B08_ATTACHMENT_004_-_Transparent_Armor_FAT_CDRL.pdf
PDF 643 KB Posted
- Attached to
- TRANSPARENT WINDOW ARMOR Federal contract opportunity
- Solicitation number
- W9098S20Q0009
About this file
This document is a Contract Data Requirements List (CDRL) for a First Article Test (FAT) report related to a federal contract opportunity for transparent window armor. The CDRL requires the contractor to submit a FAT report within 10 days of completing the FAT, which must be done within 45 days of award. The FAT is to be conducted according to the requirements in the Statement of Work and the report will be reviewed by the government for 30 days, after which the contractor will receive disposition on the FAT. FAT approval must be obtained before production can begin, which is required to start 60 days after FAT approval. The related federal contract opportunity is solicitation number W9098S20Q0009 issued by the Department of the Army Materiel Command Contracting Command Rock Island Arsenal for transparent window armor and potting.
ATTACHMENT 002 FAT CDRL
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| ATPD-2352T - Transparent Armor - 8May2011 - Distribution Code A.pdf | ||
| B08_W9098S20Q0009.pdf | ||
| ATTACHMENT_001_PRICING_SPREADSHEET.xlsx | XLSX spreadsheet | |
| B08_ATTACHMENT_002_FINAL_Scope_of_Work,_Potting_M915_B_Kit.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DD FORM 1423-1 FEB 2001
PREVIOUS EDITIONS MAY BE USED. Page 8 of 14 Pages
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item)
Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 220 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for information Operations and reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project, (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY
TDP TM OTHER X
D. SYSTEM/ITEM
M915A5 B-KIT
E. CONTRACT / PR NO. F. CONTRACTOR
1. DATA ITEM NO.
A001
2. TITLE OF DATA ITEM
TEST/INSPECTION REPORT
3. SUBTITLE
FIRST ARTICLE TEST REPORT
4. AUTHORITY (Data Acquisition Documentation No.)
DI-NDTI-80809B
5. CONTRACT REFERENCE
SECTION E
6. REQUIRING OFFICE
AMSJM-QAP
7. DD 250 REQ.
LT
9. DIST STATEMENT
REQUIRED
D
10. FREQUENCY
ONE/R
12. DATE OF FIRST SUBMISSION
ASREQ
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
8. APP CODE
A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT
SUBMISSION
ASREQ
Draft
Final Reg Repro
PCO
0 1
16. REMARKS:
The First Article Test (FAT) shall be completed within 45 days from award.
The FAT shall be conducted in accordance with Attachment 002 Statement of Work (SOW).
The FAT Report shall be submitted to the PCO within 10 days after completion of FAT. The Government requires 30 days for review. Disposition of the FAT Report will be provided through the PCO. FAT must be approved prior to production.
Delivery for production shall begin 60 days from FAT approval.
File details come from the government source that posted it. Updated .