Amendment W50S9B22Q0016.pdf
PDF 202 KB Posted
- Attached to
- Bathroom Remodel Bldg 1392 Federal contract opportunity
- Solicitation number
- W50S9B22Q0016
- Issued by
- Department of the Army National Guard
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| F 1392 ANNOTATED FLOOR PLAN_A1 A2 A3_Updated.pdf | ||
| SPEC SHEET_BATHROOM REMODELING.pdf | ||
| Entry Authority Listing.xlsx | XLSX spreadsheet | |
| B1392 ANNOTATED FLOOR PLAN_A1 A2 A3.pdf | ||
| W50S9B22Q0016.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
To add revised SOW.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 7
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 25-Aug-2022
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W50S9B22Q0016
X 9B. DATED (SEE ITEM 11)
18-Aug-2022
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
25-Aug-2022
CODE
USPFO VA 192 MISSION SUPPORT CONTRACTING
165 SWEENEY BOULEVARD
BLDG 768, SUITE 214 (LANGLEY AFB)
HAMPTON VA 23665-2207
W50S9B 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W50S9B22Q0016
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00800 - SPECIAL CONTRACT REQUIREMENTS
The following have been modified:
STATEMENT OF WORK
VIRGINIA AIR NATIONAL GUARD
192d CIVIL ENGINIEER FLIGHT
165 SWEENEY BLVD BLDG.768
JOINT-BASE LANGLEY-EUSTIS, VA 23665
BATHROOM REMODELING, FACILITY 1392
PROJECT NUMBER: MUHJ 22-6003
DATE: 08/24/2022
FOR
UNITED STATES PROPERTY AND FISCAL OFFICES
VIRGINIA AIR NATIONAL GUARD
HAMPTON, VA 23665
TABLE OF CONTENTS
SECTION PAGE
1. GENERAL INFORMATION
1.1 CUSTOMER
1.2 LOCATION
1.3 PROJECT OBJECTIVES
1.4 WORK HOURS
1.5 PERIOD OF PERFORMANCE
1.6 POCs
2. SCOPE OF WORK
2.1 DIMENSIONS AND REQUIREMENTS
2.2 JUSTIFICATION
2.3 CIVIL LAYER
2.4 DEMOLITION AND REMAINING STRUCTURES
2.5 STRUCTURAL
2.6 PLUMBING
2.7 HVAC
2.8 ELECTRICAL
2.9 COMMUNICATION
2.10 FIRE FIXTURE
2.11 MISCELLANEOUS
3. DELIBVERABLES
3.1 AS BUILTS, DRAWINGS/PROJECT CDs
3.2 WARRANTIES
4. ATTACHMENTS
4.1 LOCATION AND FLOOR PLAN
4.2 PHOTOS
4.3 DRAWINGS
1. GENERAL INFORMATION
1.1 CUSTOMER
192d Wing Civil Engineer, Virginia Air National Guard
1.2 LOCATION
192d Civil Engineer Flight
470 Popular Road Bldg.1392 Joint-Base Langley-Eustis, VA 23665
1.3 PROJECT OBJECTIVES
The purpose of this project is to renovate existing bathrooms located at building 1392 to accommodate the needs of more than 20 personnel during JISCC operations. See attachments for location and floor plan.
1.4 WORK HOURS
Work hours are Monday through Friday 0700-1700
1.5 PERIOD OF PERFORMANCE
30 days
1.6 POCs
Contracting Officer: MSgt Santos Desiree Contracting Officer’s Representative: SrA Oppong, Ben Project Manager: Mr. Louis Nemec
2. SCOPE OF WORK
The work herein includes the furnishing of all materials and equipment and performing all labor for the work indicated per statement of work listed below. All work shall conform to those standards stipulated in the building code, mechanical code, and electrical code applicable in the local jurisdiction. Any deviation from the manufacturer installation requirements must be approved prior to construction. All stated quantities are required to be field verified.
2.1 DIMENSIONS AND REQUIREMENTS
See attachment A2 & A3 “Existing layout” for specific measurements.
2.2 JUSTIFICATION
Existing bathrooms have one toilet, one sink and one shower (See attachment A3:
existing layout). This renovation is needed to accommodate the needs of more than 20 people during their JISCC operations.
2.3 CIVIL LAYER
N/A
2.4 DEMOLITION AND REMAINING STRUCTURES
Demo drop ceiling/grid and remove light fixtures, ceiling return system, vent system and fire/smoke detectors (All to be reused) located in bathrooms A & B.
Demo existing wall located in bathroom A. (See attachment A3, Existing layout).
Demo and dispose floor tiles (in the proposed toilet and shower areas) and drywalls in bathroom A.
Demo and dispose drywalls in bathroom B.
Remove and dispose existing toilet, sink and shower fixtures in bathrooms A&B.
Remove hand drying device located in bathroom B and install it next to the new sink.
Demo and dispose tiles in the kitchen area, bathroom B as well as tiles in the utility closet. (See attachment A2)
2.5 STRUCTURAL
Construct a wall (each) with metal studs in bathrooms A & B to separate the toilet from the shower.
Install new drywall and furnish drywall.
Install a curtain rod and curtains in bathrooms A & B as annotated on attachment
A3 “proposed layout”.
Install new ceiling grid and tiles (White in color and 24” X 24” in dimension) in bathrooms A&B. Ensure new ceiling is structured to accommodate ceiling light, ceiling vent, return and fire/smoke detectors. Toilet and bathroom areas should have hard ceiling.
Install an ADA or handicap accessibility shower to include all accessories/fixtures (grab bars, shower head, fold up seat etc.) in bathroom A. (See spec sheet B1 for details).
Install a floor mounted ADA toilet bowl in bathroom A and a regular floor mounted toilet bowl in bathroom B and tie into existing plumbing. (See spec sheet B7 for details).
Install new sinks (include fixtures such as faucet) in bathrooms A and B as annotated on attachment A3 and tie into existing plumbing. Ensure bathroom B has an approved ADA sink. (See spec sheet, B5 for details).
Paint ceiling and walls where required; paint three coats of new paint for a clean and neat finish and trim where necessary. Color should match existing pattern.
Install a glued down vinyl floor tile with a 12”X12” dimension. (See spec sheet, B3 for details).
Install new floor tiles in the kitchen area, bathroom B as well as in the utility closet. (See spec sheet, B3 for details).
Install a 4” cove base in the kitchen area, bathroom B and utility closet. (See spec sheet, B9 for details).
Remove water heater located in the utility room to make way for flooring installation. Reinstall water heater upon completion.
2.6 PLUMBING
Install a four piece shower system, approximately 36” X 36”X 77” in bathrooms
A&B. Ensure that the shower system in bathroom A is ADA compliant. (See spec sheet, B1 and B2 for details).
Ensure shower systems include drains, shower heads and any related fixture. Tie fixtures into existing plumbing.
Install a water fountain by the wall located between the utility closet and bathroom B (See attachment A2). Tie plumbing work into existing lines and ensure work is done according to code. (See spec sheet, B6 for details).
2.7 HVAC
Relocate existing ceiling return (applicable to A and B) to the location annotated on attachment A3 “proposed layout” and tie into existing HVAC system.
Relocate existing vent (applicable to A and B) to the location annotated on attachment A3 “proposed layout” and tie into existing HVAC system.
2.8 ELECTRICAL
Install drop ceiling lights using existing light fixtures/electrical wires. (Applicable to A and B).
Relocate light switch in bathroom B to the location annotated on attachment A3 “proposed layout”.
2.9 COMMUNICATIONS
2.10 FIRE FIXTURE
Due to the installation of new drop ceiling panel, the existing fire/smoke detectors
(2x) need to be removed, stored and reattached. See B8, fire alarm panel and fire/smoke detector (See spec sheet, B6 for details).
2.11 MISCELLANEOUS
Submit sketch/design drawings to 633d CE for review and approval
3. DELIVERABLES
3.1 AS BUILTS, DRAWINGS/PROJECT CDs
As built drawings shall be delivered upon completion of the renovation to reflect the dimensions of the bathrooms.
3.2 WARRANTIES
The contractor will provide warranty for parts and installation if applicable.
4. ATTACHMENTS
4.1 FLOOR PLAN
Location and floor plan.
4.2 PHOTOS
4.3 DRAWINGS
Annotated Sketch. (Attachments A3)
(End of Summary of Changes)