About this file
This document is an award notice for a firm fixed price construction contract to construct walls in buildings 150 and 101. The contractor shall provide all labor, materials, equipment and supervision to construct a partition wall and modify finishes and systems to create an office space according to specifications. Work includes installing drywall, doors, flooring and lights, and relocating HVAC equipment. The period of performance is 60 days with a completion deadline of 60 days after notice to proceed. The total award value is $28,976.64. The solicitation was set aside for small businesses and wage determinations apply to the work.
View the file
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
F9F3CE3114AW01
WYTD232003 Title: Construct Walls Building 150, this is to construct a dryw all partition and modify existing f inishes creating an off ice space.
This project is being solicited as a Total Small Business Set-Aside. The North American Industry Classification System (NAICS) Code is 238130, and the Small Business Size Standard is $19,000,000.00. Construction project magnitude is less than $25,000.00. A pre-bid conference and site visit has been scheduled. See Section 00100 – Instructions and Clause 52.236-27 for details. Funds are not presently available for this contract. The Government anticipates funds w ill become available prior to aw ard as this action has been identif ied on the National Guard priority list. No contract w ill be made until appropriated funds are made available. Aw ard w ill be made to the responsible bidder w hose bid conforms to the IFB and is most advantageous to the Government considering only price and price related factors.
X
DARRELL T MAXWELL 4198684237
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
13-Sep-2023
(RFP)
(IFB)
CALL:
Construct Walls - Building 150
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________60 calendar days after receiving aw ard, X notice to proceed. This performance period is mandatory, X negotiable. (See _________________________
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________17 Aug 2023 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time of fers are due.
B. An offer guarantee X is, is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______120 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
W50S8S23C0002
7. ISSUED BY CODE
USPFO OH 180 MISSION SUPPORT CONTRACTING
2660 S EBER RD
SWANTON OH 43558-8752
W50S8S
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
09:00 AM (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
WYTD232003
8. ADDRESS OFFER TO (If Other Than Item 7)
FAX:TEL: TEL: FAX:
W50S8S23B00010001 56
See Item 7
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE
8BZL7
FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
SEE SCHEDULE
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
$28,976.64 See Schedule
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE F8770027. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
DFAS DEAMS-F87700
ACCTG DISB STA NR 387700, DFAS DEAMS, 27 ARKA
LIMESTONE ME 04751-6216
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR
GREYSTONE SERVICES LLC
FAIZAH A SAYED
6195 LEWIS AVE
TOLEDO OH 43612-4341
15. TELEPHONE NO. (Include area code) 419-214-4141
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print) Barry B Beale / Contracting Officer
TEL: (419)-868-4142 EMAIL: barry.beale.1@us.af.mil
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY 13-Sep-2023
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
W50S8S23C0002
Section 00010 - Solicitation Contract Form
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Job $28,976.64 $28,976.64 WYTD232003- Construct Walls Bldg 150
FFP
The contractor shall provide all personnel, equipment, tools, materials, supervision, and quality control necessary, to construct a wall and perform interior renovations in accordance with the Performance Work Statement.
FOB: Destination MFR PART NR: Walls
PURCHASE REQUEST NUMBER: F9F3CE3114AW01
SIGNAL CODE: A
PSC CD: Y1AA
NET AMT $28,976.64
ACRN AA
CIN: 00000000000008917971
$28,976.64
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0001 Destination Government Destination Government
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
0001 60 dys. ANP 1 F9F3CE - 180TH CES
2660 SOUTH EBER ROAD
SWANTON OH 43558-8752
FOB: Destination
F9F3CE
PERFORMANCE WORK STATEMENT
PERFORMANCE WORK STATEMENT (PWS)
FOR
WYTD232003: CONSTRUCT WALLS – Buildings 150 & 101
1.0 General:
1.1 Scope: The contractor shall provide all personnel, equipment, tools, materials, supervision, and quality control necessary, except as specified in Paragraph 3.0 as Government Furnished, to construct a wall and perform interior renovations as defined in this PWS.
1.1.1 Objectives: Construct a drywall partition and modify existing finishes & MEP systems creating an office space for the 180th FW Contracting Office.
1.2 Background: The contracting office requires a space separated from other base functions to perform their duties.
1.3 Period of Performance (PoP): The Period of Performance shall be 60 days after issuance of the notice to proceed.
1.4 General Information:
1.4.1 Place and Performance of Services: The contractor shall provide services between the hours of 0700 - 1600 on Monday through Friday except on recognized US holidays or when the Government facility/installation is closed due to local or national emergencies, administrative closings, or similar Government-directed facility/installation closings. Performance shall be at Aircraft Parking Apron of the 180th Fighter Wing, 2660 S. Eber Rd., Swanton, OH 43558. The contractor shall at all times maintain an adequate work force for the uninterrupted performance of all tasks defined within this PWS when the Government facility/installation is not closed for the above reasons.
When hiring personnel, the contractor shall keep in mind that the stability and continuity of the work force are essential.
1.4.1.1 Telework: Not Applicable.
1.4.1.2 Unscheduled gate closures by the Security Police may occur at any time causing all personnel entering or exiting a closed installation to experience a delay. This cannot be predicted or prevented. Contractors are not compensated for unexpected closures or delays. Vehicles operated by contractor personnel are subject to search pursuant to applicable regulations. Any moving violation of any applicable motor vehicle regulation may result in the termination of the contractor employee’s installation driving privileges.
1.4.1.3 The contractor’s employees shall become familiar with and obey the regulations of the installation; including fire, traffic, safety and security regulations while on the installation. Contractor employees should only enter restricted areas when required to do so and only upon prior approval. All contractor employees shall carry proper identification with them at all times and shall be subject to such checks as may be deemed necessary. The contractor shall ensure compliance with all regulations and orders of the installation, which may affect performance. The Government reserves the right to direct the removal of an employee from Government property or revoke access to Government systems for misconduct, security reasons, or any overt evidence of communicable disease. Removal of contractor employees for reasons stated above does not relieve the Contractor from responsibility for total performance of this contract.
1.4.2 Recognized Holidays: The following are recognized United States (US) holidays.
The contractor shall not perform services on these days unless otherwise approved in advance by the COR and the contracting officer. Requests to work holidays shall be made a minimum of 3 working days prior to the requested day(s).
1.4.2.1 New Year’s Day: January 1st
1.4.2.2 Martin Luther King, Jr.’s Birthday
1.4.2.3 President’s Day
1.4.2.4 Memorial Day
1.4.2.5 Juneteenth National Independence Day: June 19th
1.4.2.6 Independence Day: July 4th
1.4.2.7 Labor Day
1.4.2.8 Columbus Day
1.4.2.9 Veteran’s Day: November 11th
1.4.2.10 Thanksgiving Day
1.4.2.11 Christmas Day: December 25th
1.4.3 Quality Control (QC): The contractor shall develop and maintain an effective QC Plan (QCP) to ensure services are performed in accordance with this PWS. The contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The contractor’s QCP is the means by which it assures itself that its work complies with the requirements of the contract. As a minimum, the contractor shall develop QC procedures that address the areas identified in Technical Exhibit 1, Performance Requirements Summary (PRS).
1.4.4 Quality Assurance (QA): The Government will evaluate the contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan (QASP). This plan is primarily focused on what the Government will do to ensure that the contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and acceptable quality level(s) or defect rate(s).
1.4.5 Access and General Protection/Security Policy and Procedures. The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer’s Representative (COR). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces, Director of Emergency Services or local Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DoD, Headquarters Air Force (HAF) and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.
1. The contractor shall obtain base identification and vehicle passes, if required, for all contractor personnel who make frequent visits to or perform work on the Air Force installation(s) cited in the contract. Contractor personnel are required to wear or prominently display installation identification badges or contractor-furnished, contractor identification badges while visiting or performing work on the installation.
2. The contractor shall submit a written request on company letterhead to the contracting officer listing the following: contract number, location of work site, start and stop dates, and names of employees and subcontractor employees needing access to the base. The letter will also specify the individual(s) authorized to sign for a request for base identification credentials or vehicle passes. The contracting officer will endorse the request and forward it to the issuing base pass and registration office or Security Forces for processing. When reporting to the registration office, the authorized contractor individual(s) should provide a valid driver s license, current vehicle registration, valid vehicle insurance certificate, and [insert any additional requirements to comply with local security procedures] to obtain a vehicle pass.
3. During performance of the contract, the contractor shall be responsible for obtaining required identification for newly assigned personnel and for prompt return of credentials and vehicle passes for any employee who no longer requires access to the work site.
4. Reserved.
5. Upon completion or termination of the contract or expiration of the identification passes, the prime contractor shall ensure that all base identification passes issued to employees and subcontractor employees are returned to the issuing office.
6. Failure to comply with these requirements may result in withholding of final payment.
1.4.5.1. For Contractors Requiring Common Access Card (CAC). Not Required.
1.4.5.2 For Contractors that do not require CAC but require access to a DoD Facility and/or Installation. Contractor and all associated sub-contractor’s employees shall comply with adjudication standards and procedures using the National Crime
Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Air Force Instruction (AFI) 10-245, AFI 31-101 and Air Force Manual (AFMAN) 31-113), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by Government representative)
1.4.5.3 Antiterrorism Awareness Level I Training (AT Level I). All contractor employees, to include subcontractor employees, requiring access to US Government installations, facilities and controlled access areas shall complete AT Level I training within 15 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. AT Level I may be accomplished by a Level I qualified instructor, completing the Force Protection computer-based training (CBT) course on the Advanced Distributed Learning System (ADLS) or Joint Knowledge Online at http://jko.jten.mil. Tracking for each contractor or subcontractor employee is the responsibility of unit AT Representative. The contractor shall submit certificates of completion for each affected contractor and subcontractor employee to the COR within 15 calendar days after completion of training by each employee or subcontractor personnel.
1.4.5.4 Reserved.
1.4.5.5 Communications Security/Information Technology (COMSEC/IT) Security. All communications with DoD organizations are subject to COMSEC review. All telephone communications networks are continually subject to intercept by unfriendly intelligence organizations. DoD has authorized the military departments to conduct COMSEC monitoring and recording of telephone calls originating from, or terminating at, DoD organizations. Therefore, the contractor is advised that any time contractor personnel place or receive a call they are subject to COMSEC procedures. The contractor shall ensure wide and frequent dissemination of the above information to all employees dealing with DoD information. The contractor shall abide by all Government regulations concerning the authorized use of the Government's computer network, including the restriction against using the network to recruit Government personnel or advertise job openings.
1.4.5.6 Reserved
1.4.5.7 Reserved.
1.4.5.8 Reserved
1.4.5.9 Reserved
1.4.5.10 Reserved
1.4.5.11 Requirement for OPSEC Training. In accordance with AFI 10-701, Operations Security, OPSEC PMs/Signature Managers/Coordinators will provide OPSEC training or training materials to contract employees within 30 days of employees’ initial assignment to the contract and prior to having access to any critical information (CI) and annually thereafter. General organizational orientations may need to be supplemented by duty-related orientations in the work center targeted toward specific critical information and vulnerabilities associated with the work. Initial training (OPSE 1301 - OPSEC Fundamentals) is located on the ADLS website and refresher OPSEC training is conducted annually (at Commander's Call). The contractor shall submit certificates of completion for each contractor employee to the COR within 15 calendar days after completion of training.
1.4.5.12 OPSEC Plan. Not Required.
1.4.5.13 Contracts that require Handling or Access to Classified Information: Not Required.
1.4.6 Physical Security. The contractor shall safeguard all Government property provided for contractor use. At the close of each work period, Government facilities, equipment and materials shall be secured.
1.4.6.1 Key Control: Not Required
1.4.7 Special Qualifications: Reserved.
1.4.8 Post Award Conference/Periodic Progress Meetings: The contractor agrees to attend any post award conference convened by the KO in accordance with FAR 42.5.
The KO, COR and other Government personnel, as appropriate, may meet periodically with the contractor to review the contactor’s performance. At these meetings, the KO will apprise the contractor of how the Government views the contractor’s performance and the contractor shall apprise the Government of problems, if any, being experienced.
The contractor shall resolve outstanding issues raised by the Government. Contractor attendance at these meetings shall be at no additional cost to the Government.
1.4.9 Contract Manager (CM): The contactor shall designate a CM who shall ensure performance under this contract. The name of this person, and an alternate who shall act for the contractor when the CM is absent, shall be designated in writing to the KO.
The CM or alternate shall have full authority to act for the contractor on all contract matters relating to daily operation of this contract. The CM shall work through the COR to resolve issues, receive technical instructions, and ensure adequate performance of services. The CM shall ensure that contractor employees do not perform any services outside the scope of the contract without an official modification issued by the KO. The CM shall ensure contractor employees understand that services performed outside the scope of the contract are performed wholly at the expense of the contractor.
1.4.10 Identification of Contractor Employees: All contractor personnel attending meetings, answering Government telephones and working in other situations where their contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression that they are Government employees. The contractor shall ensure that all documents or reports produced by contractor personnel are suitably marked as contractor products or that contractor participation is appropriately disclosed. The contractor’s status as a “contractor” shall be predominantly displayed in all correspondence types (to include signature blocks on e-mail) and dealings with Government or non-Government entities. Contractor personnel shall wear identification badges distinguishing themselves as such. The badges shall have the company name, employee name and the word “contractor” displayed.
1.4.10.1 The contractor shall retrieve all identification media (including vehicle passes) from its employees who depart employment for any reason. The contractor shall return all identification media (i.e., badges and vehicles passes) to the KO within 14 days of an employee’s departure.
1.4.11. Combating Trafficking in Persons: The United States Government has adopted a zero tolerance policy regarding trafficking in persons. Contractors and contractor employees shall not engage in severe forms of trafficking in persons during the period of performance of the contract; procure commercial sex acts during the period of performance of the contract; or use forced labor in the performance of the contract. The Contractor shall notify its employees of the United States Government’s zero tolerance policy, the actions that will be taken against employees for violations of this policy. The contractor shall take appropriate action, up to and including termination, against employees or subcontractors that violate the US Government policy as described at
FAR 22.17.
1.4.12 Contractor Travel: Not Applicable
1.4.13 Data Rights: Not Applicable
1.4.14 Organizational Conflicts of Interest (OCI): The contractor and subcontractor personnel performing services under this contract may receive, have access to or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications or work statements, etc.) or perform evaluation services which may create a current or subsequent OCIs, as defined in FAR Subpart 9.5. The contractor shall notify the KO immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the KO to avoid or mitigate any such OCI. The contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the KO. In the event the KO unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the KO may impose other remedies as he or she deems necessary, including prohibiting the contractor from participation in subsequent contracted requirements which may be affected by the OCI.
1.4.15 Phase In / Phase Out Periods: Not Applicable
2.0 Definitions and Acronyms:
2.1 Definitions:
2.1.1 Contractor: A supplier or vendor awarded a contract to provide specific supplies or service to the Government. The term used in this contract refers to the prime.
2.1.2 Defective Service: A service output that does not meet the standard of performance associated with the PWS.
2.1.3 Deliverable: Anything that can be physically delivered and includes non-manufactured things such as meeting minutes or reports.
2.1.4 Key Personnel: Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.
2.1.5 Physical Security: Actions that prevent the loss or damage of Government property.
2.1.6 Quality Assurance: The Government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.
2.1.7 Quality Assurance Surveillance Plan (QASP): An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.
2.1.8 Quality Control: All necessary measures taken by the Contractor to ensure that the quality of an end product or service shall meet contract requirements.
2.1.9 Subcontractor: One that enters into a contract with a prime contractor. The Government does not have privity of contract with the subcontractor.
2.2 Acronyms:
AEI Army Enterprise Infostructure AR Army Regulation AT/OPSEC Antiterrorism/Operational Security BI Background Investigation CM Contract Manager COR Contracting Officer Representative DA Department of the Army DD254 Department of Defense Contract Security Classification Specification DFARS Defense Federal Acquisition Regulation Supplement DoD Department of Defense
DSCA Defense Counterintelligence and Security Agency FAR Federal Acquisition Regulation GFP/M/E/S Government Furnished Property/Material/Equipment/Services HQDA Headquarters, Department of the Army HSPD Homeland Security Presidential Directive IA Information Assurance IS Information System(s) KO Contracting Officer NGB National Guard Bureau OCI Organizational Conflict of Interest PII Personally Identifiable Information PIPO Phase In/Phase Out POC Point of Contact PRS Performance Requirements Summary PWS Performance Work Statement QA Quality Assurance QASP Quality Assurance Surveillance Plan QC Quality Control QCP Quality Control Program SCR Service Contract Reporting SSN Social Security Number TE Technical Exhibit USD(I) Under Secretary of Defense for Intelligence
3.0 Government Furnished Property, Material, Equipment and Services (GFP/M/E/S):
The Government will provide the property, material, equipment, and/or services listed below solely for the purpose of performance under this contract:
3.1 Property: None
3.2 Materials: 4 LED recessed troffer light fixtures.
3.3 Equipment: None
3.4 Services: None
3.5 Utilities: All utilities in the facility will be available for the contactor’s use in the performance of this contract. The contractor shall instruct employees in utilities conservation practices. The contractor shall operate under conditions that preclude the waste of utilities, which include turning off the water faucets or valves after using the required amount.
4.0 Contractor Furnished Property, Materials, and Equipment (CFP/M/E): RESERVED
5.0 Requirements: The contractor shall furnish all supervision, labor, materials, equipment, and supplies and other items of expense required to perform the work specified in this document in strict accordance with the specifications and drawings for this project and provide the government a complete and useable end product. This project will bid in 2 CLINs. The first CLIN will be for the work in building 150 (Paragraphs 5.1 through 5.9.6 and associated drawings). The second CLIN is work in building 101 (Paragraphs 5.10 through 5.17 and the associated drawings).
5.1 Construct wall and perform interior renovations at building 150 (Civil Engineering) as described below and as shown on the drawings in Room 118 (CLIN 1).
5.1.1 The following drawings are attached:
Existing Lighting Plan – 150 Bldg. 150 Partial Floor Plan
5.2 Submittals: Submit technical data, catalog cut sheets, samples, test reports or other items as listed below:
5.2.1 180th FW Solid Waste Disposal and Tracking Form.
5.2.2 180th FW Ozone Depleting Substances Form for all material & equipment containing refrigerants – Not applicable for this project.
5.2.3 As-built drawings – Not applicable for this project.
5.2.4 Operations and maintenance manuals, and operating instructions for all installed material and equipment – Door hardware
5.2.5 Schedule and schedule of values
5.2.6 Submittals shall be provided with an AF Form 3000 filled out and signed by the contractor certifying the material is in compliance with the project requirements.
5.3 General:
5.3.1 Portable Toilet: Provide a portable toilet for use of contractor personnel. Not applicable for this project
5.3.2 Provide lighted barricades around perimeter of demolished pavements, sidewalks and excavations until the new concrete is properly cured.
5.3.3 The work area shall be kept clean on a continual basis to prevent items from becoming FOD. Ensure all construction debris is properly contained in dumpsters, cans, etc. and covered until removed from base.
5.3.4 The contractor shall remove and properly dispose of all demolished materials and construction debris from installation.
5.3.5 The contractor shall verify existing dimensions and conditions prior to submitting a bid and again prior to beginning work.
5.3.6 The contractor shall provide the government project manager or COR 7 days written notice before performing any disturbance of the ground to a depth below 3”. The notice shall include a drawing of the area where the work is to be done.
Mark the work area and proposed excavations with white flags or marking paint if required by the government, so existing utilities can be properly identified before beginning any demolition or excavation. Contractor shall ensure an approved Air Force Form 103 Work Clearance is issued before beginning any excavations.
5.3.7 Provide a minimum of 7 days advance notice in writing to the Contracting Officer or COR prior to the shutdown of any building utility system, street or parking lot.
5.3.8 The contractor shall insure that all work complies with all federal state and local laws and ordinances applicable to the construction of this project. Install all equipment according to the manufacturer’s written instructions. If a conflict is found, notify the Contracting Officer for resolution of the conflict prior to proceeding.
5.3.9 Prior to performing any operation requiring use of an open flame, or spark producing work obtain a burn permit from the base fire department (419-868- 4116). The contractor shall provide and maintain fire extinguishers and other safety equipment at the job site at all times as required to perform the work.
5.3.10 Provide dust partitions as needed to minimalize dust and debris from migrating to other occupied portions of the facility.
5.4 Demolition:
5.4.1 Base personnel shall remove the existing system furniture from the project area and store outside of the work area.
5.4.2 The contractor shall perform all miscellaneous demolition as required to construct the new wall, door, finishes and perform the electrical & HVAC work shown on the drawings.
5.4.3 Carpet and cove base to remain on existing walls except where needed to construct the new walls.
5.4.4 Remove ceiling tiles and grid as needed to construct the new wall. Remove all ceiling tiles inside the new room. These tiles may be used to repair and replace the ceiling the tiles outside of the new office area. Dispose of excess tiles.
Rework the existing ceiling grid as needed and repair to match the existing ceiling layout.
5.4.5 Remove 4 lights from the new office area. Wiring to remain for new lights but they will be rewired to be controlled by a new switch inside the office.
5.4.6 Relocate 2 existing lights near the proposed new east wall to the adjacent hallway area. Extend wiring as needed. These lights shall remain on the existing circuit and 3-way switch.
5.4.7 HVAC: Relocate one return air grille and supply diffuser to new location shown on the drawings. Modify ceiling grid as needed to accommodate the HVAC items.
5.5 Doors, Frames and Hardware:
5.5.1 Provide a new 3070 solid core wood door with narrow lite glass. Door shall be 1-3/4” thick and match existing finish as adjacent doors.
5.5.2 Provide a new 16-gauge hollow metal frame for the new door as indicated on the drawing. Frame shall be reinforced for door hardware. Provide door silencers with frame.
5.5.3 Provide door hardware as follows:
5.5.3.1 Medium duty hinges with ball bearings, 4.5” x 4.5”
5.5.3.2 Cylindrical Lockset – Office function, Lockset shall be able to accept a Schlage Primus full size interchangeable core. The government shall provide the core and keys. The contractor shall furnish the appropriate tail piece to work with the Schlage core.
5.5.3.3 Dome stile, floor mounted door stop.
5.5.3.4 Hardware shall match existing satin chrome finish.
5.6 Walls
5.6.1 Provide 3-5/8” wide, 25-gauge metal studs at 16” on center from floor to roof deck above unless noted otherwise.
5.6.2 Insulation to 10’ above finished floor. Provide 3.5” thick unfaced fiberglass batts.
5.6.3 Provide 5/8” drywall on each side of framing to 10’ above finished floor. Tape and finish drywall to a Level 4 finish ready to accept paint to 10’. Finish drywall where new walls intersect existing wall surfaces to blend as if original construction.
5.6.4 Paint new and existing walls where indicated. Provide one coat of latex acrylic primer and 2 finish coats of latex acrylic paint. Color to match existing walls (SW 7647 Crushed Ice).
5.6.5 Paint to match existing door frames in the building (SW 1034 Dolphin).
5.6.5 Provide 4” cove base on new walls (both sides) and existing walls if removed.
Color, height and thickness to match existing.
5.7 Ceiling:
5.7.1 Repair/replace ceiling grid at new wall to match existing.
5.7.2 Provide new ceiling tiles inside of the new office area. Match or approximate the existing color and finish.
5.7.3 Reinstall or replace ceiling tiles outside of the new walls to match existing.
5.8 HVAC: Relocate HVAC items as shown on the drawings. Extend ductwork if necessary to move the location shown.
5.9 Electrical:
5.9.1 Install new receptacles as indicated on the drawings. Reuse existing circuits from the existing system furniture feed to power new receptacles. The feed for these circuits is panel EM-2, circuits 31, 33 & 35. Connect the new receptacles equally across all three phases to evenly split the electrical load.
5.9.2 Relocate two existing lights to outside of the new office. Circuit and switching for these lights to remain.
5.9.3 Install 4 new Government Provided Lights LED 2’ x 4’ troffers with acrylic lens in the new office as shown on the drawings. Disconnect these lights from the existing 3-way switches. Provide a new single pole switch to control these lights.
These lights are powered from panel EM-2 circuit 1.
5.9.4 Install a ¾” EMT conduit from 12” above new ceiling down to a new 4” x 4” x 2” deep box for a future 4 jack computer/telephone outlet where indicated. Provide pull string in conduit. Flexible conduit may be used where installed in existing walls.
5.9.5 Conduit for all electrical feeds will be EMT or IMC in new walls. Flexible conduit may be used in existing walls.
5.9.6 All work shall be in accordance with the most recent version of the National Electrical Code.
5.10 Construct a wall and perform interior renovations as described below and as shown on the drawings for building 101, rooms 109 and 111 (CLIN 2).
5.11 The following drawings apply to the work at building 101:
Demolition Plan – 101 Floor Plan – Bldg. 101 Existing Reflected Ceiling Plan - 101 Electrical Demolition Plan – 101 Electrical Plan – Bldg. 101 Lighting Plan - 101
5.12 Construct drywall partition walls as outlined in paragraph 5.6 above. The wall at building 101 shall not be insulated.
5.12.1 Match existing colors for walls (SW1002, Big Chill), doors/frames (SW1005, Silverado) and cove base (Johnsonite No. DC-48, Grey).
5.13 Door, Frame and Hardware:
5.13.1 Provide a new 3070 hollow metal door with narrow lite glass. Door shall be 18-gauge steel, 1/3/4” thick and match existing finish as adjacent doors. Glass shall be ¼” safety glass.
5.13.2 Provide a new 16-gauge hollow metal frame for the new door where indicated on the drawing. Frame shall be reinforced for door hardware. Provide door silencers with frame.
5.13.3 Provide blocking in new wall for ground bus bar. Coordinate with the electrical contractor for requirements.
5.13.4 Provide door hardware as follows:
5.13.4.1 Medium duty hinges with ball bearings, 4.5” x 4.5”
5.13.4.2 Passage set, cylindrical
5.13.4.3 Door closer, medium duty
5.13.4.4 Floor mounted door stop, dome style
5.13.4.5 Hardware shall match existing style and finish.
5.14 Repair/replace ceiling grid where the old wall was removed and on each side of the new wall. Provide new tegular edge ceiling tiles in the area around the old and new walls to complete the ceiling. Match existing style, color and texture. Ceiling tiles not affected by construction shall remain.
5.15 Electrical:
5.15.1 All work shall be in accordance with the most recent version of the National
Electrical Code.
5.15.2 Remove ground bus bar, ground cable reel, and static ground touch pad and reinstall extending to the new wall. Provide new fasteners, and other miscellaneous materials if damaged during removal. The government has additional pieces of bus bar and standoff insulators if needed. Coordinate blocking in walls for ground bar and touch pad with the General Contractor.
5.15.3 Remove and replace receptacles (or reinstall existing) where shown on the drawings. Provide new conduit, wire, boxes and accessories as needed to install the receptacles.
5.15.4 Remove existing communications outlets as shown on the drawings.
5.15.5 Provide new boxes and conduits for future outlets as shown on the drawings.
Provide pull strings in all empty conduits.
5.15.6 Perform all demolition and removals as shown on the drawing and as needed to facilitate the work. Where patching of finish materials is required due to demolition, repairs shall be made and finished to match existing construction in color and texture.
5.16 Provide submittals outlined in paragraph 5.2 if applicable.
5.17 Follow general conditions outlined in paragraph 5.3.
5.x Service Contract Reporting: Reserved for projects over $3 million.
6.0 Applicable Publications: Publications applicable to this PWS are listed below:
Publication (Chapter/Page)
Date of Publication
Mandatory or Advisory
Website
Federal Acquisition Regulation Advisory https://www.acquisition.gov/?q=browsefar Defense Federal Acquisition
Regulation Supplement Advisory http://www.acq.osd.mil/dpap/dars/dfarspgi/current/in dex.html or https://www.acquisition.gov/dfars Joint Travel Regulation (JTR) Advisory https://www.defensetravel.dod.mil/site/travelreg.cfm
DoDM 1000.13-M-V1 DoD Identification (ID) Cards (Enclosure 2, paragraph 3.b)
01/23/2014 (Change 1:
07/28/2020)
Advisory http://www.esd.whs.mil/Directives/issuances/dodm
Federal Information Processing Standards (FIPS) Publication 201-2 Personal Identity Verification (PIV) of Federal Employees and Contractors
(paragraph 9)
August 2013 Advisory http://nvlpubs.nist.gov/nistpubs/FIPS/NIST.FIPS.201 -2.pdf
DoDM 5200.2 Procedures for the DoD Personnel Security Program
(PSP)
04/03/2017 Advisory https://www.esd.whs.mil/Directives/issuances/dodm/
DoDI 5200.46 DoD Investigative and Adjudicative Guidance for Issuing the Common
Access Card (CAC)
09/09/14 (Change 1:
05/04/2018)
Advisory https://www.esd.whs.mil/Directives/issuances/dodi/
Homeland Security Presidential Directive (HSPD)-12
Policy for a Common Identification Standard for Federal Employees and
Contractors
08/27/2004 Advisory https://www.dhs.gov/homeland-security-presidential-directive-12
DoDI 5400.11 Department of Defense Privacy and
Civil Liberties Programs
01/29/2019
Advisory https://www.esd.whs.mil/Directives/issuances/dodi/
DoD 5400.11-R Department of Defense Privacy
Program
05/14/2007 Advisory https://www.esd.whs.mil/Directives/issuances/dodm/
DoDD 8140.01 Cyberspace Workforce Management
10/05/2020
Advisory https://www.esd.whs.mil/Directives/issuances/dodd/
DoD 8570.01-M Information Assurance Workforce
Improvement Program
12/19/2005 (Change 4:
11/10/2015)
Advisory https://www.esd.whs.mil/Directives/issuances/dodm/
DoD 5220.22-M National Industrial Security Program
Operating Manual (NISPOM)
02/28/2006 (Change 2:
05/18/2016)
Advisory https://www.esd.whs.mil/Directives/issuances/dodm/
AFI 10-245
Antiterrorism
03/28/2013 (Certified current
03/30/2017)
Advisory https://www.e-publishing.af.mil/Product- Index/#/?view=pubs&orgID=10141&catID=1&series
=-1&modID=449&tabID=131
AFI 31-101
Security Forces Standards and
Procedures
08/18/2020 Advisory https://www.e-publishing.af.mil/Product- Index/#/?view=pubs&orgID=10141&catID=1&series
=-1&modID=449&tabID=131
AFMAN 31-113
Security Forces Standards and Procedures
03/05/2013 Change 1:
12/02/2015
Advisory https://www.e-publishing.af.mil/Product- Index/#/?view=pubs&orgID=10141&catID=1&series
=-1&modID=449&tabID=131
AFPD 17-1
Information Dominance Governance and Management
04/12/2016 Advisory https://www.e-publishing.af.mil/Product- Index/#/?view=pubs&orgID=10141&catID=1&series
=-1&modID=449&tabID=131
AFMAN 17-1301
Computer Security (COMPUSEC) 02/12/2020 Advisory https://www.e-publishing.af.mil/Product-
Index/#/?view=pubs&orgID=10141&catID=1&series =-1&modID=449&tabID=131
AFI 10-701
Operations Security
7/24/2019 (Change 1:
06/09/2020)
Advisory https://www.e-publishing.af.mil/Product- Index/#/?view=pubs&orgID=10141&catID=1&series
=-1&modID=449&tabID=131
6.1 Applicable Forms: Forms applicable to the PWS are listed below:
Form Date Website
DD 1172-2
Application for Identification Card/DEERS Enrollment
Mar 2017 http://www.dtic.mil/whs/directives/forms/index.htm
I-9 Employment Eligibility Verification
10/21/2019 https://www.uscis.gov/sites/default/files/files/form/i-9.pdf
DD 441
Department of Defense Security
Agreement
Feb 2020 http://www.dtic.mil/whs/directives/forms/dd/ddforms0001- 0499.htm
DD 250
Material Inspection and Receiving
Report
Aug 2000 https://www.esd.whs.mil/Directives/forms/dd0001_0499/
AF Form 3000 Material Approval Submittal
Most recent version
TECHNICAL EXHIBIT 1
Performance Requirements Summary (PRS) This PRS includes performance objectives the Government will use to determine contractor performance and will compare contractor performance to the Acceptable Quality Level (AQL).
Performance
Objective Performance Standard Acceptable Quality
Levels (AQL) Surveillance Method / By
Whom
Para. 5.0, Construct a wall and office space
Construct a wall and office space as outlined in para. 5.0 and as shown on the drawings.
Construction must meet the requirements of this
PWS and all federal codes and regulations.
On-site inspection by the COR/Project Manager
TECHNICAL EXHIBIT 2
Deliverables Schedule
PWS Reference / Deliverable Title
Frequency Number of Copies
Medium/Format Submit To
Para. 5.0.
Construct Wall and office renovations
Once, at completion of project
0 Construct project on site
COR
1.4.5.3 AT Level 1
Awareness Training
Certificates
Provide within 15 calendar days after employee completes training.
1 Electronic Submission
COR
1.4.5.11 OPSEC
Training Certificates
Provide within 15 calendar days after employee completes training.
1 Electronic Submission
COR
1.4.10 Identification
Media
Return within 14 days of employee’s departure from contract performance.
Original(s) Hard Copy KO
Section 00100 - Bidding Schedule/Instructions to Bidders
INSTRUCTIONS
SECTION 00100 INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS
1. Description of the Project: Construct Walls
2. Instructions to Bidders:
2.1. You are invited to submit a bid in response to our Invitation for Bids (IFB) for Construct Vehicle Service
Rack, W50S8S23B0001, Project Number WYTD232003, at Toledo OH ANGB.
2.2. As a result of this solicitation, the Government intends to award a Firm Fixed Price (FFP) contract resulting from this solicitation to the responsible bidder whose bid, conforming to the invitation for bids, will be most advantageous to the Government, considering only price.
2.3. This solicitation is set-aside 100% for small businesses.
3. NOTICE OF PRE-BID CONFERENCE AND SITE VISIT:
3.1. A pre-bid conference will be conducted on July 6, 2023 at 10:00 AM EST for the purposes of briefing on the bid requirements and answering questions regarding this solicitation. This conference will be held at Ohio Air National Guard, 2660 S. Eber Rd., Swanton Ohio 43558, Bldg 150, CE Training Room. Interested Contractors are highly encouraged to attend the pre-bid conference. The site visit will be held following the conference.
3.2. Due to security conditions, all offerors must register to attend this conference and site visit. Email the following information for all attendees to SMSgt Barry Beale, MSgt Scott Hartzell and Darrell Maxwell at the following addresses: 180.FW.Contracting@us.af.mil
Firm Name and Telephone Number Visitor’s Name Drivers License
3.3. This information must be provided in advance, 3 business days prior to the meeting, in order to ensure access to the military base and conference site and ensure adequate seating for the conference attendees. Even if you have access to the base you must register to ensure adequate seating. The furnishing of the above information is voluntary; however, your failure to furnish all or part of the requested information may result in the Government’s denial of your access to the pre-proposal conference. This information will be provided to the Base Security Forces who will authorize your entrance to the site.
3.4. Visitors will be required to present the following information upon arrival: (1) Vehicle Registration, (2)
Valid Drivers License, (3) Proof of Insurance for Vehicle, (4) Safety Inspection and Car Rental agreement if applicable. Any of the above information furnished by you is protected under the Privacy Act and shall not be released unless permitted by law and/or you have consented to such.
3.5. Information provided at this conference or site visit shall not qualify the terms and conditions of the solicitation and specifications. Terms of the solicitation and specifications remain unchanged unless the solicitation is amended in writing. If an amendment is issued, normal procedures relating to the acknowledgment and receipt of solicitation amendments shall apply.
3.6. A record of the conference shall be made and furnished to all prospective bidders via posting at www.SAM.gov. The record will include minutes of the meeting, including questions (on a non-attribution basis) and answers.
4. FORMAL COMMUNICATION, OFFEROR EXPLANATIONS:
4.1. Submit all questions in the format shown below by email to the contracting office at the addresses show below. Do NOT contact AE or Engineering personnel directly. Doing so will only delay your answer. All questions must come through the Contracting Office.
Subject Line: Reference No. SOLICITATION W50S8S23B0001 Email: 180.FW.Contracting@us.af.mil
PRE-BID INQUIRY FORMAT
Date of Bid Inquiry: _______________
From: ______________________________ Company Name: ________________________________
Address:_____________________________________________________________________________
Phone Number: _____________________________ Fax Number:______________________________
Email address: ________________________________________________________________________
Bid Inquiry: (Please clearly state your question) (If sent via an attachment word docs are preferred to facilitate posting of answers to the master Q&A document.)
4.1. Any explanation desired by an offeror regarding the meaning or interpretation of the solicitation, or proposals, drawings, specifications, etc. must be requested in writing and with sufficient time allowed for a reply to reach bidders before the submission of their bid.
4.2. All questions and requests for information (RFI) must be received NOT LATER THAN the Fifth working day prior to bid opening. OFFERORS ARE STRONGLY ENCOURAGED TO SUBMIT QUESTIONS
EARLY IN THIS PROCESS.
4.3. Any changes to the drawings, specifications, etc. will be issued in the form of an amendment. However, any answers that clarify or provide an interpretation to the drawings, specifications, etc. will NOT be posted via amendment but rather as a response to the RFI on SAM.gov at https://www.SAM.gov.
4.4. Receipt by the offeror must be acknowledged in the space provided on the SF 1442 or by returning a signed copy of the amendment by the time set for receipt of bids.
4.5. For security reasons, all technical and engineering data related to this solicitation will be distributed using the Contract Opportunities (SAM.gov) system. Plans and specifications are locked on SAM.gov and require Contractors to request explicit access from the Contracting Officer OR export controlled access through DLA. See complete instructions on SAM.gov. SAM.gov is a web-based dissemination tool designed to safeguard acquisition-related information for all Federal agencies. Interested bidders/offerors must register with SAM.gov before accessing the system.
4.5.1. Amendments, if/when issued will be posted to https://www.SAM.gov for electronic downloading.
This will normally be the only method of distributing amendments prior to closing; therefore, it is the offerors responsibility to check the website periodically for any amendments to the solicitation. Websites are occasionally inaccessible due to various reasons.
5. BID REPOSITORY AND BID OPENING:
5.1. A bid repository is provided for hand carried bids and is located at 180th FW, Contracting Office, Bldg 150, 2660 S. Eber Rd., Swanton, OH 43558 . Hand carried bids must be deposited in the repository prior to the time established for opening of bids. Bidders are cautioned that they will be required to sign-in to enter the facility and should allow time to accomplish this. See instructions for obtain access to the base in the Site Visit instruction.
Follow the same instruction for obtaining entry to hand carry bid. Late receipt of bids due to entry delays may not be deemed excusable and the Contracting Officer may declare the bid “late” in accordance with FAR 14.304.
5.2. The bid opening will occur at the time and date specified in Block 13 of the SF1442 USPFO OH 180
MISSION SUPPORT Contracting, Bldg 150 Training Conference Room, 2660 S. Eber Rd., Swanton, OH 43558. All interested offerors and their major subcontractors are encouraged to attend the bid opening.
6. WAGE DETERMINATION:
6.1. Construction…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .