This document is a Statement of Work for a five-year service contract to provide preventive maintenance of twelve emergency backup generators and associated transfer switches at Cuyahoga Valley National Park in Ohio. The contractor will perform three quarterly inspections and one annual certification/preventive maintenance on each generator, including load testing. The contract base year is from August 15, 2024 to August 14, 2025, with four one-year option periods. The National Park Service Midwest Region is issuing a related Request for Quote (Solicitation #140P6424Q0068) for this requirement, which is a 100% small business set-aside under NAICS code 811310 with a $12.5 million size standard. The anticipated award date is August 2024.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P6424Q0068_Amd_0002.pdf | ||
| Revised_Statement_of_Work_0002.pdf | ||
| Sol_140P6424Q0068_Amd_0001.pdf | ||
| Ammended_-_Combined_Synopsis_0001.pdf | ||
| DOL_Wage_Determination_-_Summit.pdf | ||
| Combined_Synopsis.pdf | ||
| Price_Scheudle.pdf | ||
| DOL_Wage_Determination_-_Cuyahoga.pdf | ||
| Provisions_to_be_Completed.pdf | ||
| Price_Schedule.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Cuyahoga Valley National Park Brecksville, Ohio
STATEMENT OF WORK:
Preventive Maintenance of Backup Generators and Transfer
Switches
DATED:
June 2024
NATIONAL PARK SERVICE
MIDWEST REGION
OHIO MAJOR ACQUISITION BUYING OFFICE
STATEMENT OF WORK (SOW)
1. BACKGROUND
Cuyahoga Valley National Park (CVNP) is requesting a five-year service Contract (2024 through 2029) for three (3) quarterly inspections and one (1) annual certification/preventive maintenance of twelve (12) Emergency Backup Generators and associated transfer switches located throughout the park. Each year the contractor will perform four (4) independent inspections/maintenance checks per generator. Each of the four independent inspections/maintenance (annual and 3 quarterly’s) will occur within a one-week time. All 12 generators will be inspected, tested, or maintained per SOW within the one-week period totaling approximately 4 weeks of work per year. The intention is to prevent emergency repairs by performing four inspection per year.
2. OBJECTIVES:
The objective for the contractor is to provide three (3) quarterly inspections and one (1) annual certification/preventive maintenance. All twelve (12) generators will be load banked for 2 hours once per year.
PLACE OF PERFORMANCE:
1. 30 KW Cummins @ BMVC Boston Mills Visitor Center (lift station) Model #GG02-1870842 Serial #F180376626 Transfer Switch, Cummins Address: 5793 Zielinski Ct, Peninsula Oh 44264 (behind building)
2. 25 Kw Generac @ Canal Exploration Center (lift station)
Model #QT02524GNSA Serial #4523975 Transfer Switch Generac, Model #7271640100, Serial #91800 7104 Address: 7104 Canal Rd. Independence Oh 44131
3. 35 Kw Generac @ Coonrad Ranger Station (building power)
Model #20A03003-S Serial #2058172 Transfer Switch ASCA, Model #A300220061C, Serial #100696-4 Address: 10340 Riverview Rd. Brecksville, Oh 44141
4. 60 KW Kohler @ Duffey Property (lift Station)
Model # KG60 Serial #33M6GMGM006 Transfer Switch Mod# A333GMGL0549, Ser# KSS-AFNF-0200S Address: 4765 Truxell Rd. Boston TWP, Oh 44264
5. 50 KW Generac @ CVEEC Environmental Education Center Administration Bldg (building power) Model #3625050100 Serial #2074902 Transfer Switch Generac, Model #0047940, Serial #3818974 Address: 3595 Oak Hill Rd, Peninsula Ohio 44264
6. 60 KW Generac @ CVEEC Lipscomb Barn (building and lift station)
Model #SG60AG036.8N18 Serial #3000152949 Transfer Switch Generac, Serial 82102 Address: 3675 Oak Hill Road, Peninsula Oh. 44264
7. 100 Kw Kohler @ CVEEC White Pines House (building power)
Model #100REZGD Serial #SGM32LLS2 Transfer Switch Kohler, Model #KSS-AFNA-0400S, Serial #SGM32LDZV Address: 3681 Oak Hill Rd, Peninsula Oh. 44264
8. 50 KW @ Everette Ranger Station (building power)
Model #DSFAC-517717 Serial #G100137865 Transfer Switch Cummins, Model #OTPCB-5178069, Serial #G100138529 Address: 4683 Riverview Rd. Peninsula Oh 44264
9. 25 KW @ Howe Meadow (lift station)
Model #DSKAB-5030083 Serial #2058172 Transfer Switch Cummins, Model #DSKAB-5030083, Serial #G100136401 Address: 4060 Riverview Rd. Cuyahoga Falls Oh. 44221
10. 20 KW @ Johnson Rhodie (lift Station)
Model #CH100 Serial #339M6V66037 Transfer Switch: Model #RXT-JFNC-0100A-QS7, Serial A33ygmfn2129 Address: 1538 Boston Mills Rd. Peninsula Oh. 44264
11. 60 Kw Kohler @ Pine Hollow (lift station)
Model # 60RE0ZK Serial # 33HMGMGM002 Transfer Switch: Mod # KSS-AFNF-0200S, Serial# A333GMGL0550 Address: 5465 Truxell Rd. Boston TWP, Oh. 44264
12. 22 KW @ Virginia Lake VK Lake Shelter (lift station)
Model # 20RE0ZK Serial #SGM32LMWL
Transfer Switch Kohler, Model #KSS-AFNC0200S, Serial #SGM32LDZX 1000 Truxell Rd, Peninsula Oh. 44264
3. PERIOD OF PERFORMANCE:
This contract will include one (1) base year and four (4) option years. Option years will be exercised based on the contractor’s annual performance rating.
Base year - This service will begin on August 15, 2024 and expire on August 14, 2025.
Option year 1 - This service will begin on August 15, 2025 and expire on August 14, 2026.
Option year 2 - This service will begin on August 15, 2026 and expire on August 14, 2027.
Option year 3 - This service will begin on August 15, 2027 and expire on August 14, 2028.
Option year 4 - This service will begin on August 15, 2028 and expire on August 14, 2029.
4. SCOPE:
The emergency Backup Generators/ Transfer Switches provide a vital role in the park, they provide power to all sanitary lift station pumps. These pumps transfer effluent matter out of CUVA and are considered critical infrastructure. In the event of Generator and Transfer Switch failure all effluent matter would be subject to wet well overflow and create an environmental hazard.
The contractor’s responsibility is to provide three (3) quarterly inspections and one (1) annual certification/preventive maintenance to include but not limited to:
Generator
Cooling System:
1. Engine Coolant level (Record Temp. Rating of Coolant)
2. Radiator inspection (Check for blockage on Radiator Inlet and Outlet Fins and Check for
Leaks)
3. Coolant lines (Check for Leaks and Dry Rot Hoses)
4. Block heaters (Check for Operation)
DC Electrical System
1. Battery connections (Clean Terminal Ends and Apply Battery Grease on Terminals if needed)
2. Electrical starter (Tighten and Torque Bolts to Manufacturers Specs)
3. Electrical accessories & components (Check for Broken Wires and Terminals and
Connections) AC Electrical System
1. AC wiring
2. Battery charger (Check Charger for Charging output and Document Reading)
3. Control panel
4. AC voltage regulator (Check Mounting Bolts and Belt Tension / Wiring Terminals)
Electrical accessories & components
Air Induction & Exhaust System
1. Air cleaner (Replace Annually in Spring and Date Filter)
2. Air induction piping and connections (Check for Leaks and Tighten Clamps if needed)
3. Exhaust manifold piping and connections (Check for Leaks and Tighten Clamps if needed) Lubrication System
1. Engine oil level (Add Oil if Needed)
2. Engine oil change (Annually in Spring)
3. Engine oil filter change (Annually in Spring / also Date Filter)
4. Crankcase pressure
5. Crankcase breather
6. Oil leaks (Document)
7. Generator bearings (excessive noise please document)
8. Gauges and safety mechanisms (Identify that all Safeties are Operational )
Fuel Systems
1. Fuel tank (Check for Leaks and Fuel Gage is Operational)
2. Fuel filters (Change Annually and Date Filter)
3. Fuel system components (hoses and piping / check hoses for cracks and leakage)
4. Condensation/water in fuel
Engine Linkage
1. Check and lubricate all linkages to generator sets on a regular bases.
Load Testing
All generators within this contract will be load tested at 80 percent or greater than generator specifications of load capacity for a minimum of 2 hours per generator set per year. The load testing must “cook off” any residue that was caused from annual wet stacking. Exhaust mufflers and manifolds must not show signs of wet stacking after load test is complete. The findings on the Load Tests shall be recorded and sent to COR upon completion of all generators. These reports shall be established within 7 days after completion.
Transfer Switch
1. Inspect, operate, adjust, and lubricate mechanical linkages.
2. Verify operation of mechanical interlocks.
3. Inspect and dress current carrying contacts in accordance with manufacturer’s recommendations.
4. Test automatic transfer switches Perform insulation resistance test on each phase-to-phase and phase-to-ground using a megohmeter on each service
5. Perform contact resistance test.
6. Prove correct operation of the transfer switches by manually initiating transfers in both directions.
7. Simulate the automatic conditions requiring automatic transfer switches to transfer in both directions
8. Verify starting generators where applicable.
9. Verify correct indicating light operation.
10. Verify equipment alarms
Please note: that all inspections and annual certification/preventive maintenance must be performed in accordance with industry standard practices.
6. TASKS:
Contractor will provide three (3) quarterly inspections and one (1) annual certification/preventive maintenance with documentation of any deficiencies and corrections to include any upgrades recommended. Each generator and each service visit must have paperwork that documents all work performed. Invoicing and work receipts must match, or payments will be rejected.
Contractor shall call one of the following contacts at least 24 hours prior to performing work on site: Walter Gyure: (440) 343-7325, Aaron Sherrod: (440) 759-3498, or Jim Plush (440) 343- 7394. Written certification shall be documented that all systems are performing to manufacturer’s specifications. Contractor will provide this documentation to the Contracting Officers Technical Representative (COR) no later than 7 days after each visist and after and corrective action. Load tests will be completed once annually per site. Estimates must be provided to the COR and Contracting Officer (CO) prior to the start of any repairs being authorized. Timely and accurate paperwork is mandatory. Each receipt must include all pertinent information as outlined in section 4 of this SOW. All work must be detailed on the work receipt and or invoices. Accurate work receipts made double as invoices.
7. QUALITY ASSURANCE REQUIREMENT:
The COR or designated inspector may join the technician at any time to conduct quality control checks. Contractor will complete an accurate data record and will be evaluated periodically during the contract and at the contract’s annual completion date. Incomplete or inaccurate data records by the contractor, his/her employees or subcontractors, or loss of information to the contract may result in reduced payments to the contractor and/or cancellation of this agreement.