W911XK22B0002 0001.pdf
PDF 373 KB Posted
- Attached to
- FY22 Duluth Superior Harbor Maintenance Dredging Federal contract opportunity
- Solicitation number
- W911XK22B0002
About this file
This document provides details on a federal solicitation for dredging services in Duluth, Minnesota. The U.S. Army Corps of Engineers Detroit District seeks a contractor to mobilize equipment to the Duluth-Superior Harbor, dredge between specified limits, place dredged material in designated areas, conduct required surveys, and perform maintenance work and clean-up at the Erie Pier confined disposal facility. The solicitation includes required base work and four option items. Interested small businesses must be registered in the System for Award Management and able to complete all work by November 1, 2022. The estimated value ranges from $1-5 million. This is a 100% small business set-aside conducted under NAICS code 237990.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bid Abstract W911XK22B0002 (1) (003).pdf | ||
| FY22 Duluth-Superior MD Certified Final RTA Specs.pdf | ||
| W911XK22B0002.pdf | ||
| FY22 Duluth-Superior MD Certified Final RTA Plans.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Solicitation No. W911XK22B0002 for FY22 Duluth-Superior Harbor Maintenance Dredging is amended to update sections of the specif ications and provide responses to the Requests for Information (RFI). Please see follow ing pages for details.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 20-Apr-2022
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W911XK22B0002
X 9B. DATED (SEE ITEM 11)
04-Apr-2022
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
20-Apr-2022
CODE
U.S.ARMY ENGINEER DISTRICT, DETROIT
477 MICHIGAN AVENUE, 7TH FLOOR
DETROIT MI 48226-4523
W911XK 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W911XK22B0002
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00 10 00 - SOLICITATION
The following have been added by full text:
AMENDMENT 0001
SUMMARY OF CHANGES
Amendment 0001
CHANGES TO SOLICITATION W911XK22B0002
A. Delete paragraph titled “Interim Completion Date:” in ADDENDUM 52.211-10 ALT I. Add revised paragraph titled “Interim Completion Date:” in ADDENDUM 52.211-10 ALT I with the below language.
“Required and option dredging, dredged material placement, seed inoculation/broadcasting, and 40th Avenue West Elevation Surveys are to be completed, inspected, and accepted by the Government no later than 1 November 2022.”
CHANGES TO PLANS:
None
CHANGES TO SPECIFICATIONS:
B. Delete paragraph titled “1.6.2 Construction Schedule” in 01 35 13 SPECIAL PROJECT PROCEDURES.
Add revised paragraph titled “1.6.2 Construction Schedule” in 01 35 13 SPECIAL PROJECT PROCEDURES with the below language.
“Required and option dredging, dredged material placement, seed inoculation/broadcasting, and 40th Avenue West Elevation Surveys must be completed, inspected, and accepted by the Government no later than 1 November 2022.
All other required and option work at Erie Pier CDF (required earthwork and option mowing and brush clearing) must be completed by the completion date indicated in FAR clause 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) – ALTERNATE 1 (APR 1984).”
C. Delete paragraph titled “3.4.2 CQC System Manager” in 01 45 00.00 10 QUALITY CONTROL.
Add revised paragraph titled “3.4.2 CQC System Manager” in 01 45 00.00 10 QUALITY CONTROL with the below language. “Identify as CQC System Manager an individual within the onsite work organization that is responsible for overall management of CQC and has the authority to act in all CQC matters for the Contractor. The CQC System Manager is required to be a construction person with a minimum of 5 years of dredging experience and a minimum of 2 years as a dredging CQCSM to oversee dredging and dredged material placement operations. The CQC System Manager is required to be a construction person with a minimum of 5 years of construction experience and a minimum of 2 years as a construction CQCSM to oversee earthwork and brush clearing and mowing operations at the Erie Pier CDF. This CQC System Manager is on the site at all times during construction and is employed by the prime Contractor. The CQC System Manager is assigned as CQC System Manager but may have other duties in addition to quality control. Identify in the plan an alternate to serve in the event of the CQC System Manager's absence. The requirements for the alternate are the same as the CQC System Manager.”
(End of Summary of Changes)
W911XK22B0002
File details come from the government source that posted it. Updated .