Statement of Work Landscape 2274 PDPG212900.docx
DOCX document 3 MB Posted
- Attached to
- Landscaping 2274 Federal contract opportunity
- Solicitation number
- W50S74-21-R-0008
- Issued by
- Department of the Army National Guard
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 21-R-0008-1 Landscaping 2274.pdf | ||
| 21-R-0008 Landscaping 2274.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
LANDSCAPE
BUILDING 2274
PDPG212900
163 ATTK WING, MARCH AIR RESERVE BASE CA
California Air National Guard 163 Civil Engineering Squadron
30 DEC 2020
1 GENERAL REQUIREMENTS
1.1 SCOPE
Construct approximately 1/2 acre of landscaping at Building 2274 for the 163d Attack Wing located at March ARB CA. Work includes removing existing turf area and cobble and providing grading, planters, plants, trees, irrigation, mulch, cobble, and crushed rock.
1.2 COST PROPOSAL
LANDSCAPE
Building 2274 March Air Reserve Base California
A CLIN 1
B CLIN 2
LANDSCAPE EAST LANDSCAPE WEST
1.3 PERIOD OF PERFORMACE
Work shall be completed within 90 days from Notice to Proceed.
1.4 LEFT BLANK
1.5 STAGING AND SITE ACCESS
A Materials and equipment shall be staged in adjacent staging area.
B Buildings will be occupied during construction. Coordinate schedule with COR.
1.6 EROSION CONTROL
The disturbed area is under one acre. Implement storm water control best management practices protecting storm drains as shown per attachments.
1.7 DEMOLITION
Dispose all waste and excess soil off base. Green waste bin is provided for shrubs and trees.
1.8 GRADING
Clean soil is available from adjacent RTS site.
1.9 PORTLAND CEMENT PAVING
A Provide PCC walk as shown on drawings.
B Paving shall be minimum 2,500 psi over 95% compacted base. C Light broom finish to match existing.
1.10 IRRIGATION
A Modify existing sprinkler system to provide a fully functioning drip irrigation design and installation as required for the trees and planting. Planting will require drip line and trees will require bubblers and separate valves.
B Provide Quick Couplers in valve boxes.
C Install drip line for planting and bubblers for trees as shown on details.
1.11 AMENDED SOIL
A Soil amendment shall be Aguinaga Green GPS1 or equal. B Mix 1:4 ratio amendment and soil.
1.12 FILTER FABRIC
| A | Filter Fabric shall be 500 Series Landscaper’s Choice by GCI or equal. B | Install 12’ wide rolls filter fabric over all areas as shown on the drawings. C | Overlap fabric seams 6 inches minimum. |
| D | Staple down fabric at planted areas. Rock will hold down fabric at rock areas. Fabric shall not be exposed to view at completion of project. |
1.13 INERT MATERIALS
A Provide Cobble, Crushed Rock, and DG as shown on the drawings.
B Cobbles shall be installed with the small cobbles blending into large cobble areas to create a natural appearance as directed by COR.
1.14 MULCH
A Mulch shall be Aguinaga Green Forest Floor 0-2 or equal.
2 GENERAL CONDITIONS
2.1 SUBMITTALS
A Submittals shall be in PDF format. Government will provide template AFI3000. Combine items to reduce number of submittal. Bind AF3000 with submittal documentation as one document.
1 Submittal 1: APP, QC, AHA, Schedule 2 Submittal 2: Product Data
2.2 CHANGES
All work shall be completed in a workmanlike manner according to generally accepted standard practices. Any alteration, or deviation from the drawings/specifications or contract involving extra costs or credits, will be executed as mutually agreed upon and be verified by written change order.
2.3 TESTS & INSPECTIONS
Contractor shall provide all required tests and inspections required by code.
2.4 WARRANTY
Contractor shall guarantee the material and workmanship for one (1) year following the date of substantial completion.
2.5 PROJECT CLEANUP
Construction debris will be removed on a daily basis. Special care shall be provided to prevent Foreign Object Debris (FOD) from entering the flight line. Prior to final acceptance, contractor shall remove all waste materials and debris arising from construction and shall present all construction areas in a broom clean condition.
2.6 TEMPORARY FACILITIES
Contractor shall provide sanitary facilities.
2.7 HOURS OF OPERATION
Construction shall be performed during normal duty hours which are 0630-1630, Tuesdays through Fridays, excluding federal holidays, unless otherwise required in the contract or approved by the COR. There may be situations that require the contractor to work at times other than normal working hours. When the Contractor’s work schedule conflicts with an Air Force mission requirement, the COR reschedule the work to minimize disruption.
2.8 RECOGNIZED HOLIDAYS
The Contractor is not required to provide service on federal holidays, except in emergency situations; the holidays are:
| New Year’s Day: | 1 January | ||
| Martin Luther King Day: | 3rd Monday in January Washington’s Birthday: | 3rd Monday in February Memorial Day: | Last Monday in May |
| Independence Day: | 4 July | ||
| Labor Day: | 1st Monday in September | ||
| Columbus Day: | 2nd Monday in October | ||
| Veteran’s Day: | 11 November Thanksgiving Day: | 4th Thursday in November Christmas Day: | 25 December |
If these holidays fall on Saturday, the preceding Friday will be observed. If these holidays fall on Sunday, the following Monday will be observed. If a holiday falls on a scheduled service day, the Contractor will be responsible for rescheduling services for the first day post the holiday observance.
2.9 BASE CLOSURES
Work scheduled but not accomplished because of base closure due to weather, exercises, or actual alert, will be accomplished as soon as possible after reopening the base.
2.10 CONTRACTOR IDENTIFICATION BADGES
March Air Reserve Base is a DOD installation. All badging and security checks will be done in accordance with DOD, Air Force and base Security Forces requirements.
1 Badges or temporary base passes will be issued. All commercial vehicles will be inspected each time they enter the base.
2 Badges will be issued by the 163d Security Forces Squadron (SFS) to the contractor through the 163d Civil Engineering Squadron (CES) Construction Inspector. Badges shall be issued, tracked, and collected in accordance with instructions from Security Forces.
3 The following are the requirements and procedures for the contractor:
1 Contractors and sub-contractors working on the installation for 30 calendar days or more must be issued contractor identification badges.
2 Contractors working in Controlled or Restricted areas or any area on the flight line must be issued a specific contractor identification badge or be escorted.
2.11 ANTITERRORISM TRAINING
Contractor’s superintendent shall take a 20 minute power point AT Level 1 Training. Contractor shall relay the information to all subcontractors and have subcontractor sign acknowledging training.
2.12 NPERFORMANCE OF SERVICE DURING CRISIS OR HEIGHTENED SECURITY
In the event of crisis or heightened security caused by a national emergency, natural disaster, or other cause, continue performance as required in support of the Air Force mission. The Contract price and delivery schedule may be adjusted to reflect any change of work that may be directed. This service is not determined to be essential for performance during crisis according to DODI 3020.37.
2.13 SPECIAL QUALIFICATIONS
The Contractor shall provide the name and telephone number of the Contractor’s on-site contract manager and alternate. The Contractor’s on-site manager must be able to speak and write in the English language.
2.14 INTERFACES
Do not unduly interfere with regularly scheduled Government operational activities in the performance of contract requirements. In the event a Government supervisor so requests, temporarily cease work in the area and report the instructions, to include name of the Government person involved, to the COR immediately by the most expedient means. Notify the COR verbally of disputes with customers or other base contractors and follow-up in writing.
2.15 WORK CLEARANCE REQUESTS
Government will provide an approved Work Clearance Request, AF Form 103, prior for all work which involves excavation including minor digging.
2.16 SAFETY REQUIREMENTS AND REPORTS
The Contractor shall perform work in a safe manner as required by OSHA Safety and Health Requirements. Provide a verbal report to the COR as soon as possible of each occurrence of damage to Government property or an accident resulting in death, injury, occupational disease, or adverse environmental impact. Provide a completed copy of required Accident Investigation Reports to the COR within five calendar days of each occurrence.
2.17 PARTNERING AGREEMENT
The COR may require a partnering agreement between the Government and Contractor to facilitate joint cooperation and a sound partnership of all parties involved in the execution of this contract. Partnering is the creation of a Government-Contractor relationship that promotes achievement of mutually beneficial goals. It involves an agreement in principal to share the risk involved in completing the project and to establish and promote a nurturing partnership environment. Representatives from each organization are encouraged to participate in developing a partnering agreement. The partnering agreement that results may be formal or informal. If formal, it should be reduced to writing and signed by the parties involved.
3 ATTACHMENTS
3.1 STORM WATER BMPS
3.2 DRAWINGS
Categories
EC
Erosion
Control
SE
Sediment
Control
TC
Tracking
Control
WE
Wind
Erosion
Control
NS
Non-Stormwater
Management
Control
WM
Waste Management and
Materials
Pollution
Control Legend:
Primary
Category
Secondary Category Targeted
Constituents Sediment
Nutrients Trash
Metals Bacteria Oil and
Grease Organics Potential
Alternatives SE-1 Silt Fence
SE-5
Fiber
Rolls
SE-6
Gravel
Bag
Berm
SE-8 Sandbag Barrier
SE-14
Biofilter
Bags
SE-13
Compost
Socks and
Berms If User/Subscriber modifies this fact sheet in any way, the CASQA name/logo and footer below must be removed from each page and not appear on the modified version.
)Description and Purpose Storm drain inlet protection consists of a sediment filter or an impounding area in, around or upstream of a storm drain, drop inlet, or curb inlet. Storm drain inlet protection measures temporarily pond runoff before it enters the storm drain, allowing sediment to settle. Some filter configurations also remove sediment by filtering, but usually the ponding action results in the greatest sediment reduction. Temporary geotextile storm drain inserts attach underneath storm drain grates to capture and filter storm water.
Suitable Applications
· Every storm drain inlet receiving runoff from unstabilized or otherwise active work areas should be protected. Inlet protection should be used in conjunction with other erosion and sediment controls to prevent sediment-laden stormwater and non-stormwater discharges from entering the storm drain system.
Limitations
· Drainage area should not exceed 1 acre.
· In general straw bales should not be used as inlet protection.
· Requires an adequate area for water to pond without encroaching into portions of the roadway subject to traffic.
· Sediment removal may be inadequate to prevent sediment discharges in high flow conditions or if runoff is heavily sediment laden. If high flow conditions are expected, use Storm Drain Inlet Protection
SE-10
July 2012 California Stormwater BMP Handbook Construction www.casqa.org other onsite sediment trapping techniques in conjunction with inlet protection.
· Frequent maintenance is required.
· Limit drainage area to 1 acre maximum. For drainage areas larger than 1 acre, runoff should be routed to a sediment-trapping device designed for larger flows. See BMPs SE-2, Sediment Basin, and SE-3, Sediment Traps.
· Excavated drop inlet sediment traps are appropriate where relatively heavy flows are expected, and overflow capability is needed.
Implementation General Inlet control measures presented in this handbook should not be used for inlets draining more than one acre. Runoff from larger disturbed areas should be first routed through SE-2, Sediment Basin or SE-3, Sediment Trap and/or used in conjunction with other drainage control, erosion control, and sediment control BMPs to protect the site. Different types of inlet protection are appropriate for different applications depending on site conditions and the type of inlet. Alternative methods are available in addition to the methods described/shown herein such as prefabricated inlet insert devices, or gutter protection devices.
Design and Layout Identify existing and planned storm drain inlets that have the potential to receive sediment- laden surface runoff. Determine if storm drain inlet protection is needed and which method to use.
· The key to successful and safe use of storm drain inlet protection devices is to know where runoff that is directed toward the inlet to be protected will pond or be diverted as a result of installing the protection device.
· Determine the acceptable location and extent of ponding in the vicinity of the drain inlet. The acceptable location and extent of ponding will influence the type and design of the storm drain inlet protection device.
· Determine the extent of potential runoff diversion caused by the storm drain inlet protection device. Runoff ponded by inlet protection devices may flow around the device and towards the next downstream inlet. In some cases, this is acceptable; in other cases, serious erosion or downstream property damage can be caused by these diversions. The possibility of runoff diversions will influence whether or not storm drain inlet protection is suitable; and, if suitable, the type and design of the device.
· The location and extent of ponding, and the extent of diversion, can usually be controlled through appropriate placement of the inlet protection device. In some cases, moving the inlet protection device a short distance upstream of the actual inlet can provide more efficient sediment control, limit ponding to desired areas, and prevent or control diversions.
· Seven types of inlet protection are presented below. However, it is recognized that other effective methods and proprietary devices exist and may be selected.
· Silt Fence: Appropriate for drainage basins with less than a 5% slope, sheet flows, and flows under 0.5 cfs.
· Excavated Drop Inlet Sediment Trap: An excavated area around the inlet to trap sediment (SE-3).
· Gravel bag barrier: Used to create a small sediment trap upstream of inlets on sloped, paved streets. Appropriate for sheet flow or when concentrated flow may exceed 0.5 cfs, and where overtopping is required to prevent flooding.
· Block and Gravel Filter: Appropriate for flows greater than 0.5 cfs.
· Temporary Geotextile Storm drain Inserts: Different products provide different features. Refer to manufacturer details for targeted pollutants and additional features.
· Biofilter Bag Barrier: Used to create a small retention area upstream of inlets and can be located on pavement or soil. Biofilter bags slowly filter runoff allowing sediment to settle out. Appropriate for flows under 0.5 cfs.
· Compost Socks: Allow filtered run-off to pass through the compost while retaining sediment and potentially other pollutants (SE-13). Appropriate for flows under 1.0 cfs.
· Select the appropriate type of inlet protection and design as referred to or as described in this fact sheet.
· Provide area around the inlet for water to pond without flooding structures and property.
· Grates and spaces around all inlets should be sealed to prevent seepage of sediment-laden water.
· Excavate sediment sumps (where needed) 1 to 2 ft with 2:1 side slopes around the inlet.
Installation
· DI Protection Type 1 - Silt Fence - Similar to constructing a silt fence; see BMP SE-1, Silt Fence. Do not place fabric underneath the inlet grate since the collected sediment may fall into the drain inlet when the fabric is removed or replaced and water flow through the grate will be blocked resulting in flooding. See typical Type 1 installation details at the end of this fact sheet.
1. Excavate a trench approximately 6 in. wide and 6 in. deep along the line of the silt fence inlet protection device.
2. Place 2 in. by 2 in. wooden stakes around the perimeter of the inlet a maximum of 3 ft apart and drive them at least 18 in. into the ground or 12 in. below the bottom of the trench. The stakes should be at least 48 in.
3. Lay fabric along bottom of trench, up side of trench, and then up stakes. See SE-1, Silt Fence, for details. The maximum silt fence height around the inlet is 24 in.
4. Staple the filter fabric (for materials and specifications, see SE-1, Silt Fence) to wooden stakes. Use heavy-duty wire staples at least 1 in. in length.
5. Backfill the trench with gravel or compacted earth all the way around.
· DI Protection Type 2 - Excavated Drop Inlet Sediment Trap - Install filter fabric fence in accordance with DI Protection Type 1. Size excavated trap to provide a minimum storage capacity calculated at the rate 67 yd3/acre of drainage area. See typical Type 2 installation details at the end of this fact sheet.
· DI Protection Type 3 - Gravel bag - Flow from a severe storm should not overtop the curb. In areas of high clay and silts, use filter fabric and gravel as additional filter media. Construct gravel bags in accordance with SE-6, Gravel Bag Berm. Gravel bags should be used due to their high permeability. See typical Type 3 installation details at the end of this fact sheet.
1. Construct on gently sloping street.
2. Leave room upstream of barrier for water to pond and sediment to settle.
3. Place several layers of gravel bags – overlapping the bags and packing them tightly together.
4. Leave gap of one bag on the top row to serve as a spillway. Flow from a severe storm (e.g., 10 year storm) should not overtop the curb.
· DI Protection Type 4 – Block and Gravel Filter - Block and gravel filters are suitable for curb inlets commonly used in residential, commercial, and industrial construction. See typical Type 4 installation details at the end of this fact sheet.
1. Place hardware cloth or comparable wire mesh with 0.5 in. openings over the drop inlet so that the wire extends a minimum of 1 ft beyond each side of the inlet structure. If more than one strip is necessary, overlap the strips. Place woven geotextile over the wire mesh.
2. Place concrete blocks lengthwise on their sides in a single row around the perimeter of the inlet, so that the open ends face outward, not upward. The ends of adjacent blocks should abut. The height of the barrier can be varied, depending on design needs, by stacking combinations of blocks that are 4 in., 8 in., and 12 in. wide. The row of blocks should be at least 12 in. but no greater than 24 in. high.
3. Place wire mesh over the outside vertical face (open end) of the concrete blocks to prevent stone from being washed through the blocks. Use hardware cloth or comparable wire mesh with 0.5 in. opening.
4. Pile washed stone against the wire mesh to the top of the blocks. Use 0.75 to 3 in.
· DI Protection Type 5 – Temporary Geotextile Insert (proprietary) – Many types of temporary inserts are available. Most inserts fit underneath the grate of a drop inlet or inside of a curb inlet and are fastened to the outside of the grate or curb. These inserts are removable and many can be cleaned and reused. Installation of these inserts differs between manufacturers. Please refer to manufacturer instruction for installation of proprietary devices.
· DI Protection Type 6 - Biofilter bags – Biofilter bags may be used as a substitute for gravel bags in low-flow situations. Biofilter bags should conform to specifications detailed in SE-14, Biofilter bags.
1. Construct in a gently sloping area.
2. Biofilter bags should be placed around inlets to intercept runoff flows.
3. All bag joints should overlap by 6 in.
4. Leave room upstream for water to pond and for sediment to settle out.
5. Stake bags to the ground as described in the following detail. Stakes may be omitted if bags are placed on a paved surface.
· DI Protection Type 7 – Compost Socks – A compost sock can be assembled on site by filling a mesh sock (e.g., with a pneumatic blower). Compost socks do not require special trenching compared to other sediment control methods (e.g., silt fence). Compost socks should conform to specification detailed in SE-13, Compost Socks and Berms.
Costs
· Average annual cost for installation and maintenance of DI Type 1-4 and 6 (one year useful life) is $200 per inlet.
· Temporary geotextile inserts are proprietary and cost varies by region. These inserts can often be reused and may have greater than 1 year of use if maintained and kept undamaged. Average cost per insert ranges from $50-75 plus installation, but costs can exceed $100. This cost does not include maintenance.
· See SE-13 for Compost Sock cost information.
Inspection and Maintenance
· BMPs must be inspected in accordance with General Permit requirements for the associated project type and risk level. It is recommended that at a minimum, BMPs be inspected weekly, prior to forecasted rain events, daily during extended rain events, and after the conclusion of rain events.
· Silt Fences. If the fabric becomes clogged, torn, or degrades, it should be replaced. Make sure the stakes are securely driven in the ground and are in good shape (i.e., not bent, cracked, or splintered, and are reasonably perpendicular to the ground). Replace damaged stakes. At a minimum, remove the sediment behind the fabric fence when accumulation reaches one-third the height of the fence or barrier height.
· Gravel Filters. If the gravel becomes clogged with sediment, it should be carefully removed from the inlet and either cleaned or replaced. Since cleaning gravel at a construction site may be difficult, consider using the sediment-laden stone as fill material and put fresh stone around the inlet. Inspect bags for holes, gashes, and snags, and replace bags as needed. Check gravel bags for proper arrangement and displacement.
· Sediment that accumulates in the BMP should be periodically removed in order to maintain BMP effectiveness. Sediment should be removed when the sediment accumulation reaches one-third of the barrier height.
· Inspect and maintain temporary geotextile insert devices according to manufacturer’s specifications.
· Remove storm drain inlet protection once the drainage area is stabilized.
· Clean and regrade area around the inlet and clean the inside of the storm drain inlet, as it should be free of sediment and debris at the time of final inspection.
References Stormwater Quality Handbooks - Construction Site Best Management Practices (BMPs) Manual, State of California Department of Transportation (Caltrans), March 2003.
Stormwater Management Manual for The Puget Sound Basin, Washington State Department of Ecology, Public Review Draft, 1991.
Erosion and Sediment Control Manual, Oregon Department of Environmental Quality, February 2005.
Storm Drain Inlet Protection
SE-10
June 2012 California Stormwater BMP Handbook Construction www.casqa.org
Gravel bags
Gravel bags
6. Protection can be effective even if it is not immediately adjacent to the inlet provided that the inlet is protected from potential sources of pollution.
CLIN 1
LEGEND
| ITEM | QTY DESCRIPTION | |
| FILTER FABRIC | 19,300 SF GCI LANDSCAPERS CHOICE 500 MULCH | 5,700 SF AGUINAGA FOREST FLOOR 0-2 4"D |
| CRUSHED ROCK | 5,800 SF PALM SPRINGS GOLD 3/4" 3"D, 2,000 SF GFCI |
COBBLES 7,800 SF ARIZONA RIVER ROCK .75-1.5"/1.5-3"/3-8"/6"+
G1 )20/30/20/30%, 3"D MIN. 2,000 SF 3/4" GFCI CONCRETE PAVING 300 SF 4" UNO, 2500 PSI, LIGHT BROOM, COLD JOINT
TOTAL 19,600 SF / 43,560 SF = .45 ACRE DISTURBED AREA
VISITOR CENTER
BLDG 2274
G11 G2
G4
L4
L2
G6
PCC WALK
STAGING
AC PAVING
MARCH
AIR
RESERVE
BASE
CALIFORNIA
AIR
NATIONAL
GUARD
CIVIL
ENGINEERING
SQUADRON
)L1
L2 L3
| CLEVELAND SAGE | 60 1 GAL 24"OC SALVIA CLEVELANDI COAST ROSEMARY | 40 1 GAL 24"OC WESTRINGIA FRUTICOSA VICTORIA BLUE | 50 1 GAL 24" OC SALVIA FARINACEA DESERT PURPLE SAGE | 40 1 GAL 24"OC SALVIA DORRII |
| RED MEXICAN BIRD | 6 5 GAL CAESALPINIA PILCHERRIMA PINK MULLY | 8 5 GAL MUHLENBERGIA CAPILLARIS | ||
| BOUGAINVILLEA | 3 5 GAL, LA JOLLA |
JACARANDA 2 36" BOX, MIMOSAFOLIA
DESERT MUSEUM 2 36" BOX, PALO VERDE
PROJECT
G7
L427'
G11
G10 5'
AC PAVING
CLIN 1
G1
G4 G3 G8
L3
CLIN 2
G9 G9 G9
G5
G12
CREPE MYRTLE 1 36" BOX, LAGERSTROEMIA INDICA
EXISTING TREE 15 23 BUBBLERS (2 EA & 1 EA @ 7 CREPE MYRTLES)
IRRIGATION LINE 2" MAINS, 3/4" LATERALS, 12" BFG MIN
KEYNOTES
G GRADING
1. TEMP FABRIC AND WADDLE CATCH BASIN
2. MANHOLE
3. WATER METER
4. CLEANOUT
5. DEMO, LOWER AND REPLACE PCC WALK AND STOP SIGN
6. DEMO SHRUBS
7. DEMO COBBLES
8. DEMO GRASS
9. DEMO AC PAVING
10. DEMO AC PAVING AND REPLACE W/ 6" PCC W/ #5 T&b & 12"OC
11. CONC WALK
12. ADD 6' CONC WHEEL STOP (TYP OF 19)
L LANDSCAPE
1. EXTEND LINE EA FROM (E) BUBBLER AND DRIP VALVE BOXES
2. DEMO HOSE BIB, EXTEND LINE AND PROVIDE QUICK COUPLERS IN VALVE BOX
3. BORE UNDER PCC WALK
4. CAP WATER AND DEMO VALVE BOX
LOCATION PLAN
NOTESPDPG212900
1. REMOVE GRASS, TRIMMINGS, AND TREES (3' LONG MAX) IN GOVERNMENT PROVIDED GREEN WASTE BIN AT ADJ SITE.
2. DISPOSE UNCLEAN ORGANIC LADEN SOIL AND ROCK OFFSITE. ANY EXCESS CLEAN SOIL WILL BE BALANCED ON SITE AS DIRECTED BY COR.
3. SOIL FOR GRADING AND SOIL AMENDING MAY BE OBTAINED FROM NEARBY RTS SITE.
4. REMOVE SOIL 4" DEEP IN AREA RECIEVING MATERIAL UNO FROM TOP OF PAVING, MANHOLES, CATCH BASINS, ETC. STRAIGHT SLOPE TO CATCH BASINS & TREE BASE.
5. REMOVE SOIL 12" DEEP FROM FINAL GRADE IN NEW PLANTER AREAS. HAND DIG AROUND TREE ROOTS AS REQUIRED.LANDSCAPE
BUILDING 2274
6. GRIND TREE STUMPS TO SUBGRADE. DEMO TREE ROOTS WITHIN 8 INCHES OF PAVING AND BLDGS.
7. COMPACT SUBGRADE 90% UNDER COBBLES, AND GRAVEL, 95% UNDER CONC PAVING.
8. SPRAY ALL SUBGRADE W/ DIMENSION. ALLOW TWO MONTHS BEFORE PLANTING.
9. SPRAY EXISTING PLANTERS W/ SEDGEHAMMER AND QUICKPRO & RESPRAY MONTHLY UNTIL TIME FOR PLANTING ALLOWING FOR REST TIME.
10. AMEND SOIL & INSTALL BELOW FILTER FABRIC 12" DEEP IN PLANTERS AND 3" DEEP AROUND ALL EXISTING TREES TO DRIPLINE. AMENDMENT SHALL BE 25% MIX TO CLEAN SOIL OBTAINED FROM SITE ADJACENT TO STAGING AREA.
11. INSTALL FILTER FABRIC IN ALL AREAS EXCEPT PAVING. SPRAY SEDGEHAMMER PREEMERGENT AND FLOOD PLANTERS PRIOR TO INSTALLING FABRIC. FABRIC SHALL COVER SOIL COMPLETELY AND CONCEALED FROM VIEW AFTER TOPPING MATERIAL IS INSTALLED.
12. INSTALL COBBLES, CRUSHED ROCK, AND MULCH 3" DEEP MIN, 1" BELOW ADJ PAVING FS. COBBLES SHALL BE LAID IN GRADUAL SIZES AS DIRECTED BY COR.
13. CONNECT IRRIGATION LINES (12" MIN BFG) TO EXISTING BUBBLER AND DRIP VALVES, BUBBLER FOR TREES AND DRIP IRRIGATION AT PLANTS. INSTALL DRIP BELOW FABRIC. PROVIDE (2) RAINBIRD 36" RWS AT NEW & EXISTING TREES, UNO. PROVIDE FULLY FUNCTIONAL IRRIGATION SYSTEM AND DEMONSTRATE TO GOVERNMENT.
14. SOAK TREES ONCE PER WEEK UNTIL IRRIGATION IS FUNCTIONAL.
15. REMOVE DEAD LIMBS AND PRUNE TREES TO PROMOTE GROWTH PER ANSI A300.
16. PRESSURE WASH PCC PAVING AT PROJECT COMPLETION.
17. PROVIDE 3 MONTHS MONTHLY MAINTENANCE.
G6 G7SITE PLAN
SITE PLANN
20' 40' 60'
L1
30 DEC 2020
REMOTE CONTROL VALVE
'JUMBO' VALVE BOX W/COVER PER SPECIFICATIONS
WYE STRAINER W/BALL FLUSH VALVE
1/2" ABOVE FINISH GRADE IN TURF AREAS,
2" IN SHRUB AND GROUND COVER AREAS
12" BFG MIN
UNMORTARED BRICK SUPPORTS (ALL AROUND)
UNDISTURBED OR 90% COMPACTED SUBGRADE
3 FEET OF FLEXIBLE PVC TUBING
WATERPROOF WIRE CONNECTORS
LEGEND:
1. SLIP BASE SOCKET OVER END OF WIRES.
2. CLEANLY STRIP WIRES APPROXIMATELY 5/8" FROM END.
3. PUT CRIMP SLEEVE OVER WIRE ENDS - CRIMP SLEEVES AND CUT OFF EXCESS.
4. APPLY SEALER TO INSIDE OF SEALING PLUG - FILL CAVITY WITH SEALER.
5. PULL BASE SOCKET BACK OVER END OF WIRES AS FAR AS POSSIBLE.
6. PUSH SEALING PLUG INTO BASE SOCKET.
7. PUSH WIRES TO END OF BASE SOCKET TO ASSURE COMPLETE SEALING OF CONNECTION.
8. USE DRI-SPLICE MFG. BY SPEARS, OR APPROVED EQUAL.
FINISH GRADE / TOP OF COBBLE / TOP OF MULCH
LINE-SIZE NETAFIM TLSOV FLUSH VALVE AT END OF NETAFIM BLANK TUBING RUN
VALVE BOX WITH COVER, 6-INCH SIZE
NETAFIM BLANK TUBING
24" FLEXIBLE POLY TUBING, COIL INSIDE OF VALVE BOX
SUMP: 6-INCH MINIMUM DEPTH OF 3/4-INCH WASHED GRAVEL
BRICK SUPPORT (1 OF 2)
IN-LINE PRESSURE REGULATOR
PVC SCHEDULE 80 UNIONPDPG212900
PVC SCHEDULE 80 NIPPLE (TYP.)
FINISH GRADE LATERAL LINE
PVC SCHEDULE 80 FITTING (TYP.)
2' LONG WIRE EXPANSION LOOPS
6" DEEP PEA GRAVEL SUMPLANDSCAPE
BUILDING 2274
3 WIRE CONNECTOR
DRIPLINE FLUSH VALVE
MANUAL STYLE2
1 DRIP VALVE
MARCH AIR RESERVE BASE
CALIFORNIA AIR NATIONAL GUARD 163 CIVIL ENGINEERING SQUADRON
L2DETAILS
30 DEC 2020
image3.jpeg image89.png image90.png image91.png image92.png image93.png image94.png image95.png image96.png image97.png image98.png image99.png image100.png image101.png image102.png image103.png image104.png image105.png image106.png image107.png image108.png image109.png image110.png image111.png image4.png image5.png image6.png image7.png image8.png image9.png image10.png image11.png image12.png image13.png image14.png image15.png image16.png image17.png image18.png image19.png image20.png image21.png image22.png image23.png image24.png image25.png image26.png image27.png image28.png image29.png image30.png image31.png image32.png image33.png image34.png image35.png image36.png image37.png image38.png image39.png image40.png image41.png image42.png image43.png image44.png image45.png image46.png image47.png image48.png image49.png image50.png image51.png image52.png image53.png image54.png image55.png image56.png image57.png image58.png image59.png image60.png image61.png image62.png image63.png image64.png image65.png image66.png image67.png image68.png image1.png image69.png image70.png image71.png image72.png image73.png image74.png image75.png image76.png image77.png image78.png image2.png image79.png image80.png image81.png image82.png image83.png image84.png image85.png image86.png image87.png image88.png
File details come from the government source that posted it. Updated .