Cutter_Grinder_Q&A.docx
DOCX document 13 KB Posted
- Attached to
- Cutter Grinder Federal contract opportunity
- Solicitation number
- W911PT18R0026
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Test_Part_1_For_Distribution.pdf | ||
| 4-18-3415__Rev_C_Comply_Sheet.xls | XLS spreadsheet | |
| Test_Part_2_For_Distribution.pdf | ||
| W911PT-18-R-0026_0004.pdf | ||
| Test_Part_3_For_Distribution.pdf | ||
| W911PT-18-R-0026_0003.pdf | ||
| Amendment_0002.pdf | ||
| 4-18-3415__Rev_B_Comply_Sheet.xls | XLS spreadsheet | |
| Amendment_0001.pdf | ||
| Comply_Sheet_for_WVA_Cutter_Grinder.xls | XLS spreadsheet | |
| Test_Part_2_For_Distribution.pdf | ||
| W911PT-18-R-0026.pdf | ||
| Test_Part_3_For_Distribution.pdf | ||
| Test_Part_1_For_Distribution.pdf |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Cutter Grinder Q&A
W911PT-18-R-0026
Version 1: 07 AUG 2018
1) At the end of the Comply/Non comply sheet there is Attachment A -E. Could you clarify what these are referring to? I could not find a description particular to those items on the SOW.
RESPONSE: The Compliance sheet is referencing the Enclosures listed at the end of the SOW. There are actually only four enclosures (A-D) and the Drawings. The compliance sheet has been adjusted to reflect this change.