A.02.16_EXHIBITS.pdf

PDF 2 MB Posted

Attached to
Vehicular Bridge over Paved Gutter Federal contract opportunity
Solicitation number
W9123719Q0010
Issued by
Department of the Army Corps of Engineers Engineering District Huntington

About this file

Exhibits

View the file

Other files for this federal contract opportunity

Other files attached to Vehicular Bridge over Paved Gutter, newest first.
File Type Posted
B.08.03_W9123719Q0010-0001.pdf PDF
B.08.02_W9123719Q0010.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EXHIBIT 1 – AERIAL PHOTO – BRIDGE LOCATION

EXHIBIT 2 – BRIDGE LOCATION

EXHIBIT 3 – RELIEF WELL SYSTEM

NOTE: The contractor shall take care to avoid relief wells on the downstream side of the dam.

The relief wells are approximately 20’ from the edge of the existing bridge. See typical picture below:

EXHIBIT 4: Bridge Design

Exhibit 5: Minimum Distances for Installation