2018_0108_RTA_Submittal_C_and_G_Specs.pdf

PDF 10 MB Posted

Attached to
C & G Intersection Upgrades at DLA Richmond, VA Federal contract opportunity
Solicitation number
W91236-18-B-0019
Issued by
Department of the Army Corps of Engineers Engineering District Norfolk

About this file

C& G Specs

View the file

Other files for this federal contract opportunity

Other files attached to C & G Intersection Upgrades at DLA Richmond, VA, newest first.
File Type Posted
Amendment_05_C&G_Intersection.pdf PDF
Amendment_04_C&G_Intersection_Upgrades.pdf PDF
2018_0907__Amendment_3_Submittal_C_and_G_Plans.pdf PDF
Amendment_03_C&G_Intersection.pdf PDF
C&G_Road_Intersection_Specifications_Amendment_No_3.pdf PDF
Amendment_02_W9123618B0009_C&G_Intersection.pdf PDF
Amend_01_W91236-18-B-0009.pdf PDF
2018_0108_RTA_Submittal_C_and_G_Plans.pdf PDF
18B0009_C_&_G_Intersection_Solicitation.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

C&G Road Intersection

Defense Supply Center, Richmond Task Order: W91236-14-D-0028-0011-01

Specifications

Prepared by:

WSP

Virginia Beach, Virginia

Final Submittal

January 8, 2018

RTA Submittal

C&G Road Intersection W91236-14-D-0028-0011-01

SPECIFICATION PREPARED BY:

Civil

Electrical

Landscape

Defense Supply Center, Richmond W91236-14-D-0028-0011-01 C&G Road Intersection

PROJECT TABLE OF CONTENTS

DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS

00 01 15 LIST OF DRAWINGS

00 22 13.00 20 SUPPLEMENTARY INSTRUCTIONS TO OFFERORS

DIVISION 01 – GENERAL REQUIREMENTS

01 11 00.00 50 SUMMARY OF WORK

01 30 00.20 50 ADMINISTRATIVE REQUIREMENTS

01 31 19.00 50 PROJECT MEETINGS

01 32 01.00 50 PROJECT SCHEDULE

01 33 00.00 50 SUBMITTAL PROCEDURES

01 35 26.00 50 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 02.00 50 QUALITY CONTROL SYSTEM

01 45 04.00 50 CONTRACTOR QUALITY CONTROL

01 50 02.00 50 TEMPORARY CONSTRUCTION FACILITIES

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

01 62 35 RECYCLED/RECOVERED/BIOBASED MATERIALS

01 74 19.00 50 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT

01 78 02.00 50 CLOSEOUT SUBMITTALS

DIVISION 02 – EXISTING CONDITIONS

02 61 13 EXCAVATION AND HANDLING OF CONTAMINATED MATERIAL

02 81 00 TRANSPORATION AND HANDLING OF HAZARDOUS MATERIAL

DIVISION 03 – CONCRETE

03 15 00.00 10 CONCRETE ACCESSORIES

03 30 00.00 10 CAST-IN-PLACE CONCRETE

03 35 00.00 10 CONCRETE FINISHING

03 39 00.00 10 CONCRETE CURING

DIVISION 07 – THERMAL AND MOISTURE PROTECTION

07 92 00 JOINT SEALANTS

DIVISION 26 - ELECTRICAL

26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS

DIVISION 31 – EARTHWORK

31 00 00 EARTHWORK

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 13 13.06 PORTLAND CEMENT CONCRETE PAVEMENT FOR ROADS AND SITE

FACILITIES

32 16 13 CONCRETE SIDEWALKS AND CURBS AND GUTTERS

32 92 19 SEEDING

32 93 00 EXTERIOR PLANTS

Defense Supply Center, Richmond W91236-14-D-0028-0011-01 C&G Road Intersection

DIVISION 33 - UTILITIES

33 30 00 SANITARY SEWERS

33 40 00 STORM DRAINAGE UTILITIES

33 71 02 SITE UNDERGROUND ELECTRICAL DISTRIBUTION

VDOT 2016 ROAD AND BRIDGE SPECIFICATIONS

SECTION 201 MINERAL FILLER

SECTION 202 FINE AGGREGATE

SECTION 203 COARSE AGGREGATE

SECTION 205 CRUSHER RUN AGGREGATE

SECTION 208 SUBBASE AND AGGREGATE BASE MATERIAL

SECTION 210 ASPHALT MATERIAL

SECTION 211 ASPHALT CONCRETE

SECTION 234 GLASS BEADS FOR REFLECTORIZING TRAFFIC MARKINGS

SECTION 235 RETROREFLECTORS

SECTION 239 SODIUM CHLORIDE AND CALCIUM CHLORIDE

SECTION 246 PAVEMENT MARKINGS

SECTION 247 REFLECTIVE SHEETING

SECTION 308 SUBBASE COURSE

SECTION 309 AGGREGATE BASE COURSE

SECTION 310 TACK COAT

SECTION 311 PRIME COAT

SECTION 315 ASPHALT CONCRETE PLACEMENET

SECTION 510 RELOCATING OR MODIFYING EXISTING MICELLANEOUS ITEMS

SECTION 701 TRAFFIC SIGNS

SECTION 704 PAVEMENT MARKINGS AND MARKERS

APPENDIX

GEOTECHNICAL FIELD AND LABORATORY SERVICES

2016 ROAD AND BRIDGE SPECIFICATIONS (FOR REFERENCE)

DOCUMENT 00 01 15

LIST OF DRAWINGS

02/11

PART 1 GENERAL

1.1 SUMMARY

This section lists the drawings for the project pursuant to contract clause "DFARS 252.236-7001, Contract Drawings, Maps and Specifications."

1.2 CONTRACT DRAWINGS

Contract drawings are as follows:

SHEET NO. TITLE/DESCRIPTION SHEET ID

GENERAL

1 of 50 COVER SHEET G-001

2 of 50 INDEX OF SHEETS G-002

3 of 50 LOCATION MAP G-003

4 of 50 GENERAL NOTES G-004

5 of 50 STORMWATER POLLUTION

PREVENTION PLAN

G-005

6 of 50 STORMWATER POLLUTION

PREVENTION PLAN

G-006

7 of 50 STORMWATER POLLUTION

PREVENTION PLAN

G-007

8 of 50 STORMWATER NOTES AND DETAILS G-008

CIVIL

9 of 50 EXISTING SITE PLAN KEY SHEET, LEGEND, SURVEY NOTES

V-100

10 of 50 EXISTING SITE PLAN V-101

11 of 50 EXISTING SITE PLAN V-102

12 of 50 DEMOLITION AND EROSION &

SEDIMENT CONTROL PLAN

CD-101

13 of 50 GRADING PLAN CG-101

14 of 50 SITE PLAN C-101

15 of 50 ALIGNMENT DATA SHEET C-121

16 of 50 ROADWAY PROFILE - G ROAD/C

ROAD

C-201

17 of 50 ROADWAY PROFILE -

CONNECTOR/RAMP

C-202

DSCR

C&G Road Intersection

W19236-14-D-0028-0011-01

SECTION 00 01 15

SHEET NO. TITLE/DESCRIPTION SHEET ID

18 of 50 DRAINAGE PROFILES C-203

19 of 50 TYPICAL SECTION C-301

20 of 50 SITE DETAILS C-501

21 of 50 SITE DETAILS C-502

22 of 50 SITE DETAILS C-503

23 of 50 SITE DETAILS C-504

24 of 50 SITE DETAILS C-505

25 of 50 SIGNING AND PAVEMENT MARKING

PLAN

W-101

26 of 50 MAINTENANCE OF TRAFFIC

GENERAL NOTES

W-111

27 of 50 SEQUENCE OF CONSTRUCTION

PHASING

W-112

28 of 50 TRAFFIC DETAILS W-501

29 of 50 TRAFFIC DETAILS W-502

30 of 50 TRAFFIC DETAILS W-503

31 of 50 TRAFFIC DETAILS W-504

32 of 50 TRAFFIC DETAILS W-505

33 of 50 LANDSCAPE PLANTING PLAN L-101

34 of 50 LANDSCAPE DETAILS L-501

35 thru 40 CROSS SECTIONS G ROAD X-301 thru X-306

40 thru 45 CROSS SECTIONS C ROAD X-307 thru X-311

46 of 50 CROSS SECTIONS RAMP X-312

47 thru 48 CROSS SECTIONS CONNECTOR X-313 thru X-314

ELECTRICAL

49 of 50 ELECTRICAL NOTES, LEGEND AND

ABBREVIATIONS

E-100

50 of 50 ELECTRICAL SITE PLAN -

DEMOLITION

ED-101

DSCR

C&G Road Intersection

1.3 SUBSEQUENT DATA

The soils report is included as part of the solicitation as an attachment.

-- End of Document --

DSCR

C&G Road Intersection

DOCUMENT 00 22 13.00 20

SUPPLEMENTARY INSTRUCTIONS TO OFFERORS

02/14

PART 1 GENERAL

1.1 CONTRACT LINE ITEMS

The terms Offeror and Bidder and versions thereof (offer/bid) have the same definition as used within this contract.

Provide the Contract Line Item (CLIN) lump sum price for the following items:

CLIN 0001 - BASE PRICE. Price for the entire work for Facility Improve C&G Road Intersection, in accordance with the drawings and specifications.

CLIN DESCRIPTION QUANTITY UNIT UNIT TOTAL PRICE FOR

CLIN 1

1 Total for Improve C&G Road Intersection

1 Job Price $__________

1.2 GENERAL BID NOTES

a. Award will be made on the total sum of Contract Line Item 1.

b. Evaluation of Options (JUL 1990). Except when it is determined in accordance with FAR 17.206 (b) not to be in the Government's best interest, the Government will evaluate offers for award purposes by adding the price for the Option(s) to the total price for CLIN 0001.

In accordance with FAR 52.217-5, evaluation of options will not obligate the Government to exercise the Option(s).

c. The Government may reject an offer as nonresponsive if it is materially unbalanced as to prices for the basic requirement. An offer is unbalanced when it is based on prices significantly less than cost for some work and prices which are significantly overstated for other work.

d. 1 Measurement Ton (MTON) = 40 cubic feet

e. History has shown that the average billable volume for a 40 ft.

container is 59.0 MTON. There is a weight restriction of 50,000 lbs.

per container, which includes tare weight of the container.

f. Bids will be accepted only from United States of America Contractors.

g. U.S. Contractor: To qualify as a U.S. Contractor, the firm (or if a joint venture, members of the joint venture) must be incorporated in the United States, and must comply with the following:

DSCR

C&G Road Intersection

SECTION 00 22 13.00 20

(1) The principal place of business and corporate headquarters must be in the United States.

(2) The firm must have paid corporate franchise and employment taxes in the United States for a minimum of 2 years. The firm must have filed state and federal income tax declarations for a minimum of 2 corporate years and paid any applicable taxes determined to be due as a result of such filing.

(3) The firm must employ U.S. citizens in key management positions.

h. Joint Ventures: Joint ventures will be permitted provided that members of the joint venture meet the specified requirements for a U.S.

Contractor.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Document --

DSCR

C&G Road Intersection

SECTION 00 22 13.00 20

SECTION 01 11 00.00 50

SUMMARY OF WORK FOR NORFOLK DISTRICT PROJECTS

2/2013

PART 1 GENERAL

1.1 DEFINITIONS

a. Facility: The facility is:

C Road and G Road Intersection Defense Logistics Agency - Aviation DSCR, Richmond, Virginia

CO: Contracting Officer or his authorized representative.

1.2 WORK COVERED BY CONTRACT DOCUMENTS

1.2.1 Project Description

The work includes Removing and reconstructing the C & G Road Intersection.

Work items include asphalt pavement, sidewalk, curb and gutter, storm drains, relocating the existing DMS, signing and pavement markings, and relocating a utility pole.

1.2.2 Location

The work shall be located at the DSCR where shown on the drawings.

1.3 PERSONNEL RESTRICTIONS

Personnel are limited to the immediate site areas and shall not enter buildings or facilities not involved in the work. All employees of the Contractor will be subject to all rules and regulations of the Facility which pertain to personnel. The Contractor shall erect fences and signs as specified and be responsible for the restrictions of all personnel. The Contractor's plans for restricting personnel access to the project site shall be submitted for approval as a part of the Safety Plan (Accident Prevention Plan). Facility access shall be restricted. Contractor shall comply with current security requirements. All vehicles shall be registered with the military police.

1.3.1 Security Requirements Defense Supply Center Richmond (DSCR)

No employee or representative of the Contractor will be admitted to the work site unless he furnishes satisfactory proof that he is a citizen of the United States or has proper identification to work in the United States.

a. Personnel Information - All authorized non-military personnel utilizing the base are required to have in their possession at all times a Base Visitor Pass or Base Identification. This pass is issued by the DSCR Visitors Center located at the North Gate. Proof of identity is required to obtain a visitor pass or Base Identification. The Visitors Center is open Monday through Friday except Federal holidays from 7:00 a.m. to 3:00 p.m. A minimum of 5 working days prior to start of work, the Contractor

DSCR

C&G Road Intersection

W91236-14-D-0028-0011-01 shall furnish to the Defense Supply Center Richmond (DSCR), Richmond, VA, Security Department, via the Contracting Officer, the following information for Contractor and subcontractor personnel required to enter the Station:

(1) Contract Number

(2) Beginning Date (Month, Day, Year)

(3) Ending Date (Month, Day, Year)

(4) Name of the company (The Prime Contractor and Sub Contractor)

(5) Full Name of the employee (First, Middle and Last)

(6) Address of Current (Employee's) Residence (Bldg#, Street, City, State, Zip or City and Country)

(7) Social Security Number (SS#)

(8) US Citizen (Yes / No)

(9) Gender (Male/Female)

(10) Race (American Indian or Alaska Native, Asian, Black or African American, Native Hawaiian or Other Pacific Islander, and White)

(11) Date of Birth (Month, Day, Year)

(12) Place of Birth (City, State, Country)

b. The DSCR Security Department will run a criminal history check on Contractor employees as a condition of employment. Official proof of identity or naturalization papers may be required, which will be returned once entered into the security computer system. Based on the results of the criminal history check, the Security Officer will or will not grant entry to the Station. If entry is denied, the Contractor will be immediately notified. DSCR Security may require updating or rechecking criminal history based on the duration of the contract. NOTE: DSCR Security has been denying entry to persons whose police record checks are positive.

Failure to obtain entry approval will not affect the contract price or time of completion.

c. Proof of Identity -Official identification can consist of copies of birth certificates, valid federal identification, valid state identification, or valid naturalization papers. Examples of official identification are valid state issued driver's license, military ID card, military dependent ID card, green card, etc. Expired identification is not valid.

d. Base Entry Passes - Contractor base entry passes will be valid for each entry aboard DSCR from 6:00 a.m. to 6:00 p.m., Monday through Friday except for Federal holidays, unless prior arrangements have been made with the Contracting Officer, and DSCR Security has been notified. The passes are the property of the base and are to be returned to Visitors Control at the North Gate upon completion of the contract or termination of employment. Replacement passes must be requested in writing and be accomplished by written authorization from the Contracting Officer.

DSCR

C&G Road Intersection

DSCR

C&G Road Intersection

W91236-14-D-0028-0011-01

SECTION 01 11 00.00 50

Compliance with this requirement is mandatory and certification thereof to the Contracting Officer is required prior to submitting final invoices.

Failure to return badges will hold up Contractor's final payment.

e. Contractor Responsibility for Employees - The Contractor is responsible for employees under his employment. Ensure that employees are familiar with and obey station traffic, safety, and security regulations.

f. Unofficial photography, cameras, or photographs are prohibited on DSCR property. When official photographs are required, submit a written approval request containing specific justification and details to the Contracting Officer 5 days prior.

g. Firearms, Weapons, Alcoholic Beverages, Illegal Drugs, and Contraband are prohibited on DSCR property. Violators may be prosecuted. State issued/authorized concealed weapons permits are not valid on Federal (DSCR) property.

h. Motor Vehicle Operation - Ingress and egress of personnel will be subject to the DSCR security regulations.

(1) All personnel must be made aware of the base speed limits:

25 mph (unless otherwise posted)

Speed limits are enforced and violators will be ticketed. DSCR traffic violations are processed through the federal court system.

(2) Seat belts are MANDATORY.

(3) Parking is in designated areas only, between two white lines. No parking is permitted in fire lanes, on seeded areas, in reserved parking slots, or assigned handicapped parking. Any equipment or vehicle that does not fit within a standard parking space must contact the Contracting Officer to determine a designated area for parking such equipment or vehicle.

Contractor employees shall park vehicles (Commercial or Private) in areas designated by the Contracting Officer. This area may or may not necessarily be within reasonable walking distance of the construction site. The contractor shall provide transportation between the parking area and the construction site. Contractor employee parking shall not interfere with existing and established parking requirements of the Base.

(4) Traffic accidents shall be reported immediately to the DSCR Emergency Dispatch by calling 911 or (804) 279-4888.

(5) All personnel entering the installation are subject to random vehicle inspections/searches at any time while on the base. The purpose of these inspections is to detect the theft of Government and private property, firearms, weapons, alcoholic beverages, illegal drugs, or contraband.

(6) Information required for Vehicle Passes- Driver's are required to bring the vehicle, contract number, vehicle registration, copy of vehicle insurance policy, valid state inspection documentation, and valid driver's license to the Visitor Control Center at the North Gate. Vehicles without passes will not be allowed entry to base.

i. Commercially Owned Vehicles - All commercial Vehicles are to clearly display the authorized company name or logo on both sides of the vehicle.

ii. Privately Owned Vehicles - No Privately Owned Vehicles will be allowed within the Defense Distribution Depot, Richmond, VA (DDRV) area or any other secure/controlled industrial area located on DSCR.

iii. Rental Vehicles - The driver is to show all paper work from the rental company showing that the driver is authorized to operate the subject vehicle. Rental vehicles will not be allowed in secure/controlled industrial areas located on DSCR unless the rental vehicle clearly displays the authorized operating company name or logo on both sides of the vehicle.

i. Access to Restricted Areas - Base entry passes allow access to designated areas on the installation only. Entries into secure/controlled industrial areas are prohibited unless the contract requires it.

j. Current Information - Contractors will be responsible for keeping the vehicle and employee lists current, and for securing and returning identification cards belonging to terminated employees to the DSCR Security Department.

k. Providing Information to Subcontractors - Prime Contractors shall be responsible for ensuring that subcontractors receive security information.

Failure to comply with the specified requirements will result in prime contractors and subcontractors being denied access to the construction site.

l. DSCR is not responsible for job site security. Removal of material from job-site and base are subject to security checks. Contractor is to notify DSCR security of any special measures (watchmen, alarm, etc), security concerns, security problems, or unusual activities within the job site.

1.4 TRANSPORTATION FACILITIES

The Facility is served by an all weather surfaced road network. Road(s) within the Facility proposed to be used by the Contractor shall be subject to prior approval of the Facility authorities and such roads, if used, shall be maintained throughout construction and shall be restored to as good condition as existed prior to their use. The Contractor shall also construct, subject to approval, such temporary haul roads and bridges as may be necessary for conducting his work. Any such temporary construction shall be removed and the affected area restored to its original condition.

All costs for the use of existing transportation facilities, for the construction of temporary facilities, and for maintenance, repair, removal and restoration shall be borne by the Contractor.

1.4.1 Use of Roads

Hard-surfaced roads from major and primary municipal roads serve the Facility. The movement of all vehicles within the Facility shall be confined to the roads designated and shall comply with traffic regulations within the Facility. The Contractor shall keep all roads clear of all obstructions and free of mud and other foreign materials resulting from operations. The Contractor's vehicles shall at no time follow a vehicle closer than 50 feet, and all vehicles shall pull off the road and come to a complete stop when meeting emergency vehicles, or vehicles with flashing lights. Facility speed limits and traffic controls shall be observed.

DSCR

C&G Road Intersection

1.4.2 Road Restrictions

The movement of all vehicles within the Facility shall be confined to the roads designated and shall comply with traffic regulations within the Facility. Other roads may be used only with the approval of the CO.

1.4.3 Cleated Vehicles

Cleated vehicles shall not be moved over surfaced roads except at the immediate site of the area where they are to be used.

1.5 SPECIAL CONTRACTOR REQUIREMENTS

1.5.1 COORDINATION IN WORK AREAS

1.5.1.1 Occupied Work Area

The area where work is to be accomplished will be occupied during the work. Activities of the occupants of the scheduled work area shall not be interrupted or hampered in any way without prior written approval of the Contracting Officer.

1.5.1.2 Unoccupied Work Area

The area where the Contractor is scheduled to perform the work will not be occupied during the work, however, the Contractors work activities may affect other area(s) that are occupied. All work shall be in accordance with the Contractor's work plan.

1.5.1.3 Maintenance of Utilities

Any active utilities, including but not limited to electricity, gas, water, sewer, heating, air conditioning, or any like service, that will require interruption or replacement in any occupied area affected as a result of the Contractors scheduled work activities, shall be temporarily provided by the Contractor at his own expense until the affected service is fully and permanently restored. All temporary method(s) of service replacement the Contractor proposes for use on this contract shall be approved by the CO prior to commencing the work.

1.5.1.4 Hours of Work

The normal work hours for construction shall be from 8:00 a.m. to 4:30 p.m.

Monday through Friday of each week. Any request to change these hours shall be made in writing to the Contracting Officer at least two calendar days prior to the desired day on which the change is to go into effect.

The changed hours shall not go into effect until written permission has been received from the Contracting Officer.

1.5.1.5 Existing Utility Location

Existing utilities must be located before doing any digging work on Facility. The Contractor shall be responsible to contact Miss Utility, obtain all necessary existing utility locations, which may be necessary to accomplish his work, and mark any utility lines in the immediate vicinity of his work. It shall be the responsibility of the Contractor to contact Miss Utilities at 1-800-552-7110 for locating commercial utilities 48 hours

DSCR

C&G Road Intersection prior to digging operations.

1.5.1.6 Digging Permits

Contractor is responsible for obtaining all digging permits, including associated locating and marking services, in accordance with installation and local requirements, at no additional cost to the Government.

"Clearance Permits for Digging', must be obtained before doing any work on Facility. The Contractor shall be responsible to obtain all necessary digging permits and pay costs associated with the permit,which may be necessary to accomplish his work.

1.5.1.7 Personnel Escort

An authorized Contractor representative must escort all personnel attempting to obtain a badge to Security. The representative shall sign documentation that the employee meets Security criteria and is suitable for a badge to be issued.

1.6 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER

This provision specifies the procedure for the determination of time extensions for unusually severe weather in accordance with the Contract Clause entitled "Default: (Fixed Price Construction)". In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:

a. The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.

b. The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.

1.6.1 Schedule

The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The Contractor's progress schedule must reflect these anticipated adverse weather delays in all weather dependent activities.

MONTHLY ANTICIPATED ADVERSE WEATHER DELAY WORK DAYS

BASED ON (5) DAY WORK WEEK

JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

DSCR 10 9 9 6 8 7 8 7 6 5 7 9

1.6.2 Records

Upon acknowledgement of the Notice to Proceed and continuing throughout the

DSCR

C&G Road Intersection contract, the Contractor will record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the Contractor's scheduled work day.

1.6.3 Impacted Days

The number of actual adverse weather days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day in each month, and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in the schedule of monthly anticipated adverse weather delays, above, the contracting officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with the Contract Clauses entitled "Default (Fixed Price Construction)".

1.7 EXISTING WORK

In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.

1.8 LOCATION OF UNDERGROUND UTILITIES

Obtain digging permits prior to start of excavation. Scan the construction site with electromagnetic or sonic equipment, and mark the surface of the ground where existing underground utilities or utilities encased in pier structures are discovered. Verify the elevations of existing piping, utilities,and any type of underground or encased obstruction not indicated to be specified or removed but indicated or discovered during scanning in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.

Notify the Contracting Officer at least 15 days prior to starting excavation work.

Items designated by the Contracting Officer to be salvaged shall remain the property of the Government.

The salvaged property shall be segregated, itemized, delivered, and off-loaded at the storage area located on site.

Contractor shall maintain property control records for material or equipment designated as salvage. Contractor's system of property control may be used if approved by the Contracting Officer. Contractor shall be

DSCR

C&G Road Intersection responsible for storage and protection of salvaged materials and equipment until disposition by the Contracting Officer.

1.9 PHYSICAL DATA

The physical conditions indicated on the drawings and in the specifications are the result of site visits, surveys, and borings. See civil drawings.

1.10 SITE CONTAMINATION

This site is designated a Category II site and is defined as a current or former industrial site or other hazard producing activity site which is perceived to be a clean location; however, due to former industrial or other activities within or near the site, it has the potential for contamination.

1.10.1 Contamination Removal

In the event that contamination beyond that shown or specified is encountered, the Contracting Officer shall be advised immediately. The contamination shall be removed as directed and replaced with satisfactory material. Payment therefore will be made in conformance with the CHANGES clause of the CONTRACT CLAUSES.

1.10.2 Compliance Requirements

The Contractor shall comply with applicable Federal, state and local laws, codes, ordinances and regulations (including the obtaining of licenses and permits) in connection with any hazardous material, substance or waste.

1.10.3 Requirements

The requirements of this clause and any act or failure to act by the Government shall not relieve the Contractor of any responsibility or liability for the safety of Government, Contractor or subcontractor personnel or property.

1.11 INTERRUPTIONS OF UTILITIES

1.11.1 Approval

Utility services shall be interrupted by the Contractor to relocate, make connections, or interrupt for any purpose, without written approval of the

CO.

1.11.2 Request

Request for permission to shut down services shall be submitted in writing to the CO not less than 10 calendar days prior to date of proposed interruption. The request shall give the following information:

a. Nature of Utility (Gas, L.P. or H.P., Water, Electrical, Communications, Fire Alarm Systems, Security Systems)

b. Size of line and location of shutoff.

c. Buildings and services affected.

DSCR

C&G Road Intersection

d. Hours and date of shutoff.

e. Estimated length of time service will be interrupted.

1.11.3 Service Interruptions

Services shall not be shut off until receipt of approval of the proposed hours and date from the Contracting Officer.

1.11.4 Timely Disconnections

Shutoffs which will cause interruption of Government work operations as determined by the Contracting Officer shall be accomplished during regular non-work hours or non-work days of the Using Agency without any additional cost to the Government.

1.11.5 Utilities Operation

Operation of valves on water mains will be by Government personnel. Where shutoff of water lines interrupts service to fire hydrants or fire sprinkler systems, the Facility Fire Department shall be notified by the Contractor in writing 72 hours prior to the proposed interruption. The Contractor shall arrange his operations and have sufficient material and personnel available to complete the work without undue delay and shall restore service without delay in event of emergency.

1.11.6 Gas

Flow in gas mains which have been shut off shall not be restored until the Government inspector has determined that all items serviced by the gas line have been shut off.

1.12 HISTORICAL AND ARCHAEOLOGICAL FINDS

Federal legislation provides for the protection, preservation, and collection of scientific, prehistoric, historical, and archaeological data, including relics and specimens which might otherwise be lost due to alteration of the terrain or building features as a result of any Federal construction project. Should the Contractor, or any of the Contractor's employees, or parties operating or associated with the Contractor, in the performance of this contract discover evidence of possible scientific, prehistoric, historical, or archaeological data, the Contractor shall immediately cease work at that location, avoid further disturbance, and notify the Contracting Officer, giving the location and nature of the findings. The Contractor shall forward written confirmation to the Contracting Officer as directed. The Contractor shall exercise care so as not to disturb or damage artifacts or fossils uncovered during excavation operations, and shall provide such cooperation and assistance as may be necessary to preserve the findings for removal or other disposition. Any person who, without permission, injures, destroys, excavates, appropriates, or removes any historical or prehistoric artifact, object of antiquity, or archaeological resource on the public lands of the United States is subject to arrest and penalty of law. Where appropriate by reason of discovery, the Contracting Officer may order delays in the time of performance or changes in the work, or both. If such delays or changes are ordered, an equitable adjustment will be made in the contract in accordance with the

DSCR

C&G Road Intersection applicable clauses of the contract.

1.13 SUBCONTRACTS AND WORK COORDINATION

Contract Clauses "SUBCONTRACTS", "PERMITS AND RESPONSIBILITIES", and "MATERIAL AND WORKMANSHIP" are supplemented as follows:

a. Divisions or sections of specifications are not intended to control the Contractor in dividing the work among subcontractor, or to limit work performed by any trade.

b. Contractor shall be responsible for coordination of the work of the trades, subcontractors, and materials.

c. The Government or its representative will not undertake to settle any difference between the Contractor and Contractor's subcontractors, or between subcontractors.

d. The Government reserves the right to refuse to permit employment on the work or require dismissal from the work of any subcontractor who, by reason of previous unsatisfactory work on Corps of Engineers projects, or for any other reason is considered by the Contracting Officer to be incompetent or otherwise objectionable.

1.14 CONSTRUCTION MANPOWER AND EQUIPMENT REPORT

The Contractor shall submit executed CENAO Form 987, Construction Manpower and Equipment Report daily. The report shall include manpower and equipment for the general and subcontractors. Forms are available from the Contracting Officer.

1.15 PURCHASE ORDERS

To ensure proper expediting of orders the Contractor and his subcontractors shall furnish to the Contracting Officer, one copy of each purchase order covering supplies or services required for performance of the work. Each purchase order shall clearly indicate the date of placement, the date delivery is required in order to avoid delay in the scheduled progress of the work, and the date delivery is promised by the supplier or producer.

Copies of purchase orders shall be forwarded on the date issued.

1.16 PROFIT

1.16.1 Weighted Guidelines

Weighted guidelines method of determining profit shall be used on any equitable adjustment change order or modification issued under this contract. The profit factors shall be as follows:

Factor Rate Weight Value

Degree of Risk 20 Relative difficulty of work 15 Size of Job 15 Period of performance 15

DSCR

C&G Road Intersection

-- End of Section --

DSCR

C&G Road Intersection

W91236-14-D-0028-0011-01

SECTION 01 11 00.00 50

Factor Rate Weight Contractor's investment 05 Assistance by Government 05 Subcontracting 25

1.16.2 Value

Based on the circumstances of each procurement action, each of the above factors shall be weighted from .03 to .12 as indicated below. The value shall be obtained by multiplying the rate by the weight. The value column when totaled indicates the fair and reasonable profit percentage under the circumstances of the particular procurement.

1.16.2.1 Degree of Risk

Where the work involves no risk or the degree of risk is very small, the weighting should be .03; as the degree of risk increases, the weighting should be increased up to a maximum of .12. Lump sum items will have, generally, a higher weighted value than the unit price items for which quantities are provided. Other things to consider: the portion of the work to be done by subcontractors, nature of work, where work is to be performed, reasonableness of negotiated costs, amount of labor included in costs, and whether the negotiation is before or after performance of work.

1.16.2.2 Period of Performance

The period of performance shall be 120 days from the issuance of notice to proceed.

1.17 BLASTING

Blasting will not be permitted.

PART 2 PRODUCTS

Not Used.

PART 3 EXECUTION

Not used.

SECTION 01 30 00.20 50

ADMINISTRATIVE REQUIREMENTS

10/06

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only or as otherwise designated. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section

01 33 00.00 50 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Progress and completion pictures Electronic Mail (e-mail) Address

1.4 PROGRESS AND COMPLETION PICTURES

Provide monthly, and within one month of the completion of work, digital photographs, 1600x1200x24 bit true color minimum resolution in JPEG file format showing the sequence and progress of work. Take digital photographs prior to the seventh day of each month from a minimum of ten views from points located by the Contracting Officer. Submit a sketch or drawing indicating points of view. Submit with the monthly invoice two sets of digital photographs each set on a separate CD-R, cumulative of all photos to date. Cross reference submittals in the appropriate daily report.

1.5 SUPERVISION

Contractor shall have at least one qualified supervisor capable of reading, writing, and conversing fluently in the English language on the job site during working hours. In addition, if a Quality Control (QC) representative is required on the contract, then that individual shall also have fluent English communication skills.

1.7 AVAILABILITY OF CADD DRAWING FILES

After award and upon request, the electronic "Computer-Aided Drafting and Design (CADD)" drawing files will be made available to the Contractor for use in preparation of construction data related to the referenced contract subject to the following terms and conditions. Request specific drawing numbers of files required; the entire set of drawing files will not be provided.

Data contained on these electronic files shall not be used for any purpose other than as a convenience in the preparation of construction data for the referenced project. Any other use or reuse shall be at the sole risk of the Contractor and without liability or legal exposure to the Government.

The Contractor shall make no claim and waives to the fullest extent permitted by law, any claim or cause of action of any nature against the

DSCR

C&G Road Intersection

Government, its agents or sub consultants that may arise out of or in connection with the use of these electronic files. The Contractor shall, to the fullest extent permitted by law, indemnify and hold the Government harmless against all damages, liabilities or costs, including reasonable attorney's fees and defense costs, arising out of or resulting from the use of these electronic files.

These electronic CADD drawing files are not construction documents.

Differences may exist between the CADD files and the corresponding construction documents. The Government makes no representation regarding the accuracy or completeness of the electronic CADD files, nor does it make representation to the compatibility of these files with the Contractors hardware or software. In the event that a conflict arises between the signed and sealed construction documents prepared by the Government and the furnished CADD files, the signed and sealed construction documents shall govern. The Contractor is responsible for determining if any conflict exists. Use of these CADD files does not relieve the Contractor of duty to fully comply with the contract documents, including and without limitation, the need to check, confirm and coordinate the work of all contractors for the project.

If the Contractor uses, duplicates and/or modifies these electronic CADD files for use in producing construction data related to this contract, all previous indicia of ownership (seals, logos, signatures, initials and dates) shall be removed.

1.8 ELECTRONIC MAIL (E-MAIL) ADDRESS

The Contractor shall establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic attachments in Microsoft, Adobe Acrobat, and other similar formats. Within 10 days after contract award, the Contractor shall provide the Contracting Officer a single (only one) e-mail address for electronic communications from the Contracting Officer related to this contract including, but not limited to contract documents, invoice information, request for proposals, and other correspondence. The Contracting Officer may also use email to notify the Contractor of base access conditions when emergency conditions warrant, such as hurricanes, terrorist threats, etc. Multiple email address will not allowed.

It is the Contractor's responsibility to make timely distribution of all Contracting Officer initiated e-mail with its own organization including field office(s). The Contractor shall promptly notify the Contracting Officer, in writing, of any changes to this email address.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --

DSCR

C&G Road Intersection

SECTION 01 31 19.00 50

PROJECT MEETINGS

04/06

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only or as otherwise designated. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section

01 33 00.00 50 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

A Project Submittal Schedule shall be submitted in accordance with paragraph entitled, "Project Meetings," of this section.

The Contractor shall submit a Monthly Progress Report at the first meeting of each month.

1.1 PRECONSTRUCTION CONFERENCE

1.1.1 Scheduling

After award of the construction contract and prior to the start of any construction work, the Contracting Officer (CO) will schedule and conduct a preconstruction conference. The Contractor's Project Manager, Superintendent and Quality Control System Manager shall attend this meeting. The Contractor is encouraged to have an officer of his company (Project Manager could be this person) and representation from each of his sub-contractors at the conference. This conference will be held at a location and time as specified by the CO.

1.1.2 Purpose

The purpose of this preconstruction conference is to enable the CO to outline the procedures that will be followed by the Government in its administration of this construction contract and to discuss the performance that will be expected from the Contractor. This conference will allow the Contractor an opportunity to ask questions about the Government's supervision and inspection of contract work, about security requirements, regulations, etc. The CO may invite Using Service personnel and any other Government personnel to attend this conference.

1.1.3 Discussion Items

The following is a list of items for discussion during the preconstruction conference. However, the Contracting Officer may include additional items for discussion as conditions and the work require.

a. Authority of the Area/Resident Engineer and organization of the Area/Resident office.

DSCR

C&G Road Intersection

b. Contractor's Progress Schedule.

c. Correspondence Procedures.

d. Contractor Labor Standards Provisions.

e. Contract Modifications and Administrative Procedures.

f. Contractor's Administrative, Laydown and Storage Areas.

g. Procedures for Processing Submittals.

h. Payment Estimate Data and Procedures.

i. Contractor Utilities.

j. Security Requirements and Other Regulations, if applicable.

k. Government Furnished Equipment, if applicable.

l. Disposition of Salvage Property.

m. Contractor Insurance Requirements.

n. Value Engineering Program.

o. Contractor Performance Evaluation.

p. As-Built Drawings.

q. Single Point of Contact for Warranty of Construction.

r. Turnover of Completed Facilities.

1.2 PROJECT MEETINGS

The Contractor shall attend monthly project meetings scheduled by the Government. The Contractor's Superintendent shall attend scheduled project meetings. Subcontractor representatives shall also attend.

A Monthly Progress Report shall be submitted with the progress schedule, and shall address potential factors of delay, deficiencies, material delivery schedules, submittals, and safety issues.

A Project Submittal Schedule shall be submitted showing full coordination with the project schedule. All products and tests under each submittal number shall be prioritized and linked to the progress schedule.

1.3 OTHER MEETINGS

Other meetings are or may be scheduled to be held after the Preconstruction Conference, and such meetings may include the following:

a. Accident Prevention Safety Plan

b. Quality Control Plan.

DSCR

C&G Road Intersection

c. Environmental Protection Plan.

d. Warranty Management Plan (Post Construction Warranty Conference)

1.4 FACILITY MEETINGS

The Facility may also schedule meetings with the Contractor through the CO during the progress of construction work.

1.5 MINUTES OF MEETINGS

The Government will prepare minutes of the meeting and will provide the Contractor with a signed original for review and concurrence. The minutes shall include all items discussed at the meeting and the Government will make all corrections provided by the Contractor and resubmit the corrected minutes to the Contractor within seven days.

1.6 Warranty Management Plan

The Contractor shall provide a Warranty Management Plan, not less than 30 days prior to the Post-Construction Warranty Conference. As a minimum, include a table, showing the requirements, and attach certificates:

a. List of warranties provided.

b. List of equipment, names of manufacturers and suppliers and phone numbers.

c. Period of warranties and Start Date.

d. List of Extended Warranties.

e. Warranty Certificates.

f. Single Point of Contact for Warranty of Construction.

PART 2 PRODUCTS (This Part Not Used)

PART 3 EXECUTION (This Part Not Used)

-- End of Section --

DSCR

C&G Road Intersection

SECTION 01 32 01.00 50

PROJECT SCHEDULE

10/06

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

ER 1-1-11 (1995) Progress, Schedules, and Network Analysis Systems

1.2 QUALIFICATIONS

The Contractor shall designate an authorized representative who shall be responsible for the preparation of all required project schedule reports.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only or as otherwise designated. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section

01 33 00.00 50 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Qualifications

Standard Activity Coding Dictionary

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

Pursuant to the Contract Clause, SCHEDULE FOR CONSTRUCTION CONTRACTS, a Project Schedule as described below shall be prepared. The NAS Project Schedule shall be a composite schedule. The scheduling of construction shall be the responsibility of the Contractor. Contractor management personnel shall actively participate in its development. Subcontractors and suppliers working on the project shall also contribute in developing and maintaining an accurate Project Schedule. The approved Project Schedule shall be used to measure the progress of the work, to aid in evaluating time extensions, and to provide the basis of all progress payments. The Government will use the NAS Project Schedule to evaluate the

DSCR

C&G Road Intersection contractor's progress for timely completion, plan for Quality Assurance verification of the work and evaluate the effects of a proposed modification on the contract duration (critical path activities)

3.2 QUALIFICATIONS- CONTRACTOR SCHEDULING REPRESENTATIVE

The Contractor shall designate, a scheduling representative, the individual tasked with the responsibility for preparation-updating-revision of the NAS schedule who shall be responsible for the preparation and submittal of the entire NAS project schedule including all items specified below and revisions to the schedule or supplemental completion schedules, as applicable or directed by the Contracting Officer. The scheduling representative shall be approved by the Contracting Officer based on a resume indicating as a minimum, formal training from software vendor or 5 years experience in working with NAS schedules.

3.3 BASIS FOR PAYMENT

The schedule shall be the basis for measuring Contractor progress. Lack of an approved schedule or scheduling personnel will result in an inability of the Contracting Officer to evaluate Contractor's progress for the purposes of payment. Failure of the Contractor to provide all information, as specified below, shall result in the disapproval of the entire Project Schedule submission and the inability of the Contracting Officer to evaluate Contractor progress for payment purposes. In the case where Project Schedule revisions have been directed by the Contracting Officer and those revisions have not been included in the Project Schedule, the Contracting Officer may hold retainage up to the maximum allowed by contract, each payment period, until revisions to the Project Schedule have been made.

3.4 PROJECT SCHEDULE

The contractor shall prepare the NAS schedule using a computer software system. The system utilized by the Contractor shall be capable of satisfying all requirements of this specification and ER 1-1-11. Manual methods used to produce any required information shall require prior approval by the Contracting Officer. The Contracting Officer intends to use PRIMAVERA P3. Should the contractor utilize software that is different than that utilized by the Contracting Officer, based on the software utilized by the contractor for the preparation of the NAS schedule, the contractor shall provide a copy of the software and a license to the Administrative Contracting Officer at the Government field office. The Contractor shall submit a copy of the user's manual outlining the selected CPM computer program's mathematical analysis capabilities, details, functions and operation. The Contractor shall provide to the Government a complete input listing for the selected software.

3.4.1 Use of the Critical Path Method

The Critical Path Method (CPM) of network calculation shall be used to generate the Project Schedule. The Contractor shall provide the Project Schedule in the Precedence Diagram Method (PDM).

3.4.2 Level of Detail Required

The Project Schedule shall include an appropriate level of detail. Failure to develop or update the Project Schedule or provide data to the

DSCR

C&G Road Intersection

Contracting Officer at the appropriate level of detail, as specified by the Contracting Officer, shall result in the disapproval of the schedule. The Contracting Officer will use, but is not limited to, the following conditions to determine the appropriate level of detail to be used in the Project Schedule:

3.4.2.1 Activity Durations

Contractor submissions shall follow the direction of the Contracting Officer regarding reasonable activity durations. Durations shall be in work days.

3.4.2.2 Responsibility

All activities shall be identified in the project schedule by the party responsible to perform the work. Responsibility includes, but is not limited to, the subcontracting firm, contractor work force, or government agency performing a given task. Activities shall not belong to more than one responsible party. The responsible party for each activity shall be identified by the Responsibility Code.

3.4.2.3 Work Areas

All activities shall be identified in the project…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it.