Q and A.pdf

PDF 95 KB Posted

Attached to
Fluorescent Penetrant Line Installation Federal contract opportunity
Solicitation number
W50S9222Q9015
Issued by
Department of the Army National Guard

View the file

Other files for this federal contract opportunity

Other files attached to Fluorescent Penetrant Line Installation, newest first.
File Type Posted
Attachment 1 - Performance Work Statement.pdf PDF
Combo Solicitation - Fluorescent Penetrant Line Install.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation Number W50S9222Q9015

Question & Answer

06 August 2022

Q1: Moving of the old line and the new line will require pallet jacks or a forklift. Is the government providing those or do we need to price in rentals for that equipment?

A1: A forklift is recommended and will not be provided by the Government.

Q2: How far away is the new unit from the NDI lab bldg. 74, how far does the old unit have to moved?

A2: Both units will be moved a minimum of 500 ft. and a maximum of 1,000 ft.

Q3: What if existing government utilities are not in proper working order, are not correct in size or amperage?

A3: The Government has already confirmed that the current utilities match. The electrical required is the same as our current system, water pressure and air psi are sufficient. In the event the contractor discovers that there is a utility that is not in proper working order, the contractor shall immediately stop work and notify both the Government Point of Contact and the Contracting Office.