Attachment_1_-_Technical_Specifications.pdf

PDF 1 MB Posted

Attached to
Dashields L/D Guidewall Stabilization Federal contract opportunity
Solicitation number
W911WN-16-B-8006
Issued by
Department of the Army Corps of Engineers Engineering District Pittsburgh

About this file

Attachment 1 - Technical Specifications

View the file

Other files for this federal contract opportunity

Other files attached to Dashields L/D Guidewall Stabilization, newest first.
File Type Posted
Bid_Opening_Attendance_Register.pdf PDF
BidResults_16-B-8006.pdf PDF
W911WN-16-B-8006-0002.pdf PDF
LDAO_420_S-5095-A.pdf PDF
GF_LDAO_100_S-0063-A.pdf PDF
LDAO_420_S-3093-A.pdf PDF
W911WN-16-B-8006-0001.pdf PDF
LDAO_100_G-0031-A.pdf PDF
W911WN-16-B-8006.pdf PDF
Attachment_2_Drawings.pdf PDF
Attachment_3_-_Wage_Determination_PA4_7.1.16.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W911WN-16-B-8006

Guide Wall Stabilization

Dashields Locks and Dam, Ohio River Allegheny County Pennsylvania

Certified Final Documents – RTA W911WN-16-B-8006 Technical Specifications

June 2016

Upper and Lower Guide Wall Stabilization Dashields Locks and Dam

PROJECT TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 22 00.00 10 MEASUREMENT AND PAYMENT

01 32 01.00 10 PROJECT SCHEDULE

01 32 23.00 08 SURVEY AND ALIGNMENT CONTROL

01 32 33 DIGITAL PROGRESS IMAGES

01 33 00 SUBMITTAL PROCEDURES

01 35 00.00 08 SPECIAL PROCEDURES

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 01.00 08 USACE QUALITY CONTROL

01 45 01.10 USACE QUALITY CONTROL SYSTEM (QCS)

01 50 10 PROJECT AND SAFETY SIGNS

01 57 20.00 10 ENVIRONMENTAL PROTECTION

01 57 23.00 10 STORMWATER POLLUTION PREVENTION MEASURES

01 78 02.00 15 CLOSEOUT SUBMITTALS (AS-BUILT DRAWINGS)

DIVISION 02 - EXISTING CONDITIONS

02 22 13 VIBRATION MONITORING REQUIREMENTS FOR EXISTING STRUCTURES

02 42 00.00 08 DISPOSAL OF MATERIALS

DIVISION 03 - CONCRETE

03 01 32 CONCRETE REHABILITATION FOR CIVIL WORKS

03 11 14.00 10 FORMWORK FOR CONCRETE

03 15 00.00 10 CONCRETE ACCESSORIES

03 20 00.00 10 CONCRETE REINFORCING

03 31 01.00 10 CAST-IN-PLACE STRUCTURAL CONCRETE FOR CIVIL WORKS

DIVISION 05 - METALS

05 50 14 STRUCTURAL METAL FABRICATIONS

05 50 15 CIVIL WORKS FABRICATIONS

DIVISION 09 - FINISHES

09 97 02 PAINTING: HYDRAULIC STRUCTURES

DIVISION 13 - SPECIAL CONSTRUCTION

13 50 00 INSTRUMENTATION (INCLINOMETER CASING)

DIVISION 31 - EARTHWORK

31 00 00 EARTHWORK

31 05 22 GEOTEXTILES FABRICS

31 11 00 CLEARING AND GRUBBING

31 41 16 METAL SHEET PILING

31 62 16.16 STEEL PIPE PILES

31 68 13 PERMANENT ROCK ANCHORS

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 31 13 CHAIN LINK FENCES AND GATES

32 92 19 SEEDING

PROJECT TABLE OF CONTENTS Page 1 Certified Final Technical Specifications - RTA W911WN-16-B-8006

DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION

35 31 19 STONE PROTECTION

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 2

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 22 00.00 10

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 REFERENCES

1.2 JOB PAYMENT ITEMS

1.2.1 Reimbursement For Actual Performance And Payment Bond Premiums

1.2.2 Mobilization and Demobilization

1.2.2.1 Payment

1.2.2.2 Unit of Measure

1.2.2.3 Payment Item

1.2.3 Erosion and Sediment Controls

1.2.3.1 Payment

1.2.3.2 Unit of Measure

1.2.3.3 Payment Item

1.2.4 Adjustment to Guard Fence and Related Items on Guide Walls

1.2.4.1 Payment

1.2.4.2 Unit of Measure

1.2.4.3 Payment Items

1.2.5 Remove and Reinstall of Stone Protection at Lower Guide Wall

1.2.5.1 Payment

1.2.5.2 Unit of Measure

1.2.5.3 Payment Item

1.2.6 Clearing and Grubbing

1.2.6.1 Payment

1.2.6.2 Unit of Measure

1.2.6.3 Payment Item

1.2.7 Remove and Reinstall Mooring Piles

1.2.7.1 Payment

1.2.7.2 Unit of Measure

1.2.7.3 Payment Items

1.2.8 Seeding

1.2.8.1 Payment

1.2.8.2 Unit of Measure

1.2.8.3 Payment Item

1.2.9 Inclinometer Casings

1.2.9.1 Payment

1.2.9.2 Unit of Measure

1.2.9.3 Payment Items

1.3 UNIT PRICE PAYMENT ITEMS

1.3.1 Digital Progress Images

1.3.1.1 Payment

1.3.1.2 Measurement

1.3.1.3 Unit of Measure

1.3.1.4 Payment Item

1.3.2 Remove and Reinstall Security Fence

1.3.2.1 Payment

1.3.2.2 Measurement

1.3.2.3 Unit of Measure

1.3.2.4 Payment Items

SECTION 01 22 00.00 10 Page 1

1.3.3 Earthwork

1.3.3.1 Payment

1.3.3.2 Measurement

1.3.3.3 Unit of Measure

1.3.3.4 Payment Items

1.3.4 Concrete Removal

1.3.4.1 Payment

1.3.4.2 Measurement

1.3.4.3 Unit of Measure

1.3.4.4 Payment Item

1.3.5 Concrete

1.3.5.1 Payment

1.3.5.2 Measurement

1.3.5.3 Unit of Measure

1.3.5.4 Payment Item

1.3.6 Concrete Reinforcing

1.3.6.1 Payment

1.3.6.2 Measurement

1.3.6.3 Unit of Measure

1.3.6.4 Payment Item

1.3.7 Drilling and Grouting for Dowels and Anchors

1.3.7.1 Payment

1.3.7.2 Measurement

1.3.7.3 Unit of Measure

1.3.7.4 Payment Item

1.3.8 Holes for Rock Anchors

1.3.8.1 Payment

1.3.8.2 Measurement

1.3.8.3 Unit of Measure

1.3.8.4 Payment Items

1.3.9 Grouting Holes Which Fail Watertightness Test

1.3.9.1 Payment

1.3.9.2 Measurement

1.3.9.3 Unit of Measure

1.3.9.4 Payment Item

1.3.10 Testing of Rock Anchors

1.3.10.1 Payment

1.3.10.2 Measurement

1.3.10.3 Unit of Measure

1.3.10.4 Payment Items

1.3.11 Permanent Rock Anchors

1.3.11.1 Payment

1.3.11.2 Measurement

1.3.11.3 Unit of Measure

1.3.11.4 Payment Item

1.3.12 Furnishing and Installing Sheet Piling and Pipe Pile

1.3.12.1 Payment

1.3.12.2 Measurement

1.3.12.3 Unit of Measure

1.3.12.4 Payment Item

1.3.13 Furnishing New Sheet Piling for Upper Guide Wall Arches

1.3.13.1 Payment

1.3.13.2 Measurement

1.3.13.3 Unit of Measure

1.3.13.4 Payment Item

1.3.14 Removal of Existing Steel Sheet Piling

1.3.14.1 Payment

1.3.14.2 Measurement

1.3.14.3 Unit of Measure

SECTION 01 22 00.00 10 Page 2

1.3.14.4 Payment Item

1.3.15 Guard Fence at Upper Guide Wall Sheet Pile Wall

1.3.15.1 Payment

1.3.15.2 Measurement

1.3.15.3 Unit of Measure

1.3.15.4 Payment Items

1.3.16 Geotextile

1.3.16.1 Payment

1.3.16.2 Measurement

1.3.16.3 Unit of Measure

1.3.16.4 Payment Item

1.3.17 Stone Protection

1.3.17.1 Payment

1.3.17.2 Measurement

1.3.17.3 Unit of Measure

1.3.17.4 Payment Item

1.3.18 Walkway

1.3.18.1 Payment

1.3.18.2 Measurement

1.3.18.3 Unit of Measure

1.3.18.4 Payment Item

-- End of Section Table of Contents --

SECTION 01 22 00.00 10 Page 3

SECTION 01 22 00.00 10

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN INSTITUTE OF STEEL CONSTRUCTION (AISC)

AISC 303 (2010) Code of Standard Practice for Steel Buildings and Bridges

1.2 JOB PAYMENT ITEMS

Payment items for the work of this contract for which contract job payments will be made are listed in the BIDDING SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, shall be included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.

1.2.1 Reimbursement For Actual Performance And Payment Bond Premiums

Payment for reimbursement for actual performance and payment bond premiums will be made as specified in 00800 SPECIAL CONTRACT REQUIREMENTS, clause

PAYMENT FOR PERFORMANCE AND PAYMENT BONDS.

0001 REIMBURSEMENT FOR ACTUAL PERFORMANCE AND PAYMENT BOND PREMIUMS,

BASE CONTRACT

1001 REIMBURSEMENT FOR ACTUAL PERFORMANCE AND PAYMENT BOND PREMIUMS,

AWARDABLE OPTION

1.2.2 Mobilization and Demobilization

1.2.2.1 Payment

Payment for this item shall constitute full compensation for all labor, equipment, material, and supply costs to move machinery, tools, and supplies onto the project site, including any special facilities required to provide equipment access to the work areas, and to remove such items from Government property at the close of the project. Mobilization will be paid at 60% of the job and 40% for demobilization.

SECTION 01 22 00.00 10 Page 4

1.2.2.2 Unit of Measure

Unit of measure: Job

1.2.2.3 Payment Item

0002 MOBILIZATION AND DEMOBILIZATION

1.2.3 Erosion and Sediment Controls

1.2.3.1 Payment

This work is specified in Section 01 57 23.00 10 STORM WATER POLLUTION PREVENTION MEASURES. Payment will be made for costs associated with furnishing, installing, maintaining and removing sediment and erosion controls measures. The Job price shall include, but not limited to, all run-on and run-off controls including compost socks, filter bags, rock construction entrances, turbidity curtain, rock filters, dewatering, dust control, etc; as shown on the drawings or as defined in the Erosion and Sediment Control Plan. Price shall include all materials, labor, equipment, and supplies as required by the specifications, Contract Drawings, Erosion and Sediment Control plan, and all applicable regulatory authorities.

1.2.3.2 Unit of Measure

Unit of measure: Job.

1.2.3.3 Payment Item

0004 EROSION AND SEDIMENT CONTROLS

1.2.4 Adjustment to Guard Fence and Related Items on Guide Walls

1.2.4.1 Payment

This work is specified in and Section 05 50 15 CIVIL WORKS FABRICATIONS.

Payment will be made for costs associated with operations necessary for the removal of existing guard fence and 4' high chain link fence and installing new guard fence at the downstream end of the Lower Guide Wall and removal of existing guard fence and installing new guard fence at the upstream end of the Upper Guide Wall, including but not limited to installation of new guard fence posts and 2-strand wire guard fence, and all miscellaneous metal work incidental to guard fence installation. Price shall include all materials, labor, equipment, and supplies associated with this work.

1.2.4.2 Unit of Measure

Unit of measure: Job

1.2.4.3 Payment Items

0007 ADJUSTMENTS TO GUARD FENCE AND RELATED ITEMS AT LOWER GUIDE WALL

0030 ADJUSTMENTS TO GUARD FENCE AT UPPER GUIDE WALL

SECTION 01 22 00.00 10 Page 5

1.2.5 Remove and Reinstall of Stone Protection at Lower Guide Wall

1.2.5.1 Payment

This work is specified in Section 31 00 00 EARTHWORK and Section 35 31 19 STONE, CHANNEL, SHORELINE/COASTAL PROTECTION FOR STRUCTURES. Payment will be made for costs associated with the excavation of derrick stone/riprap see Reference Drawing O-LDA-68/7.2), stockpiling stone within construction work limits, and re-installation or disposal, as applicable, of the stone protection at downstream slope as shown in the contract drawings. Price shall include all materials, labor, equipment, and supplies associated with this work.

1.2.5.2 Unit of Measure

Unit of measure: Job

1.2.5.3 Payment Item

0008 REMOVE AND REINSTALL STONE PROTECTION AT DOWNSTREAM SLOPE

1.2.6 Clearing and Grubbing

1.2.6.1 Payment

This work is specified in Section 31 11 00 CLEARING AND GRUBBING; and Section 02 42 00.00 08 DISPOSAL OF MATERIALS. Payment will be made for costs associated with clearing, removal, and disposal of all debris (woody debris, bushes, trees, stumps, etc.) encountered within the limits shown on the drawings. Price shall include all materials, labor, equipment, and supplies associated with this work.

1.2.6.2 Unit of Measure

Unit of measure: Job

1.2.6.3 Payment Item

0024 CLEARING AND GRUBBING

1.2.7 Remove and Reinstall Mooring Piles

1.2.7.1 Payment

Payment will be made for costs associated with operations necessary for the removal the existing mooring piles at the boat slip behind the Upper Guide Wall and reinstallation after completion of the new pile wall and excavation at the Upper Guide Wall. Price shall include all materials, labor, equipment, and supplies associated with removing and reinstalling the piles.

1.2.7.2 Unit of Measure

Unit of measure: Job

1.2.7.3 Payment Items

0038 REMOVE AND REINSTALL MOORING PILES, UPPER GUIDE WALL BOAT SLIP

SECTION 01 22 00.00 10 Page 6

1.2.8 Seeding

1.2.8.1 Payment

This work is specified in Section 32 92 19 SEEDING. Payment will be made for costs associated with furnishing acceptable topsoil (if not stockpiled onsite), preparation of indicated areas, placement of topsoil to the required depth, mixing in indicated soil supplements and seeding of all disturbed areas. Price shall include all materials, labor, equipment, and supplies associated with this work.

1.2.8.2 Unit of Measure

Unit of measure: Job

1.2.8.3 Payment Item

0044 SEEDING

1.2.9 Inclinometer Casings

1.2.9.1 Payment

Payment will be made for costs associated with installation of inclinometer casings at the Upper Guide Wall as specified. The price shall include all materials, labor, equipment, and supplies associated with drilling and furnishing and installing the two inclinometer casings.

1.2.9.2 Unit of Measure

Unit of measure: Job

1.2.9.3 Payment Items

0045 INCLINOMETER CASINGS, UPPER GUIDE WALL

1.3 UNIT PRICE PAYMENT ITEMS

Payment items for the work of this contract on which the contract unit price payments will be made are listed in the BIDDING SCHEDULE and described below. The unit price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each of the unit price items.

1.3.1 Digital Progress Images

1.3.1.1 Payment

This work is specified in Section 01 32 33 DIGITAL PROGRESS IMAGES.

Payment will be made for costs associated with furnishing monthly digital progress images, as specified. Each set shall consist of all specified hard copies and electronic copies of each photographic session as specified. Price shall include all materials, labor, equipment, and supplies associated with this work.

SECTION 01 22 00.00 10 Page 7

1.3.1.2 Measurement

Measurement will be made of the number of sets of photographs taken and delivered to the Contracting Officer as approved or directed by the Contracting Officer or authorized representative. Each set shall consist of all specified hard copies and electronic copies of each photographic session as specified.

1.3.1.3 Unit of Measure

Unit of measure: Sets

1.3.1.4 Payment Item

0003 DIGITAL PROGRESS IMAGES

1.3.2 Remove and Reinstall Security Fence

1.3.2.1 Payment

This work is specified in and Section 32 31 13 CHAIN LINK FENCES AND GATES. Payment will be made for costs associated with operations necessary for the removal and reinstallation of the security fence, including but not limited to installation of new fence, new anchor bolts, hardware, new fence posts and rails, fabric and barbed wire as required, and all miscellaneous metal work incidental to fence installation. Price shall include all materials, labor, equipment, and supplies associated with this work.

The item REMOVE SECURITY FENCE, LOWER GUIDE WALL shall includes removing the existing fence as shown on the contract drawings, and disposal of removed materials.

The item NEW SECURITY FENCE, LOWER GUIDE WALL shall includes installing new 8' chain link fence and posts, as shown on the contract drawings. The item also include installing a new overhang section, new 4' high chain link fence, and connection to the existing chain link fence.

The item REMOVE SECURITY FENCE, UPPER GUIDE WALL includes removing the existing chain link fence disposal of removed materials.

The item REMOVE VEHICLE AND PERSONNEL GATES, UPPER GUIDE WALL includes removing the existing chain link fence disposal of removed materials.

The item NEW SECURITY FENCE, UPPER GUIDE WALL includes new 8' chain link fence and posts, as shown on the contract drawings. The item also include installing a new overhang section and connection to the existing chain link fence.

1.3.2.2 Measurement

Measurement of removal of fence will be made by the linear foot of fence removed, including gates where applicable. Measurement of installation of new fence will be made by linear feet of fence installed, including line and corner posts. Measurement of new fence gates will be made by the number of each type of gate installed.

1.3.2.3 Unit of Measure

Unit of measure: Linear Feet, Each

SECTION 01 22 00.00 10 Page 8

1.3.2.4 Payment Items

0005 REMOVE SECURITY FENCE, LOWER GUIDE WALL

0006 NEW SECURITY FENCE, LOWER GUIDE WALL

0025 REMOVE SECURITY FENCE, UPPER GUIDE WALL

0026 REMOVE VEHICLE AND PERSONNEL GATES, UPPER GUIDE WALL

0027 NEW SECURITY FENCE, UPPER GUIDE WALL

0028 NEW 12' DOUBLE SWING VEHICLE GATE, UPPER GUIDE WALL

0029 NEW 3' PERSONNEL GATE, UPPER GUIDE WALL

1.3.3 Earthwork

1.3.3.1 Payment

This work is specified in Section 31 00 00 EARTHWORK and Section 02 42 00.00 08 DISPOSAL OF MATERIALS. Payment will be made for costs associated with required common excavation, shoring, and disposal of excess and unsuitable material as specified and as shown in the contract drawings. Price shall include all materials, labor, equipment, and supplies associated with this work.

1.3.3.2 Measurement

Measurement of quantities will be made for the actual volume of common excavation completed within the limits, lines and grades shown on the contract drawings. No allowance will be made for overdepth excavation of for the removal of any material outside the required lines unless authorized by the Contracting Officer. The volume of material removed shall be determined by the average-end-area method, based on cross sections taken by field survey prior to and after completion of common excavation, or other method approved by the Contracting Officer. The cross section surveys shall be obtained by the Contracting Officer at a maximum 50-foot interval over the length of the excavated area prior to and after excavation to determine the actual amount of material removed. Volume computations shall be performed by the Contractor, and copies of all cross section data and computations shall be submitted to the Contracting Officer within 48 hours following completion of the field cross sections.

1.3.3.3 Unit of Measure

Unit of measure: cubic yard

1.3.3.4 Payment Items

0009 EXCAVATION, LOWER GUIDE WALL

0031 EXCAVATION, UPPER GUIDE WALL

1.3.4 Concrete Removal

1.3.4.1 Payment

This work is specified in Section 03 01 32 CONCRETE REHABILITATION FOR CIVIL WORKS. Payment will be made for costs associated with milling the back face of the Lower Guide Wall, which includes preparatory work, removal of concrete and embedded items, and disposal of concrete debris and unsuitable material. No payment will be made for milling outside the specified area of work. Price shall include all materials, labor, equipment, and supplies associated with this work.

SECTION 01 22 00.00 10 Page 9

1.3.4.2 Measurement

Concrete removal will be measured for payment based upon the actual volume of concrete removed within the pay lines as indicated on the drawings. No measurement will be made of concrete removal outside the pay lines shown which is incidental to the indicated removal unless such removal is specifically authorized by the Contracting Officer. No deductions will be made for rounded or beveled edges or for voids or embedded items that are either less than five cubic feet in volume or one square foot in cross section.

a. Remove concrete to the lines of removal indicated on the contract drawings. A tolerance of plus or minus 1 inch will be allowed about the lines indicated. Concrete removals that vary by more than the indicated tolerance will be acceptable, unless evidence indicates that deteriorated concrete is still present or the variation in tolerance results in a violation of the requirements for material placement, in which case removal shall continue to the lines indicated. Additional concrete removal beyond the allowable tolerance will be acceptable when deteriorated concrete is found as determined in accordance with Section 03 01 32 CONCRETE REHABILITATION FOR CIVIL WORKS, and the limits of such removal are set and approved by the Contracting Officer.

Unauthorized concrete removals in excess of 1 inch beyond the lines shown will not be acceptable, and repair of such excess area shall be performed by the Contractor to the satisfaction of the Contracting Officer and at no additional cost to the Government.

b. Determine the volume of vertical concrete removal from cross sections made prior to and after removal. Make cross sections from surveyed measurements on a 5 by 5 foot grid system, unless otherwise specified by the Contracting Officer. Take initial survey of the existing surface prior to removal, and take final surveys on the same control stations. Calculate volumes by the average-end-area method using the cross sections surveyed, unless otherwise specified. For areas of vertical concrete removal which are not readily accessible for survey, determine the volume of concrete from the neat lines of concrete removal as shown on the contract drawings, with the approval of the Contracting Officer,. Do not include any volume of concrete removal made beyond the allowable tolerances specified.

1.3.4.3 Unit of Measure

Unit of measure: cubic yards

1.3.4.4 Payment Item

0010 CONCRETE REMOVAL, LOWER GUIDE WALL

1002 CONCRETE REMOVAL,UPPER GUIDE WALL WALKWAY

1.3.5 Concrete

1.3.5.1 Payment

This work is specified in Section 03 31 01.00 101 CAST-IN-PLACE STRUCTURAL CONCRETE FOR CIVIL WORKS, Section 03 15 00.00 10 CONCRETE ACCESSORIES, Section 03 31 01.00 10 CAST-IN-PLACE STRUCTURAL CONCRETE FOR CIVIL WORK.

Payment will be made for costs associated with the installation complete and in place of concrete, as shown on the contract drawings. Payment shall

SECTION 01 22 00.00 10 Page 10 include, but not be limited to, tools, transportation, sheeting, bracing, shoring, formwork, ready-mix concrete, aggregate, additives, surface preparation, bonding agents, curing provisions and all other appurtenances and incidentals to concrete placement. Price shall include all materials, labor, equipment, and supplies associated with this work. Payment for concrete shall also include the new corner protection and painting new stripes on the Lower Guide Wall.

1.3.5.2 Measurement

Measurement for payment shall be based upon the actual volume of concrete placed within the limits as shown on the contract drawings and as accepted by the Contracting Officer. Measurement will be made by average end area method or other method approved by the Contracting Officer between the approved removal surface and the finished line shown on the contract drawings.

1.3.5.3 Unit of Measure

Unit of measure: cubic yard

1.3.5.4 Payment Item

0011 CAST-IN-PLACE STRUCTURAL CONCRETE, LOWER GUIDE WALL

1.3.6 Concrete Reinforcing

1.3.6.1 Payment

This work is specified in Section 03 20 00.00 10 CONCRETE REINFORCING.

Payment will be made for costs associated with furnishing, transporting, delivering and placing reinforcing steel bars/dowels, including all splices and couplers required, as indicated on the contract drawings. These dowels will be placed within existing concrete and within the new concrete. Price shall include all materials, labor, equipment, and supplies associated with this work.

1.3.6.2 Measurement

Measurement for payment shall be by the actual weight of reinforcing steel/dowels acceptably installed per approved shop drawings. All measurements for payment shall be made by or in presence of the Contracting Officer.

1.3.6.3 Unit of Measure

Unit of measure: pound

1.3.6.4 Payment Item

0012 REINFORCING STEEL, LOWER GUIDE WALL

1.3.7 Drilling and Grouting for Dowels and Anchors

1.3.7.1 Payment

This work is specified in Section 03 20 00.00 10 CONCRETE REINFORCING.

Payment will be made for costs associated with drilling and grouting of holes for steel dowels and bars as indicated on the contract drawings.

SECTION 01 22 00.00 10 Page 11

Price shall include all materials, except reinforcing steel, dowels, and anchor bolts which will be paid for under Concrete Reinforcing, labor, equipment, and supplies associated with this work. Payment for dowels and reinforcing steel for the Lower Guide Wall will be made at the contract unit price for REINFORCING STEEL, LOWER GUIDE WALL. Payment for DRILL AND INSTALL ANCHORS, UPPER GUIDE WALL shall include the cost of the anchors.

No separate payment will be made for drilling for anchor bolts for chain link fence post attachment, and all cost in connection therewith shall be included in the applicable unit price for chain link fence installation.

1.3.7.2 Measurement

Measurement of drilling holes and grouting dowels and anchors will be made by the linear foot of hole actually drilled and grouted to the depth indicated. Measurement will be made from the surface of the concrete after removal or surface preparation and will be made to the nearest inch. No payment will be made for holes improperly drilled or grouted nor for repairs required due to damage caused by the drilling and grouting operations.

1.3.7.3 Unit of Measure

Unit of measure: linear foot

1.3.7.4 Payment Item

0013 DRILLING AND GROUTING DOWELS AND REINFORCING STEEL, LOWER GUIDE

WALL

1003 DRILL AND INSTALL ANCHORS, UPPER GUIDE WALL WALKWAY

1.3.8 Holes for Rock Anchors

1.3.8.1 Payment

This work is specified in Section 31 68 13 PERMANENT ROCK ANCHORS. Payment will be made for costs associated with drilling or forming holes in concrete and drilling holes in soil and rock for rock anchors, including costs for guide templates; casings; disposal of cored material; performing measurements for payment; all advanced planning and engineering; and all other incidental costs in connection with these aspects of the work under this contract. Payment for drilling in concrete shall include cored starter/pilot holes if required. Payment for drilling holes in concrete will not be made for advancing the drill through casing previously placed during construction of the concrete wedge, if applicable.

Payment will be made for installing casing in new concrete, or drilling though the new concrete if casing is not installed, will be made as specified for ROCK ANCHORS, HOLES IN EXISTING CONCRETE. Payment for drilling through existing concrete will be made as specified for ROCK

ANCHORS, DRILLING HOLES IN EXISTING CONCRETE.

1.3.8.2 Measurement

Drilling or forming holes in concrete and drilling holes in soil, and rock for rock anchors will be measured for payment to the nearest foot of each type of material encountered, based upon the linear feet of hole actually formed or drilled in concrete, soil, and rock and redrilling grouted holes in accordance with the specifications. No measurement will be made for advancing the drill through previously placed casing.

SECTION 01 22 00.00 10 Page 12

1.3.8.3 Unit of Measure

Unit of measure: linear foot

1.3.8.4 Payment Items

0014 ROCK ANCHORS, HOLES IN NEW CONCRETE

0015 ROCK ANCHORS, DRILLING HOLES IN EXISTING CONCRETE

0016 ROCK ANCHORS, DRILLING AND CASING HOLES IN SOIL

0017 ROCK ANCHORS, DRILLING HOLES IN ROCK

0019 ROCK ANCHORS, REDRILLING GROUTED HOLES

1.3.9 Grouting Holes Which Fail Watertightness Test

1.3.9.1 Payment

This work is specified in Section 31 68 13 PERMANENT ROCK ANCHORS. Payment will be made for costs associated with furnishing, handling, transporting and storing of grout materials, and for furnishing all labor and supplies incidental to the work. The costs shall also include the costs of all material and labor for grouting holes which fail the watertightness test.

1.3.9.2 Measurement

Measurement for payment will be made for the actual length of hole grouted in-place.

1.3.9.3 Unit of Measure

Unit of measure: linear foot

1.3.9.4 Payment Item

0018 ROCK ANCHORS, GROUTING OF HOLES WHICH FAIL WATERTIGHTNESS TEST

1.3.10 Testing of Rock Anchors

1.3.10.1 Payment

This work is specified in 31 68 13 PERMANENT ROCK ANCHORS. Payment will be made for costs associated with performing watertightness tests, performance tests, and proof tests on permanent rock anchors.

1.3.10.2 Measurement

Testing will be measured for payment based upon the number of tests actually performed in accordance with the specifications or as directed by the Contracting Officer

1.3.10.3 Unit of Measure

Unit of measure: each.

1.3.10.4 Payment Items

0020 ROCK ANCHORS, WATERTIGHTNESS TESTS

0022 ROCK ANCHORS, PERFORMANCE TESTS

0023 ROCK ANCHORS, PROOF TESTS

SECTION 01 22 00.00 10 Page 13

1.3.11 Permanent Rock Anchors

1.3.11.1 Payment

This work is specified in Section 31 68 13 PERMANENT ROCK ANCHORS. Payment will be made for all costs associated with furnishing and installing permanent rock anchors complete, including splices and couplers, with permanent casing and anchor head components, in accordance with the contract drawings. These costs shall also include the cost of all materials and labor for grouting the annular space between the rock anchor permanent casing and the drilled hole. In addition, the costs shall include all costs for material and labor to place the final grout for the anchors, and all evaluations required by the Contractor's rock anchor engineer. No payment will be made for anchors which do not meet the acceptance criteria.

1.3.11.2 Measurement

Rock anchors will be measured for payment for the number of anchors actually installed in accordance with the specifications.

1.3.11.3 Unit of Measure

Unit of measure: Each

1.3.11.4 Payment Item

0021 FURNISH AND INSTALL PERMANENT ROCK ANCHORS

1.3.12 Furnishing and Installing Sheet Piling and Pipe Pile

1.3.12.1 Payment

Payment for sheet piling quantities will be made at the applicable contract price per linear foot for furnished and installed sheet piling. Payment will cover all cost of furnishing, handling, storing and installing piling including placing, driving, cutting holes and other materials and work incident thereto except the cost of furnishing piling will not be included in the contract price for driving piling removed under this contract.

Payment shall also include all costs for painting piling, where applicable, and for cutting off top of piling at the specified elevation. Payment for the pile wall cap shall include all costs of furnishing, installing, and painting the modified beam pile cap. Payment for installing sheet piling at the Upper Guide Wall arches shall include all costs associated with driving the piling removed from the boat slip and new piling furnished under this contract.

1.3.12.2 Measurement

Measurements shall be the actual linear feet of piling installed between the cutoff elevation shown on the drawings and the tip actual tip elevation as approved by the Contracting Officer. Pile length provided over the required length for ease of installation are the responsibility of the Contractor. No separate measurement or payment will be made for pile cutoffs or splices. The Contracting Officer shall approve all methods and procedures for quantity surveys. Measurement of the pile cap at the Upper Guide Wall will be the actual length of pile cap installed as approved by the Contracting Officer.

SECTION 01 22 00.00 10 Page 14

1.3.12.3 Unit of Measure

Unit of measure: linear foot.

1.3.12.4 Payment Item

0032 FURNISH AND INSTALL AZ44-700N PILING, UPPER GUIDE WALL

0033 FURNISH AND INSTALL FABRICATED PIPE PILE, UPPER GUIDE WALL

0034 AZ44 PILE WALL CAP, UPPER GUIDE WALL

0040 INSTALL SHEET PILING AT UPPER GUIDE WALL ARCHES

1.3.13 Furnishing New Sheet Piling for Upper Guide Wall Arches

1.3.13.1 Payment

Payment for sheet piling quantities will be made at the applicable contract price per linear foot for installed sheet piling. Payment will cover all cost of furnishing, handling, and storing piling. Payment for installing the new sheet piling at the Upper Guide Wall arches will be made as specified for INSTALL SHEET PILING AT UPPER GUIDE WALL ARCHES.

1.3.13.2 Measurement

Measurements shall be the actual linear feet of piling installed between the cutoff elevation shown on the drawings and the tip actual tip elevation as approved by the Contracting Officer. Pile length provided over the required length for ease of installation are the responsibility of the Contractor. No separate measurement or payment will be made for pile cutoffs or splices. The Contracting Officer shall approve all methods and procedures for quantity surveys.

1.3.13.3 Unit of Measure

Unit of measure: Linear Feet.

1.3.13.4 Payment Item

0039 FURNISH PZ 22 SHEET PILING FOR UPPER GUIDE WALL ARCHES

1.3.14 Removal of Existing Steel Sheet Piling

1.3.14.1 Payment

Payment shall cover all cost of removing, handling, and storing existing sheet piling at the Upper Guide Wall Boat Slip. Payment for removing existing pile shall include all cost of cleaning interlocks and reconditioning piles as necessary for reuse. Payment for installing the removed sheet piling at the Upper Guide Wall arches will be made as specified for INSTALL SHEET PILING AT UPPER GUIDE WALL ARCHES.

1.3.14.2 Measurement

The length of sheet piling installed will be measured to the nearest tenth of a linear foot. For installed pilings directed to be cut off before reaching the penetration depth shown, the portion cut off will be measured for payment as the difference between the total length of piling shown on the plans for that location and the length of piling installed below the point of cut-off.

SECTION 01 22 00.00 10 Page 15

1.3.14.3 Unit of Measure

Unit of measure: Linear Feet.

1.3.14.4 Payment Item

0036 REMOVE PZC 26 SHEET PILING, UPPER GUIDE WALL BOAT SLIP

1.3.15 Guard Fence at Upper Guide Wall Sheet Pile Wall

1.3.15.1 Payment

This work is specified in and Section 05 50 15 CIVIL WORKS FABRICATIONS.

Payment will be made for costs associated with furnishing and installing the guard fence at the Sheet Pile Wall. Price shall include all materials, labor, equipment, and supplies associated with this work as specified and as shown on the drawings. No separate payment will be made for new guard fence on the Upper and Lower Guide Walls, and all work in connection therewith shall be included in the applicable contract price for adjustments to the guard fence.

1.3.15.2 Measurement

Measurement will be made by linear feet of guard fence installed.

1.3.15.3 Unit of Measure

Unit of measure: Linear Feet

1.3.15.4 Payment Items

0035 GUARD FENCE AT UPPER GUIDE WALL SHEET PILE WALL

1.3.16 Geotextile

1.3.16.1 Payment

This work is specified in Section 31 05 22 GEOTEXTILES. Payment will be made for costs associated with placement of geotextile fabric as indicated on the contract drawings. Price shall include all materials, labor, equipment, and supplies associated with this work.

1.3.16.2 Measurement

Measurement for payment shall be by the actual area of geotextile acceptably installed based on the surface area of slope covered. No measurement will be made of geotextile in overlaps. All measurements for payment shall be made by or in presence of the Contracting Officer.

1.3.16.3 Unit of Measure

Unit of measure: square yard.

1.3.16.4 Payment Item

0041 GEOTEXTILE, UPPER GUIDE WALL

SECTION 01 22 00.00 10 Page 16

1.3.17 Stone Protection

1.3.17.1 Payment

This work is specified in Section 35 31 19 STONE PROTECTION. Payment will be made for costs associated with removing existing stone protection, furnishing new stone, and placing stone rip-rap as shown in the contract drawings. Price shall include all materials, labor, equipment, and supplies associated with this work.

1.3.17.2 Measurement

Measurement of existing stone to be removed or furnished will be made for the actual volume of stone removed or placed within the limits, lines and grades shown on the contract drawings. The volume of material removed shall be determined by the average-end-area method based on cross sections taken by field survey prior to and after completion of stone removal or other method approved by the Contracting Officer. The cross section surveys shall be obtained by the Contracting Officer at a maximum 50-foot interval over the length of disturbance prior to and after stone installation to determine the actual amount of material placed. Volume computations shall be performed by the Contractor, and copies of all cross section data and computations shall be submitted to the Contracting Officer within 48 hours following completion of the field cross sections.

Placement of stone placed will be measured for payment as the area, as measured in the field, of the surface on which the stone is placed as approved by the Contracting Officer.

1.3.17.3 Unit of Measure

Unit of measure: Cubic Yard, Square Yards.

1.3.17.4 Payment Item

0037 REMOVE AND STOCKPILE EXISTING R-6 STONE PROTECTION, UPPER GUIDE

WALL (Cubic Yard) 0042 FURNISH R-4 STONE PROTECTION, UPPER GUIDE WALL (Cubic Yard) 0043 PLACE STONE PROTECTION, UPPER GUIDE WALL (Square Yard)

1.3.18 Walkway

1.3.18.1 Payment

This work is specified in Section 05 50 15 CIVIL WORKS FABRICATION.

Payment will be made for costs associated with designing, furnishing and installing new walkway at Upper Guide Wall in accordance with the contract drawings and specifications. Price shall include fabrication of the walkway, and all materials, labor, equipment, and supplies associated with completing this work.

1.3.18.2 Measurement

Metalwork fabrication for the walkway will be measured for payment based upon computed weights per fabricated piece or assembly for the various metals as classified on the approved detail drawings except as indicated below. Indicate computed weights on the detail drawings submitted for approval. Approval of the detail drawings will constitute acceptance of the computed weights shown thereon. When measurement of complicated shapes

SECTION 01 22 00.00 10 Page 17 can be determined more readily by scale weights per fabricated piece or assembly the use of certified scale weights will be approved as the basis for measurement. Weights shall be calculated in accordance with AISC 303, Section 9.2.

1.3.18.3 Unit of Measure

Unit of measure: Pounds

1.3.18.4 Payment Item

1004 FURNISH AND INSTALL NEW WALKWAY,UPPER GUIDE WALL

SECTION 01 22 00.00 10 Page 18

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 32 01.00 10

PROJECT SCHEDULE

PART 1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

1.3 PROJECT SCHEDULER QUALIFICATIONS

1.4 QUALITY ASSURANCE

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

3.1.1 Approved Project Schedule

3.1.2 Schedule Status Reports

3.1.3 Default Terms

3.2 BASIS FOR PAYMENT AND COST LOADING

3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS

3.3.1 Critical Path Method

3.3.2 Level of Detail Required

3.3.2.1 Activity Durations

3.3.2.2 Procurement Activities

3.3.2.3 Mandatory Tasks

3.3.2.4 Government Activities

3.3.2.5 Activity Responsibility Coding (RESP)

3.3.2.6 Activity Work Area Coding

3.3.2.7 Contract Changes/Requests for Equitable Adjustment (REA)

Coding (MODF)

3.3.2.8 Contract Line Item (CLIN) Coding (BIDI)

3.3.2.9 Phase of Work Coding (PHAS)

3.3.2.10 Category of Work Coding (CATW)

3.3.2.11 Definable Features of Work Coding (FOW1, FOW2, FOW3)

3.3.3 Scheduled Project Completion and Activity Calendars

3.3.3.1 Project Start Date

3.3.3.2 Schedule Constraints and Open Ended Logic

3.3.3.3 Early Project Completion

3.3.4 Interim Completion Dates

3.3.4.1 Start Phase

3.3.4.2 End Phase

3.3.4.3 Phase "X" Hammock

3.3.5 Default Progress Data Disallowed

3.3.6 Out-of-Sequence Progress

3.3.7 Negative Lags and Start to Finish Relationships

3.3.8 Calculation Mode

3.3.9 Milestones

3.4 PROJECT SCHEDULE SUBMISSIONS

3.4.1 Preliminary Project Schedule Submission

3.4.2 Initial Project Schedule Submission

SECTION 01 32 01.00 10 Page 1

3.4.3 Periodic Schedule Updates

3.4.4 Standard Activity Coding Dictionary

3.5 SUBMISSION REQUIREMENTS

3.5.1 Data CD's

3.5.2 Narrative Report

3.5.3 Approved Changes Verification

3.5.4 Schedule Reports

3.5.4.1 Activity Report

3.5.4.2 Logic Report

3.5.4.3 Total Float Report

3.5.4.4 Earnings Report by CLIN

3.5.5 Network Diagram

3.5.5.1 Continuous Flow

3.5.5.2 Project Milestone Dates

3.5.5.3 Critical Path

3.5.5.4 Banding

3.5.5.5 S-Curves

3.6 PERIODIC SCHEDULE UPDATE MEETINGS

3.6.1 Update Submission Following Progress Meeting

3.6.2 Status of Activities

3.6.2.1 Start and Finish Dates

3.6.2.2 Remaining Duration

3.6.2.3 Percent Complete

3.6.2.4 Logic Changes

3.6.2.5 Other Changes

3.7 REQUESTS FOR TIME EXTENSIONS

3.7.1 Justification of Delay

3.7.2 Submission Requirements

3.7.3 Additional Submission Requirements

3.8 DIRECTED CHANGES

3.9 OWNERSHIP OF FLOAT

-- End of Section Table of Contents --

SECTION 01 32 01.00 10 Page 2

SECTION 01 32 01.00 10

PROJECT SCHEDULE

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

ER 1-1-11 (1995) Administration -- Progress, Schedules, and Network Analysis Systems

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Project Scheduler Qualifications; G, RO Project Schedule; G, RO

1.3 PROJECT SCHEDULER QUALIFICATIONS

Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of reports. The authorized representative must have a minimum of 2-years experience scheduling construction projects similar in size and nature to this project with scheduling software that meets the requirements of this specification. Representative must have a comprehensive knowledge of CPM scheduling principles and application.

1.4 QUALITY ASSURANCE

Designate an authorized representative to be responsible for the preparation of the schedule and all required updating (activity status) and preparation of reports. The authorized representative shall be experienced in scheduling projects similar in nature and complexity to this project and shall be experienced in the use of the scheduling software that meets the requirements of this specification.

SECTION 01 32 01.00 10 Page 3

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

Prepare for approval a Project Schedule, as specified herein, pursuant to the Section 00700 CONTRACT CLAUSES, 52.236-15 SCHEDULE FOR CONSTRUCTION CONTRACTS. Show in the schedule the sequence in which the Contractor proposes to perform the work and dates on which the Contractor contemplates starting and completing all schedule activities. The scheduling of the entire project, including the design and construction sequences, is required. The scheduling of design and construction is the responsibility of the Contractor. Contractor management personnel shall actively participate in its development. Subcontractors and suppliers/designers working on the project shall also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool.

3.1.1 Approved Project Schedule

Use the approved Project Schedule to measure the progress of the work and to aid in evaluating time extensions. Make the schedule cost loaded and activity coded. The schedule will provide the basis for all progress payments. If the Contractor fails to submit any schedule within the time prescribed, the Contracting Officer may withhold approval of progress payments until the Contractor submits the required schedule.

3.1.2 Schedule Status Reports

Provide a Schedule Status Report on at least a monthly basis. If, in the opinion of the Contracting Officer, the Contractor falls behind the approved schedule, take steps necessary to improve its progress including those that may be required by the Contracting Officer, without additional cost to the Government. In this circumstance, the Contracting Officer may require the Contractor to increase the number of shifts, overtime operations, days of work, and/or the amount of construction plant, and to submit for approval any supplementary schedule or schedules as the Contracting Officer deems necessary to demonstrate how the approved rate of progress will be regained.

3.1.3 Default Terms

Failure of the Contractor to comply with the requirements of the Contracting Officer shall be grounds for a determination, by the Contracting Officer that the Contractor is not prosecuting the work with sufficient diligence to ensure completion within the time specified in the contract. Upon making this determination, the Contracting Officer may terminate the Contractor's right to proceed with the work, or any separable part of it, in accordance with the default terms of the contract.

3.2 BASIS FOR PAYMENT AND COST LOADING

Use the schedule as the basis for determining contract earnings during each update period and therefore the amount of each progress payment. Lack of an approved schedule update, or qualified scheduling personnel, will result in the inability of the Contracting Officer to evaluate contract earned value for the purposes of payment. Failure of the Contractor to provide all required information will result in the disapproval of the preliminary, SECTION 01 32 01.00 10 Page 4 initial and subsequent schedule updates. In the event schedule revisions are directed by the Contracting Officer and those revisions have not been included in subsequent revisions or updates, the Contracting Officer may hold retainage up to the maximum allowed by contract, each payment period, until such revisions to the Project Schedule have been made. Activity cost loading shall be reasonable, as determined by the Contracting Officer. The aggregate value of all activities coded to a contract CLIN shall equal the value of the CLIN on the Schedule.

3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS

The computer software system utilized to produce and update the Project Schedule shall be capable of meeting all requirements of this specification. Failure of the Contractor to meet the requirements of this specification will result in the disapproval of the schedule.

3.3.1 Critical Path Method

Use the Critical Path Method (CPM) of network calculation to generate the Project Schedule. Prepare the Project Schedule using the Precedence Diagram Method (PDM).

3.3.2 Level of Detail Required

Develop the Project Schedule to an appropriate level of detail. Failure to develop the Project Schedule to an appropriate level of detail, as determined by the Contracting Officer, will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail.

3.3.2.1 Activity Durations

Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods. Less than 2 percent of all non-procurement activities shall have Original Durations (OD) greater than 20 work days or 30 calendar days. Procurement activities are defined herein.

3.3.2.2 Procurement Activities

The schedule must include activities associated with the submittal, approval, procurement, fabrication and delivery of long lead materials, equipment, fabricated assemblies and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days. A typical procurement sequence includes the string of activities: submit, approve, procure, fabricate, and deliver.

3.3.2.3 Mandatory Tasks

The following tasks must be included and properly scheduled:

a. Submission and approval of as-built drawings.

b. Contractor's pre-final inspection.

c. Correction of punchlist from Contractor's pre-final inspection.

d. Government's pre-final inspection.

SECTION 01 32 01.00 10 Page 5

e. Correction of punchlist from Government's pre-final inspection.

f. Final inspection.

3.3.2.4 Government Activities

Show Government and other agency activities that could impact progress.

These activities include, but are not limited to: approvals, approvals, design reviews, environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.

3.3.2.5 Activity Responsibility Coding (RESP)

Assign responsibility Code for all activities to the Prime Contractor, Subcontractor or Government agency responsible for performing the activity.

Activities coded with a Government Responsibility code include, but are not limited to: Government approvals, Government design reviews, environmental permit approvals by State regulators, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements. Code all activities not coded with a Government Responsibility Code to the Prime Contractor or Subcontractor responsible to perform the work. Activities shall not have more than one Responsibility Code. Examples of acceptable activity code values are: DOR (for the designer of record); ELEC (for the electrical subcontractor); MECH (for the mechanical subcontractor); and GOVT (for USACE). Unacceptable code values are abbreviations of the names of subcontractors.

3.3.2.6 Activity Work Area Coding

Assign Work Area code to activities based upon the work area in which the activity occurs. Define work areas based on resource constraints or space constraints that would preclude a resource, such as a particular trade or craft work crew, from working in more than one work area at a time due to restraints on resources or space. Examples of Work Area Coding include different areas within a floor of a building, different floors within a building, and different buildings within a complex of buildings. Activities shall not have more than one Work Area Code. Not all activities are required to be Work Area coded. A lack of Work Area coding will indicate the activity is not resource or space constrained.

3.3.2.7 Contract Changes/Requests for Equitable Adjustment (REA) Coding

(MODF)

Assign Activity code to any activity or sequence of activities added to the schedule as a result of a Contract Modification, when approved by the Contracting Officer, with a Contract Changes/REA Code. Key all Code values to the Government's modification numbering system. Any activity or sequence of activities added to the schedule as a result of alleged constructive changes made by the Government may be added to a copy of the current schedule, subject to the approval of the Contracting Officer.

Assign Activity codes for these activities with a Contract Changes/REA Code. Key the code values to the Contractor's numbering system. Approval to add these activities does not necessarily mean the Government accepts responsibility and, therefore, liability for such activities and any associated impacts to the schedule, but rather the Government recognizes such activities are appropriately added to the schedule for the purposes of maintaining a realistic and meaningful schedule. Such activities shall

SECTION 01 32 01.00 10 Page 6 not be Responsibility Coded to the Government unless approved. An activity shall not have more than one Contract Changes/REA Code.

3.3.2.8 Contract Line Item (CLIN) Coding (BIDI)

Code all activities to the CLIN on the Contract Line Item Schedule to which the activity belongs.