Revsision_1.0_SOW_ER_LIDAR.pdf

PDF 116 KB Posted

Attached to
Extended Range LIDAR Federal contract opportunity
Solicitation number
W91151-19-R-0025
Issued by
Department of the Army Materiel Command Mission and Installation Contracting Command Fort Hood

About this file

Revision 1.0 ER-LIDAR Statement of Work (SOW).

View the file

Other files for this federal contract opportunity

Other files attached to Extended Range LIDAR, newest first.
File Type Posted
REV_3.0_ER_LIDAR_SOW_01AUG19.pdf PDF
REV_2.0_ER_LIDAR_SOW.pdf PDF
SOW_ER_LIDAR_v1.3.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WHITE SANDS MISSILE RANGE (WSMR)

STATEMENT OF WORK (SOW)

Army Test and Evaluation Command (ATEC) Extended Range-Light Detection and Ranging

(ER-LIDAR)

Range Operations (RO) DIRECTORATE

16 May 2019

Rev. 1.0

1.0 Introduction

1.1 Scope

This Statement of Work (SOW) establishes the requirement for the provision of an ER-LIDAR system.

This capability will provide the ATEC test ranges a research and development (R&D) platform for capturing wind profiles at higher altitudes than what the Ranges currently have in operations.

1.2 Background

The ER-LIDAR will provide a real-time source of wind profile data (speed and direction) that is used in support of range customers. It is paramount to have this capability in terms of the safety implications it has on testing and personnel safety respectively as well as performance during testing.

2.0 Requirements

2.1 ER-LIDAR

The Contracting office shall research possible options regarding this requirement, its availability and performance. It is critical this capability meets and/or exceeds the requirements set forth in section 2.2 as this device will be used as an R&D test bed to make a determination if it is an instrument that will enhance the Department of Defense’s (DOD) test and evaluation (T&E) of future capabilities. The various ATEC Range Meteorology (MET) commodities will use the data collected from this T&E effort to make their final decision regarding future investments in this capability.

2.2 ER-LIDAR Specification Requirements

The following specifies requirements, objectives and performance standards set forth of the required performance of the ER-LIDAR.

2.2.1 Key Performance Parameters (KPPs)

Range: 0km to 11km + Data Collection: 10Hz (10min) Sampling Operation: Continuous Measuring Vertical and Horizontal Measuring Operational Temperature: -10°C to 40°C Transportable and portable without heavy equipment

3.0 Delivery Requirements

The Contractor shall give the Government a three week notice when delivery to WSMR is planned so all parties can coordinate a schedule.

4.0 Acceptance Testing and Training

The ER-LIDAR system shall be ready for final stand-alone acceptance testing approximately 365 days or less after award to the Contractor. The Contractor shall deliver the system to WSMR where it will be setup to manufacturer specifications and tested for operational performance. The Contractor shall make arrangements with the Government to provide training in the operations and maintenance of the system in parallel with acceptance testing. Final delivery of system should include manuals and any literature associated with the system