W911N2-22-Q-0045 0003 amendment.pdf
PDF 369 KB Posted
- Attached to
- Medium CNC Vertical Milling Machine Federal contract opportunity
- Solicitation number
- W911N222Q0045
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| W911N2-22-Q-0045 0002.pdf | ||
| W911N2-22-Q-0045 0001.pdf | ||
| SOL W911N222Q0045.pdf | ||
| Attachment - Safety Review.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TREVOR L. MONN
LETTERKENNY CONTRACTING OFFICE
1 OVERCASH AVENUE, CCAM-MLK
717-267-9361
CHAMBERSBURG PA 17201-4150
W25G1Q216000OG
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to revise Section 4..2.3 of the Purchase Description due to technical oversight, and extend the Offer Due Date by three (3) business days to 2 September 2022.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 12
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 29-Aug-2022
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W911N222Q0045
X 9B. DATED (SEE ITEM 11)
28-Jul-2022
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
29-Aug-2022
CODE
LETTERKENNY ARMY DEPOT
LETTERKENNY CONTRACTING OFFICE - ACC-RSA-LEAD
1 OVERCASH AVENUE, ATTN: CCAM-MLK, BLDG 2S
CHAMBERSBURG PA 17201-4150
W911N2 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE W911N2
FACILITY CODECODE
EMAIL:TEL:
W911N222Q0045
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 1449 - CONTINUATION SHEET
SOLICITATION/CONTRACT FORM
The required response date/time has changed from 30-Aug-2022 03:00 PM to 02-Sep-2022 03:00 PM.
The following have been added by full text:
REVISED PURCHASE DESCRIPTION
LETTERKENNY ARMY DEPOT
PURCHASE DESCRIPTION
MEDIUM CNC VERTICAL MILL
BLDG 350 ANNEX
1.0 GENERAL INFORMATION:
1.1 SCOPE: Request the purchase of one (1) medium sized Computer Numerically Controlled (CNC) vertical mill. This specification establishes the minimum requirements for the purchase of contractor installed medium CNC vertical mill at Letterkenny Army Depot (LEAD). The contractor shall provide all professional architectural, engineering and construction services for the preparation of all necessary drawings, specifications, calculations, cost estimates and related design, permits, fabrication, construction, installation and testing services for the completion of this project. The vertical mill shall be installed turnkey in accordance with Original Equipment Manufacturer specification and standards. Specifications are based upon commercially available products and shall meet or exceed the minimum requirements specified in section 4.0 Specifications.
1.2 PLACE AND PERFORMANCE OF INSTALLATION: All work shall be performed in building 350
Annex between the hours of 6:00 AM and 3:30 PM, Monday thru Thursday, exclusive of Federal Holidays and special depot closures (typically the Monday before or Thursday after Federal Holidays that fall on a Saturday, Sunday, Tuesday or Thursday). Other hours, weekend, and holiday work will be considered separately as requested by the contractor with adequate advanced notice and approved by the Contracting Officer.
1.3 SECURITY REQUIREMENTS: Contractor and all associated sub-contractor’s employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Risk Management or Security Office. Contractor workforce shall comply with all personal identity verification requirements as directed by DOD, HQDA and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes. The contractor and all associated subcontractor employees shall also comply with adjudication standards and processes using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014- 05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
1.3.1 Security, Safety and Fire Protection: All work shall comply with LEAD Regulation 385-1 and Pamphlet 385-4. The equipment and the installation shall also meet all the safety criteria set forth in OSHA 1926.501 and ANSI/ASSE Z359.
1.3.2 Media Devices: All pictures shall be taken by LEAD representative and approved before release.
1.3.3 AT Level I Awareness Training: All contractor employees, to included subcontractor employees, requiring access to Army Installations, facilities, and controlled access areas shall complete AT Level 1 awareness training within 30 calendar days after contract start date and within 30 calendar days of new employees commencing performance. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 15 calendar days after completion of training. AT level 1 awareness training is available on the Letterkenny Army Depot homepage – www.lead.army.mil
1.3.4 Physical Security: The contractor shall safeguard all Government property provided for contractor use. At the close of each work period, Government facilities, equipment and materials shall be secured.
1.3.5 iWATCH Training: The contractor and all associated sub-contractors with an area of performance within an Army-controlled installation, facilities or area shall brief all employees on the local iWATCH program.
This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR or contracting officer. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance. The contractor shall report completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 15 calendar days after completion of training. iWATCH training is available on the Letterkenny Army Depot homepage – www.lead.army.mil
1.3.6 OPSEC Training: Per AR 530-1, Operations Security, new contractor employees and associated sub-contractor employees shall complete Level I OPSEC training within 30 calendar days of their reporting for duty and annually thereafter. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 15 calendar days after completion of training. Level 1 OPSEC training is available on the Letterkenny Army Depot homepage – www.lead.army.mil.
2.0 GOVERNMENT RESPONSIBILITIES:
2.1 GOVERNMENT FURNISHED PROPERTY AND MATERIALS: The Government will provide the facilities, equipment, materials and/or services listed below:
2.1.1 Facilities: The Government will provide clear access to all working areas necessary for the contractor to perform the installation outlined, during the specified hours listed in section 1.2.
2.1.2 Equipment: none
2.1.3 Materials: Stock material for testing.
2.1.4 Services: none
2.2 SITE PREPARATION: Letterkenny Army Depot will provide a clear area for installation of the vertical mill.
2.3 UTILITIES: LEAD will provide adequate utilities for the installation and operation of the machines within
30’ of the equipment disconnect. LEAD will also provide temporary utilities for the operation of equipment required for the installation of the industrial equipment.
2.4 DELIVERY AND STORAGE: The Government will not be responsible for loading, unloading, or providing any extended storage, prior to installation, of materials or equipment as part of this contract.
3.0 CONTRACTOR RESPONSIBILITIES: The contractor shall be responsible to inform all of his workers, direct or contracted, and ensure they follow the information within this specification. The contractor shall also have a representative onsite to manage the project and be the point of contact (POC) to communicate and coordinate with Letterkenny’s POC.
3.1 POST PROCESSOR: The contractor shall verify their machine is compatible with MasterCam 2020 and newer software. If not, the contractor must supply a post for their machine and MasterCam 2020 and newer version software.
3.2 PROJECT SCHEDULE: A project schedule shall be submitted by the contractor, within 30 days after receipt of the purchase order, to include a timeline for material delivery, installation, testing and training.
3.3 UTILITY REQUIREMENTS: The contractor shall provide certified utility requirements within 15 days after receipt of the purchase order. They shall include type, number of connections, and requirements.
3.4 FIELD VERIFICATION: It shall be the responsibility of the contractor to verify, in the field, all measurements, locations of structures and utilities, and any other physical conditions which would affect the progress, or quantity of work. Any errors by the contractor, due to omission of field verification, shall not be the basis for any increase in contract price. Where existing utilities or other obstructions interfere with the progress of the contract, the contractor shall provide all materials and labor to relocate all obstructions as required and approved by the Contracting Officer.
3.5 SPECIAL FOUNDATION: None.
3.6 UTILITY INSTALLATION: Utilities are to be run overhead. The contractor shall provide all materials, equipment, tools, and labor necessary for the installation of all utilities.
3.7 DISPOSAL OF MATERIALS AND EQUIPMENT: All salvageable materials and equipment removed by the contractor shall be delivered to the Depot Property Disposal Yard, Facilities Engineering Division warehouse, or other sites as directed by the Contracting Officer, or his representative and shall remain the property of the Government. Delivery shall be made during normal operating hours of the receiving activity. No Government materials or equipment shall be removed from the reservation by the contractor.
All packing, packaging, and scrap material accumulated during the performance of the contract shall be removed and disposed of properly by the contractor.
3.8 DUST CONTROL: The contractor shall control the amount of dust generated during the installation of the system foundation and components, and shall prevent the spread of dust to occupied portions of the building. Use of water will not be permitted when it will result in, or create, hazardous or objectionable conditions such as ice, flooding or pollution.
3.9 PROTECTION OF EXISTING STRUCTURES AND EQUIPMENT: The contractor shall take all necessary precautions to insure against damage to existing structures and equipment to remain in place.
3.10 INSTALLATION OF NEW EQUIPMENT: The contractor shall be responsible for supplying all parts, material, equipment, tools, and labor required to install the equipment provided under this contract. This shall include off-loading equipment, moving it to the installation site, positioning and installing floor mountings. The contractor shall make all connections to existing utilities necessary for proper operation.
The contractor shall remove and dispose all packaging and preservative material. Removed components shall not be taken from the Depot property. Removed components shall be placed in a location designated by the TPOC.
3.11 WIRING: All electrical work and materials shall be in compliance with the National Electrical Code and
National Electrical Manufacturers Association. All electrical installations shall be inspected and accepted by a certified electrician. All work shall be subject to inspection by LEAD electricians.
3.12 COMPRESSED AIR AND WATER: Schedule 40 (minimum) black steel pipe, valves, and all materials necessary, shall be supplied and installed to provide the equipment with required adequate air and water supplies. Connections will be near the machine location (see paragraph 2.3).
3.13 FLUIDS: The contractor shall provide all necessary fluids and chemical additives required for the start-up and proper operation of the equipment. The contractor shall supply LEAD with SDSs for all the necessary fluids within 30 days after award of contract.
3.14 INSURANCE/LICENSING/BONDING: The contractor shall possess all necessary insurance, licensing, and bonding required by businesses to perform the type of work they are responsible to complete this installation. Also, any hot work (welding, burning, etc.) the contractor will do, the contractor is required to contact the Letterkenny fire department (717-267-8108) at least 24 hours in advance of the hot work to be performed.
3.15 SPECIAL FOUNDATION: The shop floor is between eight (8) and ten (10) inches thick concrete. The contractor shall be responsible for determining if the equipment requires a special foundation to meet the requirements of this specification. If a special foundation is required, the contractor shall prepare certified drawings of the proposed foundation including all calculations. The drawings shall bear the seal and signature of a professional engineer and be submitted to LEAD a minimum of ten (10) weeks before the scheduled start of the equipment installation. The drawing shall be approved by LEAD prior to any work being performed on the depot. The contractor shall provide all materials, equipment, and labor necessary for the removal and disposal of the existing slab, excavation, grading, and installation of the new foundation. All excavated material and other excess material shall be removed from the depot and disposed of by the Contractor in accordance with Federal, State, and local regulations. If floor mountings are required, the contractor will notify, prior to equipment shipping.
4.0 REQUIREMENTS:
4.1 MACHINE OPTIONS: The CNC vertical mill shall have the following minimum options:
High Pressure, High Flow adjustable cylinder air for high speed machining 64GB expanded built in memory High Speed Machining (up to 1200 ipm) High intensity LED lighting (auto on/off with doors or switch) Wireless Intuitive Probing System Through Spindle Coolant system, 1000 psi for up to 15,000 rpm Internal High Voltage Isolated Transformer for 480V power Exhaust System Enclosure Control cabinet a/c cooling Auxiliary Coolant Filter CT50 Through Spindle Coolant Pull Studs (quantity of 10) Turnkey Install include rigging, setup, utility install, and startup IUID Tag plate per MIL-STD-130x Freight
4.1.1 Documentation: Two sets (each) of paper and one (each) CD of operator instruction manuals, maintenance service manuals, and parts listing manuals shall be provided for the furnished systems. These manuals shall be written in the English language.
4.1.2 Preservation, Packaging and Delivery: The contractor shall utilize standard commercial methods for preservation and packaging appropriate for each unit and acceptable to commercial carriers. As a minimum, all areas susceptible to damage from exposure to the elements shall be preserved and/or packed to prevent damage. The contractor shall be responsible for ensuring the equipment is delivered to LEAD in good condition.
4.1.3 Warranty: The contractor shall furnish with the equipment a standard commercial warranty or full one year warranty (parts, labor, and shipping, at minimum), whichever is greater. The contractor shall provide commercial warranties for any subcontracted components that will be underwritten. The contractor shall supply all corresponding warranty contact names and phone numbers before the end of the project. The warranty shall be effective beginning immediately after final acceptance of the equipment and not before that time.
4.1.4 Inspection and Acceptance: The equipment shall be examined for design, construction, materials, components, and workmanship to determine compliance with the contract and this specification. Any deviation from these requirements shall be cause for rejection.
4.2 MACHINE CONTROL SYSTEM:
4.2.1 Control Features: The CNC vertical mill shall have a FANUC type control, or equivalent. All machine functions shall be controlled and monitored through the operator’s control panel/interface; shall be capable of being set through machine code input into the control, and part programs downloaded from a LAN through the Ethernet connection. The control will have a probing system that performs the functions of work offsets, tool length offsets, spindle orientation, coordinate rotation and scaling, visual programming, in process inspections, and tool breakage detection. The Control shall include, but not limited to, the following minimum features:
15 inch Color TFT LCD screen 1 GB program memory Emergency shutdown buttons Graphic Dry Run Color Extra-large touchscreen display Remote Jog Handle Local Area Network Interface (Ethernet) Machine background editing Electronic thermal comp of each linear axes Rigid tapping Advanced pocket milling Power failure detection module Tool Life Management Self-Diagnostics
4.2.2 Control Software Compatibility: The control shall be a FANUC style control or equivalent and shall be compatible with MasterCam 2020 and current version software.
4.2.3 Maintenance Control Access: The machine controller must allow maintenance LEVEL 1 access to machine controls for routine and unique tasks and features. This can be done in the form as a password or key. Control access for maintenance below factory tech level will be included with this machine procurement. If there isn’t pre-set access, the access password, key, etc. must be included with this machine procurement.
4.3 MACHINE FEATURES: The machine shall include, but not limited to, the following minimum features:
60 hp spindle motor with 10,000 rpm, minimum Geared head 50 Taper spindle Table size of at least 62”x23” and capacity of 4,000 pounds
X, Y, & Z axes rapid travel of 750 inches per minute (ipm), minimum Max x, y, z travel of at least 60”, 26”, and 25”, respectively Window air blast 30 tool side mount changer and 1 in spindle Programmable coolant nozzle Automatic Chip Auger 95 gallon flood coolant system Machine footprint (maximum) 137” wide x 95” deep Coolant Tank Oil Skimmer
4.4 GENERAL REQUIREMENTS:
4.4.1 Painting: All surfaces to be painted shall be cleaned of all foreign matter. The equipment shall be painted
IAW standard commercial practice that shall not be less than one coat of primer and one coat of finish color.
4.4.2 Lubrication: Means shall be provided to ensure adequate lubrication to all moving parts. All oil holes, grease fittings and filler caps shall be easily accessible.
4.4.3 Power Requirements: All power requirements shall be 480V 3ph. If any requirement is not, the contractor shall supply all required transformers.
4.4.4 Automatic Lubrication: The system shall include a centralized lubrication system to automatically provide lubricant to critical components.
4.4.5 Energy Efficiency: All equipment that directly consumes energy in normal operation shall be designed and constructed for the highest degree of energy efficiency as governed by the latest developments available within industry.
4.5 SAFETY AND ENVIRONMENTAL REQUIREMENTS:
The contractor is reminded that LEAD maintains a Safety Management System (SMS) and is ISO 45001 certified.
LEAD’s safety policy and safety program (LEAD-R 385-1) can be requested at usarmy.letterkenny.usamc.list.lead-safety-office@army.mil
It is the contractor’s responsibility to be familiar with these documents and to comply with their contents.
Any and all on site work at LEAD shall be completed in accordance with applicable OSHA, DoD, DOT, Army, and LEAD Safety requirements. As a federal installation, additional requirements other than OSHA apply to contractors performing work at LEAD. Examples include full conformance to all applicable NFPA standards, ANSI standards, and other consensus standards for the industry covered by the subject contract. It is the responsibility of the contractor to be familiar with all applicable standards prior to starting work.
If contractor personnel determine a procedure is unsafe, they shall discontinue work immediately and contact their Program Manager who shall notify safety personnel and the COR. As soon as LEAD Safety Office personnel determine that the unsafe conditions have been corrected, the COR will notify the contractor Program Manager that personnel may resume work.
Additionally, all contractor supervisors and employees shall read and be knowledgeable of the governing SOP(s) prior to signing the SOP(s) and starting the operation.
All contractor personnel shall wear the appropriate PPE when in the following work areas: industrial buildings, at construction sites, test sites and test facilities. Failure to wear/use PPE may cause removal from the job site and/or seizure of non-compliant equipment/items.
The contractor shall comply with reporting requirements of 29 CFR Part 1904, AR 385-40 and APGR
385-4, and shall report accidents resulting in injury or death and accidents resulting in damage to Government property, supplies, and equipment to the COR promptly of the occurrence.
In case of injury/accident, the contractor shall complete an injury/accident investigation report and submit it to the COR Office with a copy to the LEAD Safety Office.
All shipped material shall include a current product Safety Data Sheet (SDS) for any chemical products being shipped other than residue. This includes items like engine oil.
All safety messages or recalls related to the safe use of products produced by the contractor will be provided to the COR for the Contract within 5 days of contractor’s awareness of the message or notice.
As part of the applicability of engineering controls, all equipment with rotating and moving parts at point of operation shall comply with LEAD 385-1 Chapter 17-3- Policies: One or more methods of machine guarding shall be provided to protect the operator and other employees in the machine area from hazards such as those created by point of operation, nip/pinch points, rotating parts, flying chips, and sparks. Examples of guarding methods are: physical barrier guards, electronic safety devices, guarding by distance, and physical restraints. The point of operation of machines whose operations exposes an employee to injury shall be guarded. The guarding device shall be in conformity with any appropriate standard (OSHA, ANSI, Equipment Owner’s Manual). In the absence of applicable specific standards guarding shall be designed and constructed as to prevent the operator, or any employees who may come in contact, from having any part of his/her body in the danger zone during operation. All machines designed for fixed locations shall be securely anchored to prevent walking or moving during operation.
4.5.1 Equipment Hazards: All hazards inside the machinery shall be guarded against unauthorized access. Clearly visible signs and symbols shall warn personnel in the area, and interlocks, safety mats and redundant deactivation systems shall guard against accidental access to the tooling and moving parts. Guards shall be easily removable to facilitate inspection, maintenance, or repair.
4.5.2 Mercury Restriction: The equipment shall not contain mercury compounds nor be exposed to free mercury during manufacture.
4.5.3 Asbestos Restriction: Asbestos and materials containing asbestos shall not be used in or on the equipment.
4.5.4 PCB Restriction: Equipment and materials containing Polychlorinated Biphenyl (PCB) shall not be shipped to Letterkenny Army Depot.
4.6 INSTALLATION REQUIREMENTS:
4.6.1 Design and Installation: The contractor shall provide all parts, labor, and services for the design, fabrication and installation of the vertical mill and accessory equipment. The contractor shall provide competent English-speaking personnel to place the system in operation and to conduct the acceptance tests and training of depot personnel. The contractor, through his service personnel, shall be fully responsible for the offloading, installation, activation, and testing of the system and the service personnel shall remain until system activation and testing has successfully been completed. Under no circumstances should the contractor plan on gratuitous Depot assistance during installation, activation, and testing such as diagnosis, troubleshooting, or repair of the system.
4.6.2 Badges: Identification badges will be issued for admittance of personnel before performing work or service on this contract. The identification badge is the property of the US Government and must be returned upon termination or demand. The contractor/vendor agrees that he will ensure all badges issued to employees are returned to the Badge and Identification Section, Security Division, Letterkenny Army Depot promptly on termination of need or on expiration, which occurs first. The badge room is located in Bldg. 2, phone # 717- 267-5301. Hours of operation are 7:30 AM to 3:30 PM, Monday thru Friday, exclusive of Federal Holidays.
4.6.3 Fire Extinguishers: The LEAD R 385-1 designates the type and number of fire extinguishers required to perform the contracted work. The LEAD Fire Department will not provide any extinguisher support. The contractor can gain the above information through a pre-construction conference, visiting the fire department, or phone 717-267-8231.
4.6.4 Use of Portable Gas or Arc Equipment: The contractor shall obtain a permit, from the LEAD Fire
Department, to use portable gas or arc equipment for cutting, welding or open flame operations. The Fire Department will require one day advance notice to permit necessary inspection before actually starting work, and notification when work is finished to allow for re-inspection. The Fire Department can be notified by calling ext. 8231. The contractor shall take necessary precautions to prevent fires IAW NFPA Standard No.
51B and LEAD R 420-13.
4.6.5 Spills: Any spills or releases of materials or wastes must be reported immediately to the site supervisor, the
LEAD Fire Department, and the LEAD Environmental Office per the LEAD Installation spill Contingency Plan (ISCP). Any such spills or releases generated by the contractor shall be contained, cleaned and disposed of by the contractor per the direction of the LEAD on-scene coordinator.
5.0 APPLICABLE DOCUMENTS:
OSHA Safety and Health Standards 29 CFR 1910 Occupational Safety and Health Standards (copies may be obtained at http://www.osha.gov)
Letterkenny Army Depot (LEAD) Publications:
LEAD Regulation 385-1: LEAD Safety and Occupational Health Program LEAD Pamphlet 385-4 – Safety Requirements for Security, Safety, and Fire Prevention for Contractors
Performing Work on LEAD (Copies may be obtained at LEAD Directorate of Contracting, Bldg. 2)
National Fire Protection Association NFPA Standard 70 – National Electric Code NFPA Standard 79 – Electrical Standard for Industrial Machinery (copies may be obtained from http://www.nfpa.org/)
Unified Facilities Criteria UFC 3-600-01 - Fire Protection Engineering For Facilities (copies may be obtained from http://www.nfpa.org/)
6.0 QUALITY ASSURANCE:
6.1 QUALITY CONFORMANCE INSPECTION: The vertical mill and all accessory components shall be subject to a quality conformance inspection, performed by a designated Depot representative, to determine compliance with this specification.
6.2 TESTS:
6.2.1 Accuracy: If an accuracy test was performed by the OEM before the machine was shipped, the contractor shall repeat the accuracy test at LEAD after complete installation. The results of the test performed at LEAD shall be compared to those from the test at the factory. If no accuracy test was performed at the factory, the contractor shall be responsible for developing test procedures to demonstrate the accuracy and operation of the machine to be in compliance with the requirements of this specification. All test procedures shall be submitted to and approved by Depot Technical Point of Contact (TPOC) prior to the start of testing. To support the testing procedures, LEAD will provide a supply of mild steel material of various thicknesses for use during the performance tests and training. If mild steel is not available, other readily available materials may be used. The contractor shall prove out all problems.
6.2.2 Post Processing Verification: Once the machine is operational, the contractor shall run, successfully, a proven part program through their post-processor and download to the machine. The machine shall run from the downloaded part program and then checked for accuracy of the part and program. The contractor shall prove out all problems with the post.
6.3 TECHNICAL INSTRUCTION: The contractor shall be responsible for providing technical instruction of four (4) Depot personnel in the operation of the equipment and software and four (4) Depot personnel in the maintenance of the equipment supplied under this contract. All instructions, oral and written, shall be in the English language. The project LEAD TPOC will coordinate with individuals to be trained upon successful completion of all installation and test specifications.
7.0 INFORMATION TECHNOLOGY (IT) INDUSTRIAL SYSTEM REQUIREMENTS:
7.1 OPERATING SYSTEM (OS) SPECIFICATIONS:
7.1.1 If applicable, the system’s OS must be Microsoft Windows 10, Windows Server 2012R2, or Red Hat Linux v6.X. Any OS supplied with the system must contain all service packs, updated patches, and hot fixes. All patching and fixes will be current as of a predefined date agreed upon by the vendor and the government.
7.1.2 Defense Information System Agency (DISA) Security Technical Implementation Guides (STIGS) are configuration standards for the Department of Defense and contain technical guidance to lock down information systems and software applications that might otherwise be vulnerable to malicious attacks. The contractor shall be responsible for ensuring all appropriate STIGs are implemented and their software runs acceptably while secure.
7.1.3 The Army Golden Master (AGM) is a collection of security settings for Microsoft Operating systems which must be applied to all Army computer systems. LEAD will supply the AGM to the contractor who shall ensure their software functions as intended, when installed on top of the AGM.
7.2 PROGRAMMABLE LOGIC CONTROLLERS (PLC): If a PLC is to be installed within the system, it shall be manufactured by a government approved source and shall provide an Ethernet adapter to allow for connection to the Industrial Network if required. If an Ethernet connection is used to interconnect the PLC to peripheral equipment, an additional Ethernet port shall be provided.
7.3 SYSTEM SOFTWARE SPECIFICATIONS:
7.3.1 Software Installations: If installing application code at LEAD, the contractor shall install the code within a standard container (E.g., Program Files) and located in a volume separate from the standard System Files.
Interactive applications are required to run as services and daemons and any time WEB services are used, file types (E.g., XML and HTML) must be separated.
7.3.2 Software Licensing: When installed, the software licensing for computers, control units and other IT systems will be surrendered to the Information Technology Configuration Manager and will become the property of the Government upon acceptance of the system.
7.3.3 If software has been customized for LEAD’s use or is any software other than Commercial Off The Shelf
(COTS); the contractor shall provide copies of all source code, firmware and software used in the system, as well as one set of backup and configuration software for PLC’s, control and communication computers, and data acquisition. All programs shall be tested and fully operational before acceptance. All acceptance testing will adhere to common User Acceptance Testing (UAT) standards as defined by the government.
7.3.4 If any special programming software or programming software interface devices such as hardware "keys", dongles or "PIC" modules, are required to access software, these programs and devices shall be provided to LEAD along with the necessary registration information. If custom application software was written and provided, a copy of the required compiler and compiler license shall also be provided. At acceptance, all items shall become property of the government. Software and hardware purchased for this project shall be registered to Commander, Letterkenny Army Depot, Chambersburg, PA 17201.
7.4 SYSTEM ENVIRONMENT SPECIFICATIONS:
7.4.1 All supplied software must be capable of operating in a multi-user environment and data which contains permissions information shall be hidden from view and inaccessible to those with less than administrator level access. Shared accounts shall not be used, and users shall only be authorized the minimum security rights to operate the application software. Users will not have access to system or software configuration items (e.g., Control Panel, software and hardware installation). Under no circumstances will the intended end user log in using the Administrator or Root account for routine operation of the equipment. The use of these accounts will be restricted to only administrative activities which will be carried out by LEAD Information Technology personnel. All software products shall employ a minimum of three permission based levels of access.
7.4.1.1 Administrator - Full control at root level, restricted to LEAD IT personnel and when required, the
Contractor.
7.4.1.2 Maintenance - Mid-level control required to perform maintenance and alter control parameters as needed.
7.4.1.3 Operator - Minimum control necessary to perform the routine operation of software. The Operator shall not be able to alter the programming of software, make changes to executable files, or modify control parameters.
7.4.2 Application Interoperability: If an application will interfere with the operation of the industrial system, E.g., (McAfee Anti-Virus), the Contractor shall provide a written statement to the LEAD IT Directorate explaining the technical restrictions placed upon them.
7.4.3 Auditing: If applicable, the contractor shall enable audit files and data logs for access by LEAD
Cybersecurity personnel to audit access and actions on the equipment.
7.4.4 User Acceptance Testing (UAT): LEAD Cyber Security Personnel will have the ability to conduct validation testing with approved security tools prior to equipment being introduced to the shop floor. This testing will also satisfy any UAT requirements. A UAT Plan will be furnished prior to testing and all equipment documentation will be made available for review during the test. If discrepancies are discovered the contractor shall remediate identified issues prior to government acceptance.
7.5 DOCUMENTATION REQUIREMENTS:
7.5.1 A complete set of instruction manuals containing all the information necessary to operate, maintain, and reinstall all software and hardware contained within the system shall be provided by the Contractor. These manuals shall include step-by-step instructions which facilitate the rebuilding of the system in the event of a fatal system crash.
7.5.2 If networked, the Contractor shall provide the system’s network design drawings to the Information Technology Directorate. These drawings should include complete directional data flow diagrams that include all ports and protocols in use.
7.5.3 The Contractor shall provide to Industrial Automation at least two electronic copies of all control unit programs. These copies should include description files of the ladder logic and any cabling required to connect to the control systems. No control units will be password protected and no other form of lockout measure shall be implemented by anyone other than LEAD IT employees. The Contractor shall also provide electrical wiring diagrams for all installed control systems to this LEAD Industrial Automation group.
7.5.4 Certificate of Networthiness: Certificate of Networthiness (CoN) certification ensures Automated
Information Systems (AIS) utilizing the Army Network are developed in compliance with the Clinger Cohen Act and are secure, supportable, sustainable, and compatible with the Army Enterprise Infrastructure (AEI) (as defined in AR 25-1). All new AIS capabilities and all capability modifications and upgrades must be assessed to validate their Networthiness (network security, network impact, compatibility with the infrastructure, infrastructure requirements, spectrum support, security policy compliance, Joint Technical Architecture –Army (JTA-A) standards compliance, communications and information manpower, training, logistics support, schedule, and funding). If software is installed within the system, the Contractor shall work with LEAD Directorate of Information Management (DOIM) personnel to check for CoN availability and when not available, ensure a CoN is requested and all documentation is submitted.
7.6 PROPOSAL DEVIATIONS: Proposals or specifications that deviate from those described herein shall be coordinated for specific approval or rejection by the LEAD Information Technology representatives prior to shipment, installation, or acceptance of the equipment.
8.0 FINAL ACCEPTANCE: Once all conditions of this contract are met, final acceptance will be after 100 hours of continuous operation without a breakdown or failure, or 14 days, whichever comes first. If the machine has a failure or breakdown and it is determined that is the fault of the machine hardware or software, the operating time and 14-day timeframe start over each time this happens. After the 100 hour operating time or 14 days have been met, final payment of this contract will be made.
The following have been deleted:
REVISED PURCHASE DESCRIPTION
(End of Summary of Changes)