Tab 04 SOW.pdf

PDF 262 KB Posted

Attached to
Alteryx Server & Designer Procurement Federal contract opportunity
Solicitation number
80NSSC886865Q
Issued by
National Aeronautics and Space Administration Shared Services Center

About this file

This document is a Statement of Work (SOW) for a federal contract opportunity. The objective is to procure Alteryx Server & Designer products and services, including installation, configuration, training, and support. The key details are:

The required products and services are: 1) Analytics Innovation Program - Large (VAR), and 2) Alteryx Server Quick Start which includes installation, configuration, backup, and training. The place of performance is NASA Langley Research Center. The period of performance is 11/25/2024 - 8/24/2025 for the Analytics Innovation Program, and 11/25/2024 - 5/24/2025 for the Alteryx Server Quick Start. This is a brand name requirement for authorized resellers only, and a Letter of Authorization (LOA) must be included with the response. Responses must reference the Solicitation Number 80NSSC886865Q.

View the file

Other files for this federal contract opportunity

Other files attached to Alteryx Server & Designer Procurement, newest first.
File Type Posted
Tab 06 BNJ Redacted.pdf PDF
Tab 12 RFQ 80NSSC886865Q.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

1. Objective/Requirements

The information listed below is required to complete this purchase.

2. Characteristics, Scope, and Specs

LINE PART NO. DESCRIPTION QTY.

1 AX-187271-611 Analytics Innovation Program - Large (VAR) 1 2 PS-187372-611 Alteryx Server Quick Start (Includes installation and configuration of 1 server

(Production or Sandbox), 1 Designer Connect, Server back-up, 3 hours of training for up to 10 people; 8 hours)

3. Place of Performance

NASA Langley Research Center

4. Period of Performance

Line 1: 11/25/2024 – 8/24/2025

Line 2: 11/25/2024 – 5/24/2025

File details come from the government source that posted it. Updated .