This Statement of Work (SOW) details NASA Glenn Research Center's requirements for procuring calibration flanges for the Hailstorm program in 2025. The SOW requires the procurement of two specific flanges: a 16" Class 900 ANSI B16.5 Weldneck flange (Schedule 80) and a 14" Class 900 ANSI B16.5 Weldneck flange (Schedule 80), both made of 304SS material. The material must be delivered by September 1, 2025, with final inspection to be conducted by the PSL Facility Engineer upon arrival. The procurement is for the Neil A. Armstrong Test Facility in Sandusky, Ohio, and will support a calibration test planned for the fourth quarter of 2025. No Health and Safety Plan (HASP) is required, and there are no unique considerations or environmental impacts associated with this procurement.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Tab 10 RFQ 80NSSC25912604Q.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
FOR
PSL Calibration Flanges for Hailstorm Program
NATIONAL AERONAUTICS AND SPACE ADMINISTRATION
GLENN RESEARCH CENTER
NEIL A. ARMSTRONG TEST FACILITY
3597 SCHEID ROAD
SANDUSKY, OHIO 44870
LEWIS FIELD
21000 BROOKPARK ROAD
CLEVELAND, OHIO 44135
Background
The PSL will run a calibration test for the upcoming Hailstorm program in CY Q4 of 2025. To run the calibration needed to meet customer requirements, a 14” 900# class 304SS weld neck, Schedule 80 flange must be procured. A 16” 14” 900# class 304SS weld neck, Schedule 80 flange must also be procured.
Quality Assurance Standards (e.g. ISO 9001, AS9100, NFPA, ASME Boiler & Pressure Vessel Code, etc.)
ANSI B16.5
Government Furnished Items (items that help perform the work; not the item being worked)
☐None
Unique Considerations
☐None
Environmental Impacts
☐None
Health and Safety Plan (HASP) Is a HASP required for this work? No. This is for supplies only.
Pressure Vessels and Systems Does this work include pressure vessels and systems? No
Scope of Work Description Procure 1 each of:
Flange: 16” Class 900 ANSI B16.5 Weldneck flange, Schedule 80 Flange: 14” Class 900 ANSI B16.5 Weldneck flange, Schedule 80
Inspections Final inspection upon arrival at facility: PSL Facility Engineer
Milestones Material needed by 9/01/2025
Deliverables
Flange: 16” Class 900 ANSI B16.5 Weldneck flange, Schedule 80 Flange: 14” Class 900 ANSI B16.5 Weldneck flange, Schedule 80