with written proof that all insurance required by State and Local Governments have been acquired for the time ed under this contract. No further insurance requirements will be imposed by the Corps of Engineers for this contract.
Wage Rate:
In accordance with contract clause FAR 52.222-6, Davis-Bacon wage rates are applicable to this procurement and can be located at https://beta.sam.gov/
Contractor Invoice:
Contractor shall submit their invoice to:
North Fork of Pound Lake Reservoir Attn: Harold Miller 7530 Old North Fork Rd Pound, VA 24279
(C) (276) 223-8207
(P) (276) 835-9544 X 8970 Harold.E.Miller@usace.army.mil
Recent Maintenance The elevator system has been most recently serviced on the following occasions:
· Sep. 2016
· Aug. 2015
· Nov. 2014
· Sep. 2014
References The most current editions and versions of the publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.
ASME INTERNATIONAL (ASME):
· ASME A17.1 – Safety Code for Elevators and Escalators
· ASME A17.2.1 – Inspectors’ Manual for Elevators
NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA):
· NEMA MG 1 – Motors and Generators
· NEMA WC 7 – Cross-linked, Thermosetting, Polyethylene Insulated Wire and Cable for the Transmission and Distribution of Electrical Energy
· NEMA WC 8 – Ethylene-Propylene-Rubber Insulated Wire and Cable for the Transmission and Distribution of Electrical Energy
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA):
· NFPA 70 National Electrical Code
UNDERWRITERS LABORATORIES (UL)
· UL 6 Rigid Metal Conduit
USACE
· EM 385-1-1 Safety and Health Requirements Manual The contractor is responsible for ensuring their designs and workmanship meet the standards listed above.
System Description
Purpose The elevator controller and all components, systems, and sub-assemblies shall conform to the requirements of ASME A17.1, except that provisions for fire service are not required. The controller shall be designed to have the capacity to lift a live load, exclusive of the car and cable, at a speed as specified in the following schedule. The approximate travel, terminal floors, and the number of stops and openings shall be as shown in the schedule. The elevator shall serve the floors with stops and openings in accordance with the requirements indicated.
The ultimate goal is to provide rehab services to the elevator that result in an elevator system that provides project staff with reliable and safe service.
Existing Elevator Schedule Elevator Designation: North Fork of Pound Lake Reservoir Dam Intake Structure Elevator Service: Passenger/Freight/Utility Capacity: 1200 lbs Speed: 100 feet per minute Landings: 7 Voltage Available: 220V 3 phase 60 Hz Motor: 3 phase 5 HP dual speed 1200/400 rpm Existing Controller Nameplate:
Figure 2 Existing Controller Data Sheet
Figure 3 Car Lighting: 1x default incandescent main light, 2x emergency lighting incandescent lights from single fixture Original Installer: Southern Elevator Company Standard Products Materials and equipment shall be the standard products of manufacturers regularly engaged in the fabrication of elevator controllers and equipment and shall essentially duplicate items which have been in satisfactory use for at least five (5) years prior to solicitation.
Equipment and components used on this project must be of new condition and manufactured within 365 days of the contract award date. Reconditioned and/or aftermarket or surplus equipment is not acceptable for use on this project.
Name Plates Motor equipment shall have the manufacturer’s name, address, type or style, model or serial number, catalog number, and electrical and mechanical characteristics on a plate permanently secured to the frame of the equipment.
Environmental Conditions Temperature Range: 0 Degrees F to 104 Degrees F
Humidity: Non-condensing up to 100% Altitude: Up to 5,000 ft Dust: Not controlled Submittals The Contractor shall submit descriptive literature with their quotation for review upon receipt in the district office. The descriptive literature submitted shall include manufacturers catalog sheets for the elevator controller and motor including the processor module and other modules that make up the microprocessor based controller and all other components located in the controller enclosure. Complete manufacturer data sheets and catalogue cuts shall be provided for all work items.
Following award of the contract, the successful Contractor shall provide drawings and literature as set forth below. Government approval is required for submittal with a “G” designation; submittals not having a “G” designation are for information only. When used, a designation following the “G” designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with the requirements outlined in these specifications.
Accident Prevention Plan (G-SO) After contract award and before beginning work submit an Accident Prevention Plan (APP) as required in Appendix A of USACE’s EM 385-1-1. The Contractor is required to follow all applicable safety provisions in USACE EM 385-1-1. Details of APP requirements are found in Section 18.
Shop Drawings and Product Data (G-EC) Submit shop drawings consisting of a complete list of equipment and materials, including illustrations, schedules, manufacturer’s descriptive and technical literature, performance charts, description of the controller, motor, definitions of symbols used, printout of microprocessor logic with complete documentation, motor, setting of all dip switches (if appropriate), and other information required for fabrication and installation of the equipment. Shop drawings shall include dimension layouts in the plan and elevations showing the arrangement of the elevator controller and equipment. This submittal must be provided to the Government after contract award. Government approval must be granted prior to beginning work.
Testing (G-EC) Upon completion of performance testing and acceptance of the installed system, submit test reports showing all field tests performed to provide compliance with the specified performance criteria. All data and procedures shall be recorded and provided in the report.
Elevator Mechanics (FIO) Submit certificate of experience for the elevator mechanics prior to starting work. Contractor shall have at least 10 years of experience in the service and installation of elevators.
Operation and Maintenance Manuals (G-EC) Submit three (3) complete copies of operating instructions outlining the step-by-step procedures for system start up, operation, and shutdown. The instructions shall include the manufacturer's name, model number, service manual parts list, and brief descriptions of all pieces of equipment and their basic operating features. Operating instructions shall be submitted and approved prior to the training course discussed in paragraph MAINTENANCE. The Contractor shall provide the name, address, and phone number of the local representative of the elevator controller supplier.
Submit three (3) complete copies of maintenance instructions listing routine maintenance procedures, possible breakdowns and repairs, and troubleshooting guides. The manual shall include a write-up on how to interpret the troubleshooting codes that are provided by the controller. The instructions shall include equipment layout and wiring and control diagrams of the system as installed. The manuals shall also include complete descriptive literature, catalog cuts and all other pertinent information submitted during the shop drawing process, including printout and documentation of the control program used for operation of the elevator. Maintenance instructions shall be submitted and approved prior to the start of the training course described in paragraph MAINTENANCE.
Submit three (3) complete copies of all ladder logic and/or programming for the VFD and/or PLC control hardware. This shall include a list of input/output and associated cable numbers/loads. Code/logic shall be submitted and approved prior to the start of the training course described in paragraph MAINTENANCE.
Qualifications Elevator mechanics employed to install, supervise personnel involved in installation, and test the elevator shall be certified to have not less than two years’ experience installing, supervising personnel involved in installation, and testing elevators of the type and rating specified. Helpers or apprentices with less than two years’ experience will be permitted to work only under the direct supervision of a certified elevator mechanic.
Project Site Conditions The contractor shall become familiar with the jobsite, verify all dimensions and space requirements in the field and on shop drawings, become familiar with existing elevator control system and advise the Contracting Officer of any discrepancy before performing any fabrication or installation work.
Training A training course shall be conducted by a qualified individual or individuals employed by the elevator controller supplier and familiar with the installation. The training course shall be for Government personnel as designated by the Contracting Officer. The training period shall consist of a total of 8 hours during a normal work day and shall start after the system is functionally completed and tested, but prior to final acceptance. The field instructions shall cover familiarization of the new equipment provided, routine maintenance tasks, troubleshooting of the controller, details of the processor and I/O modules including the operation of the system and how all components work together, and shall be based on the items contained in the operating and maintenance instructions. The Contracting Officer shall be notified at least 14 days prior to the date of the proposed training course.
Equipment Specifications
Elevator Hoistway Entrances Elevator hoistway entrance shall conform to the following:
Each hoistway door is equipped with a tamper-proof interlock which shall be used by the controller to prevent operation of the car until doors are locked in the closed position as defined by ASME A17.1 and shall prevent opening of the door at the landing from the corridor side unless the car is at rest at the landing or is traveling through the leveling zone, or unless the hoistway access switch is used. Existing retiring cams for hoistway door interlocks shall continue to be used as necessary.
Call Buttons The new controller shall provide the same function as the existing controller and use all existing hall and car call buttons for elevator operation unless replaced. If existing hall call button is replaced, pressure on a button shall illuminate the button to indicate that a call in the desired direction has been registered.
Car Operating Panel (COP) The car operating panel includes push buttons numbered to correspond to the floor served, and various additional switches, buttons, and light jewels, including: stop, alarm button, and level select. The new controller shall use the existing control units just as the existing controller does unless otherwise necessary. In addition to the existing controls, the contractor shall furnish and install a new audible signaling device in the car that is energized in the event that an operator has the elevator parked, or has otherwise made the elevator unavailable on a floor, and the elevator is called from a hall call station. The audible signaling device shall be that customarily used for the function described, shall be energized only when the hall call station is depressed and shall operate at an acceptable sound pressure level.
The operating panel in the car consists of the following operating devices:
a) Car light switch.
b) Emergency stop switch which, when operated, will stop the car independently of the limit switches
c) Level select buttons Hall Call Station Hall call operating devices at the landing consist of a push button at each landing. If replaced, push buttons shall illuminate when a call is registered.
Power Outage Operation The elevator control system shall be so arranged that upon failure of the normal power supply, the elevator shall provide the following operation:
· When the normal power supply fails, the car shall shut down.
· Upon return of power service, the car shall automatically move to the nearest floor or a predetermined floor.
Elevator Operation Existing operating devices to supply the operation described herein consist of a series of push buttons in the car numbered to correspond to the various landings, elevator call button at each landing, all connected electrically to the control system governing floor selection, direction of travel, acceleration, and deceleration.
Car calls shall be registered by passengers within the car by pressing the buttons corresponding to the floors to which they wish to go. Hall calls shall be registered by pressing the buttons in the hall push button fixture. Once the demand for elevator service has been established and the car has received its start signal, the operation shall be as follows:
| - | When the doors are fully closed and the interlock circuit established, the desired floor will be selected and the car shall start to move in the direction established by the control system. The car shall accelerate and decelerate automatically and stop at the first floor for which a car button has been registered or at the first corridor floor for a demand which has been assigned to the car. The car shall stop at all floors for which car calls are registered in the order in which such floors are reached and shall, in addition, stop for any corridor demands assigned to the car in the order in which these corridors are reached. |
| - | The doors on the car are such that they can be opened only when the car is stopped within the unlocking zone. The car shall become available for assignment at whatever floor the last car demand has been satisfied in the direction in which the car is then traveling. |
| - | The operating device shall be so arranged that with the pressing of one or more car or landing buttons the car shall start automatically and stop at the first floor for which the button has been pressed corresponding to the direction in which the car is traveling. The car shall stop in the order in which the floors are reached at all floors for which calls have been registered, irrespective of the sequence in which the buttons have been pressed, provided the button for a given floor has been pressed sufficiently in advance of the car's arrival at that floor to permit the stop to be made. When a car has stopped in response to the pressing of a landing button and a car button is pressed corresponding to the direction in which the car has been traveling, within a predetermined interval of time after the stop, the car shall continue in that direction, regardless of other landing calls registered. The car shall remain at the last floor it was directed to move to until it is directed to move to another floor by hall call buttons or by actuation of pushbuttons on car operating panel. |
| - | The hoistway doors and car gates are the manually operated type. |
Fire Service Not required at this time. However, provision for future installation shall be accommodated.
Leveling Devices The contractor shall furnish and install a new leveling device to automatically bring the car to the floor landings. The car shall automatically re-level at each landing to correct over-travel or under-travel or maintain the level, regardless of load on the car, rope slippage, or stretch of cables. The error in the stopping accuracy shall not exceed plus or minus 1/4 in.
Hoisting Machine The hoisting machine is the worm-geared traction type with motor, brake, worm gearing, traction sheave, and bearings.
Hoist Motor The existing hoist motor is the two speed, alternating current type, newly installed in last 10 years. The existing motor shall be removed and replaced with a new motor compatible with the new VFD controller and per MEMA MG1. The new motor shall work with the new controller to be furnished without overheating. The new motor windings shall be rated by the manufacturer as inverter duty. Speed regulation of the car with full-rated load shall be verified to ensure that it does not exceed plus or minus 5 percent of the average on a round trip. See paragraph on testing for information on verification of speed regulation.
The following motor performance specifications shall be equal to or greater than the existing equipment:
· Rated Voltage
· Rated Horsepower
· Rated Torque
· Pull-out Torque
· Insulation Rating
· Temp Rise
· Rated Speed Brake Assembly The existing brake is spring-applied and electrically released and shall be applied automatically in the event of interruption of the power supply. The release magnet coil circuit shall be opened by the various safety devices, power failure, failure of the equipment to function in the proper manner for safe operation of the car, or normal stopping of the car.
Controller The controller shall feature a non-proprietary, solid-state microprocessor used in conjunction with a compatible and commercial off the shelf (COTS) Variable Frequency Drive and overload relay that provides power to the motor. The controller shall be provided with a nameplate, white letters on black background, engraved to read “ELEVATOR CONTROLLER”.
The control system shall govern the starting, stopping, and direction of travel of the elevator and provide the operation specified herein. The elevator controller shall be the microprocessor-based logic type. Components required for proper performance of the elevator shall be neatly mounted and wired and completely enclosed in a cabinet with a mechanically latched door. The controller processor shall be new, unused, of current manufacture and shall be a standard product of the manufacturer. The programmable logic controller (PLC) system shall be that which is customarily used in elevator controllers. Replacement of any of the components of the microprocessor control system shall not require purchase of custom manufactured equipment, but instead, purchase of off-the-shelf components manufactured in volume. The control program shall be contained in non-volatile memory such as EPROM, EEPROM or FLASH memory such that upon failure of electrical power service to the controller, the control program will be retained in processor memory without the use of backup batteries. The processor and I/O modules shall be the modular type and shall be replaceable simply by unplugging from the rack or backplane and plugging the new module in. A processor or I/O module that is soldered in to the backplane or rack is not acceptable. Processor programming shall be accomplished in conventional relay ladder logic or as otherwise approved by the contracting officer. The contractor shall include in their shop drawing submittals the proposed processor logic and all related documentation. The O&M manuals provided by the contractor shall provide complete documentation on the final version of processor logic provided in the controller.
Additional Controller Specification:
Controller shall be ASME 17.5 Labeled, approved by an OSHA NRTL. All assemblies, power supplies, chassis switches, and relays shall be mounted on a type of metal frame in a NEMA rated cabinet that is self-supporting and that completely encloses the equipment. A means to heat and cool the inside temperature of the cabinet and its contents shall be provided. Solid state components mounted within the controller shall be designed to operate between 32 to 100 degrees Fahrenheit, humidity non-condensing up to 85 percent.
All controller switches and relays shall have contacts of a design and material to ensure maximum conductivity, long life and reliable operation without overheating or excessive wear, and shall provide a wiping action to prevent sticking due to fusion. Switches carrying highly inductive currents shall be provided with arc shields or suppressors.
· Where time delay relays are used in the circuits, they shall be of acceptable design, adjustable and reliable. Condenser timing or electronic timing circuits shall be consistent.
· Each device in all panels shall be properly identified by name, letter or standard symbol which shall be neatly stencil painted or decaled in an indelible and legible matter. Identification markings shall be coordinated with identical markings used on wiring diagrams. The ampere rating shall be marked on all circuit protection devices. All conductors to and within controllers and supervisory panels shall be neatly formed, laced and identified.
· Elevator travel will not be extended in the future so controllers shall not be provided with wiring and components to accommodate any future travel to additional floors.
· Printed circuit boards made by the elevator controller manufacturer shall be kept to a minimum so that:
· Longevity of components is assured and not compromised.
· Hardware changes over the product lifetime are kept to a minimum.
· The life of the product is not dependent on the life of the manufacturer.
· They are the same across all product lines, to ensure the least amount of inventory.
· Training to learn to work with the controller will not be required although field and in-house training will be available if it is desired by the building owner’s elevator maintenance technicians and/or their selected elevator maintenance company personnel.
· All parts shall be available through the controller manufacturer or a third party vendor.
· The controller electrical drawing and bill of material shall be submitted for approval and also included in the Operation and Maintenance Manual.
· If a printed circuit board interface for the car operation panel is provided or required by the elevator controller to be installed in the car operating panel, then there shall be on that printed circuit board and on-board diagnostic tool displaying in plain English the mode of elevator operation with a menu system written in plain elevator language to determine the status of signals so as to allow parameter adjustment, and display of faults.
· If a printed circuit board interface is provided for the top of the elevator car, there shall be on that printed circuit board an on-board diagnostic tool displaying in plain English the mode of operation with a menu system written in plain elevator industry language to determine the status of signals for parameter adjustments, and to display faults.
· The controller shall provide smooth, step-less acceleration and deceleration of the elevator, automatically and irrespective of the load in the car. All control equipment shall be enclosed in NEMA rated cabinets with lockable, hinged door(s) and shall be provided with a means of air circulation. All non-conducting metal parts in the machine room shall be grounded in accordance with National Electric Code. All cabinets shall be securely attached to the building structure.
· Circuit boards for the control of each elevator system; dispatching, signals, door operation and special operation shall be installed in a NEMA Enclosure. Circuit boards shall be classified as self-extinguishing and adequate thickness to support the components mounted thereon. They shall be spaced to prevent accidental contact between individual circuit boards and modules.
· Field wiring or alteration shall not be necessary in order to replace defective modules.
· Each device, module and circuit protection devices (with voltage and ampere rating) shall be identified by name, letter or standard symbol in an approved indelible and legible manner on the device or panel. Identification markings shall be coordinated with identical markings on wiring diagrams.
· Light emitting diodes (LED) shall be for visual monitoring of individual modules.
· Circuits shall assure fail-safe operation and to prevent elevator movement should a component malfunction.
· Field wiring changes required during construction shall be made only to connection points and not to the individual module circuitry or components. If it is necessary to alter individual modules they shall be returned to the factory where design changes shall be made and module design records changed so correct replacement units will be available.
· All logic symbols and circuitry designations shall be in accordance with ASME and NEC standards.
· Solid state components shall be designed to operate within a temperature range of 32 to 104 degrees Fahrenheit, humidity non-condensing up to 85 percent.
· Wiring connections for operating circuits and for external control circuits shall be brought to terminal blocks mounted in an accessible location within the controller cabinet. Terminal blocks using pierce through serrated washers shall not be used.
Transient Protection Transient protection equipment shall be provided. If transient protection equipment is customarily provided for the microprocessor control equipment, that equipment recommended by the manufacturer is acceptable. If transient protection is not customarily provided, the contractor shall provide a 120VAC transient protector that provides sufficient protection. The protection device shall be located on the line side of the microprocessor controller power supply. The ground terminal on the transient protector shall be taken to building equipment ground.
Motor Controller (VFD) Elevator control shall be affected by means of a compact solid state motor control unit for each and every elevator with electrical characteristics to suit the power supply. The system shall consist of the necessary three phase, full-wave bridge rectifiers.
Solid state motor control unit shall operate with high efficiency and low power consumption, have the capacity to handle peak currents typical of elevator service and contain a balanced, coordinated fault protection system which shall accomplish the following:
a) Protect the complete power circuit and specifically the power semi-conductors from failure under short circuit (bolted fault) conditions
b) Protect against limited faults arising from partial grounds, partial shorts in the motor armature or in the power unit itself
c) Protect the drive against sustained overloads. A solid state overload circuit shall be used
d) Protect motor and power unit against instantaneous peak overload
e) Provide semi-conductor transient protection
f) Provide phase sequence protection to ensure incoming line is phased properly
g) Removable printed circuit boards shall be provided for the VVVF control Conduit/Raceway All conduit installed shall be rigid galvanized steel (RGS). RGS shall conform to UL 6. As stated above, the contractor may choose to pull the existing wiring out of the existing raceway in the hoistway for the elevator door limit switches, hall call stations, hall car positions indicating lights, etc., or may choose to install new raceway in the hoistway. If the contractor chooses to install new raceway, it shall be RGS type. The new raceway shall be secured to the wall using lead anchor shields and screws or as otherwise accepted by the Resource Manager.
Wiring The insulation on conductors shall be rated for a voltage equal to or greater than the maximum voltage on adjacent conductors. The traveling cable wiring insulation, controller, incoming power wiring, and wiring to the elevator hoist motor shall be rated minimum of 600Vac at a temperature of 90 degrees C and shall conform to the applicable requirements of NEMA WC7 and NEMA WC 8. The insulation on all conductors shall be cross-linked polyethylene or approved equal.
Installation
Wiring Wiring shall be provided as necessary for all elevator equipment, and installation shall comply with the requirements of NFPA 70. The minimum size wire permitted shall be No. 18 AWG for control and signal circuits and No. 12 AWG for power and lighting circuits. Existing work light 150 watt incandescent lamp fixtures and grounded duplex receptacles are located on the top and bottom of the car. The contractor shall furnish and install all new wiring, except for the wiring inside the car that is connected to existing devices. All existing switches, interlocks, pushbuttons, lights etc. are to be re-used unless it is determined during the work that components are in poor condition and that replacement of same is appropriate. It is anticipated that all of the limit switches and interlocks are in an acceptable condition and can remain in use.
All wiring, except short lengths (6 inches or less) and traveling cables shall be in approved raceway. Short sections of wire which may require shifting for connection to switches and equipment may be installed in flexible conduit. Wires shall be identified and identification shall match the symbols shown on the wiring diagrams.
a. Control and signal wires shall be brought to accessible numbered terminal blocks on the controller.
b. Intra-panel wiring shall be a flame resisting type.
Traveling Cables The Contractor shall remove the existing traveling cable installed between their termination point on the car and their termination point at the existing controller. New traveling cable shall be furnished, installed and secured so that stress relief for conductors is provided. Rungs are available on the car for hanging the multi-conductor traveling cable(s). Traveling cable(s) shall terminate at numbered terminal blocks in the car and in the new controller. Traveling cable(s) shall be provided with a separate shielded circuit for the communication system and shall be hung so that the proper size loop can be obtained.
Installation Elevator controller and equipment shall be installed in accordance with ASME A17.1, NFPA 70 and the manufacturer's recommendation. Car Position sensing equipment shall be set plumb and parallel and be sufficiently supported at intervals not exceeding those recommended by the manufacturer of the car position sensing system. Any equipment installed in the hoistway shall be secured to the existing concrete walls with expansion shields and bolts or screws. Any holes that remain in any enclosures or boxes as a result of the work done under this contract shall be sealed with hole plugs that completely and functionally seal the hole.
The new controller enclosure shall be cleaned, primed and painted at the plant of the controller enclosure manufacturer. The contractor shall furnish the necessary material and labor to provide a suitable installation of conduit and wiring to connect equipment. The installation shall be accomplished in a good workmanship manner and shall be approved by and coordinated with the Contracting Officer or authorized representative.
Adjustments The Contractor shall test and adjust the equipment to achieve proper operation. Such testing and adjusting shall be in accordance with the applicable provisions of ASME A17.1 and as specified herein.
Warranty Period Regular adjustments to the elevator(s) shall be performed during the warranty period by competent and trained elevator mechanics during regular working hours of regular working days and shall include adjusting, lubricating, and cleaning of equipment. The Contractor shall furnish required supplies and parts except those parts required because of misuse, accident, or negligence not caused by the Contractor. The need for adjustments will be determined by the Resource Manager and will be based on the condition of the elevator operation.
Testing Tests to be performed are specified below. The Contractor shall notify the Contracting Officer in writing ten (10) days prior to the date of performing the acceptance test. The Contractor shall furnish all test instruments and during any test, such deficiencies shall be corrected and the tests repeated. All costs associated with retesting shall be borne by the Contractor.
Test Period The elevator shall be tested for a period of 30 minutes of continuous run with specified rated load in the car. During the test run, the car shall be stopped at all floors in both directions of travel for a standing period of 10 seconds per floor. A manual test of the final limits (up and down over travel) shall also be performed.
Speed Load Tests The actual speed of the elevator car in both directions of travel shall be determined with the rated load and with no load in the elevator car. The actual measured elevator car speed with the rated load in the up direction shall be within 5 percent of rated speed. The contractor shall provide the weights for load testing. It is anticipated that the elevator machinery/motor will meet this test. Therefore, this test is for documentation purposes only.
Car Levelling Tests Elevator car's leveling devices shall be tested in both directions of travel for accuracy of landing at all floors with no load in the car and with the rated load in the car. The error in the stopping accuracy shall not exceed plus or minus 1/4 inch as stated above.
Brake Test The brake test shall be conducted with the rated load in the car. Brakes shall stop and hold the car with the rated load. Sufficient power shall be applied to the brake magnets so that pads do not drag on the braking surface.
Insulation Resistance Tests The complete wiring system of the elevator shall be free of short circuits and grounds. Conductors shall have an insulation resistance of not less than 1 mega-ohm between each conductor and ground and between each conductor and all other conductors. These measured resistance values shall be recorded at the time of installation.
Operational Check The contractor shall develop a checklist and submit for Contracting Officer approval. The checklist shall be partially comprised of all operations/features available with the existing elevator and any new features provided by the new controller. The checklist may be used during the 30 minute period of elevator operation described in Test Period Above. The check shall incorporate all tests required to verify operation of all car position and direction indicating lights at all floors and in the car. The contractor shall furnish and install any lamps that may be required ensure all lamps installed are working.
Over-speed Test The testing shall include that test required to verify proper operation of the existing car over-speed sensor (governor). The sensor is set to decelerate the car when the speed of the car reaches between 20% to 40% more of the rated car travel speed. The Government will be responsible for costs associated with any adjustments or repair required should the governor fail the test. The test shall determine the car speed at which the switch contact opens the circuit to de-energize the controller upon overspeed. The test shall demonstrate that the contact does indeed cause de-energization of the hoist motor. The test shall also demonstrate that the force required to “set” the “overspeed brakes” on the elevator car is within acceptable limits with regard to the tensile strength of the rope and working limits of the equipment to which it is connected.
Warranty The Contractor shall provide a warranty for the work described herein. The warranty shall cover the equipment furnished herein and shall provide for all parts and labor required to maintain the system in operation. The warranty shall be valid for a period of one calendar year from the date of Acceptance of the equipment for beneficial use on behalf of the Government.
Site Clean Up The Contractor shall remove from the site, and legally dispose of all rubbish resulting from the work under this Contract. If needed contractor shall provide a separate dumpster located on site as directed by the Resource Manager. Rubbish shall be removed daily and not allowed to accumulate or overflow the dumpster.
Safety The Contractor shall be responsible for the maintenance of all safety barricades at hoistway openings from the point they start their work until such time as the hoistway doors are adequately and safely installed and operational. The Contractor will be responsible for a Pre-Construction risk assessment.
Inspection and Acceptance
Inspection The work will be conducted under the general direction of the Contracting Officer and is subject to inspection by his appointed inspectors to insure strict compliance with the terms of the contract. Any part of the equipment not in compliance with these specifications will be rejected and the Contractor shall promptly remedy or replace the defective part or parts to the satisfaction of the Contracting Officer, without cost to the Government. The Contractor shall keep the Contracting Officer informed as to the general progress of the work. No inspector is authorized to change any provision of the specifications without written authorization of the Contracting Officer, nor shall the presence or absence of an inspector relieve the Contractor from any requirements of the contract.
Final Tests and Acceptance The elevator controller will be inspected and final tests shall be performed as specified herein. Upon completion of satisfactory inspection and testing and submission of O&M manuals, the equipment will be accepted on behalf of the Government.
Performance The Contractor will be required to commence work under this contract within ten (10) calendar days after the day of receipt of Notice of Award, to prosecute said work diligently, and to complete all work within 90 days from date of Notice of Award. The Contractor shall coordinate his delivery plans with the Resource Managers. The contractor will be allowed to work only between the hours of 7:30AM and 4:00PM Eastern time, seven days per week except Federal holidays. The project Resource Manager may but is not obligated to, allow work times other than those specified herein. The contractor shall coordinate his work schedule with the Resource Manager. Once the contractor has taken an elevator out of service, he shall have it unavailable for no more than 5 consecutive days. Otherwise, during the duration of the contract, the Contractor will be required to make accommodations for reasonable use of the elevator by the Government for gate operations and maintenance of equipment in the intake structure. It is acceptable to operate the elevator during this time using the maintenance pushbutton station on the top of the card or the car operating panel.
Federal Holidays: When one of the designated holidays falls on a Sunday the following Monday is observed as a legal holiday. When a legal holiday falls on a Saturday, the preceding Friday is observed as a holiday. Work that interferes with other ongoing functions at the project shall be scheduled around normal working hours to be approved by Project Manager. Work shall be scheduled around the above listed Federal holidays unless approved in advance.
Ten Federal holidays observed are as follows:
New Year’s Day (January 1st) Martin Luther King Day (3rd Monday in January) President’s Day (3rd Monday in February) Memorial Day (Last Monday in May) Independence Day (July 4th) Labor Day (1st Monday in September) Columbus Day (2nd Monday in October) Veterans Day (November 11th) Thanksgiving Day (4th Thursday in November) Christmas Day (December 25th)
Delivery Costs of delivery of the equipment shall be included in the contract price and shall be coordinated with the Resource Manager through the Contracting Officer.
Omissions from the Contract Specification The Contractor shall check the specifications furnished immediately upon their receipt and shall promptly notify the Contracting Officer of any errors. Omissions from the specifications or the mis-description of details of work which are manifestly necessary to carry out the intent of the specifications, or which are customarily performed, shall not relieve the Contractor from performing such omitted details of the work but they shall be performed as if fully and correctly set forth and described in the specifications.
Shop Drawings The Point of Contact for shop drawing submittals will be provided after contract award.
The Contractor shall prepare and submit for approval 3 copies of all shop drawings as called for under the various sections of these specifications. These drawings shall be complete and detailed. It shall be the responsibility of the Contractor to check and coordinate shop drawings of his subcontractors and suppliers prior to submitting them. With each submittal of shop drawings, the Contractor shall certify that he has reviewed the shop drawings in detail and that they are correct and in strict conformance with the contract drawings and specifications except as otherwise explicitly stated. Upon completion of review by the Contracting Officer, if approved, each copy of the drawings will be identified as having received such approval by being so stamped and dated. The Contractor shall make any corrections required. If the Contractor considers any correction indicated to constitute a change to the contract specifications, notice as required under the contract clause, "Changes" shall be given to the Contracting Officer. Two sets of all shop drawings will be retained by the Contracting Officer and one set will be returned to the Contractor. The approval of the drawings shall not be construed as a complete check, but will indicate only that the general method of construction and detailing is satisfactory. Approval of such drawings will not relieve the Contractor of the responsibility for any error which may exist as the Contractor shall be responsible for the dimensions and design of adequate connections, details, and satisfactory construction of all work.
This is the start of the file's text. The full file is on GovTribe.