SEE ADDENDUM

(No Collect Calls)

W911PT23Q0056 31-Mar-2023

b. TELEPHONE NUMBER

518-266-4641

8. OFFER DUE DATE/LOCAL TIME

02:30 PM 07 Apr 2023

5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

STANDARD FORM 1449 (REV. 2/2012)

Prescribed by GSA – FAR (48 CFR) 53.212

(TYPE OR PRINT)

(SIGNATURE OF CONTRACTING OFFICER)

ADDENDA X ARE

26. TOTAL AWARD AMOUNT (For Gov t. Use Only )

23.

CODE 10. THIS ACQUISITION IS

SUCH ADDRESS IN OFFER

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT

BELOW IS CHECKED

TELEPHONE NO.

W911PT9. ISSUED BY

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK

7. FOR SOLICITATION

INFORMATION CALL:

a. NAME

MARIA DECRESCENZO

2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER

(TYPE OR PRINT)

30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER

30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA

1 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.X

25. ACCOUNTING AND APPROPRIATION DATA

1. REQUISITION NUMBER

20.

ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.

OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

SEE SCHEDULE

ARE NOT ATTACHED

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED

(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE

SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:

. YOUR OFFER ON SOLICITATION

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN

% FOR:SET ASIDE:UNRESTRICTED OR X

SMALL BUSINESSX

17a.CONTRACTOR/ CODE FACILITY

OFFEROR CODE

ARMY CONTRACTING COMMAND-WARREN (WVA)

ATTN: CCTA-HDW/BLDG 10

1 BUFFINGTON STREET

WATERVLIET NY 12189-4000

18a. PAYMENT WILL BE MADE BY CODE

RATED ORDER UNDER

DPAS (15 CFR 700)

13a. THIS CONTRACT IS A

13b. RATING

CODE15. DELIVER TO CODE W911PT 16. ADMINISTERED BY

12. DISCOUNT TERMS11. DELIVERY FOR FOB DESTINA-

TION UNLESS BLOCK IS

MARKED

SEE SCHEDULE

14. METHOD OF SOLICITATION

RFQ IFB RFPX

ARMY CONTRACTING COMMAND-WARREN (WVA)

SERVICES TEAM

ATTN: CCTA-HDW/BLDG 10

1 BUFFINGTON STREET

WATERVLIET NY 12189-4000

TEL: 518-266-4535 FAX:

FAX:

TEL: SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

8(A)

HUBZONE SMALL

BUSINESS

SIZE STANDARD:

$17,500,000

NAICS:

561710

X

OFFER DATED

29. AWARD OF CONTRACT: REF.

DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND

EMAIL:

TEL:

31c. DATE SIGNED

SEE SCHEDULE

SCHEDULE OF SUPPLIES/ SERVICESITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT

24.22.21.19.

WOMEN-OWNED SMALL BUSINESS (WOSB)

ELIGIBLE UNDER THE WOMEN-OWNED

SMALL BUSINESS PROGRAM

EDWOSB

32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

(CONTINUED)

PAGE 2 OF66

ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________

32a. QUANTITY IN COLUMN 21 HAS BEEN

RECEIVED INSPECTED

32b. SIGNATURE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE

37. CHECK NUMBER

FINALPARTIALCOMPLETE

36. PAYMENT35. AMOUNT VERIFIED

CORRECT FOR

34. VOUCHER NUMBER

FINAL

33. SHIP NUMBER

PARTIAL

38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY

41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT

41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE

42a. RECEIVED BY (Print)

42b. RECEIVED AT (Location)

42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS

STANDARD FORM 1449 (REV. 2/2012) BACK

Prescribed by GSA – FAR (48 CFR) 53.212

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

SEE SCHEDULE

20.

SCHEDULE OF SUPPLIES/ SERVICES

21.

QUANTITY UNIT

22. 23.

UNIT PRICE

24.

AMOUNT

19.

ITEM NO.

W911PT23Q0056

Section SF 30 - BLOCK 14 CONTINUATION PAGE

LOCAL NARRATIVES

A.__ NOTICE OF WATERVLIET ARSENAL INFORMATION/REQUIREMENTS

(a) IMPORTANT DELIVERY/QUALITY REQUIREMENTS:

(1) ALL OFFERORS MUST CAREFULLY REVIEW THE DELIVERY REQUIREMENT IN THE

REQUEST FOR QUOTE OR SOLICITATION. WHEN SUBMITTING AN OFFER/BID, PLEASE

ENSURE THAT YOU CAN MEET THE DELIVERY SCHEDULE.

(2) ON TIME DELIVERY IS VERY CRITICAL. THEREFORE, YOU MUST ADHERE TO THE

DELIVERY REQUIREMENTS INDICATED IN ANY RESULTANT AWARD. FAILURE TO

COMPLY WITH THE CONTRACTUAL DELIVERY SCHEDULE, MAY RESULT IN TERMINATION

OF THE ORDER OR REQUIRE CONSIDERATION IF THE GOVERNMENT ELECTS TO EXTEND

DELIVERY. (NOTE: Non-availability of raw materials, subcontractor issues, scheduling conflicts, should be considered at the time you are submitting your offer/bid. They are not acceptable excuses for failing to meet the delivery after award).

(3) PROVIDING QUALITY PRODUCTS THAT CONFORM TO THE CONTRACT ARE JUST AS

IMPORTANT AS MEETING THE REQUIRED DELIVERY. DELIVERY OF NON-CONFORMING

PRODUCTS RESULTS IN DELIVERY DELAYS AND INCREASED COSTS TO THE ARSENAL.

(4) PAST PERFORMANCE FOR QUALITY AND DELIVERY MAY BE A MAJOR

CONSIDERATION IN MAKING DETERMINATIONS FOR FUTURE CONTRACT AWARDS.

NOTICE: Throughout this document we may use the terms “we” and “you”, the term “we” means the government of the United States of America, and the term “you” means the contractor.

(b) WATERVLIET ARSENAL INFORMATION FOR CONTRACTORS:

“Watervliet Arsenal Information for Contractors” document is incorporated by reference in all solicitations and contracts. The full text version of the instructions is available at Internet address:

http://www.wva.army.mil/Documents/Contracting/WAIC.pdf Upon request, the contracting officer will make its full text available.”

POC - CONTRACT SPECIALIST/BUYER: Maria Decrescenzo

TELEPHONE NUMBER: 518-266-4641

E-MAIL ADDRESS: maria.d.decrescenzo.civ@army.mil

CONTRACTOR DUNS NUMBER/CAGE CODE/FAX NUMBER:

Please provide the following information for your company.

VENDOR NAME: ___________

VENDOR POC: ___________

POC PHONE: ___________

E-MAIL ADDRESS (see note below): ___________

DUNS NUMBER ___________

CAGE CODE (if known) ___________

TAX ID NUMBER ___________

VENDOR FAX NUMBER ___________

NOTE: Your e-mail address is required so that in the event you receive the resultant award, we can e-mail it to you.

If we experience difficulties with e-mail, it will be data faxed.

(c) AWCF BULK FUND _x__ DOES ____ DOES NOT APPLY

(d) POSTERS:

(1) Contracts for Material, Supplies, Articles and Equipment Exceeding $15,000/Service Contract Labor Standards. Orders subject to these Acts require contractors to post WH Publication 1313, “Employee Rights on Government Contracts”.

(2) Construction Orders. Orders for construction require contractors to post WH Publication 1321, “Employee Rights under the Davis Bacon” and the Office of Federal Contract Compliance poster on “Equal Employment Opportunity is the Law.”

(3) These posters can be accessed electronically at http://www.dol.gov .

(4) Hard copies of the posters will be made available upon request to the contracting officer.

(e) PAYMENTS:

Any vendor that receives an award (except those paid by credit card or accommodation check) can view invoice payments made by DFAS at https://wawf.eb.mil/ using the “my invoice” system. You will be required to register in order to view payments. Payment information is maintained for 120 days from invoice payment. Vendors can find out when invoices have been paid by Electronic Funds Transfer (EFT), etc. This website can save valuable time and frustration over billing questions and it is a free service.

(f) RELEASE OF INFORMATION:

The contractor shall not release or authorize release of DoD specifications; acceptance test results; information involving critical military technology; or any other information in which the DoD maintains proprietary rights, or is otherwise confidential or classified. This restriction includes any endorsement by the Department of Army of a contractor. Release of information under the circumstances referenced above requires the prior written approval of the Contracting Officer responsible for this contract. It is the contractor’s responsibility to be familiar with, and comply with the requirements of Chapter 5, page 22, paragraph 5-48, of AR 360-1 may be found at http://www.usapa.army.mil/pdffiles/r360_1.pdf

C._1_ Submission of Recordable Injuries and Illness Cases (Dec 2012) (ACC-Warren (WVA)) Watervliet Arsenal is pursuing OSHA Voluntary Protection Program (VPP) recognition. The VPP impacts all contractors whose employees cumulatively work more than 1000 hours per quarter within a calendar year at Watervliet Arsenal (herein referred to as “applicable contractors”).

It is the contractor’s responsibility to ensure its employees and managers are in full compliance with OSHA requirements and have a general understanding of VPP. Detailed information on VPP is available on the OSHA website at http://www.osha.gov/dcsp/vpp/index.html . All contractors, whether regularly involved in routine site operations or engaged in temporary projects such as construction or repair, must follow the safety and health rules of Watervliet Arsenal.

Applicable contractors are required to annually submit to Watervliet Arsenal, ATTN: TAWV-XO-S/Safety Office, Bldg. 10, 1 Buffington Street, Watervliet, NY 12189-4000 or email: usarmy.watervliet.tacom.list.wate-safety@mail.mil the following documents (covering the previous calendar year quarters) by 15 January:

- Total Case Incidence Rate (TCIR) - the number of recordable injuries and illness cases per 100 full-time employees that a site has experienced in a given time frame.

- Days Away, Restricted, and/or Transfer Case Incident Rate (DART) - Number of recordable injuries and illness cases per 100 full-time employees resulting in days away from work, restricted work activity, and/or job transfer that a site has experienced in a given time frame.

- OSHA Form 300A

Applicable contractors may submit the above immediately following the completion of a quarter, if desired.

H._1_ SERVICES/CONSTRUCTION REQUIREMENTS

(a) SCHEDULE UNIT OF MEASURE NOTE: When "LOT" is stated as a unit of measure it is the equivalent to

"JOB".

(b) WORK PERFORMED ON-SITE AT WATERVLIET ARSENAL:

The contractor agrees that each employee working at Watervliet Arsenal will sign the “Contractor Personnel Agreement on Non-Disclosure of Watervliet Arsenal Technology below. Signatures must be received by the Contract Administrator before work may begin and any resultant delay won’t be considered an excusable delay to contract performance as defined in the contract clause “Default”. Additional copies of this Non-Disclosure Statement can be found on the Internet at http://www.wva.army.mil/Documents/Contracting/nondis.pdf

(d) CONTRACTOR PERSONNEL AGREEMENT ON NON-DISCLOSURE

OF WATERVLIET ARSENAL TECHNOLOGY

(1) The Undersigned, as an employee of _________________________ (Name of Firm) agrees to the following terms and conditions.

(2) Any knowledge gained, as a result of my being permitted on Watervliet Arsenal’s premises, concerning cannon production technology (as defined below) or other technology on any defense item being manufactured or developed at Watervliet Arsenal, will not be released outside of _________________________ (Name of firm) and/or the United States of America (this prohibition includes, but is not limited to, the company’s domestic and foreign subsidiaries, affiliates, etc.), nor will such technology be used to manufacture or assist another in the manufacture of cannon (as described below) or other defense items being manufactured or developed at Watervliet Arsenal, without the written prior approval of Watervliet Arsenal.

(3) Definitions:

(a) CANNON: is defined as any and all components/parts of a complete assembly consisting of a tube, breech mechanism, tube attachments, muzzle appendages, firing mechanisms, and all integral components.

It may also be a component of a weapons system of 40mm Bore or over such as tank guns, towed and self-propelled howitzers, naval guns, mortars and recoilless guns.

(b) CANNON PRODUCTION TECHNOLOGY: is defined as the technical data package and manufacturing technology.

(1) TECHNICAL DATA PACKAGE: cannon engineering drawings, specifications and standards.

(2) MANUFACTURING TECHNOLOGY: technical knowledge, documentation, assistance and equipment and machines used and/or useful in the manufacturing of cannon.

(c) TECHNICAL KNOWLEDGE: the know how collected, trade secrets, production experience and special skills necessary for the production of cannon and the technical information and inventions necessary for the manufacture of cannon and relating to the manufacture of cannon.

(d) TECHNICAL DOCUMENTATION: manufacturing technical data comprised of drawings, specifications, schemes, composition, descriptions, methods of calculations, instructions and other information necessary for the manufacture of cannon.

(e) TECHNICAL ASSISTANCE: all assistance required to make practical and economical use of the technology required to manufacture cannon, such as delivery of documentation, training of personnel, instructions, consultations and acquainting of specialists with the most economical method of using this technology in the manufacture of cannon.

(f) EQUIPMENT AND MACHINES: production machines, machine accessories, apparatuses, spare parts and tooling used for cannon manufacture.

TYPED OR PRINTED NAME, SIGNATURE DATE

TYPED OR PRINTED NAME, SIGNATURE DATE

TYPED OR PRINTED NAME, SIGNATURE DATE

(e) JOB SITE AVAILABILITY:

The work site will be available for performance during normal business hours:

Monday through Thursday Business Hours: 7:00 a.m. EST to 3:00 p.m. EST

Friday Business Hours: Every other Friday from 7:00 a.m. EST to 2:00 p.m. EST

Fridays will be staggered with every other Friday being a closed business day. The first Friday of 2023 to be closed is January 13, 2023.

Based on the above, service contractors should call contract/purchase order administrator in advance if service is scheduled for a Friday to determine if the Arsenal will be open for business.

When a federal holiday is normally observed on Friday, the Arsenal may be closed on the preceding Thursday. In this case, contact the contract/purchase order administrator in advance if scheduling service to determine if the Arsenal will be open for business.

Work at other than the above hours won’t be allowed unless the contractor makes an application at least 48 hours in advance and gets written contracting officer approval. No guarantee is made that the job site will be made available other than as stated above.

(f) CONTROL OF FOREIGN VISITORS TO WATERVLIET ARSENAL:

Offerors are advised that any employee or representative of their company who is not a U.S. citizen, (or is representing a foreign company) and is a U.S. citizen), planning on visiting the Watervliet Arsenal for the purpose of attending: bid conferences, bid openings, site visits, engineering services, or any other visit related to this solicitation will be escorted at all times by an arsenal representative while on the installation grounds.

Therefore, offerors must notify the Contracting Officer in advance (a minimum of two [2] weeks) of any proposed visit by a non-U.S. citizen or U.S. citizen representing a foreign firm, to assure proper clearance for entry into the arsenal. Failure to comply, or disclose a foreign national visitor, may subject the Contractor to the penalties set forth in 18 U.S.C.A. Section 1001, Chapter 14.

Due to manpower constraints, Watervliet Arsenal is often unable to provide escort services during contract performance. Therefore, if the resulting contract requires performance on Watervliet Arsenal property, employees, individuals or subcontractors representing the successful offeror who are not U.S. citizens may not, depending on staffing levels and the availability of escorts, be allowed access to the Arsenal for purpose of contract performance.

Be further advised that the inability of the Arsenal to provide escorts resulting in denial of access to Watervliet Arsenal of the aforementioned personnel will not be considered an excusable delay to contract performance as defined in the contract clause “Default” contained in the contract. Therefore, offerors should consider the above contingencies during offer preparation.

(h) CONTRACTOR IDENTIFICATION:

Contractor employees shall identify themselves as contractor personnel by introducing themselves or being introduced as contractor personnel and displaying distinguishing badges or other visible identification for meetings with Government personnel. In addition, contractor personnel shall appropriately identify themselves as contractor employees in telephone conversations and in formal and informal written correspondence, and when working in situations where their actions could be construed as official government acts.

A.__ Electronic Contracting Electronic Bids/Proposals/Commercial Offers Required in Response to this Solicitation (June 2020) ACC-WVA

(a) All Army Contracting Command – Watervliet Arsenal (WVA) solicitations will be publicized on the SAM.gov website (https://sam.gov /). Any additional attachments, including Technical Data Packages, when available electronically, will be separate attachments or links embedded in the solicitation.

(b) Bids/Proposals must be submitted in electronic media. When submitting your bid/proposal electronically, the bid/proposal and any supplemental information (such as spreadsheets, backup data, technical information), can be submitted using any of the following electronic formats:

(1) Microsoft* Office Products (Watervliet can read Microsoft* Office 2007 and lower); Word, Excel, or PowerPoint. Spreadsheets must be sent in a format that includes all formulate macro and format information. Print image is not acceptable.

(2) Files in Adobe PDF (Portable Document Format). Scanners should be set to 300 dots per inch.

(3) Files in HTML (Hypertext Markup Language). HTML documents must not contain active links to live Internet sites or pages. All linked information must be contained within your electronic bid/offer and be accessible offline.

(4) Other electronic formats are not acceptable.

(c) Please select only one medium by which to transmit each bid/proposal.

(d) Timely receipt of offers/proposals:

(1) Your attention is called to the solicitation closing date and time on the solicitation is local time for the Army Contracting Command – Watervliet Arsenal (WVA). Lateness rules for electronic submissions for bids are outlined in FAR 52.214-7, “Late Submissions, Modifications, and Withdrawal of Bids,” for proposals in FAR 52.215-1, “Instructions to Offerors—Competitive Acquisition” or FAR 52.212-1, “Instructions to Offerors-Commercial Items.” Pay particular attention to the applicable clause as it relates to the timing of submissions.

(2) NOTE: There is no “expected” or “target” length of time for proposal submission; size and content may be factors, therefore offerors are strongly cautioned to submit their proposals allowing adequate time for submission.

(3) Solicitations may remain posted on the SAM.gov website after the solicitation closes. Even though the system may allow you to submit a proposal after the closing date/time, your proposal will be considered late and may not be considered for award.

(e) Security Note: If you choose to password-protect access to your bid/offer, you must provide the password to Watervliet Arsenal at least ten days prior to the opening/closing date. Contact the buyer identified in “Watervliet

Arsenal Information/Requirements”. Passwords used only for the purpose of write protecting files need not be provided.

(f) Electronic bids/proposals must include, as minimum:

(1) E-mailed bids/proposals must include a signed SF 33 cover sheet, SF 1449 or SF 1442 (whichever is applicable) that can be scanned. If scanned, attach it to your e-mail offer (or first e-mail message if you are sending multiple e-mails due to length).

(2) All applicable fill-in provisions. For solicitations issued on an SF 33 or SF 1442, this would include Sections A, B, F, and K. For solicitations issued on an SF 1449, you must review the solicitation to ascertain where all of the required fill-ins are located since commercial acquisitions do not have designated sections.

(3) A statement of agreement to all the terms, conditions, and provisions of the solicitation.

(4) Any other information required by the solicitation.

(g) Please see FAR 14.406 for a description of the steps the Government shall take with regard to unreadable electronic bids received via the media described in paragraphs (b) above. See FAR 15.207(c) for a description of steps the government shall take with regard to unreadable proposals.

(h) Bidders/Offerors shall make every effort to ensure that their bid/proposal is virus-free. Bids/proposals (or portions thereof) submitted which DO reflect the presence of a virus, or which are otherwise rendered unreadable by damage in electronic transit, shall be treated as “unreadable” per paragraph (h) above. Use of any formats other than those listed above may result in the file being quarantined and will be considered by Watervliet Arsenal to be “unreadable” files.

Note (Macros): The virus scanning software used by our e-mail systems cannot always distinguish a macro from a virus. Therefore, sending a macro embedded in an email message or an email attachment may cause the email bid/offer to be quarantined. In that event paragraph (g) above applies.

*Registered trademark

C.__ REQUEST FOR QUOTE RESPONSES

ALL RESPONSES MUST BE ELECTRONIC. YOU MUST SUBMIT YOUR QUOTE RESPONSES USING

THE FOLLOWING METHODS:

(a) Email to: maria.d.decrescenzo.civ@army.mil

(b) Request for Quotes must be filled out completely and sent in its entirety to be considered responsive.

VEGITATION CONTROL SOW

STATEMENT OF WORK (SOW)

VEGETATION CONTROL

PART 1 GENERAL

1.01 Overview.

A. This Statement of Work (SOW) defines the effort required for the performance of the Watervliet Arsenal’s vegetation control and pesticide (herbicide, fungicide and insecticide) program.

1. The program shall include the elimination of broadleaf weeds, weeds and crabgrass from the

Watervliet Arsenal lawns and grounds. Project work includes the elimination of all vegetation from specific areas as defined in the scope of work.

2. Project work EXCLUDES GOLF COURSE GREENS.

3. All work shall be performed in accordance with the Watervliet Arsenal’s Pest Management plan, 200-5, federal and local regulations.

1.02 Hours of Operation.

A. Normal duty hours are 7:00 AM through 4:00 PM, Monday through Thursday, and 7:00 AM through 3:00 PM on select Fridays (the arsenal is closed every-other Friday). Federal holidays are non-work days. If a federal holiday falls on a Saturday or Sunday, the preceding Friday or following Monday is a work holiday. Work taking place outside normal duty hours must be requested, approved and coordinated in advance.

1.03 General Requirements.

A. The contractor shall perform all work in strict conformance with Watervliet Arsenal Instructions for Contractors (WAIC). The contractor shall read and understand this document prior to submitting a proposal. The WAIC is publically available at:

http://www.wva.army.mil/Documents/Contracting/WAIC.pdf

B. The contractor shall supply all tools, materials, supplies, equipment, labor, temporary utilities and supervision necessary for the complete execution of the requirements within the contract documents and requirements of this SOW.

C. The contractor shall, prior to submitting a proposal, review (i) all contract documents, and (ii) the project work site, and shall provide written notice to Contracting Specialist detailing any discrepancies that are found between the contract documents and the project work site.

D. The contractor shall notify the Contracting Specialist a minimum of two (2) business days before the contractor starts work. The contractor shall notify the COR a minimum of seven (7) business days before the shut-down of a utility or building service.

E. The contactor shall clean all work areas, at the end of each work day, to remove all tools, equipment, debris, materials, and all waste from the work site.

1.04 Safety Requirements.

A. General.

1. The contractor shall be responsible for complying with all DOD, Army, Federal, and State health and safety requirements which are applicable to this project, and shall use all means and precautions available to ensure the safety of the occupants and protection to the existing buildings and structures.

A. Contractor Safety Plan.

1. The contractor shall submit a safety plan which is specific to the work activity being performed under the scope of this project for Government review and approval.

B. PPE Requirements.

1. The contractor shall don all personal protective equipment (PPE) required and recommended by the pesticide manufacturer. PPE use will be monitored by the project COR, WVA’s Industrial Hygiene Office and WVA’s Pest Management Coordinator (PMC). Failure to comply with manufacturer’s recommendations will result in a “Stop Work Order” at no cost to the government.

C. Adverse Weather Conditions.

1. No work shall be performed during adverse weather conditions that may contribute to pesticides drifting to non-target areas or vegetation, or are in violation of the pesticide application instructions.

D. Spill Control.

1. The contractor shall carry a spill kit as specified in the Pest Management Plan to address spills to the environment. The contractor shall shut down application equipment to prevent further spillage. The contractor shall call the WVA’s Emergency Response line, (518) 266-5222, to report the incident. The contractor shall have the capability of contacting the Emergency Response line at all times, without tracking pesticides into any Watervliet Arsenal buildings.

The contractor shall remain at the spill site, at a safe distance, to provide information to reporting response unit. The contractor shall be responsible for all costs associated with cleanup activities related to the contractor’s spill.

E. Chemical Mixing and Storage.

1. No chemicals shall be mixed or stored on Watervliet Arsenal property. All mixing shall take place prior to admittance to the Watervliet Arsenal. The contractor must have a Commercial Pesticide Category “3B – Turf” and “6A – Right-of-Way Vegetation Control” license.

F. Safety Data Sheets (SDS).

1. The contractor shall submit SDSs and all chemical product data with the bid package.

G. Medical Emergency.

1. The contractor shall contact Watervliet Arsenal’s Emergency Response line, (518) 266-5222, in the event of a medical emergency. The Watervliet Arsenal’s emergency response team will respond accordingly.

1.02 Contractor Personnel.

A. Contract Manager. The contractor shall provide a Contract Manager who shall be responsible for the performance of work. The name of this person, and an alternate or alternates, who shall act for the contractor when the manager is absent, shall be designated in writing to the contracting officer. The contract manager or alternate shall be available, during normal duty hours, within Watervliet Arsenal to meet on the installation with government personnel (designated by the contracting officer) to discuss problem areas.

B. Contractor Employees. The contractor shall not employ any person for work on this contract if such employee is identified to the contractor by the contracting officer and/or Watervliet Arsenal security as a potential threat to the health, safety, security, general well-being or operational mission of the installation and its population.

C. Pesticide License. All contractor employees shall be licensed for the activity which they are to perform. Evidence of certification shall be furnished, in writing, to the CO and approval given prior to employee beginning work. The Contractor shall possess a current Commercial State of New York License. Each of the Contractor’s personnel (pest applicator) that apply pesticides shall have a current Commercial State of New York Applicator’s License with a category 6a. The license must always be from the state in which work will occur.

1.03 Period of Performance.

A. The contractor shall be required to (i) commence work under this contract within 7 calendar days after the date the contractor receives notice to proceed, (ii) prosecute the work diligently.

1.04 Project Schedule.

A. The contractor shall create a project schedule and submit for Government review and approval. The project schedule shall detail the phases of work and the overall timeline for the execution of the work.

The contractor shall include delivery dates, appropriate milestones, and shall clearly detail any requirements for work performed outside of regular hours of operation.

1.05 Equipment Identification.

A. The contractor shall create and affix a label to all large equipment, dumpsters, and other mobilized property, which is weather-resistant (laminated, or within a see-thru label hanger), securely affixed to the equipment or visible through a window, and which clearly displays the General Contractor’s:

1. Company name

2. POC name (first, last)

3. POC phone number

4. Project Number (see title page of SOW)

1.06 Applicable Documents.

A. Watervliet Arsenal Instructions for Contractors (WAIC).

B. Environmental Conservation Law Sections 33-1004 and 33-1005.

C. New York State regulation 6 NYCRR Section 325.41.

D. Environmental Conservation Law Article 33, Title 12

1.07 Submittals.

A. The contractor shall e-mail all submittals to the Contracting Specialist for review and approval. All submittals require government approval unless otherwise explicitly stated.

B. The contractor shall reference APPENDIX A “Consolidated List of Submittals” for complete list of required submittals.

C. The contractor shall provide a copy of pesticide usage in accordance with the New York State Pesticide Reporting Law (Environmental Conservation Law Article 33, Title 12), for all chemicals and pesticides used at Watervliet Arsenal each year. The contractor shall complete a Pest

Management Report (DD Form 1532) and Pest Management Maintenance Record (DD Form 1532-1).

Reports must include: Pesticide type, total yearly usage, total amount (in lbs.) of Active Ingredient (AI) used, updates on applicators, applicator certifications and expiration dates, EPA Registration number of each pesticide used and locations applied. Reports shall be submitted no later than 1 January.

PART 1 PRODUCTS

1.01 General.

A. Unless otherwise stated, all materials for this project shall be new. All products shall not contain any asbestos, mercury, chromium/lead paint, Class I Freon, and Polychlorinated Biphenyls (PCB), and shall state such on the manufacturer’s original packaging.

B. All work shall be in strict accordance with product manufacturer’s instructions and specifications, including but not limited to manufacturer guidance for storage, staging, application, installation, and disposal of the product.

C. All construction materials shall meet the applicable requirements of the DoD Green Procurement Program, specifically recycled content products, environmentally preferable products and services, biobased products, energy-and water-efficient products, alternate fuel vehicles and alternative fuels, products using renewable energy, and alternatives to hazardous or toxic chemicals as found at <http://www.acq.osd.mil/dpap/cpic/cp/docs/USA001967-08-DPAP.pdf>.

PART 2 – HERBICIDE, FUNGICIDE AND INSECTICIDE

2.01 Land Use and Layout of Facilities.

A. The Watervliet Arsenal is made up of seventy-two (72) building and ten (10) structures on an area of

140.5 acres. The facility consists of 34.3 acres of improved grounds, 17 acres of semi-improved grounds and 91 acres of unimproved grounds. The facility contains wooden buildings and structures subject to biological deterioration, as well as several miles of railroad track. The facility presently contains twenty-two (22) military family housing quarters. See Appendix C – Watervliet Arsenal Site Map, Grass Plan

2.02 Basic Services.

A. Crabgrass, broadleaf and miscellaneous weeds – Approximately 20 acres, Minimum Three (3) Applications.

The contractor shall eliminate crabgrass, broadleaf and miscellaneous weeds from the Watervliet Arsenal lawns, athletic fields, golf course (excluding greens), cemetery, playgrounds and parks.

Treatments shall include the areas under hedges and shrubs. The total area for application is approximately 20 acres. Refer to Appendix C, “Watervliet Arsenal Site Map, Grass Plan”.

1. One (1) pre-emergent application shall be applied in early spring. Three (2) selective weed control applications shall be applied, one in late spring and fall.

2. The contractor shall not spray the children’s playground, swimming pool area or the pavilion areas between June 1st and October 15th.

3. Remediation areas in “Siberia” can only be sprayed using Roundup or similarly approved produce.

4. To meet the requirements of this section of the SOW, the contractor shall eliminate crabgrass, broadleaf and miscellaneous weeds from the Watervliet Arsenal lawns and grounds.

B. White Grub application - Approximately 20 acres, Minimum One (1) Application.

The contractor shall apply White Grub application to the Watervliet Arsenal lawns, athletic fields, golf course (excluding greens), cemetery, playgrounds and parks. Treatments shall include the areas under hedges and shrubs. The total area for application is approximately 20 acres. Refer to Appendix C, “Watervliet Arsenal Site Map, Grass Plan”.

1. One application to be applied between June and August.

2. To meet the requirements of this section of the SOW, the contractor shall apply white grub application to the Watervliet Arsenal lawns and grounds.

C. Non-Selective Weed Application – Approximately 30 acres, Minimum One (1) Application

The contractor shall perform vegetation elimination services with non-selective weed application to the Watervliet Arsenal stock areas, electrical sub-stations, railroad tracks (minimum of 12 inches on either side), all sidewalks (including those on the exterior perimeter along Broadway Street and I55 roadways), stairs, curbs, roadways, monuments, all building within 6 inches, all trees with a diameter of 4 inches or more, all fence lines and designated landscaped areas. The total area for application is approximately 30 acres.

1. Four (4) optional non-selective touch-up applications in between main spraying maybe required at the request of COR or CO with a notification of one (1) week in advance.

2. One initial treatment to be applied on or before 1 June (weather permitting) unless otherwise negotiated with COR or Contracting Officer (CO).

3. The contractor is required to perform monthly inspections and perform necessary spot treatments to maintain weed free areas using a Non-Selective weed application using chemicals approved by Safety and Environmental Office.

4. To meet the requirements of this section of the SOW, the contractor shall eliminate weeds and vegetation from the Watervliet Arsenal stock areas, electrical sub-stations, railroad tracks (minimum of 12 inches on either side), all sidewalks (including those on the exterior perimeter along Broadway Street and I55 roadways), stairs, curbs, roadways, monuments, all building within 6 inches, all trees with a diameter of 4 inches or more, all fence lines and designated landscaped areas. .

2.03 Notification Requirements.

A. The contractor shall provide notification a minimum of 48 hours prior to application to Watervliet Arsenal residents and Albany County residents neighboring the Watervliet Arsenal grounds, in accordance with Environmental Conservation Law Sections 33-1004 and 33-1005 and New York State regulation 6 NYCRR Section 325.41.

1. Notice for Arsenal employees and tenants shall be submitted via email to;

Marc Kouffman, Watervliet Arsenal Grounds and Operations Supervisor Email: marc.s.kouffman.civ@mail.mil Phone (Desk): (518) 266-4849 Phone (Cell): (518) 944-8057

If the contractor is unable to reach the WVA employee listed above within the allocated time frame please contact either;

Maria Decrescenzo, Contract Specialist Email: maria.d.decrescenzo.civ@mail.mil Phone: (518) 266-4641

PART 3 CLOSEOUT REQUIREMENTS

3.01 Cleanup of Work Site.

A. The contactor shall clean all work areas and remove all tools, equipment, debris, materials, and all waste from the premises.

B. The contractor shall remove all debris from any remote holding locations, to include any excavation and concrete equipment chute cleanout debris.

C. The contractor shall remove their equipment from Watervliet Arsenal premises within five (5) working days after completion of project work.

PART 4 APPENDICES

A. Consolidated List of Submittals B. Quality Assurance Surveillance Plan (QASP) C. Watervliet Arsenal Site Map, Grass Plan

APPENDIX A: Consolidated List of Submittals Line Item Submitted Submittal Needed By Submittal Reviewed By (Office)

1 Safety Data Sheets for Hazardous Materials

(SDS)

NLT 7 Calendar Days After Award

Safety Office

2 Signed Contractor Asbestos Notification Form NLT 7 Calendar Days After Award

Environmental Office

3 Signed Lockout/Tagout (LOTO) Notification Acknowledgement Record

NLT 7 Calendar Days After Award

Safety Office

4 Project Schedule NLT 7 Calendar Days After Award

COR

5 Employee Pesticide Application Certificates NLT 7 Calendar Days After Award

COR

6 Pest Management Report (DD Form 1532) and Pest Management Maintenance Record (DD Form 1532-1)

Environmental Office

7 Pesticide Use Proposal (PUP) and Plan Update Form (PUF)

Environmental Office

PEST CONTROL SOW

STATEMENT OF WORK FOR PEST CONTROL SERVICES

1. DESCRIPTION OF SERVICES. The contractor shall provide all management, licenses, tools, supplies, chemicals, equipment, transportation and labor to develop and implement Integrated Pest Management (IPM) control at Watervliet Arsenal; in a manner that will ensure the health and general well being of installation personnel.

The following types of pests are common on this installation, and their abatement should be specifically addressed:

Pests include - termites, mosquitoes, crawling insects, spiders, mice, birds (pigeons in buildings), and other vertebrate pest. . These pests may be found in any building or any grounds at Watervliet Arsenal. Domestic animals are excluded from this contract.

2. PROGRAM OBJECTIVE - To perform integrated pest management while employing a judicious use of both chemical and non-chemical control techniques that achieve effective pest control with minimal environmental contamination. All pest control will be in compliance with pertinent laws and regulations.

3. BASIC SERVICES 3.1 Pest Control Preventive Maintenance Program. - Contractor to inspect and apply chemicals as required preventing infestation of all Watervliet Arsenal Food Service Buildings on a monthly basis.

Areas include Snack bars located in bldg 10, 20, 25-3, 35, 40-4, Officers Club and Cafeteria area in Bldg 21.

Inspections occur on the first Wednesday of every month.

3.2 Service Call Work. A service call is an unscheduled request for pest control services initiated by building or family housing occupants, or by designated Government representatives. The Government's work reception center will advise the Contractor by phone of all service call requests received and the classification of each call as either emergency or routine based on the definitions provided below. A description of the pest problem, date and time received, location, classification, and other appropriate information will be placed on a Service Call Work Form.

Service calls may be for pest control services and nuisance pest removal (live or dead) in all Arsenal buildings on an as needed basis.

3.2.1 Emergency Calls. Emergency calls will consist of obtaining control of pests which could affect the health or well being of personnel. The Contractor shall respond immediately and must be on site to provide an initial inspection and treatment within 2 hours after receipt of an emergency call.

3.2.2 Routine Calls. All non-emergency service calls will be classified as routine. The Contractor shall complete the initial inspection and treatment for each routine service call within 48 hours (two days) working days after receipt.

3.3 Call Backs. The Contractor shall perform corrective action within 48 hours (except Sundays and holidays) after receipt of notice from the COR or CO that inspection has revealed control limits have been exceeded. Call backs shall be made at no additional cost to the Gsovernment; there is no limit to the number of call backs.

4.PERFORMANCE

JOB ELEMENT

STANDARD

REMEDIATION

Para 3.1 Inspection/Preventive of Food Handling Areas

Inspect Areas Monthly/Preventative measure for any infestation

No more than two customer complaints and 2 call backs per month

Para 3.2.1 Emergency Calls

Respond within 2 hours No more than two customer complaints and 2 call backs per month

Para 3.2.2 Routine Calls

Respond with 48 hours No more than two customer complaints and 2 call backs per month

5. QUALITY ASSURANCE. The government representative will evaluate the contractors by intermittent on-site inspections and receipts of complaints from base personnel

6. GOVERNMENT REMEDIES. Failure to meet performance standard on two of the 12 months period of performance could be grounds for not exercising next year option year. Contractor’s failure to correct nonconforming services the contracting officer shall follow the requirements of FAR 52.212-4, Contract Terms and Conditions for Commercial Items (May 1997).

7. HOURS OF OPERATION. Visitors will only be allowed access to Watervliet Arsenal during normal duty hours, which are 6:30 AM through 4:00PM, Monday through Thursday, and 6:30 AM through 3:00 PM work Fridays (the arsenal is closed every other Friday). Work may be performed on shutdown Fridays, after normal duty hours, Saturdays, Sundays or holidays only after prior arrangements have been requested and approved in advance.

Requests to work other than normal duty hours must be submitted 48 hours in advance to the COR. If a Federal holiday falls on a Saturday or Sunday, the preceding Friday or following Monday is the work holiday. The COR or Arsenal Point of Contact will submit a request to the Security Office and arrange for a responsible arsenal POC to be on post at all times when the visitor is on post.

8. SECURITY REQUIREMENTS. Contractor employees must be U.S. citizens and sign in at the gate to gain access to Watervliet Arsenal. They will be issued visitor badges and must follow speed limits, as posted and park in parking spaces as painted.

9. SPECIAL QUALIFICATIONS. The contractor will have a licensed pest control manager specifically assigned to support this contract and available within 24 hours to meet with government personnel. Moreover, all contract employees that apply pesticides must have a New York State pesticide application certificate/license a copy of this certification should be submitted with proposal. The contractor will be responsible to ensure that the licenses/certificates and training of contractor personnel are kept current.

9.1 CHEMICALS - All mixing and storage of pesticides shall be performed off the installation. If the contractor spills or releases any hazardous substances (example, Substances listed in 40 CFR 302), the contractor must immediately notify the Government Representative and base environmental coordinator by dialing 5888 on an Arsenal phone, or 266-5888 on an outside phone, for spill response.

10- OTHER REQUIREMENTS:

10.1 - Contractor shall provide a copy of the New York State report of pesticides used at Watervliet Arsenal each year, not later than February 5th of each year, for the previous year. This report must include: Pesticide used, amount in pounds, EPA Registration number of each pesticide used and the % of active ingredients (as found on the label) and location applied.

CLAUSES INCORPORATED BY FULL TEXT

252.232-7006 WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (JAN 2023)

(a) Definitions. As used in this clause—

“Department of Defense Activity Address Code (DoDAAC)” is a six position code that uniquely identifies a unit, activity, or organization.

“Document type” means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).

“Local processing office (LPO)” is the office responsible for payment certification when payment certification is done external to the entitlement system.

“Payment request” and “receiving report” are defined in the clause at 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.

(b) Electronic invoicing. The WAWF system provides the method to electronically process vendor payment requests and receiving reports, as authorized by Defense Federal Acquisition Regulation Supplement (DFARS) 252.232- 7003, Electronic Submission of Payment Requests and Receiving Reports.

(c) WAWF access. To access WAWF, the Contractor shall—

(1) Have a designated electronic business point of contact in the System for Award Management at https://www.sam.gov; and

(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this web site.

(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web-Based Training Course and use the Practice Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the “Web Based Training” link on the WAWF home page at https://wawf.eb.mil/.

(e) WAWF methods of document submission. Document submissions may be via web entry, Electronic Data Interchange, or File Transfer Protocol.

(f) WAWF payment instructions. The Contractor shall use the following information when submitting payment requests and receiving reports in WAWF for this contract or task or delivery order:

(1) Document type. The Contractor shall submit payment requests using the following document type(s):

(i) For cost-type line items, including labor-hour or time-and-materials, submit a cost voucher.

(ii) For fixed price line items—

(A) That require shipment of a deliverable, submit the invoice and receiving report specified by the Contracting Officer.

N/A

(B) For services that do not require shipment of a deliverable, submit either the Invoice 2in1, which meets the requirements for the invoice and receiving report, or the applicable invoice and receiving report, as specified by the Contracting Officer.

Invoice as 2-in-1 (Services Only)

(iii) For customary progress payments based on costs incurred, submit a progress payment request.

(iv) For performance based payments, submit a performance based payment request.

(v) For commercial item financing, submit a commercial item financing request.

(2) Fast Pay requests are only permitted when Federal Acquisition Regulation (FAR) 52.213-1 is included in the contract.

(3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system.

Routing Data Table*

Field Name in WAWF Data to be entered in WAWF

Pay Official DoDAAC HQ0303

Issue By DoDAAC W911PT

Admin DoDAAC** W911PT

Inspect By DoDAAC N/A

Ship To Code N/A

Ship From Code N/A

Mark For Code N/A

Service Approver (DoDAAC) N/A

Service Acceptor (DoDAAC) W911PT

Accept at Other DoDAAC N/A

LPO DoDAAC N/A

DCAA Auditor DoDAAC N/A

Other DoDAAC(s) N/A

(4) Payment request. The Contractor shall ensure a payment request includes documentation appropriate to the type of payment request in accordance with the payment clause, contract financing clause, or Federal Acquisition Regulation 52.216-7, Allowable Cost and Payment, as applicable.

(5) Receiving report. The Contractor shall ensure a receiving report meets the requirements of DFARS Appendix F.

(g) WAWF point of contact.

(1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity’s WAWF point of contact.

N/A

(2) Contact the WAWF helpdesk at 866-618-5988, if assistance is needed.

(End of clause)

Section SF 1449 - CONTINUATION SHEET

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Lot

POST WIDE PEST CONTROL

FFP

The contractor shall provide all management, licenses, tools, supplies, chemicals, equipment, transportation and labor to develop and implement Integrated Pest Management (IPM) control at Watervliet Arsenal, to include pigeon control/elimination program. See Statement of Work for all detailed information.

Billing monthly in arrears.

Billing monthly: $__________

Service Contract Act, current revision, applies and is incorporated.

Technical POC Marc Kouffman

FUND TYPE: AWCF, SIO: 69042, COST CENTER: M7PEST

FOB: Destination

NSN: AASSVC3025018T

MILSTRIP: W16H1F3025018T

PURCHASE REQUEST NUMBER: W16H1F3025018T

PSC CD: F105

NET AMT

0002 1 Lot

POST WIDE WEED CONTROL

FFP

POST WIDE WEED AND VEGETATION CONTROL APPLICATION per ATTACHED PERFORMANCE WORK SCOPE (PWS) which is hereto attached and incorporated.

Service Contract Labor Standards 15-4143 (current revision), applies and is incorporated.

Price per each Optional Non Selective Touch Up Applications (not to exceed 4 each) $________. Any applications not used will be removed at end of period of performance.

Technical POC is MARC KOUFFMAN

FUND TYPE: AWCF, SIO: 69042, COST CENTER: M7PEST

FOB: Destination

NSN: AASSVC3025018N

MILSTRIP: W16H1F3025018N

PURCHASE REQUEST NUMBER: W16H1F3025018N

0003 1 Lot

OPTION POST WIDE PEST CONTROL

FFP

The contractor shall provide all management, licenses, tools, supplies, chemicals, equipment, transportation and labor to develop and implement Integrated Pest Management (IPM) control at Watervliet Arsenal, to include pigeon control/elimination program. See Statement of Work for all detailed information.

Billing monthly in arrears.

Billing monthly: $__________

Service Contract Act, current revision, applies and is incorporated.

Technical POC Marc Kouffman

FUND TYPE: AWCF, SIO: 69042, COST CENTER: M7PEST

FOB: Destination

NSN: AASSVC3025018T

MILSTRIP: W16H1F3025018T

0004 1 Lot

OPTION POST WIDE WEED CONTROL

FFP

POST WIDE WEED AND VEGETATION CONTROL APPLICATION per ATTACHED PERFORMANCE WORK SCOPE (PWS) which is hereto…

This is the start of the file's text. The full file is on GovTribe.