W90VN6-17-T-0079_0002.pdf
PDF 306 KB Posted
- Attached to
- PORTABLE TOWER SYSTEM Federal contract opportunity
- Solicitation number
- W90VN6-17-T-0079
About this file
This amendment is to post questions answers in reference to the solicitation. This please note W90VN6-17-T-0078 0002 is the only amendment for this procurement (AS OF 25 SEP 2017 1800 LOCAL TIME). W90VN6-17-T-0039 0001 was generated by computer error.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| W90VN6-17-T-0079_0003.pdf | ||
| W90VN6-17-T-0079.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
411TH CSB, KOREA - RCO OSAN
POC: CPT VOGLEZON, ROYSTON S.
TEL: (031) 661-1148
E-MAIL: ROYSTON.S.VOGLEZON.MIL@MAIL.MIL
APO AP 06278-2039
UNITED STATES OF AMERICA (THE)
F3J6AF7255A001
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Questions and answ ers as of 16:30, 25 SEP 2017 (Local Time). All other terms and conditions remain unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 25-Sep-2017
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W90VN6-17-T-0079
X 9B. DATED (SEE ITEM 11)
21-Sep-2017
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
25-Sep-2017
CODE
411TH CONTRACTING SUPPORT BRIGADE, KOREA
RCO OSAN, UNIT #2039
APO AP 96278-2039
UNITED STATES OF AMERICA (THE)
W90VN6 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE W90VN6
FACILITY CODECODE
EMAIL:TEL:
W90VN6-17-T-0079
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 1449 - CONTINUATION SHEET
The following have been added by full text:
QUESTIONS AND ANSWERS
1. Painting/color
a. Concerning the question about paint, as long as the trailer/tower and accessories are constructed of a metal that will not rust/corrode or degrade due to weather conditions or environmental factors, we do not care if the metal is bare. If the trailer/tower and accessories are not constructed of anti-corrosive materials, we request they are painted gray.
2. What are the power specs for the DC generator, Voltage, Hz, KW?
a. 12 VDC capable of supplying required power to raise the tower, and supply power to all electrical components.
3. Will AC generator option be considered in lieu of DC generator?
a. Yes
4. Does the tower trailer system require any special military paint/color?
a. No specific paint scheme or color is required. Paint is not required if the trailer/tower materials are non-corrosive.
5. Are four (4) tower sections the maximum allowed?
a. Number of tower sections do not matter as long as the total tower height reaches 79 feet, and 87 feet with an antenna mast
6. What are the salient characteristics for the radio cabinet?
a. BAY FULLY INSTALLED, NEMA 4, POWDER COATED, FRONT & REAR DOORS WITH
SS LOCKABLE LATCHES, 19" RACK RAILS WITH VIBRATION ISOLATORS,INCLUDES
120/240VAC 60A LOAD CENTER, 30A POWER INLET, (2) DOUBLE DUPLEX GFCI
RECEPTACLES (INTERIOR), GROUNDING BUS BAR AND ROXTEC I/O PORT.
7. What is the maximum retracted length, diameter, and quantity of coax used?
a. The cable to be used with this tower is a maximum of 4 cables (each 3/8" diameter, LMR-400 type coax cable) at approximately 100 feet each. Please be advised that LMR cable itself is not part of this solicitation, however, this is the type and quantity of cable we intend to use with it.
8. In lieu of ground anchors, Alltech would like to propose the option of guying the tower to the trailer chassis and outriggers for reduced deployment time and reduced deployment footprint.
a. No.
W90VN6-17-T-0079
9. Are there extra days for shipping the six (6) trailer tower systems or is it already included the 120 days?
a. Already included in the 120 days b.
10. Can a smaller overlap of 4 feet between sections be used in lieu of 7 feet?
a. Section overlap must be a minimum of 5 feet...max of 7 feet
11. The payload of 350 lbs at 70 mph
a. Is the 70 mph 3s gusts or survival speed? Any ice?
i. 70 mph gusts. Yes, ice must be a factor
b. What is the sail area of selected equipment?
i. Max 3 feet
c. Structure class?
i. Class II
d. Topographic and exposure category?
i. Exposure B
(End of Summary of Changes)
File details come from the government source that posted it. Updated .