Control No: FY19-21 Contractor Mountain Valley Mechanical, Corp.
Program/Equipment: Compressor and Actuator Purchase and Install
JUSTIFICATION REVIEW DOCUMENT
FAR SUBPART 13.5 SIMPLIFIED PROCEDURES FOR CERTAIN COMMERCIAL ITEMS –
SOLE SOURCE JUSTIFICATION AND APPROVAL – Not to Exceed $700,000
Program/Equipment: Replace 2 existing compressors with two (2) new efficient air compressors for the Chemical Test Division, West Desert Test Center, Dugway Proving Ground.
Authority: 41 U.S.C. 1903 for Special Emergency Procurement) as implemented by FAR Subpart 13.5.
Amount:
Reviews: I have reviewed this justification and find it adequate to support an urgent/unusual and compelling purchase of the equipment and install.
Program Manager:
Signature:
Version – September 2018
FOR OFFICIAL USE ONLY
Control No: FY19-21 Contractor Mountain Valley Mechanical, Corp.
Program/Equipment: Compressor and Actuator Purchase and Install
Version – September 2018
FOR OFFICIAL USE ONLY
FAR SUBPART 13.5 SIMPLIFIED
PROCEDURES FOR CERTAIN
COMMERCIAL ITEMS
1. Contracting Activity: Mission and Installation Contracting Command, Dugway Proving Ground, 5330 Valdez Circle, Dugway, UT 84022.
2. Description of Action: Dugway Proving Ground Chemical Test Division (CTD) has a requirement to replace 2 existing compressors with two (2) new efficient air compressors including anchors, vibration isolation, manufacturer's enclosure, power supply, connections to existing system piping, plumbing, and controls, etc. Compressors are located at West Desert Test Center (Ditto Area) CTD at Dugway Proving Grounds, UT.
Projected award is September 26, 2019 and fiscal year 2019, RDT&E funds will be used. The estimated of this requirement is
X An acquisition plan is not required because this procurement does not meet the threshold at Defense Federal Acquisition Regulation Supplement 207.103(d)(i)(B).
3. Description of Supplies/Services: Purchase two new air compressors and associated actuators:
Minimum Specifications:
1. Minimum 300 SCFM at 125 PSIG.
2. 460V, 3-phase, 60 Hz.
3. Age of compressor from manufacture date is not greater than one year.
4. Thermal and acoustical insulation with a flame spread rating not higher than 75, and smoke developed rating not higher than 150 when tested in accordance with ASTM E84.
5. Rotary Screw
6. Oil Flooded Screw Type
7. Pressure range to 125 psi
8. Air tank capacity 1600 gallons.
Version – September 2018 FOR OFFICIAL USE ONLY
Delivery Date: four months after the contract is awarded
Total:
4. Authority Cited: Simplified Procedures for Certain Commercial Items, 41 U.S.C. 1901 (or 41 U.S.C. 1903 for Special Emergency Procurement) as implemented by FAR Subpart 13.5:
Unusual and compelling urgency FAR 6.302-2 Exclusive licensing agreements Industrial mobilization Other: State the purpose
5. Reason for Authority Cited:
a. Why is this an urgent need?
Critical safety systems have failed at the Materiel Test Facility (MTF). This failure has greatly increased the risk of conducting hazardous operations with Chemical Warfare Agents (CWAs) at the MTF. Residual safety systems are on the verge of collapse and are expected to failure at any time. Complete failure will put workers and the environment at risk of exposure to CWAs. In additional, failure of the residual systems will halt vital chemical defensive testing that support the safety of soldiers. This effort will replace/repair the failed systems and protect our workforce and the environment from the hazards of Chemical Warfare Agents.
b. What would be the impact if the purchase of equipment and install were delayed for up to 8 weeks to allow for competition of requirement?
As stated above - The residual safety systems of the MTF are on the verge of collapse. These systems are many years beyond their expected life cycle. Delay greatly increases the likelihood that safety systems will completely fail before they can be repaired/replaced. Failure of the residual systems will put the workforce and the environment at risk of exposure to Chemical Warfare Agents.
c. What would the life/safety/health impact be if requirement not completed as soon as possible?
Chemical Warfare Agents are some of the most hazardous chemicals known to man. The risk of failure of the residual safety systems is very high. This leads to a high life/safety/health and environmental impact.
d. What would the cost impact be if current equipment failed?
If the residual safety systems failed during a hazardous operation with CWA the cost could be in the hundreds of thousands of dollars. This does not include the possibility of damage to life, health or the environment.
Version – September 2018 FOR OFFICIAL USE ONLY
6. Actions to Increase Competition:
This is an urgent and compelling requirement. If time were available to compete, at least one other provider would be capable of providing (Compressor Pump and Service, Salt Lake City, Utah).
7. Market Research: The proposed provider, Mountain Valley Mechanical (MVM), installed the existing 2 generators that currently supply laboratory air to the CHEM TEST facility. This company has manpower and equipment to quickly install, setup, program the systems using knowledge gained during install of other two compressors now supply air to lab.
NOTE: This action is put in place to complete a partially completed contract that was cancelled when the Department of Health and Human Services (HHS) abruptly terminated the action due to their contract warrants being suspended. MICC-DPG has been pressed into supplying the effort to complete the requirement.
8. Other Facts:
9. Technical/Requirements Certification: I certify that the supporting data under my cognizance which are included in the justification are accurate and complete to the best of my knowledge and belief.
10. Best Value Determination/Fair and Reasonable Cost Determination: I hereby determine that the order represents a fair and reasonable price to the Government. Additionally. The MICC- DPG office will ask for “other than certified” cost/price information to show labor rates, overhead, material costs, etc. are fair and reasonable PER FAR Part 15.
This determination will be made using the following: price analysis and IGCE
__X__Other: Contract Specialist has gathered estimates from manufacturers.
10. Reviews: I have reviewed this justification and find it adequate to support limiting competition:
Contracting Officer: