W911PT19Q0018-0001 CNC Induction Hardening System.docx

DOCX document 54 KB Posted

Attached to
CNC Induction Hardening System Federal contract opportunity
Solicitation number
W911PT19Q0018
Issued by
Department of the Army Materiel Command Contracting Command Detroit Arsenal

About this file

This document contains a contract data requirements list (DD Form 1423) for a federal solicitation seeking a new CNC induction hardening system. The solicitation from the Department of the Army Materiel Command Contracting Command Detroit Arsenal (W911PT19Q0018) requires the delivery of one CNC induction hardening system per Specification #11-18-3424, Revision B. The contractor must submit certifications and documentation on asbestos/mercury-free materials, lead/chromium-free paint, and PCB-free components within 30 days of award. Additional required submittals include machine floor plans, tooling catalogs, installation drawings, operating/maintenance instructions, schematics, and software documentation to be delivered before or with the machine. The response deadline is not specified.

View the file

Other files for this federal contract opportunity

Other files attached to CNC Induction Hardening System, newest first.
File Type Posted
Attachment 0001 Comply Sheet - WVA CNC Induction Hardening System per 11-18-3424.xls XLS spreadsheet
W911PT19Q0018 CNC Induction Hardening System released.docx DOCX document
Attachment 0002 - Use of Existing GFP.xlsx XLSX spreadsheet

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W911PT19Q0018

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 1449 - CONTINUATION SHEET

SUPPLIES OR SERVICES AND PRICES

CLIN 0001

The CLIN extended description has changed from:

New CNC Induction Hardening System per Specification #11-18-3424, Rev. A, dated 6/21/2018.Contractor to include contract data prepared and delivered in accordance with CONTRACT DATA REQUIREMENTS LIST (DD FORM 1423) which is attached hereto as EXHIBIT A. NOT SEPERATELY PRICEDMID:VR-A

To:

New CNC Induction Hardening System per Specification #11-18-3424, Rev. B, dated 3/12/2020.Contractor to include contract data prepared and delivered in accordance with CONTRACT DATA REQUIREMENTS LIST (DD FORM 1423) which is attached hereto as EXHIBIT A. NOT SEPERATELY PRICEDMID:VR-A

The following have been modified:

EXHIBIT A

CONTRACT DATA REQUIREMENTS LIST Form Approval OMB No. 0704-0188 Public reporting burden for this collection of information is estimated to average 440 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.: 0001 D. SYSTEM/ITEM....: WVA CNC Induction Hardening System

B. EXHIBIT...............: A E. CONTRACT/PR NO.: W911PT-19-Q-0018

C. CATEGORY..............: F. CONTRACTOR.....: TBD

1. DATA ITEM NO......: A001

2. TITLE OF DATA ITEM: Asbestos and Mercury Free Certification

3. SUBTITLE..........:

4. AUTHORITY.........: DI-MISC-81356A

5. CONTRACT REFERENCE: Specification, Item 3.1.9.5

6. REQUIRING OFFICE..: WVA – Manufacturing/Engineering

7. DD250 REQ.........: NO

8. APP CODE..........: N/A

9. DIST. STMT. REQD..: A

10. FREQUENCY.........: ONE/R

11. AS OF DATE........: Contract Award Date

12. DATE OF FIRST SUB.: 30 Days Prior to Machine Delivery

13. DATE OF SUBS. SUB.: ASREQ

14. DISTRIBUTION A. ADDRESSEES B. COPIES

DRAFT FINAL

Reg Repro james.j.kardas.civ@mail.mil 1

15. TOTAL: 1

16. REMARKS: Inclusive of the requirements in item 3.1.12.5 Asbestos and Mercury Free Certification, contractor format is authorized.

17. PRICE GROUP:

18. ESTIMATED TOTAL PRICE:

G. PREPARED BY: Jaclyn Beadnell I. APPROVED BY:

H. DATE: 17 March 2020 J. DATE

DD FORM 1423-E, APR 00 PAGE 1 OF 1 PAGES

CONTRACT DATA REQUIREMENTS LIST Form Approval OMB No. 0704-0188 Public reporting burden for this collection of information is estimated to average 440 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.: 0001 D. SYSTEM/ITEM....: WVA CNC Induction Hardening System

B. EXHIBIT...............: A E. CONTRACT/PR NO.: W911PT-19-Q-0018

C. CATEGORY..............: F. CONTRACTOR.....: TBD

1. DATA ITEM NO......: A002

2. TITLE OF DATA ITEM: Lead-Free and Chromium-Free Paint Certification

3. SUBTITLE..........:

4. AUTHORITY.........:

5. CONTRACT REFERENCE: Specification, Item 3.1.9.7

6. REQUIRING OFFICE..: WVA – Manufacturing/Engineering

7. DD250 REQ.........: NO

8. APP CODE..........: N/A

9. DIST. STMT. REQD..: A

10. FREQUENCY.........: ONE/R

11. AS OF DATE........: Contract Award Date

12. DATE OF FIRST SUB.: 30 Days Prior to Machine Delivery

13. DATE OF SUBS. SUB.: ASREQ

14. DISTRIBUTION A. ADDRESSEES B. COPIES

james.j.kardas.civ@mail.mil 1

16. REMARKS: Inclusive of the requirements in item 3.1.12.5 Asbestos and Mercury Free Certification, contractor format is authorized.

17. PRICE GROUP:

18. ESTIMATED TOTAL PRICE:

DD FORM 1423-E, APR 00 PAGE 1 OF 1 PAGES

Public reporting burden for this collection of information is estimated to average 440 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.: 0001 D. SYSTEM/ITEM....: WVA CNC Induction Hardening System

B. EXHIBIT...............: A E. CONTRACT/PR NO.: W911PT-19-Q-0018

C. CATEGORY..............: F. CONTRACTOR.....: TBD

1. DATA ITEM NO......: A003

2. TITLE OF DATA ITEM: PCB Free Certification

3. SUBTITLE..........:

4. AUTHORITY.........:

5. CONTRACT REFERENCE: Specification, Item 3.1.9.8

6. REQUIRING OFFICE..: WVA – Manufacturing/Engineering

7. DD250 REQ.........: NO

8. APP CODE..........: N/A

9. DIST. STMT. REQD..: A

10. FREQUENCY.........: ONE/R

11. AS OF DATE........: Contract Award Date

12. DATE OF FIRST SUB.: Within 30 Days after Award

13. DATE OF SUBS. SUB.: ASREQ

14. DISTRIBUTION A. ADDRESSEES B. COPIES

james.j.kardas.civ@mail.mil 1

16. REMARKS: Inclusive of the requirements in item 3.1.12.5 Asbestos and Mercury Free Certification, contractor format is authorized.

17. PRICE GROUP:

18. ESTIMATED TOTAL PRICE:

DD FORM 1423-E, APR 00 PAGE 1 OF 1 PAGES

Public reporting burden for this collection of information is estimated to average 440 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.: 0001 D. SYSTEM/ITEM....: WVA CNC Induction Hardening System

B. EXHIBIT...............: A E. CONTRACT/PR NO.: W911PT-19-Q-0018

C. CATEGORY..............: F. CONTRACTOR.....: TBD

1. DATA ITEM NO......: A004

2. TITLE OF DATA ITEM: Machine and Equipment Floor Plan

3. SUBTITLE..........:

4. AUTHORITY.........:

5. CONTRACT REFERENCE: Specification, Item 3.1.20.1

6. REQUIRING OFFICE..: WVA – Manufacturing/Engineering

7. DD250 REQ.........: NO

8. APP CODE..........: N/A

9. DIST. STMT. REQD..: A

10. FREQUENCY.........: ONE/R

11. AS OF DATE........: Contract Award Date

12. DATE OF FIRST SUB.: 10 days after contract award date

13. DATE OF SUBS. SUB.: ASREQ

14. DISTRIBUTION A. ADDRESSEES B. COPIES

james.j.kardas.civ@mail.mil 1

16. REMARKS: Inclusive of the requirements in item 3.1.12.5 Asbestos and Mercury Free Certification, contractor format is authorized.

17. PRICE GROUP:

18. ESTIMATED TOTAL PRICE:

H. DATE: 17 March 2020

DD FORM 1423-E, APR 00 PAGE 1 OF 1 PAGES

Public reporting burden for this collection of information is estimated to average 440 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.: 0001 D. SYSTEM/ITEM....: WVA CNC Induction Hardening System

B. EXHIBIT...............: A E. CONTRACT/PR NO.: W911PT-19-Q-0018

C. CATEGORY..............: F. CONTRACTOR.....: TBD

1. DATA ITEM NO......: A005

2. TITLE OF DATA ITEM: Catalog of Standard Tooling and Accessories

3. SUBTITLE..........:

4. AUTHORITY.........:

5. CONTRACT REFERENCE: Specification, Item 3.1.20.2

6. REQUIRING OFFICE..: WVA – Manufacturing/Engineering

7. DD250 REQ.........: NO

8. APP CODE..........: N/A

9. DIST. STMT. REQD..: A

10. FREQUENCY.........: ONE/R

11. AS OF DATE........: Contract Award Date

12. DATE OF FIRST SUB.: Within 30 Days after Award

13. DATE OF SUBS. SUB.: ASREQ

14. DISTRIBUTION A. ADDRESSEES B. COPIES

james.j.kardas.civ@mail.mil 1

16. REMARKS: Inclusive of the requirements in item 3.1.12.5 Asbestos and Mercury Free Certification, contractor format is authorized.

17. PRICE GROUP:

18. ESTIMATED TOTAL PRICE:

DD FORM 1423-E, APR 00 PAGE 1 OF 1 PAGES

Public reporting burden for this collection of information is estimated to average 440 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.: 0001 D. SYSTEM/ITEM....: WVA CNC Induction Hardening System

B. EXHIBIT...............: A E. CONTRACT/PR NO.: W911PT-19-Q-0018

C. CATEGORY..............: F. CONTRACTOR.....: TBD

1. DATA ITEM NO......: A006

2. TITLE OF DATA ITEM: Non-Standard (Special) Tooling and Accessories

3. SUBTITLE..........:

4. AUTHORITY.........:

5. CONTRACT REFERENCE: Specification, Item 3.1.20.3

6. REQUIRING OFFICE..: WVA – Manufacturing/Engineering

7. DD250 REQ.........: NO

8. APP CODE..........: N/A

9. DIST. STMT. REQD..: A

10. FREQUENCY.........: ONE/R

11. AS OF DATE........: Contract Award Date

12. DATE OF FIRST SUB.: At time of Machine Delivery

13. DATE OF SUBS. SUB.: ASREQ

14. DISTRIBUTION A. ADDRESSEES B. COPIES

james.j.kardas.civ@mail.mil 1

16. REMARKS: Inclusive of the requirements in item 3.1.12.5 Asbestos and Mercury Free Certification, contractor format is authorized.

17. PRICE GROUP:

18. ESTIMATED TOTAL PRICE:

DD FORM 1423-E, APR 00 PAGE 1 OF 1 PAGES

Public reporting burden for this collection of information is estimated to average 440 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.: 0001 D. SYSTEM/ITEM....: WVA CNC Induction Hardening System

B. EXHIBIT...............: A E. CONTRACT/PR NO.: W911PT-19-Q-0018

C. CATEGORY..............: F. CONTRACTOR.....: TBD

1. DATA ITEM NO......: A007

2. TITLE OF DATA ITEM: Installation Instructions and Drawings

3. SUBTITLE..........:

4. AUTHORITY.........:

5. CONTRACT REFERENCE: Specification, Item 3.1.20.4

6. REQUIRING OFFICE..: WVA – Manufacturing/Engineering

7. DD250 REQ.........: NO

8. APP CODE..........: N/A

9. DIST. STMT. REQD..: A

10. FREQUENCY.........: ONE/R

11. AS OF DATE........: Contract Award Date

12. DATE OF FIRST SUB.: 60 Days prior to scheduled delivery of machine

13. DATE OF SUBS. SUB.: ASREQ

14. DISTRIBUTION A. ADDRESSEES B. COPIES

james.j.kardas.civ@mail.mil 1

16. REMARKS: Inclusive of the requirements in item 3.1.12.5 Asbestos and Mercury Free Certification, contractor format is authorized.

17. PRICE GROUP:

18. ESTIMATED TOTAL PRICE:

DD FORM 1423-E, APR 00 PAGE 1 OF 1 PAGES

Public reporting burden for this collection of information is estimated to average 440 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.: 0001 D. SYSTEM/ITEM....: WVA CNC Induction Hardening System

B. EXHIBIT...............: A E. CONTRACT/PR NO.: W911PT-19-Q-0018

C. CATEGORY..............: F. CONTRACTOR.....: TBD

1. DATA ITEM NO......: A008

2. TITLE OF DATA ITEM: Lubrication Diagram and Instruction

3. SUBTITLE..........:

4. AUTHORITY.........:

5. CONTRACT REFERENCE: Specification, Item 3.1.20.5

6. REQUIRING OFFICE..: WVA – Manufacturing/Engineering

7. DD250 REQ.........: NO

8. APP CODE..........: N/A

9. DIST. STMT. REQD..: A

10. FREQUENCY.........: ONE/R

11. AS OF DATE........: Contract Award Date

12. DATE OF FIRST SUB.: Delivered at time of Machine Delivery

13. DATE OF SUBS. SUB.: ASREQ

14. DISTRIBUTION A. ADDRESSEES B. COPIES

james.j.kardas.civ@mail.mil 1

16. REMARKS: Inclusive of the requirements in item 3.1.12.5 Asbestos and Mercury Free Certification, contractor format is authorized.

17. PRICE GROUP:

18. ESTIMATED TOTAL PRICE:

DD FORM 1423-E, APR 00 PAGE 1 OF 1 PAGES

Public reporting burden for this collection of information is estimated to average 440 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.: 0001 D. SYSTEM/ITEM....: WVA CNC Induction Hardening System

B. EXHIBIT...............: A E. CONTRACT/PR NO.: W911PT-19-Q-0018

C. CATEGORY..............: F. CONTRACTOR.....: TBD

1. DATA ITEM NO......: A009

2. TITLE OF DATA ITEM: Operating Instructions

3. SUBTITLE..........:

4. AUTHORITY.........:

5. CONTRACT REFERENCE: Specification, Item 3.1.20.6

6. REQUIRING OFFICE..: WVA – Manufacturing/Engineering

7. DD250 REQ.........: NO

8. APP CODE..........: N/A

9. DIST. STMT. REQD..: A

10. FREQUENCY.........: ONE/R

11. AS OF DATE........: Contract Award Date

12. DATE OF FIRST SUB.: Delivered at time of Machine Delivery

13. DATE OF SUBS. SUB.: ASREQ

14. DISTRIBUTION A. ADDRESSEES B. COPIES

james.j.kardas.civ@mail.mil 1

16. REMARKS: Inclusive of the requirements in item 3.1.12.5 Asbestos and Mercury Free Certification, contractor format is authorized.

17. PRICE GROUP:

18. ESTIMATED TOTAL PRICE:

DD FORM 1423-E, APR 00 PAGE 1 OF 1 PAGES

Public reporting burden for this collection of information is estimated to average 440 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.: 0001 D. SYSTEM/ITEM....: WVA CNC Induction Hardening System

B. EXHIBIT...............: A E. CONTRACT/PR NO.: W911PT-19-Q-0018

C. CATEGORY..............: F. CONTRACTOR.....: TBD

1. DATA ITEM NO......: A010

2. TITLE OF DATA ITEM: Maintenance and Troubleshooting Instructions for all Machine Systems

3. SUBTITLE..........:

4. AUTHORITY.........:

5. CONTRACT REFERENCE: Specification, Item 3.1.20.7

6. REQUIRING OFFICE..: WVA – Manufacturing/Engineering

7. DD250 REQ.........: NO

8. APP CODE..........: N/A

9. DIST. STMT. REQD..: A

10. FREQUENCY.........: ONE/R

11. AS OF DATE........: Contract Award Date

12. DATE OF FIRST SUB.: Delivered at time of Machine Delivery

13. DATE OF SUBS. SUB.: ASREQ

14. DISTRIBUTION A. ADDRESSEES B. COPIES

james.j.kardas.civ@mail.mil 1

16. REMARKS: Inclusive of the requirements in item 3.1.12.5 Asbestos and Mercury Free Certification, contractor format is authorized.

17. PRICE GROUP:

18. ESTIMATED TOTAL PRICE:

DD FORM 1423-E, APR 00 PAGE 1 OF 1 PAGES

Public reporting burden for this collection of information is estimated to average 440 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.: 0001 D. SYSTEM/ITEM....: WVA CNC Induction Hardening System

B. EXHIBIT...............: A E. CONTRACT/PR NO.: W911PT-19-Q-0018

C. CATEGORY..............: F. CONTRACTOR.....: TBD

1. DATA ITEM NO......: A011

2. TITLE OF DATA ITEM: Electronic and Hydraulic Schematics

3. SUBTITLE..........:

4. AUTHORITY.........:

5. CONTRACT REFERENCE: Specification, Item 3.1.20.8

6. REQUIRING OFFICE..: WVA – Manufacturing/Engineering

7. DD250 REQ.........: NO

8. APP CODE..........: N/A

9. DIST. STMT. REQD..: A

10. FREQUENCY.........: ONE/R

11. AS OF DATE........: Contract Award Date

12. DATE OF FIRST SUB.: To be delivered at time of machine delivery

13. DATE OF SUBS. SUB.: ASREQ

14. DISTRIBUTION A. ADDRESSEES B. COPIES

james.j.kardas.civ@mail.mil 1

16. REMARKS: Inclusive of the requirements in item 3.1.12.5 Asbestos and Mercury Free Certification, contractor format is authorized.

17. PRICE GROUP:

18. ESTIMATED TOTAL PRICE:

DD FORM 1423-E, APR 00 PAGE 1 OF 1 PAGES

Public reporting burden for this collection of information is estimated to average 440 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.: 0001 D. SYSTEM/ITEM....: WVA CNC Induction Hardening System

B. EXHIBIT...............: A E. CONTRACT/PR NO.: W911PT-19-Q-0018

C. CATEGORY..............: F. CONTRACTOR.....: TBD

1. DATA ITEM NO......: A012

2. TITLE OF DATA ITEM: Repair Parts Catalog

3. SUBTITLE..........:

4. AUTHORITY.........:

5. CONTRACT REFERENCE: Specification, Item 3.1.20.9

6. REQUIRING OFFICE..: WVA – Manufacturing/Engineering

7. DD250 REQ.........: NO

8. APP CODE..........: N/A

9. DIST. STMT. REQD..: A

10. FREQUENCY.........: ONE/R

11. AS OF DATE........: Contract Award Date

12. DATE OF FIRST SUB.: Within 30 Days prior to Delivery of Machine

13. DATE OF SUBS. SUB.: ASREQ

14. DISTRIBUTION A. ADDRESSEES B. COPIES

james.j.kardas.civ@mail.mil 1

16. REMARKS: Inclusive of the requirements in item 3.1.12.5 Asbestos and Mercury Free Certification, contractor format is authorized.

17. PRICE GROUP:

18. ESTIMATED TOTAL PRICE:

DD FORM 1423-E, APR 00 PAGE 1 OF 1 PAGES

Public reporting burden for this collection of information is estimated to average 440 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.: 0001 D. SYSTEM/ITEM....: WVA CNC Induction Hardening System

B. EXHIBIT...............: A E. CONTRACT/PR NO.: W911PT-19-Q-0018

C. CATEGORY..............: F. CONTRACTOR.....: TBD

1. DATA ITEM NO......: A013

2. TITLE OF DATA ITEM: Program Manuals

3. SUBTITLE..........:

4. AUTHORITY.........:

5. CONTRACT REFERENCE: Specification, Item 3.1.20.10

6. REQUIRING OFFICE..: WVA – Manufacturing/Engineering

7. DD250 REQ.........: NO

8. APP CODE..........: N/A

9. DIST. STMT. REQD..: A

10. FREQUENCY.........: ONE/R

11. AS OF DATE........: Contract Award Date

12. DATE OF FIRST SUB.: Delivered at time of Machine Delivery

13. DATE OF SUBS. SUB.: ASREQ

14. DISTRIBUTION A. ADDRESSEES B. COPIES

james.j.kardas.civ@mail.mil 1

16. REMARKS: Inclusive of the requirements in item 3.1.12.5 Asbestos and Mercury Free Certification, contractor format is authorized.

17. PRICE GROUP:

18. ESTIMATED TOTAL PRICE:

DD FORM 1423-E, APR 00 PAGE 1 OF 1 PAGES

Public reporting burden for this collection of information is estimated to average 440 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.: 0001 D. SYSTEM/ITEM....: WVA CNC Induction Hardening System

B. EXHIBIT...............: A E. CONTRACT/PR NO.: W911PT-19-Q-0018

C. CATEGORY..............: F. CONTRACTOR.....: TBD

1. DATA ITEM NO......: A014

2. TITLE OF DATA ITEM: Software Documentation

3. SUBTITLE..........:

4. AUTHORITY.........:

5. CONTRACT REFERENCE: Specification, Item 3.1.20.11

6. REQUIRING OFFICE..: WVA – Manufacturing/Engineering

7. DD250 REQ.........: NO

8. APP CODE..........: N/A

9. DIST. STMT. REQD..: A

10. FREQUENCY.........: ONE/R

11. AS OF DATE........: Contract Award Date

12. DATE OF FIRST SUB.: Within 30 Days after delivery of Machine

13. DATE OF SUBS. SUB.: ASREQ

14. DISTRIBUTION A. ADDRESSEES B. COPIES

james.j.kardas.civ@mail.mil 1

16. REMARKS: Inclusive of the requirements in item 3.1.12.5 Asbestos and Mercury Free Certification, contractor format is authorized.

17. PRICE GROUP:

18. ESTIMATED TOTAL PRICE:

DD FORM 1423-E, APR 00 PAGE 1 OF 1 PAGES

(End of Summary of Changes) image1.wmf

File details come from the government source that posted it. Updated .