PIEDMONT LAKE
RR1 32665 BELMONT RIDGE RD
PIEDMONT OH 43983-9801
TEL: 740-968-4440 FAX: 740-968-4486
W81F8E60885447
REQUEST FOR QUOTATIONS
(THIS IS NOT AN ORDER) 1
PAGE OF PAGES
1. REQUEST NO. 2. DATE ISSUED RATING
W91237-16-T-0077 24-Jun-2016 5a. ISSUED BY
8. TO: NAME AND ADDRESS, INCLUDING ZIP CODE
IMPORTANT: This is a request for information, and quotations furnished are not offers. If you are unable to quote, please so indicate on this form and return it to the address in Block 5a. This request does not commit the Government to pay any costs incurred in the preparation of the submission of this quotation or to contract for supplies or services. Supplies are of domestic origin unless otherwise indicated by quoter. Any representations and/or certifications attached to this
Request for Quotations must be completed by the quoter.
11. SCHEDULE (Include applicable Federal, State, and local taxes)
ITEM NO.
(a)
SUPPLIES/ SERVICES
(b)
QUANTITY
(c)
UNIT
(d)
UNIT PRICE
(e) (f)
SEE SCHEDULE
AMOUNT
% No. %
NOTE: Additional provisions and representations [ ] are [ ] are not attached.
13. NAME AND ADDRESS OF QUOTER (Street, City, County, State, and ZIP Code)
14. SIGNATURE OF PERSON AUTHORIZED TO
SIGN QUOTATION
15. DATE OF
QUOTATION
16. NAME AND TITLE OF SIGNER (Type or print) (Include area code)
TELEPHONE NO.
AUTHORIZED FOR LOCAL REPRODUCTION STANDARD FORM 18 (REV. 6-95)
PREVIOUS EDITION NOT USABLE Prescribed by GSA FAR (48 CFR) 53.215-1(a)
THIS RFQ X[ ] IS [ ] IS NOT A SMALL BUSINESS SET-ASIDE
6. DELIVER BY (Date)
SEE SCHEDULE
AND/OR DMS REG. 1
UNDER BDSA REG. 2
4. CERT. FOR NAT. DEF.3. REQUISITION/PURCHASE
REQUEST NO.
USACE, CONTRACTING BRANCH
SAMANTHA STILES, 502 8TH STREET
HUNTINGTON WV 25701
9. DESTINATION (Consignee and address, including ZIP Code)
7. DELIVERY
[ ]X FOB
DESTINATION
[ ] OTHER
(See Schedule)
07-Jul-2016(Date)
PLEASE FURNISH QUOTATIONS TO THE ISSUING OFFICE IN BLOCK 5a ON OR BEFORE CLOSE OF BUSINESS:10.
304-399-5705SAMANTHA L STILES
(Name and Telephone no.) (No collect calls)5b. FOR INFORMATION CALL:
d. CALENDAR DAYSc. 30 CALENDAR DAYSb. 20 CALENDAR DAYS12. DISCOUNT FOR PROMPT PAYMENT a. 10 CALENDAR DAYS
Section B - Supplies or Services and Prices
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Job
PES Paving
FFP
Contractor shall provide all supplies, material, labor and supervision necessary to support the project roadway paving for Piedmont Dam, Piedmont, OH as described in the attached statement of work in Section C.
FOB: Destination
PURCHASE REQUEST NUMBER: W81F8E60885447
NET AMT
BID SCHEDULE
Line Item No. Description of Requirement
Qty./Unit of Measure Extended Price
Reimbursement of actual cost of payment bond for quotes in excess of $35,000.00 JOB $______________
Labor to pave the project roadways for Piedmont Dam, Piedmont, OH, in accordance with the attached Scope of Work.
JOB
Materials and supplies to pave the project roadways for Piedmont Dam, Piedmont, OH, in accordance with the attached Scope of Work.
JOB
TOTAL: $_______________
*SITE VISITS ARE HIGHLY RECOMMENDED PRIOR TO PROVIDING A QUOTE. SEE CLAUSE
52.236-27 FOR ADDITIONAL INFORMATION.
*PLEASE DIRECT ALL QUESTIONS TO SAMANTHA L. STILES AT (304) 399-5705 or Samantha.L.Stiles@usace.army.mil. ANY INFORMATION RECEIVED AT THE SITE VISIT WHICH
CONFLICTS WITH THIS SOLICITAION SHOULD BE BROUGHT TO THE ATTENTION OF MS.
STILES. THE SOLICITATION AND RESULTING CONTRACT SHALL BE THE GOVERNING
DOCUMENT IN ALL CASES.
** QUOTES CAN BE FAXED OR E-MAILED TO SAMANTHA L. STILES AT (304)
399-5705 or Samantha.L.Stiles@usace.army.mil. E-mail is the preferred method.
Per FARS 36.204 the estimated price range for this project is between $25,000.00 and $100,000.00.
NOTE 1: In accordance with FAR Part 28.102-1(b)(1), the Contractor will be required to provide one of the following payment protections for all construction contracts greater than $35,000.00 but not greater than $150,000.00.
(i) Payment bond
(ii) Irrevocable letter of credit
A Payment Bond or Irrecovable Letter of Credit is the SELECTED payment protection for the Government. The penal amount of bond shall be 100% of the original contract price. If the contract price increases, the Government will require an increase in the penal sum of the existing bond. This bond shall be submitted to the Contracting Officer within 10 days after receipt of award.
The payment made under this provision shall not exceed the amount included for Bid Item 0001 of the bid schedule, which payment shall take into consideration any discounts or rebates to the Contractor from the Surety.
FURTHERMORE, THE GOVERNMENT SHALL ONLY REIMBURSE THE CONTRACTOR THE ACTUAL
AMOUNT PAID TO THE SURETY COMPANY FOR PAYMENT BONDS, LESS ANY DISCOUNTS OR
REBATES. AN INVOICE FROM THE SURETY SHALL BE PROVIDED BEFORE PAYMENT IS MADE.
CONTRACTORS ARE ADVISED THAT BID ITEM 0001 IS ONLY FOR THE COST OF BONDS. OTHER
COSTS SHOULD BE ALLOCATED TO THE REMAINING BID ITEM(S).
NOTE 2: The Government will award a contract resulting from this solicitation to the responsible offeror whose offer conforming to the solicitation will be most advantageous to the Government, price and other factors considered. The following technical factors may be used in evaluating offers and are of equal importance:
Experience in the work required (if work is to be performed by a subcontractor, provide the name and necessary credentials, See FAR Clause 52.222-11), capability to perform the work, past performance and schedule control.
Technical factors are significantly more important than price.
QUOTATION INSTRUCTIONS:
1. If subcontractor will be used for this work, please provide company name and credentials/qualifications:
2. Contractors must be registered in the System for Awards Management (SAM) database (www.SAM.gov) to receive an award. (Formerly the Central Contractor Registration (CCR) database and the On-Line Representations and Certifications (ORCA).) Any reference to CCR or ORCA in any clause or provision is referring to the www.sam.gov website.
3. Provide business DUNS number: _______________________________ (phone 800-333-0505 for DUNS).
4. Provide business CAGE code: __________________________________
5. Tax Identification Number: ___________________________________
6. Contractors shall provide completed FAR clause 52.204-8 (Annual Representations and Certifications) found in Section K of this solicitation with their quote, if the Contractors have not completed their annual representations and certifications electronically via the SAM website at www.sam.gov. (See Paragraph 2 above)
7. Contractors are not required to submit an Accident Prevention Plan (APP) with their quote. The successful offeror will be required to submit this document upon award. The APP must be accepted by the Government Designated Authority prior to the preconstruction conference. EXAMPLES of the APP may be found at http://www.lrh.usace.army.mil/CT under the General Contracting Information heading.
The contractor that receives this award will have 10 calendar days to provide an Accident Prevention Plan (APP). If this deadline is not met, the contractor will be given a cure notice stating that they will have 10 calendar days to cure their non-performance. The contractor will have a total of 30 calendar days from date of award to provide an acceptable APP, otherwise the contract will be terminated for cause.
Section C - Descriptions and Specifications
STATEMENT OF WORK
Statement of Work and Technical Specifications For
Road Network and Parking Area Paving at Piedmont Dam Ohio
1 DESCRIPTION OF SERVICES: Provide all necessary labor, equipment and materials to construct and pave a 400’legnth of road (approximately 13,000 sq. feet) with cul-de- sac, and attached parking areas located at U.S. Army Corps of Engineers (USACE), Piedmont Dam Ohio facilities 32665 Belmont Ridge Road Piedmont, Ohio 43983. (See Appendix “A” for a map of the project roadway). The roadway will be a width of 20 feet wide, and constructed using an asphalt surface. The road will have 2 un-separated lanes of traffic.
1.1 Place of Performance: U.S. Army Corps of Engineers, Piedmont Dam, 32665 Belmont Ridge Road Piedmont, Ohio 43983.
1.2 Specific Requirements: The contractor shall perform the following tasks:
1.2.1 Remove Existing pavement, grade and widen existing surface down to acceptable soils for sub-grade to a depth acceptable for emplaced sub-grade. Any areas that require widening to a width of 20 feet will be widened on lake side of road.
1.2.2 Ensure sub-grade is acceptable; soil that is unacceptable must be removed and replaced with select fill to a depth of at least 1 foot.
1.2.3 Emplace and compact sub-base course at a depth of 2 inches.
1.2.4 Install 4 inches of new 304 aggregate to entire roadway
1.2.5 Install prime coat applied at a rate of 0.45 – 1.25 liters per square meter.
1.2.6 Install tack coat applied with SS-1H Tack material or equivalent at a rate of .075G per square yard.
1.2.7 Apply and compact 2.5 inches of base course asphalt, then install 1.5 inches of surface course asphalt.
1.2.8 Existing pavement that is milled will be transported to downstream access road and tailgated along existing roadway. This material will be compacted with pavement roller.
The roadway is approximately ¼ mile from area of primary work.
1.2.9 Any quantities provided are for quoting purposes only. Contractors are responsible for verifying quantities and locations of work prior to quoting or being awarded the contract.
1.3 Engineer Materials Technical Specifications: All materials used in this project shall meet the requirements of the USACE, the EM 385-1-1, and shall not be recycled, previously used, nor repaired.
1.4 General Design Requirements:
1.4.1 Road alignment and profile shall be determined by Contractor. The Contractor shall design the roadway with good drainage and erosion protection. Contractor shall straighten road alignment as much as possible. Drainage is required on both sides of the road. All intersecting roads, paths, driveways and culvert crossings are required to have a smooth transition to the new road alignment.
1.4.2 The road shall be built up above existing grade for storm water protection. Poor sub-grade material shall be removed and replaced with clean, compactable, gravel. Portions of the road shall be realigned and constructed at an elevation greater than the anticipated water level.
1.4.3 Sub-base Preparation: The sub-base should be well-graded, shaped to the desired cross-section (as specified by the typical cross-section plans), compacted to the specified density, well-drained, free from excessive moisture but not completely dry, and swept clean. Apply the prime coat when the base is almost dry so that it will absorb the prime material.
1.4.4 Prime Coat: The prime coat should penetrate the base about ½ inch of the sub-base, filling the voids. Plan priming operations so that there will always be an adequate amount of cured, primed base ahead of the surfacing operations; but not so far ahead that the base will become dirty or completely cured (dead). If prime coat is applied in late spring or during the summer the following bituminous materials are acceptable for prime coat: RT-2, RT-3, RT-4, MC-30, MC-70, SS-1, SS-1h, cationic slow-setting emulsified asphalt (CSS)-1, and CSS-1h. During the cold months of the winter, use rapid-setting asphalt cutbacks such as RC-70 and RC-250. Treatment should be applied at a rate of
0.45 – 1.25 liters per square meter.
1.4.5 Aggregate Base Course: Shall consist of crushed stone containing angular shapes and surfaces with no rounded surfaces. The following types of rocks are acceptable crushed stone: granite and similar phanerocrystalline igneous rocks, limestone, dolomite (>11% magnesium oxide (MgO), sandstone, or metamorphic quartzite, or similar rocks.
Limestone shall be a carbonate rock containing less than 11% magnesium oxide (MgO).
All aggregates shall contain less than 5% of shale, clay lumps, coal, lignite, soft or unfragmented stone, or other deleterious materials.
1.4.5.1 Acceptable gradations are as indicated in the table below.
References United Facilities Criteria (UFC) 3-250-03 “Standard Practice Manual for Flexible Pavements” and UFGS 02704, “Aggregate and/or graded-crushed aggregate base course” (Supersedes UFGS-02722A)
Source Acceptance Tests
Sieve Analysis (including 0.02 mm No. 635 size material).
Liquid limit and plasticity index.
Moisture-density relationship.
Wear.
Soundness.
Weight per cubic meter foot of Slag.
In-Place Tests Density tests shall be performed on every lift of material placed and at a frequency of one set of tests for every 250 square meters, or portion thereof, of completed area.
Sieve Analysis (including 0.02 mm No. 635 size material) shall be performed for every 50 metric tons of material placed.
Liquid limit and plasticity index tests shall be performed at the same frequency as the sieve analysis.
Weather No construction when near or below freezing.
Coarse Aggregate
Aggregate Base Course (ABC) coarse aggregate shall not show more than 50 percent loss when subjected to the Los Angeles abrasion test in accordance with ASTM C131. The amount of flat and elongated particles shall not exceed 30 percent. A flat particle is one having a ratio of width to thickness greater than 3; an elongated particle is one having a ratio of length to width greater than 3. In the portion retained on each sieve specified, the crushed aggregates shall contain at least 50 percent by weight of crushed pieces having two or more freshly fractured faces with the area of each face being at least equal to 75 percent of the smallest mid-sectional area of the piece. When two fractures are contiguous, the angle between planes of the fractures must be at least 30 degrees in order to count as two fractured faces.
Crushed gravel shall be manufactured from gravel particles 50 percent of which, by weight, are retained on the maximum size sieve listed in this table.
Fine Aggregate
The portion of any component or of the completed course passing the
0.425 mm No. 40 sieve shall be either non-plastic or have a liquid limit not greater than 25 and a plasticity index not greater than 5.
Blending The coarse and fine aggregates shall be mixed in a stationary plant, or in a traveling plant or bucket loader on an approved paved working area. Maximum lift is 150 mm.
Compaction Compaction shall continue until each layer has a degree of compaction that is at least 100 percent of laboratory maximum density through the full depth of the layer.
Thickness Requirements
The total compacted thickness of the base course shall be within 13 mm (1/2 inch) of the thickness indicated. Average job thickness shall be the average of all thickness measurements taken for the job, but shall be within 6 mm 1/4 inch of the thickness indicated. The total thickness of the base course shall be measured at intervals in such a manner as to ensure one measurement for each 500 square meters yards of base course. Measurements shall be made in 75 mm 3 inch diameter test holes penetrating the base course.
Finishing Grade and smoothness requirements. Maintain – limited traffic – no surface rutting.
1.4.5.2 Accepted Gradations for Aggregate Base Course:
1.4.6 Aggregate Base Preparation: The base should be well-graded, shaped to the desired cross-section (as specified by the typical cross-section plans), compacted to the specified density, well-drained, free from excessive moisture but not completely dry, and swept clean. Apply the tack coat when the base is almost dry so that it will absorb the prime material.
1.4.7 Tack Coat: Shall be a cutback asphalt, grades RC-70 or RC-250; an emulsified asphalt, grades MS-1, SS-1, SS-1h, CSS-1, CSS-1h; or an asphalt cement, grades AC- 2.5, 5, 10, AR-1000, 2000, or 4000 applied at a rate of 0.15 to 0.75 liters per square meter. The maximum application rate of .75 liters per square meter should not be exceeded as it may result in a bleeding and flushing action and loss of stability. The tack coat should become tacky within a few hours. A tack coat is not required on the primed base unless the prime coat has completely cured and become coated with dust.
1.4.8 Application Notes for Road-Mix Pavement:
1.4.8.1 Bitumen for Road-Mix: Ensure the base and sub-grade is well prepared and properly drained. The road mix will be laid in two lifts, each ranging from 2 inches in compacted depth.
The total thickness of the finished compacted road surface will be 3 ½ to 4 inches. Refer to the Mixed-in-place road mix row below in Table 2-2 for acceptable grades of asphalt cutbacks. Medium curing (MC) cutback is the most preferable. The mix gradation should be an open-graded mix. It shall contain coarse and fine particles in a continuous gradation.
However, it will not contain enough fine articles to fill the voids between large particles so it will be less dense.
1.4.8.2 Aggregate for Road-Mix: Aggregate should be hauled in from a nearby source. Do not scarify the aggregate from the existing sub-grade or base. Table 2-3 below shows the recommended gradation limits and Table 4-3 shows the suggested bituminous material content for each gradation. After blending the aggregate in windrows, take samples for sieve analysis. The gradation of the aggregate might have to be changed to meet specific field conditions. Acceptable deviations are-
Aggregate passing the # 4 sieve: +/- 7%
Aggregate passing the # 30 sieve: +/- 5%
Aggregate passing the #200 sieve: +/- 2%
The ideal aggregate will be well-graded, sandy gravel or clean sand. The maximum size of the aggregate is approximately 1 ¼ inch. Test for moisture content before mixing the aggregate with asphalt cutbacks. If the aggregate is too wet, use a mechanical mixer, a grader, or an improvised plow to allow the excess moisture to evaporate. The moisture content of CA should not exceed 3%.
Mix Proportions: The percentage of bituminous material shown in Table 4-3 below will vary in relation to the absorptive quality of the aggregate, the rate of evaporation of volatile substances, and other factors. With dense graded aggregates, do not use too much bituminous material.
Ensure that all particles of the mix are coated and uniform in color. If the mix is too lean, it will stand almost vertical in the windrow; if it is too rich, it readily flows back to its previous shape. If the mix is correctly proportioned, a handful squeezed into a ball retains its shape.
1.4.8.1 Construction: Construct the road-mix pavement on a dry base when it is not raining and the atmospheric temperature is above 10 degrees Celsius or 50 degrees F. Sequences of operations are as follows:
Inspect and recondition the base.
Prime the base and allow the prime to cure.
Place and windrow the aggregate at the side of the primed base and allow the aggregate to dry.
Spread the aggregate on the cured, primed base.
Spread the bituminous material on the aggregate in one-third increments.
Mix the bituminous material with the aggregate.
Blade and aerate the mix.
Spread the mix to the specified uncompacted thickness.
Compact the surface.
Apply Tack coat.
Repeat aggregate and bituminous mix process for second lift.
Apply seal coat if necessary.
This figure shows the typical sequence of operations:
1.4.8.2 If using cutback asphalt for spraying or mixing, heat it to a temperature of 80-200 degrees F (27-93 degrees C). Apply asphalt emulsions at 50 - 120 degrees F (10-50 degrees C) and tar at 80-225 degrees F (27-107 degrees C).
2 GENERAL INFORMATION:
2.1 Standards:
2.1.1 Construction shall adhere to the approved design and this SOW unless modified in writing by the Lower Tuscarawas Facility Manager, or Piedmont Project personnel. The Contractor will not be compensated for any modifications unless it receives written authorization from the PRT Engineer or the PPO to make such modification(s) before performing the work.
2.1.2 The Contractor's design and construction must comply with technical requirements contained herein. The Contractor shall provide design and construction using the best blend of cost, construction efficiency, system durability, ease of maintenance and environmental compatibility.
2.1.3 The design and product requirements are minimum requirements. The Contractor may propose alternate design or products (equipment and material) that are more commonly used in the region that will be equally or more cost effective or allow for more timely completion, but furnish the same system durability, ease of maintenance and environmental compatibility. The Contractor will be required to submit information as requested by the Contracting Officer, Project Engineer, or their representative to make a comparison of the proposed alternate. All variations must be approved by the Contracting Officer or their representative in writing.
2.1.4 The project includes furnishing all supervision, management, labor, materials, and equipment. Construction equipment shall be in good working order and shall be operated safely at all times.
2.1.5 Contractor's design and construction must comply with technical requirements contained herein and any other specifications or drawings provided. In the event of conflicting requirements, the most stringent requirement will apply, and the Contractor shall notify the Contracting Officer or their representative of the issue.
2.2 Site Clean-Up And Restoration: The contractor shall ensure the work site and areas around the work site are free of any debris and materials upon completion of work each day, as well as at the completion of the job. Contractor shall remove and properly dispose of all materials and equipment at the completion of the job. Unused materials or equipment owned by the USACE shall be returned to a location designated by the PPO. Upon completion of work, the work site shall be restored, insofar as is reasonably possible, to its condition prior to work, including replacement of vegetation, sidewalks, grading, drainage, and similar conditions affected by work during the performance of this Contract.
Supervision: The contractor shall personally supervise the work or have a designated Contractor Representative on site at all time work is being performed under this contract.
Special Considerations
1. Work shall be performed Monday – Friday 7:30 am thru 4:00 pm, excluding government holidays.
2. Care shall be taken to control public access utilizing barricades and signage during the work and in the evenings, until work is completed
Contractor and Government Equipment and Supplies The contractor shall furnish all personnel, equipment, transportation, disposal, supplies and materials to perform the work. No government equipment or supplies shall be used for this project. The Contractor shall Provide Personal Protection Equipment (PPE) to include steel-toed safety boots, hard hat, safety glasses or goggles, hearing protection, sleeved shirts, long pants, gloves, sunscreen and other applicable PPE specified in EM 385-1-1 and Appendix A).
Equipment, Material, and Supply Inspections: All materials shall be inspected upon delivery and or prior to use by government personnel. Materials shall be of high quality, commercial grade and meet or exceed industry standards or otherwise specified by COR and this contract.
Contractor Safety Requirements
Contractor Safety Requirements:
A. General. Contractor shall comply with all Federal, State and Local safety requirements including those specified by the Occupational Safety and Health Act (OSHA) in 29 CRF 1910 General Industry Standard, 1926 Construction Standard and the U.S. Army Corps of Engineers Safety & Health Requirements Manual EM 385-1-1 as currently revised at date of solicitation. Where a conflict exists between safety standards/requirements the contractor shall comply with the more stringent requirement. If the Contractor fails or refuses to promptly comply with safety requirements as specified herein, any project employee may stop all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to any such work stoppage shall be made subject to any claims for extension of time or for excess costs or damages sustained by the Contractor. Also, the Contractor will not be paid for work not performed as a result of the stop order.
B. Contractor Accident Prevention Plan (APP). The Contractor shall prepare a site-specific Accident Prevention Plan as outlined in EM 385-1-1, Appendix A beginning with subparagraph 3.k on page A-10. Contractor must address each element/sub-element in the order they appear in the outline. Any element the contractor feels is not applicable to work under this contract must be listed and a brief explanation provided. Plan must be accepted by the Contracting Officer prior to commencement of any work. Contractors are encouraged to contact the USACE Safety & Occupational Health Office for questions or information regarding the development of contract Accident Prevention Plans. Office hours are Monday-Friday 8:30 a.m. - 4 p.m. at (304)399-5039/5032/5326.
The web address for EM 385-1-1 is:
http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1- 1.pdf
(Attached for your information and use is CESO Checklist A-01. This checklist was developed to assist you in the development of a site-specific Accident Prevention Plan. This checklist is provided as a tool only.)
C. Contractor Risk Management Process. Contractor may use Job Safety analyses
(JSAs), Job Hazard Analyses (JHAs) or Activity Hazard Analysis (AHA) for the purpose of risk assessment. Before beginning each work activity Contractor performing that work activity shall prepare an initial assessment (AHA/JSA/JHA) listing each job step, anticipated hazards, site conditions, equipment, materials, personnel and control measures to be implemented. A Risk Assessment Code (RAC) shall be assigned to each step assessing the level of risk remaining after implementation of controls. Once this process is complete a RAC will be assigned to the activity as a whole (cannot be lower than the highest step RAC). Residual risk must be communicated to the proper authority for acceptance in order to proceed. It is the Contractor's responsibility to prepare the AHA/JSA/JHA. Analysis with RAC shall be accepted by the GDA and discussed with al engaged in the activity including Contractor, subcontractor(s), and on-site government representative prior to commencement of work.
Names of Competent Person(s) and Qualified Person(s) required for a particular activity (e.g., excavation, scaffolding, fall protection, or other activities specified by OSHA and/or EM 385-1-1) shall be identified and included in the AHA/JSA/JHA and proof of their competency/qualification.
NOTES:
Work crews of two or more must have two people holding current qualifications in First Aid and CPR from the American Red Cross, American Heart Association or a licensed physician. Training must include a hands-on element and the contractor must maintain appropriate First Aid kit on site. Single individuals working alone must have current certification in First Aid as a minimum.
Contractor shall employee a minimum of one Competent Person at each worksite to function as the Site Safety and Health Officer (SSHO). The SSHO as a minimum must have completed the 30-hour OSHA Construction or General Industry Safety class or its equivalent as specified in EM 385-1-1 Section 01.A.17.b and have a minimum of 5 years safety experience relative to the work being completed. The SSHO must be on-site at all times work is being performed. (Note: SSHO qualification requirements may be waived at the discretion of the USACE District Safety & Occupational Health Office for extremely low risk operations.)
Crane operators, riggers and signal persons shall be trained, licensed and meet the physical and drug testing requirements specified in EM 385-1-1 Section 16.
All electrical work must be completed by a Qualified Person with verifiable credentials as specified in EM 385-1-1, Section 11.A.01.c. Electrical work will require contractor to submit a Control of Hazardous Energy Plan (LOTO) in accordance with EM 385- 1- 1, Section 12.
D. Accident/Mishap Reporting: The Contractor shall report all recordable mishaps to the GDA within 24-hours in accordance with EM 385-1-1 Section 01.D. Accidents shall be investigated to determine causal factors and corrective actions shall be implemented.
Accidents resulting in: days away injuries, days away illnesses, restricted/transfer injuries, property damage of $5,000.00 or more shall be investigated and reported to the GDA using the USACE Accident Investigation Report Form ENG 3394 within 24 hours of the occurrence.
(1) Immediate notification to the GDA is required for all serious accidents:
a. Fatal Injury/illness;
b. Permanent totally disabling injury/illness;
c. Permanent partial disabling injury/illness;
d. One (1) or more persons hospitalized as inpatients as a result of a single occurrence
e. $500,000 or greater accidental property damage;
f. Three (3) or more individuals become ill or have a medical condition suspected to be related to a site condition, or a hazardous or toxic agent on the site;
g. USACE aircraft destroyed or missing;
The Contractor shall maintain an OSHA Log of Work Related Injuries and Illnesses, OSHA Form 300 and comply with all accident reporting and recordkeeping requirements specified in 29
CFR 1904.39.
(2) In addition to the above, any mishap occurring in any of the following high hazard areas shall be reported immediately to the GDA, investigated and corrective actions implemented.
electrical);
a. Electrical (includes Arc Flash, electrical shock, etc.);
b. Uncontrolled Release of Hazardous Energy (includes electrical and non-
c. Load Handling Equipment (LHE) or Rigging;
d. Fall-from-Height (any level or other than same surface);
e. Underwater Diving
W91237-16-T-0077
Site Visit
Offerors are encouraged to make a site visit by contacting:
Brian Edgar Project Supervisor U.S. Army Corps of Engineers Piedmont Dam 32665 Belmont Ridge Road
Piedmont, Ohio 43983 740-968-4440
Contractor Submittals The successful offeror shall provide as a minimum the following documentation. All contractor submittals must be reviewed and accepted by the contracting officer or government designated authority prior to commencement of any work.
A. Accident Prevention Plan
B. Activity Hazard Analysis
C. Invoice as stated on the contract award.
D. Manhour report to project office at completion of work.
DAMAGE REPORTS. All instances where Government materials, supplies, property, And/or equipment are damaged shall be reported immediately to the Project Supervisor at Piedmont Dam. When the damage is caused by contract employees, a written report of The incident and extent of such damage shall be submitted to the Project Supervisor, Within 2 work days (less weekends and holidays) of occurrence. For property damage Accidents of $2,000 or more, the Contractor will complete and submit to the Resource Manager a copy of ENG 3394.
CONTRACT EMPLOYEES' CONDUCT AND COMPETENCY. All contracts Employees shall conduct themselves in a proper manner at all times. Since the majority of work shall be performed in the presence of the general public, the conduct of all Employees are critical and will be closely monitored. Use of controlled substances or Consumption of beer or alcoholic beverages by contract employees is strictly prohibited.
The contractor may be required to immediately remove from the work site any employee Of the Contractor who is incompetent or who endangers persons or property or whose Physical or mental condition is such that it would impair the employee's ability to Satisfactorily perform the work.
CONTRACTOR INVOICE: Contractor shall submit their invoice to:
Facility Manager Lower Tuscarawas Area Office 49320 County Road 497 Coshocton, Ohio 43812-9496
WORKING HOURS. Normal working hours are Monday through Friday, 7:30 a.m. to 4:00 p.m. Work inside Government buildings or other secured areas shall be performed During the above referenced work hours.
Ten Federal holidays observed are as follows:
New Year's Day (January 1st) Martin Luther King Day (3rd Monday in January) President's Day (3rd Monday in February) Memorial Day (Last Monday in May) Independence Day (July 4th) Labor Day (1st Monday in September) Columbus Day (2nd Monday in October) Veteran's Day (November 11th) Thanksgiving Day (4th Thursday in November) Christmas Day (December 25th)
When one of the above designated holidays falls on a Sunday, the following Monday is Observed as a legal holiday. When a legal holiday falls on a Saturday, the preceding Friday is observed as a holiday.
Work that interferes with other ongoing functions at the project shall be scheduled around Normal working hours. Work shall be scheduled around the above listed Federal holidays Unless approved in advance.
Work shall be performed during daylight hours and days to be worked will be at the Discretion of the Project Supervisor.
DEFICIENCIES. If the Contractor fails to perform, or if performance in any area is Judged unsatisfactory, the Government will take corrective action. See FAR Clause 52.246-12 (Inspection of Construction)
PRE-CONSTUCTION CONFERENCE. The Contractor shall attend a pre-construction conference, Prior to the initiation of work under this contract. The Contractor's Accident Prevention Plan and all contractor submittals must be approved prior to this meeting.
SECURITY REQUIREMENTS
All Contractor and subcontractor employees working on this contract who require access in or around Huntington District facilities (i.e. flood control dams plants, navigation locks, etc.) shall receive a favorable background investigation in accordance with “Homeland Security Presidential Directive 12: Policy for a Common Identification Standard for Federal Employees and Contractors” (HSPD-12). The Huntington District Security Management Office (SMO) will complete the background investigation and make the final determination of an employee’s suitability for work on Government property.
The SMO and has the right to deny any contractor or subcontractor employee from working on a contract based on results of the background investigation. The Government, Contractor, and sub-contractors shall not permit any employee access to drawings, records, photos, sites, or projects until the Huntington District Security Management Office has approved them. The Contractor is responsible for meeting this requirement. Contractor’s failure to adhere to this can result in penalties, fines, or sanctions up to and including contract termination and or forfeiture of future contract consideration.
Contractors shall submit a complete investigation package for each contractor and subcontractor employee to the Huntington District Security Management Office within ten (10) working days after award of any contract, OR prior to the individual being permitted unescorted access in or around all District facilities. The documents listed below are required:
SF-85, Questionnaire for Non-sensitive Positions (See http://www.opm.gov/forms/ to print form) FD-258, Contractor Fingerprint Card (one card for digital prints, 2 for ink prints) (Note: a trained/qualified individual must take prints; ORI block on FD-258 must be USOPM000Z) (Contractor Fingerprint Cards (FD-258) may be obtained by contacting the Huntington District Security Management Office)
Contractor shall report any change(s) in personnel at least 5 working days prior to individual(s) needing access to the site. The Contractor shall provide the same information as listed above for any new employees.
Following submission of paperwork the Huntington District Security Management Office will conduct an initial criminal check based on the information provided. If there are no issues, SMO will provide approval via email to the Contractor and the Contracting Officer or their Designated Representative. If the SMO cannot give approval due to unfavorable report(s), it will notify the Contracting Officer and the Designated Representative; the KO will contact the Contractor. The Government will not provide a reason for disapproval; it will be up to the Contractor and or its employee to investigate the employee’s background information.
FOREIGN NATIONALS
The Contractor shall provide the package listed above, as well as additional materials noted below, for all non-U.S. citizens who have lived in the United States for at least three years. The Contractor is to expect additional time in the approval process for all foreign nationals due to the level of review and elevation of the review to Headquarters Staff to accomplish. All non-U.S. citizens, including permanent residents, must comply with the following paragraph:
In accordance with Engineering Regulation 380-1-18, “Technology Transfer, Disclosure of Information and Contacts with Foreign Representatives” dated 1 August 1996, Section 4, all foreign nationals who work on Corps of Engineers’ contracts shall be approved by the Headquarters US Army Corps of Engineers (HQ USACE) Foreign Disclosure Officer before beginning work on this contract; this regulation includes subcontractor employees. The Contractor shall submit to the Huntington District Security Management Office, the names of all foreign nationals proposed for performance under this contract, along with documentation to verify legal admittance into the United States, and has authority to work and/or attend school in the U.S. Such documentation shall include at least one of the following a U.S. passport, Certificate of U.S. Citizenship (INS Form N-560 or N-561), Certificate of Naturalization (INS Form N-550 or N-570), Alien Registration Card with photograph (INS Form I-151 or I-551), Employment Authorization Card (INS Form I- 688A), etc. A cleared federal employee shall escort foreign nationals at all times unless otherwise approved in writing by the Huntington District Security Management Office.
In order to assure forms are properly completed, and to minimize time delays, Contractor is encouraged to work closely with the Huntington District Security Management Office.
The Government will return for correction incomplete forms, illegible forms, etc. which will delay the contractor/subcontractor from beginning work. No subcontractor shall submit forms directly to the Huntington District Security Management Office; these documents shall come through the Prime Contractor.
Security requirements are subject to change in accordance with HSPD-12, Office of Personnel Management, regulation or policy changes, etc. The Government shall add any changes to security requirements by modification to the contract.
The Contractor shall contact the Huntington District Security Management Office by phone, letter, or email at the following numbers/addresses:
CELRH-SM
502 Eighth Street Huntington, WV 25701
Sandra L. Hardwick, phone (304) 399-5612; email sandra.l.hardwick@usace.army.mil
Matthew D. Green, phone (304) 399-5294; email matthew.d.green@usace.army.mil
AT/OPSEC
1. Access and General Protection/Security Policy and Procedures. All contractor and all associated subcontractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks or background investigation and to meet installation/facility access requirements to be accomplished by installation Provost Marshall Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any installation or facility change, the Government may require changes in contractor security matters or processes.
2. For contractors who do not require CAC, but require access to a DoD facility or installation. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05 / AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative, as NCIC and TSDB are available), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
3. Contractor Employees Who Require Access to Government Information Systems.
All contractor employees with access to a government info system must be registered in the Army Training Certification Tracking System (ATCTS) at commencement of services, and must successfully complete the DOD Information Assurance Awareness prior to access to the information systems and then annually thereafter in accordance with personnel security standards listed in AR 25-2 (Information Assurance), an appropriate background investigation will be conducted prior to accessing the government information systems.
4. Pre-Screen candidates using E-Verify Program. The Contractor must prescreen Candidates using the E-verify Program http://www.dhs.gov/E‐Verify website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than three (3) business days after the initial contract award.
ATTACHMENT 1
APPENDIX A
MINIMUM BASIC OUTLINE FOR ACCIDENT PREVENTION PLANS
An Accident Prevention Plan (APP) is a safety and health policy and program document.
The following areas are typically addressed in an APP, but an APP shall be job-specific and shall also address any unusual or unique aspects of the project or activity for which it is written.
The APP shall interface with the employer’s overall safety and health program, and a copy shall be available on the work site. Any portions of the overall safety and health program that are referenced in the APP shall be included as appropriate. ANSI/ASSE A10.38 should be referenced for Programmatic Issues.
1. SIGNATURE SHEET. Title, signature, and phone number of the following:
a. Plan preparer (Qualified Person, Competent Person, such as corporate safety staff person, QC);
b. Plan must be approved, by company/corporate officers authorized to obligate the company;
c. Plan concurrence (e.g., Chief of Operations, Corporate Chief of Safety, Corporate Industrial Hygienist, project manager or superintendent, project safety professional, project QC). Provide concurrence of other applicable corporate and project personnel (Contractor).
2. BACKGROUND INFORMATION. List the following:
a. Contractor;
b. Contract number;
c. Project name;
d. Brief project description, description of work to be performed, and location;
phases of work anticipated (these will require an AHA).
3. STATEMENT OF SAFETY AND HEALTH POLICY. Provide a copy of current corporate/company Safety and Health Policy Statement, detailing commitment to providing a safe and healthful workplace for all employees. The Contractor’s written safety program goals, objectives, and accident experience goals for this contract should be provided.
4. RESPONSIBILITIES AND LINES OF AUTHORITIES. Provide the following:
a. A statement of the employer’s ultimate responsibility for the implementation of his SOH program;
b. Identification and accountability of personnel responsible for safety at both corporate and project level. Contracts specifically requiring safety or industrial hygiene personnel shall include a copy of their resumes. Qualifications shall include the OSHA 30-hour course or equivalent course areas as listed here:
(1) OSH Act/General Duty Clause;
(2) 29 CFR 1904, Recordkeeping;
(3) Subpart C: General Safety and Health Provisions, Competent Person;
(4) Subpart D: Occupational Health and Environmental Controls, Citations and Safety Programs;
(5) Subpart E: PPE, types and requirements for use;
(6) Subpart F: understanding fire protection in the workplace;
(7) Subpart K: Electrical;
(8 Subpart M: Fall Protection;
(9) Rigging, welding and cutting, scaffolding, excavations, concrete and masonry, demolition; health hazards in construction, materials handling, storage and disposal, hand and power tools, motor vehicles, mechanized equipment, marine operations, steel erection, stairways and ladders, confined spaces or any others that are applicable to the work being performed.
c. The names of Competent and/or Qualified Person(s) and proof of competency/qualification to meet specific OSHA Competent/Qualified Person(s) requirements must be attached. The District SOHO will review the qualifications for acceptance;
d. Requirements that no work shall be performed unless a designated competent person are present on the job site;
e. Requirements for pre-task safety and health analysis;
f. Lines of authority;
g. Policies and procedures regarding noncompliance with safety requirements (to include disciplinary actions for violation of safety requirements) should be identified;
h. Provide written company procedures for holding managers and supervisors accountable for safety.
5. SUBCONTRACTORS AND SUPPLIERS. If applicable, provide procedures for coordinating SOH activities with other employers on the job site:
a. Identification of subcontractors and suppliers (if known);
b. Safety responsibilities of subcontractors and suppliers.
6. TRAINING.
a. Requirements for new hire SOH orientation training at the time of initial hire of each new employee.
b. Requirements for mandatory training and certifications that are applicable to this project (e.g., explosive actuated tools, confined space entry, crane operator, diver, vehicle operator, HAZWOPER training and certification, PPE) and any requirements for periodic retraining/recertification.
c. Procedures for periodic safety and health training for supervisors and employees.
d. Requirements for emergency response training. > See paragraph 9.b. below for a list of requirements that may require emergency response training.
7. SAFETY AND HEALTH INSPECTIONS.
a. Specific assignment of responsibilities for a minimum daily job site safety and health inspection during periods of work activity: Who will conduct (e.g., SSHO, PM, safety professional, QC, supervisors, employees – depends on level of technical proficiency needed to perform said inspections), proof of inspector’s training/qualifications, when inspections will be conducted, procedures for documentation, deficiency tracking system, and follow-up procedures;
b. Any external inspections/certifications that may be required (e.g., USCG).
8. ACCIDENT REPORTING. The Contractor shall identify person(s) responsible to provide the following:
a. Exposure data (man-hours worked);
b. Accident investigations, reports, and logs: Report all accidents as soon as possible but not more than 24 hours afterwards to the Contracting Officer/Representative (CO/COR). The contractor shall thoroughly investigate the accident and submit the findings of the investigation along with appropriate corrective actions to the CO/COR in the prescribed format as soon as possible but no later than five (5) working days following the accident. Implement corrective actions as soon as reasonably possible;
c. The following require immediate accident notification:
(1) A fatal injury;
(2) A permanent total disability;
(3) A permanent partial disability;
(4) The hospitalization of three or more people resulting from a single occurrence;
(5) Property damage of $200,000 or more.
9. PLANS (PROGRAMS, PROCEDURES) REQUIRED BY THE SAFETY MANUAL.
Based on a risk assessment of contracted activities and on mandatory OSHA compliance programs, the Contractor shall address all applicable occupational risks and compliance plans. Using the EM 385-1-1 as a guide, plans may include but not be limited to:
a. Layout plans (04.A.01);
b. Emergency response plans:
(1) Procedures and tests (01.E.01);
(2) Spill plans (01.E.01, 06.A.02);
(3) Firefighting plan (01.E.01, Section 19);
(4) Posting of emergency telephone numbers (01.E.05);
(5) Man overboard/abandon ship (Section19.A.04);
(6) Medical Support. Outline on-site medical support and off-site medical arrangements including rescue and medical duties for those employees who are to perform them, and the name(s) of on-site Contractor personnel trained in first aid and CPR. A minimum of two employees shall be certified in CPR and first-aid per shift/site (Section 03.A.02; 03.D);
c. Plan for prevention of alcohol and drug abuse (01.C.02);
D Site sanitation plan (Section 02);
E Access and haul road plan (4.B);
f. Respiratory protection plan (05.G);
g. Health hazard control program (06.A);
h. Hazard communication program (06.B.01);
i. Process Safety Management Plan (06.B.04);
j. Lead abatement plan (06.B.05 & specifications);
k. Asbestos abatement plan (06.B.05 & specifications);
l. Radiation Safety Program (06.E.03.a);
m. Abrasive blasting (06.H.01);
n. Heat/Cold Stress Monitoring Plan (06.I.02)
O. Crystalline Silica Monitoring Plan (Assessment) (06.M);
p. Night operations lighting plan (07.A.08);
q. Fire Prevention Plan (09.A);
R. Wild Land Fire Management Plan (09.K);
s. Hazardous energy control plan (12.A.01);
t. Critical lift Plan (16.H);
u. Contingency plan for severe weather (19.A.03);
v. Float Plan (19.F.04);
w. Site-Specific Fall Protection & Prevention Plan (21.C);
x. Demolition plan (to include engineering survey) (23.A.01);
y. Excavation/trenching plan (25.A.01);
z. Emergency rescue (tunneling) (26.A.);
AA. Underground construction fire prevention and protection plan (26.D.01);
Bb. Compressed air plan (26.I.01);
cc. Formwork and shoring erection and removal plans (27.C);
Dd. PreCast Concrete Plan (27.D);
Ee. Lift slab plans (27.E);
Ff. Steel erection plan (27.F.01);
Gg. Site Safety and Health Plan for HTRW work (28.B);
Hh. Blasting Safety Plan (29.A.