RFP SPRRA1-17-R-0378
View the file
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION, OFFER AND AWARD 1. This Contract Is A Rated Order Under
DPAS (15 CFR 700)
Rating Page of Pages
2. Contract Number 3. Solicitation Number 4. Type of Solicitation 5. Date Issued 6. Requisition/Purchase Number Sealed Bid (IFB)
Negotiated (RFP)
7. Issued By Code 8. Address Offer To (If Other Than Item 7)
NOTE: In sealed bid solicitations ‘offer’ and ‘offeror’ mean ‘bid’ and ‘bidder’.
SOLICITATION
9. Sealed offers in original and copies for furnishing the supplies or services in the Schedule will be received at the place specified in item 8, or if handcarried, in the depository located in until (hour) local time (Date).
Caution - Late Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and conditions contained in this solicitation.
10. For Information A. Name B. Telephone (No Collect Calls) C. E-mail Address
Call: Area Code Number Ext.
11. Table Of Contents
(X) Sec. Description Page(s) (X) Sec. Description Page(s)
Part I - The Schedule Part II - Contract Clauses A Solicitation/Contract Form I Contract Clauses
B Supplies or Services and Prices/Costs Part III - List Of Documents, Exhibits, And Other Attach.
C Description/Specs./Work Statement J List of Attachments D Packaging and Marking Part IV - Representations And Instructions E Inspection and Acceptance K Representations, Certifications, and F Deliveries or Performance Other Statements of Offerors G Contract Administration Data L Instrs., Conds., and Notices to Offerors H Special Contract Requirements M Evaluation Factors for Award
OFFER (Must be fully completed by offeror) NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.
12. In compliance with the above, the undersigned agrees, if this offer is accepted within _____ calendar days (60 calendar days unless a different period is inserted by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the designated point(s), within the time specified in the schedule.
13. Discount For Prompt Payment 10 Calendar Days (%) 20 Calendar Days (%) 30 Calendar Days (%) Calendar Days (%) (See Section I, Clause No. 52.232-8)
14. Acknowledgment of Amendments (The offeror acknowledges Amendment No. Date Amendment No. Date receipt of amendments to the SOLICITATION for offerors and related documents numbered and dated):
15A. Name and Code Facility 16. Name and Title of Person Authorized to Sign Offer Address of (Type or Print) Offeror
15B. Telephone Number 15C. Check if Remittance Address is 17. Signature 18. Offer Date Area Code Number Ext. Different From Above – Enter such
Address In Schedule
AWARD (To be completed by Government)
19. Accepted As To Items Numbered 20. Amount 21. Accounting And Appropriation
22. Authority For Using Other Than Full And Open Competition: 23. Submit Invoices To Address Shown In Item
10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( ) (4 copies unless otherwise specified)
24. Administered By (If other than Item 7) Code 25. Payment Will Be Made By Code
26. Name of Contracting Officer (Type or Print) 27. United States Of America 28. Award Date
(Signature of Contracting Officer)
IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.
AUTHORIZED FOR LOCAL REPRODUCTION Standard Form 33 (Rev. 9-97) Previous edition is unusable Prescribed By GSA-FAR (48 CFR) 53.214(c)
SPRRA1-17-R-0378
X
2017AUG04
2017SEP0104:00pm
DOA1
2017AUG04 SEE SCHEDULE
SPRRA1
DEFENSE LOGISTICS AGENCY
5201 MARTIN ROAD/DLA-AVN-AH
REDSTONE ARSENAL AL 35898-7340
KEARY L O'FLAHERTY
(256)876-4440
DLA-AVN-AHA
KEARY.OFLAHERTY@DLA.MIL
1 48
X 1
X 4
X 15 X 16 X 17
X 19
X 21
X 27
X 36
X 37
X 45
X 48
CONTINUATION SHEET
Reference No. of Document Being Continued Page of
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
SECTION A - SUPPLEMENTAL INFORMATION
Buyer Name: KEARY L O'FLAHERTY
Buyer Office Symbol/Telephone Number: DLA-AVN-AHA/(256)876-4440
Type of Contract 1: Firm Fixed Price
Kind of Contract: Supply Contracts and Priced Orders
Weapon System: UH-60
*** End of Narrative A0000 ***
A-1. THIS REQUIREMENT IS 100% SMALL BUSINESS SET-ASIDE IN ACCORDANCE WITH FAR 19.502-2. ONLY OFFERS FROM SMALL BUSINESS FIRMS WILL BE
CONSIDERED.
NOTE: Sub-tier items for this part are source controlled. Government does not have drawings for sub-tier items. Potential awardee shall obtain all sub-tier items directly from the required manufactured top level part number.Traceability to all sub-tier parts shall be submitted with proposal. Sub-Tier Components are identified below:
P/N: 70400-01607-111 VPN: 105700-2 Eaton Corporation (CAGE Code 17472)
P/N: 70400-01609-045 Uses bearing 38950-00903-104 as well as an arm. The arm may be formed at any qualified fabricator.
P/N: 70400-01609-045 STDP Rev F. is full and open - Any qualified source can Manufacture.
P/N: 38950-00903-104 VPN: MKSP4ASD1002 New Hampshire Ball Bearings
(CAGE Code 50294) and VPN: MKSP4-5 A1174 RBC Aircraft Products (CAGE Code 3NPS1)
Commercially Available Parts:
AN320-4 (Nut)
AN386-3-17 (Pin)
AN975-4 (Washer)
MS24665-153 (Cotter Pin)
NAS1149C0432B (Washer, Flat)
A-2. THIS REQUIREMENT IS IN SUPPORT OF THE UH-60 BLACKHAWK WEAPON SYSTEM.
A-3. THIS ITEM IS NOT A FLIGHT SAFETY/CRITICAL SAFETY ITEM (CSI).
A-4. PRODUCTION LOT TESTING (PLT) IS NOT REQUIRED.
A-5. CONTRACTOR FIRST ARTICLE TEST (FAT) IS REQUIRED
A-6. SNRR MARKINGS ARE NOT REQUIRED.
A-7. TAMMS-A MARKINGS ARE NOT REQUIRED.
A-8. IUID MARKINGS ARE NOT REQUIRED. THE DFARS CLAUSE 252.211-7003 ITEM IDENTIFICATION AND VALUATION IS NOT INCLUDED IN SECTION F.
A-9. SERIAL NUMBERING IS NOT REQUIRED.
A-10. FIT CHECK IS NOT REQUIRED.
A-11. ARMS EXPORT CONTROL IS APPLICABLE.
THE TECHNICAL DATA PACKAGE PROVIDED ON CD CONTAINS TECHNICAL DATA WHOSE EXPORT IS RESTRICTED BY THE ARMS EXPORT CONTROL ACT (TITLE 22
U.S.C., SEC 2751 ET SEQ.) OR EXECUTIVE ORDER 12470. VIOLATION OF THESE EXPORT LAWS ARE SUBJECT TO SEVERE CRIMINAL PENALTIES.
A-12. THIS IS A FIVE YEAR INDEFINITE DELIVERY INDEFINITE QUANTITY (IDIQ), FIRM FIXED PRICE EFFORT.
A-13. FUNDS WILL BE OBLIGATED/CITED UPON ISSUANCE OF EACH DELIVERY ORDER.
A-14. CONTRACTOR POINT OF CONTACT INFORMATION:
NAME: ___________________________________
TELEPHONE NUMBER: ___________________________________
E-MAIL ADDRESS: ________________________________________
2 48
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
A-15. DCMA ACO POINT OF CONTACT INFORMATION: TBD AT TIME OF AWARD
A-16. OFFERS SHALL BE SUBMITTED IN ACCORDANCE WITH FAR CLAUSE 52.215-1. FACSIMILE SUBMISSIONS ARE NOT AUTHORIZED. CONTRACTOR MAY E-MAIL
TO KEARY.OFLAHERTY@DLA.MIL OR MAIL TO:
DEFENSE LOGISTICS AGENCY
ATTN: KEARY O'FLAHERTY
DSCR-AHAC, BLDG 2501
REDSTONE ARSENAL, AL 35898-5280
A-17. ACCELERATED DELIVERY IS ENCOURAGED AND AUTHORIZED AT NO ADDITIONAL COST TO THE GOVERNMENT
A-18. PROCUREMENT HISTORY IS AVAILABLE.
SPRRA110D0045/0004/0005AA QTY.201 $3,634.00EA 19494 SEYER INDUSTRIES 04.11.2014
SPRRA110D0045/0003/0002AA QTY.150 $3,234.00EA 19494 SEYER INDUSTRIES 19.07.2011
W58RGZ11D0174/0001/0001AA QTY. 45 $1,380.00EA 0B1B6 PROTOTYPE ENG. 20.05.2011
SPRRA110C0002/0001/0001AA QTY.100 $5,117.00EA 54878 ROTAIR INDUSTRIES 23.11.2009
CONTRACTOR FIRST ARTICLE TEST
Number of samples to be tested = 1
Deliver FOB: Destination
Inspection: Origin
Acceptance: Destination (By the PCO)
BY: TBD
Ship To: ATTN: DLA Aviation Huntsville Post Award Team
5201 Martin Road
Redstone Arsenal, Alabama 35898
(With an information copy to the ACO)
OR
Email To: DLAHSVPostAwardTeam@dla.mil
Delivery Schedule:
280 Days ARO: Contractor First Article completed and Report Submission
30 Days: Government Review and Notification to Contractor
128 DAFAA: Delivery of Production Units
438 DARO
NOTICE: YOUR ATTENTION IS INVITED TO FEDERAL ACQUISITION REGULATION (FAR) 15.403-3, RELATIVE TO THE REQUIREMENTS FOR OBTAINING OTHER
THAN CERTIFIED COST OR PRICING DATA. THERFORE, YOU MAY BE REQUIRED TO SUBMIT OTHER THAN COST AND PRICING DATA, IF REQUESTED. OFFEROR MAY
USE THEIR OWN FORMAT TO PROVIDE, AT A MINIMUM, A BREAKDOWN OF ALL THE COST ELEMENTS TO INCLUDE PROFIT/FEE WHICH COMPRISE THE TOTAL
PROPOSED PRICE OR SALES HISTORY. FAILURE TO PROVIDE OTHER THAN COST AND PRICING DATA IF REQUESTED WILL RESULT IN YOUR OFFER BEING
CONSIDERED NON-RESPONSIVE.
FOR LONG LEAD TIME ITEMS AND/OR LONG TERM CONTRACTS, THE PARTIES RECOGNIZE THERE IS A RISK THAT PART(S) OR COMPONENT(S) REQUIRED FOR
PERFORMANCE OF THE CONTRACT/PURCHASE ORDER MAY BECOME UNAVAILABLE DUE TO OBSOLESCENCE. UPON RECEIPT OF THE CONTRACT/PURCHASE ORDER, CONTRACTOR IS RESPONSIBLE FOR VERIFYING ITS SOURCES OF SUPPLY. IF AT ANY TIME DURING THE COURSE OF PERFORMANCE CONTRACTOR BECOMES AWARE
THAT IT IS UNABLE TO PROCURE A PART OR COMPONENT NECESSARY TO FULFILL THE REQUIREMENTS OF THE CONTRACT, THE CONTRACTOR SHALL NOTIFY THE
CONTRACTING OFFICER IN WRITING WITHIN THIRTY DAYS. NOTIFICATION SHALL INCLUDE CONTRACTORS RECOMMENDATION FOR CORRECTION OF THE PROBLEM, IF POSSIBLE, WITH ESTIMATED COST AND SCHEDULE IMPACT, IF ANY. THE CONTRACTING OFFICER WILL DETERMINE THE APPROPRIATE COURSE OF ACTION
AND PROVIDE DIRECTION TO THE CONTRACTOR. IN NO EVENT WILL CONTRACTOR PROCEED WITH IMPLEMENTATION OF ITS RECOMMENDATION WITHOUT WRITTEN
DIRECTION FROM THE CONTRACTING OFFICER. AT THE SOLE DISCRETION OF THE CONTRACTING OFFICER, THE CONTRACT MAY BE TERMINATED IN WHOLE OR IN
PART, AS APPROPRIATE.
*** END OF NARRATIVE A0001 ***
3 48
PIIN/SIIN
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
SECTION B - SUPPLIES OR SERVICES AND PRICES/COSTS
0001 ADJUSTER ASSEMBLY
NSN: 1680-01-159-4583
Mfr CAGE: 81996
Mfr Part Number: 70400-21613-043 REV. 5
This is a five year Indefinite Delivery Indefinite
Quantity (IDIQ) Contract. Funds will be obligated/cited upon the issuance of each delivery order. The government will only be obligated to order the stated minimum quantity. The government is not obligated to issue any additional orders against this contract; however, the government reserves the right to order up to the maximum quantity.
The government has segregated the potential quantities into five years. However, this does not preclude exercising its rights under FAR 52.216-19 by ordering the maximum quantity specified in FAR
52.216-19(b)(1) at any time during the indefinite quantity period. The government's minimum quantity to be awarded simultaneously with the award of the basic contract is 180 each.
The initial delivery order will meet or exceed the minimum quantity at the first year pricing. The government's maximum quantity during the indefinite quantity period is 1150 each. The delivery order minimum order quantity is 75 each.
Delivery for each order shall commence 292 days after date of order. At no time will the contractor be required to ship more than "15" units per month unless mutually agreed to by both parties.
Prices quoted for each year will be valid for all quantities ordered during that ordering period.
Year 1 will be from date of award through day 365 days after receipt of order (DARO).
Year 2 will begin 366 DARO and end 730 DARO.
Year 3 will begin 731 DARO and end 1,095 DARO.
Year 4 will begin 1,096 DARO and end 1,461 DARO.
Year 5 will begin 1,462 DARO and end 1,826 DARO.
All references to F.O.B. origin throughout this solicitation apply ONLY to quantities ordered after the first ordering period.
The estimated (E) quantity listed herein does not commit the government to order that or any quantity above the minimum quantity.
(End of narrative A001)
4 48
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
0001AA YEAR ONE PRODUCTION QUANTITY WITH FIRST ARTICLE _______________________________________________
TESTING 180 (E) EA $ $ _______ ______________ __________________
COMMODITY NAME: ADJUSTER ASSEMBLY
CLIN CONTRACT TYPE:
Firm Fixed Price
PRON: AX6F7042AX PRON AMD: 01
Description/Specs./Work Statement _________________________________
TOP DRAWING NR: STDP 70400-21613
REVISION: D
Packaging and Marking _____________________
PACKAGING/PACKING/SPECIFICATIONS:
MIL-STD-129 MARKINGS SHALL APPLY
UNIT PACK: 001 INTERMEDIATE PACK: 000
LEVEL PRESERVATION: Military
LEVEL PACKING: A
All Wood Packaging Material (WPM) must be ISPM-15
Compliant
ESTIMATED MAXIMUM UNIT PACKAGE WEIGHT (POUNDS) AND
SIZE (INCHES):
WT [17.3] LB
LN [15]IN
WD [15] IN
DP [15.3] IN
MIL-STD-2073-1 Codes, Appendix J:
JI/A/MP[45]; JII/CD[1]; JIII/PM[ZZ]; JIV/WM[GB];
JV/CD [NA];JVI/CT[B];JVII/UC [ZZ];JVII/IC
[00];JIX/A/PK [F];JX/SM [17];JVIIIA/OPI[M]
Supplemental Information: ZZ=UC-8110-00-254-5715, MS27684-7,PM -12 ON BEARING.
(End of narrative D001)
Inspection and Acceptance _________________________
INSPECTION: Origin ACCEPTANCE: Origin
Deliveries or Performance _________________________
DOC SUPPL
REL CD MILSTRIP ADDR SIG CD MARK FOR TP CD ______ ________ ______ ______ ________ _____
001 W58H0Z6267BE01 W62G2T J 2
DEL REL CD QUANTITY DAYS AFTER AWARD __________ ______________ ________________
001 15 0438
5 48
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
002 15 0468
003 15 0498
004 15 0518
005 15 0548
006 15 0578
007 15 0608
008 15 0638
009 15 0668
010 15 0698
011 15 0728
012 15 0758
FOB POINT: Destination
SHIP TO:
(W62G2T) XU W1A8 DLA DIST SAN JOAQUIN
25600 S CHRISMAN ROAD
REC WHSE 57
TRACY,CA,95304-5000
SECOND ORDERING PERIOD DELIVERIES SHALL COMMENCE 438
DAYS AFTER THE DATE OF THE DELIVERY ORDER AWARD AT A
RATE OF 15 UNITS PER MONTH UNTIL SHIPPED COMPLETE.
(End of narrative F001)
0001AB YEAR ONE PRODUCTION QUANTITY WITHOUT FIRST __________________________________________
ARTICLE TESTING 180 (E) EA $ $ _______________ ______________ __________________
COMMODITY NAME: ADJUSTER ASSEMBLY
CLIN CONTRACT TYPE:
Firm Fixed Price
PRON: AX6F7042AX PRON AMD: 01
Description/Specs./Work Statement _________________________________
TOP DRAWING NR: STDP 70400-21613
REVISION: D
Packaging and Marking _____________________
PACKAGING/PACKING/SPECIFICATIONS:
MIL-STD-129 MARKINGS SHALL APPLY
UNIT PACK: 001 INTERMEDIATE PACK: 000
6 48
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
LEVEL PRESERVATION: Military
LEVEL PACKING: A
All Wood Packaging Material (WPM) must be ISPM-15
Compliant
ESTIMATED MAXIMUM UNIT PACKAGE WEIGHT (POUNDS) AND
SIZE (INCHES):
WT [17.3] LB
LN [15]IN
WD [15] IN
DP [15.3] IN
MIL-STD-2073-1 Codes, Appendix J:
JI/A/MP[45]; JII/CD[1]; JIII/PM[ZZ]; JIV/WM[GB];
JV/CD [NA];JVI/CT[B];JVII/UC [ZZ];JVII/IC
[00];JIX/A/PK [F];JX/SM [17];JVIIIA/OPI[M]
Supplemental Information: ZZ=UC-8110-00-254-5715, MS27684-7,PM -12 ON BEARING.
(End of narrative D001)
Inspection and Acceptance _________________________
INSPECTION: Origin ACCEPTANCE: Origin
Deliveries or Performance _________________________
DOC SUPPL
REL CD MILSTRIP ADDR SIG CD MARK FOR TP CD ______ ________ ______ ______ ________ _____
001 W58H0Z6267BE01 W62G2T J 2
DEL REL CD QUANTITY DAYS AFTER AWARD __________ ______________ ________________
001 15 0292
002 15 0322
003 15 0352
004 15 0382
005 15 0412
006 15 0442
007 15 0472
008 15 0502
009 15 0532
010 15 0562
7 48
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
011 15 0592
012 15 0622
FOB POINT: Destination
SHIP TO:
(W62G2T) XU W1A8 DLA DIST SAN JOAQUIN
25600 S CHRISMAN ROAD
REC WHSE 57
TRACY,CA,95304-5000
SECOND ORDERING PERIOD DELIVERIES SHALL COMMENCE 292
DAYS AFTER THE DATE OF THE DELIVERY ORDER AWARD AT A
RATE OF 15 UNITS PER MONTH UNTIL SHIPPED COMPLETE.
(End of narrative F001)
0001AC FIRST ARTICLE TEST REPORT 1 EA $ ** NSP ** $ ** NSP ** _________________________ ______________ __________________
COMMODITY NAME: ADJUSTER, ASSEMBLY
FIRST ARTICLE TEST TIME IS 3 DAYS. UNITS TO BE TESTED
IS 1 EACH. BEGIN TESTING 262 DAYS AFTER CONTRACT ___
AWARD (DACA). END TESTING 265 DACA. FIRST ARTICLE ___
TEST REPORT DUE 280 DACA. THE GOVERNMENT HAS 30 DAYS ___ __
TO APPROVE/DISAPPROVE THE TEST REPORT.
THE FIRST ARTICLE TEST UNIT SHALL NOT BE RETAINED BY
THE CONTRACTOR AS A MANUFACTURING STANDARD.
FAR 52.209-3 ALTERNATE I IS INCLUDED UNDER WHICH THE
CONTRACTOR IS REQUIRED TO PRODUCE THE FIRST ARTICLE
AND THE PRODUCTION QUANTITY AT THE SAME FACILITY.
(End of narrative B001)
Packaging and Marking _____________________
Inspection and Acceptance _________________________
INSPECTION: Origin ACCEPTANCE: Destination
Deliveries or Performance _________________________
DOC SUPPL
REL CD MILSTRIP ADDR SIG CD MARK FOR TP CD ______ ________ ______ ______ ________ _____
001 3
DEL REL CD QUANTITY DEL DATE __________ ______________ ___________
001 1 AS REQUIRED
8 48
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
FOB POINT: Destination
SHIP TO:
(SPRRA1) DLA AVIATION AT HUNTSVILLE, AL
DLR PROCUREMENT OPERATIONS (AH)
5201 MARTIN ROAD
REDSTONE ARSENAL,AL,35898-7340
0002 ADJUSTER, ASSEMBLY
NSN: 1680-01-159-4583
Mfr CAGE: 81996
Mfr Part Number: 70400-21613-043 REV. 5
0002AA YEAR TWO PRODUCTION QUANTITY 243 (E) EA $ $ ____________________________ ______________ __________________
COMMODITY NAME: ADJUSTER, ASSEMBLY
CLIN CONTRACT TYPE:
Firm Fixed Price
Description/Specs./Work Statement _________________________________
TOP DRAWING NR: STDP 70400-21613
REVISION: D
Packaging and Marking _____________________
PACKAGING/PACKING/SPECIFICATIONS:
MIL-STD-129 MARKINGS SHALL APPLY
UNIT PACK: 001 INTERMEDIATE PACK: 000
LEVEL PRESERVATION: Military
LEVEL PACKING: A
All Wood Packaging Material (WPM) must be ISPM-15
Compliant
ESTIMATED MAXIMUM UNIT PACKAGE WEIGHT (POUNDS) AND
SIZE (INCHES):
WT [17.3] LB
LN [15]IN
WD [15] IN
DP [15.3] IN
MIL-STD-2073-1 Codes, Appendix J:
JI/A/MP[45]; JII/CD[1]; JIII/PM[ZZ]; JIV/WM[GB];
JV/CD [NA];JVI/CT[B];JVII/UC [ZZ];JVII/IC
[00];JIX/A/PK [F];JX/SM [17];JVIIIA/OPI[M]
Supplemental Information: ZZ=UC-8110-00-254-5715, MS27684-7,PM -12 ON BEARING.
9 48
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
(End of narrative D001)
Inspection and Acceptance _________________________
INSPECTION: Origin ACCEPTANCE: Origin
Deliveries or Performance _________________________
FOB POINT: Origin
SHIP TO:
(Y00000) SHIPPING INSTRUCTIONS FOR CONSIGNEE
(SHIP-TO) WILL BE FURNISHED PRIOR
TO THE SCHEDULED DELIVERY DATE FOR
ITEMS REQUIRED UNDER THIS
REQUISITION.
SECOND ORDERING PERIOD DELIVERIES SHALL COMMENCE 292
DAYS AFTER THE DATE OF THE DELIVERY ORDER AWARD AT A
RATE OF 15 UNITS PER MONTH UNTIL SHIPPED COMPLETE.
SHIPPING INSTRUCTIONS SHALL BE PROVIDED 30 DAYS PRIOR
TO FIRST SCHEDULED DELIVERY.
(End of narrative F001)
0003 ADJUSTER, ASSEMBLY
NSN: 1680-01-159-4583
Mfr CAGE: 81996
Mfr Part Number: 70400-21613-043 REV. 5
0003AA YEAR THREE PRODUCTION QUANTITY 243 (E) EA $ $ ______________________________ ______________ __________________
COMMODITY NAME: ADJUSTER, ASSEMBLY
CLIN CONTRACT TYPE:
Firm Fixed Price
Description/Specs./Work Statement _________________________________
TOP DRAWING NR: STDP 70400-21613
REVISION: D
Packaging and Marking _____________________
PACKAGING/PACKING/SPECIFICATIONS:
MIL-STD-129 MARKINGS SHALL APPLY
UNIT PACK: 001 INTERMEDIATE PACK: 000
LEVEL PRESERVATION: Military
LEVEL PACKING: A
10 48
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
All Wood Packaging Material (WPM) must be ISPM-15
Compliant
ESTIMATED MAXIMUM UNIT PACKAGE WEIGHT (POUNDS) AND
SIZE (INCHES):
WT [17.3] LB
LN [15]IN
WD [15] IN
DP [15.3] IN
MIL-STD-2073-1 Codes, Appendix J:
JI/A/MP[45]; JII/CD[1]; JIII/PM[ZZ]; JIV/WM[GB];
JV/CD [NA];JVI/CT[B];JVII/UC [ZZ];JVII/IC
[00];JIX/A/PK [F];JX/SM [17];JVIIIA/OPI[M]
Supplemental Information: ZZ=UC-8110-00-254-5715, MS27684-7,PM -12 ON BEARING.
(End of narrative D001)
Inspection and Acceptance _________________________
INSPECTION: Origin ACCEPTANCE: Origin
Deliveries or Performance _________________________
FOB POINT: Origin
SHIP TO:
(Y00000) SHIPPING INSTRUCTIONS FOR CONSIGNEE
(SHIP-TO) WILL BE FURNISHED PRIOR
TO THE SCHEDULED DELIVERY DATE FOR
ITEMS REQUIRED UNDER THIS
REQUISITION.
THIRD ORDERING PERIOD DELIVERIES SHALL COMMENCE 292
DAYS AFTER THE DATE OF THE DELIVERY ORDER AWARD AT A
RATE OF 15 UNITS PER MONTH UNTIL SHIPPED COMPLETE.
SHIPPING INSTRUCTIONS SHALL BE PROVIDED 30 DAYS PRIOR
TO FIRST SCHEDULED DELIVERY.
(End of narrative F001)
0004 ADJUSTER, ASSEMBLY
NSN: 1680-01-159-4583
Mfr CAGE: 81996
Mfr Part Number: 70400-21613-043 REV. 5
11 48
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
0004AA YEAR FOUR PRODUCTION QUANTITY 242 (E) EA $ $ _____________________________ ______________ __________________
COMMODITY NAME: ADJUSTER, ASSEMBLY
CLIN CONTRACT TYPE:
Firm Fixed Price
Description/Specs./Work Statement _________________________________
TOP DRAWING NR: STDP 70400-21613
REVISION: D
Packaging and Marking _____________________
PACKAGING/PACKING/SPECIFICATIONS:
MIL-STD-129 MARKINGS SHALL APPLY
UNIT PACK: 001 INTERMEDIATE PACK: 000
LEVEL PRESERVATION: Military
LEVEL PACKING: A
All Wood Packaging Material (WPM) must be ISPM-15
Compliant
ESTIMATED MAXIMUM UNIT PACKAGE WEIGHT (POUNDS) AND
SIZE (INCHES):
WT [17.3] LB
LN [15]IN
WD [15] IN
DP [15.3] IN
MIL-STD-2073-1 Codes, Appendix J:
JI/A/MP[45]; JII/CD[1]; JIII/PM[ZZ]; JIV/WM[GB];
JV/CD [NA];JVI/CT[B];JVII/UC [ZZ];JVII/IC
[00];JIX/A/PK [F];JX/SM [17];JVIIIA/OPI[M]
Supplemental Information: ZZ=UC-8110-00-254-5715, MS27684-7,PM -12 ON BEARING.
(End of narrative D001)
Inspection and Acceptance _________________________
INSPECTION: Origin ACCEPTANCE: Origin
Deliveries or Performance _________________________
FOB POINT: Origin
12 48
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
SHIP TO:
(Y00000) SHIPPING INSTRUCTIONS FOR CONSIGNEE
(SHIP-TO) WILL BE FURNISHED PRIOR
TO THE SCHEDULED DELIVERY DATE FOR
ITEMS REQUIRED UNDER THIS
REQUISITION.
FOURTH ORDERING PERIOD DELIVERIES SHALL COMMENCE 292
DAYS AFTER THE DATE OF THE DELIVERY ORDER AWARD AT A
RATE OF 15 UNITS PER MONTH UNTIL SHIPPED COMPLETE.
SHIPPING INSTRUCTIONS SHALL BE PROVIDED 30 DAYS PRIOR
TO FIRST SCHEDULED DELIVERY.
(End of narrative F001)
0005 ADJUSTER, ASSEMBLY
NSN: 1680-01-159-4583
Mfr CAGE: 81996
Mfr Part Number: 70400-21613-043 REV. 5
0005AA YEAR FIVE PRODUCTION QUANTITY 242 (E) EA $ $ _____________________________ ______________ __________________
COMMODITY NAME: ADJUSTER, ASSEMBLY
CLIN CONTRACT TYPE:
Firm Fixed Price
Description/Specs./Work Statement _________________________________
TOP DRAWING NR: STDP 70400-21613
REVISION: D
Packaging and Marking _____________________
PACKAGING/PACKING/SPECIFICATIONS:
MIL-STD-129 MARKINGS SHALL APPLY
UNIT PACK: 001 INTERMEDIATE PACK: 000
LEVEL PRESERVATION: Military
LEVEL PACKING: A
All Wood Packaging Material (WPM) must be ISPM-15
Compliant
ESTIMATED MAXIMUM UNIT PACKAGE WEIGHT (POUNDS) AND
SIZE (INCHES):
WT [17.3] LB
LN [15]IN
WD [15] IN
DP [15.3] IN
MIL-STD-2073-1 Codes, Appendix J:
JI/A/MP[45]; JII/CD[1]; JIII/PM[ZZ]; JIV/WM[GB];
JV/CD [NA];JVI/CT[B];JVII/UC [ZZ];JVII/IC
13 48
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
[00];JIX/A/PK [F];JX/SM [17];JVIIIA/OPI[M]
Supplemental Information: ZZ=UC-8110-00-254-5715, MS27684-7,PM -12 ON BEARING.
(End of narrative D001)
Inspection and Acceptance _________________________
INSPECTION: Origin ACCEPTANCE: Origin
Deliveries or Performance _________________________
FOB POINT: Origin
SHIP TO:
(Y00000) SHIPPING INSTRUCTIONS FOR CONSIGNEE
(SHIP-TO) WILL BE FURNISHED PRIOR
TO THE SCHEDULED DELIVERY DATE FOR
ITEMS REQUIRED UNDER THIS
REQUISITION.
FIFTH ORDERING PERIOD DELIVERIES SHALL COMMENCE 292
DAYS AFTER THE DATE OF THE DELIVERY ORDER AWARD AT A
RATE OF 15 UNITS PER MONTH UNTIL SHIPPED COMPLETE.
SHIPPING INSTRUCTIONS SHALL BE PROVIDED 30 DAYS PRIOR
TO FIRST SCHEDULED DELIVERY.
(End of narrative F001)
14 48
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
SECTION D - PACKAGING AND MARKING
RP001: DLA PACKAGING REQUIREMENTS FOR PROCUREMENT
(1) Additional Packaging and Marking Requirements:
(a) Prohibited cushioning and wrapping materials: Use of asbestos, excelsior, newspaper, shredded paper (all types, including wax paper and computer paper), and similar hygroscopic or non-neutral materials and all types of loose fill materials, including polystyrene, is prohibited for application such as cushioning, fill, stuffing, and dunnage. In addition, the use of yellow wrapping or packaging material is prohibited except where used for the containment of radioactive material.
(b) MIL-STD-129 establishes requirements for contractors that ship packaged materiel to the Government to provide both linear bar codes and two-dimensional (2D) symbols on shipping labels. Shipping labels with 2D symbols are referred to as Military Shipping Labels (MSL) and are required on all CONUS and OCONUS shipments with the following exceptions:
(1) Subsistence items procured through full-line food distributors (prime contractors), market ready type items shipped within the
Continental United States (CONUS) to customers within CONUS;
(2) Any item for which ownership remains with the contractor until the item is placed in designated locations at the customer location prior to issuance to the customer. Government control begins upon placement of the item by the contractor into the designated location or issuance from the designated location by contractor personnel (i.e., the contractor is required to stock bins at the customer location and/or issue parts from a contractor controlled parts room).
(3) Bulk petroleum, oil and lubricant products delivered by pipeline; or tank car, tanker and tank trailer for which the container has a capacity greater than 450 L (119 gallons) as a receptacle for a liquid; a maximum net mass greater than 400 kg (882 pounds) and a capacity greater than 450 L (119 gallons) as a receptacle for a solid; or a water capacity greater than 454 kg (1000 pounds) as a receptacle for a gas.
(4) Medical items procured through Customer Direct suppliers or prime contractors that do not enter the Defense Transportation System.
(5) Delivery orders when the basic contract has not been modified to require MIL-STD-129.
(c) MIL-STD-129 provides numerous illustrations of what should be bar?coded and the recommended placement of the bar code. Further information is available on the DLA Packaging Web Site at:
http://www.dla.mil/LandandMaritime/Offers/Services/TechnicalSupport/Logistics/Packaging.aspx
(2) Requirements for Treatment of Wood Packaging Material (WPM):
a) Assets packed in or on wood pallets, skids, load boards, pallet collars, wood boxes, reels, dunnage, crates, frames, and cleats must comply with the Heat Treatment (HT) or Heat Treatment/Kiln Dried (HT/KD) (continuous at 56 degrees Centigrade for 30 minutes) standard in DoD Manual 4140.65-M "Compliance for Defense Packaging: Phytosanitary Requirements for Wood Packaging Material (WPM)". WPM must be stamped or branded with the appropriate certification markings as detailed in DOD 4140.65-M and be certified by an accredited American
Lumber Standards Committee (ALSC)?recognized agency. The WPM certification markings must be easily visible, especially in pallet loads, to inspectors.
(3) Palletization shall be in accordance with MD00100452, REVISION C, DATED 09/2016 found at http://www.dla.mil/LandandMaritime/Offers/Services/TechnicalSupport/Logistics/Packaging/Palletization.aspx
*** END OF NARRATIVE D0001 ***
15 48
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
SECTION E - INSPECTION AND ACCEPTANCE
This document incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at these addresses:
http://farsite.hill.af.mil/VFFARA.HTM or http://farsite.hill.af.mil/VFDFARA.HTM or http://farsite.hill.af.mil/VFAFARa.HTM
If the clause requires additional or unique information, then that information is provided immediately after the clause title.
Regulatory Cite Title Date Regulatory Cite Title Date _______________ ______________________________________________________________________ ____________ _______________ ______________________________________________________________________ ____________
E-1 52.246-2 INSPECTION OF SUPPLIES--FIXED-PRICE AUG/1996
E-2 52.246-16 RESPONSIBILITY FOR SUPPLIES APR/1984
E-3 52.246-11 HIGHER-LEVEL CONTRACT QUALITY REQUIREMENT DEC/2014
(a) The contractor shall comply with the higher-level quality standard(s) listed below.
ANSI/ISO/ASQ 9001:2008, AS 9100 OR EQUIVALENT, TAILORING: ALL PARAGRAPHS UNDER 7.3 (DESIGN AND DEVELOPMENT) DO NOT APPLY
(b) The contractor shall include applicable requirements of the higher-level quality standard(s) listed in paragraph (a) of this clause and the requirement to flow down such standards, as applicable, to lower-tier subcontracts in--
(1) Any subcontract for critical and complex items (see 46.203(b) and (c)); or
(2) When the technical requirements of a subcontract require--
(i) Control of such things as design, work operations, in-process control, testing and inspection; or
(ii) Attention to such factors as organization, planning, work instructions, documentation control, and advanced metrology.
(End of clause)
16 48
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
SECTION F - DELIVERIES OR PERFORMANCE
This document incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at these addresses:
http://farsite.hill.af.mil/VFFARA.HTM or http://farsite.hill.af.mil/VFDFARA.HTM or http://farsite.hill.af.mil/VFAFARa.HTM
If the clause requires additional or unique information, then that information is provided immediately after the clause title.
Regulatory Cite Title Date Regulatory Cite Title Date _______________ ______________________________________________________________________ ____________ _______________ ______________________________________________________________________ ____________
F-1 52.211-17 DELIVERY OF EXCESS QUANTITIES SEP/1989
F-2 52.242-15 STOP-WORK ORDER AUG/1989
F-3 52.242-17 GOVERNMENT DELAY OF WORK APR/1984
F-4 52.247-29 F.O.B. ORIGIN FEB/2006
F-5 52.247-30 F.O.B. ORIGIN, CONTRACTOR'S FACILITY FEB/2006
F-6 52.247-34 F.O.B. DESTINATION NOV/1991
F-7 52.247-48 F.O.B. DESTINATION--EVIDENCE OF SHIPMENT FEB/1999
F-8 52.247-58 LOADING, BLOCKING, AND BRACING OF FREIGHT CAR SHIPMENTS APR/1984
F-9 52.247-59 F.O.B. ORIGIN--CARLOAD AND TRUCKLOAD SHIPMENTS APR/1984
F-10 52.247-65 F.O.B. ORIGIN, PREPAID FREIGHT--SMALL PACKAGE SHIPMENTS JAN/1991
F-11 252.211-7006 PASSIVE RADIO FREQUENCY IDENTIFICATION JUN/2016
Insert 0001AA, DLA DISTRIBUTION, SAN JOAQUIN, CA., and W62G2T
0002AA-0005AA TBD in the blanks in paragraph (b)(1)(ii)(B) within the above referenced clause.
F-12 52.211-9 DESIRED AND REQUIRED TIME OF DELIVERY JUN/1997
(a) The Government desires delivery to be made according to the following schedule:
DESIRED DELIVERY SCHEDULE
ITEM NO. QUANTITY WITHIN DAYS
AFTER DATE OF
CONTRACT
0001AA 180 438 DACA
0001AB 180 292 DACA
0001AC 1 280 DACA
0002AA 243(E) 292 DACA
0003AA 243(E) 292 DACA
0004AA 242(E) 292 DACA
0005AA 242(E) 292 DACA
If the offeror is unable to meet the desired delivery schedule, it may, without prejudicing evaluation of its offer, propose a delivery schedule below. However, the offerors proposed delivery schedule must not extend the delivery period beyond the time for delivery in the
Governments required delivery schedule as follows:
REQUIRED DELIVERY SCHEDULE
ITEM NO. QUANTITY WITHIN DAYS
AFTER DATE OF
CONTRACT
0001AA 180 585 DACA
0001AB 180 390 DACA
0001AC 1 280 DACA
0002AA 243(E) 390 DACA
0003AA 243(E) 390 DACA
0004AA 242(E) 390 DACA
0005AA 242(E) 390 DACA
17 48
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
Offers that propose delivery of a quantity under such terms or conditions that delivery will not clearly fall within the applicable required delivery period specified above, will be considered non-responsive and rejected. If the offeror proposes no other delivery schedule, the desired delivery schedule above will apply.
OFFERORS PROPOSED DELIVERY SCHEDULE
ITEM NO. QUANTITY WITHIN DAYS
AFTER DATE OF
CONTRACT
(b) Attention is directed to the Contract Award provision of the solicitation that provides that a written award or acceptance of offer mailed or otherwise furnished to the successful offeror results in a binding contract. The Government will mail or otherwise furnish to the offeror an award or notice of award not later than the day the award is dated. Therefore, the offeror shall compute the time available for performance beginning with the actual date of award, rather than the date the written notice of award is received from the
Contracting Officer through the ordinary mails. However, the Government will evaluate an offer that proposes delivery based on the
Contractors date of receipt of the contract or notice of award by adding (1) five calendar days for delivery of the award through the ordinary mails, or (2) one working day if the solicitation states that the contract or notice of award will be transmitted electronically. (The term working day excludes weekends and U.S. Federal holidays.) If, as so computed, the offered delivery date is later than the required delivery date, the offer will be considered nonresponsive and rejected.
(End of Clause)
RQ009: INSPECTION AND ACCEPTANCE AT ORIGIN
1. The Governments Quality Assurance Representative (QAR) will inspect supplies described by manufacturer's name/code and part number at origin location(s):
a. The QAR may require that objective evidence be furnished establishing the name and address of the plant that manufactures the supplies to ensure that a domestic product is being supplied.
b. Objective evidence of performance must be present for all quality assurance requirements specified in the contract. The QAR may require additional examinations and tests to determine:
i. Completeness of item
ii. Material is new and unused
iii. Absence of rust
iv. Contamination, or deterioration
v. Correct identification/item marking
vi. Correct packaging
vii. Absence of any damage
viii. Compliance with preparation for delivery
2. If the supplier is not the manufacturer of the supplies, objective evidence must be furnished to establish that the supplies were produced by the approved manufacturer.
3. For supplies designated as former Government surplus (whether described by manufacturers name/code and part number, or by Military or
Federal specification or drawing), the original package markings of each item shall be verified to previous Government contract number and part number. Any deviation shall be cause for rejection of the item. The Procuring Activity may add additional inspection requirements based on the evaluation of the surplus offer. Such additional requirements will be identified before the award.
*** END OF NARRATIVE F0001 ***
18 48
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
SECTION G - CONTRACT ADMINISTRATION DATA
Regulatory Cite Title Date Regulatory Cite Title Date _______________ ______________________________________________________________________ ____________ _______________ ______________________________________________________________________ ____________
G-1 252.232-7006 WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS MAY/2013
(a) Definitions. As used in this clause--
"Department of Defense Activity Address Code (DoDAAC)" is a six position code that uniquely identifies a unit, activity, or organization.
"Document type" means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).
"Local processing office (LPO)" is the office responsible for payment certification when payment certification is done external to the entitlement system.
(b) Electronic invoicing. The WAWF system is the method to electronically process vendor payment requests and receiving reports, as authorized by DFARS 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.
(c) WAWF access. To access WAWF, the Contractor shall--
(1) Have a designated electronic business point of contact in the System for Award Management at https://www.acquisition.gov; and
(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this
Web site.
(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web-Based Training Course and use the Practice
Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the "Web Based Training" link on the
WAWF home page at https://wawf.eb.mil/.
(e) WAWF methods of document submission. Document submissions may be via Web entry, Electronic Data Interchange, or File Transfer
Protocol.
(f) WAWF payment instructions. The Contractor must use the following information when submitting payment requests and receiving reports in WAWF for this contract/order:
(1) Document type. The Contractor shall use the following document type(s).
MATERIAL RECEIPT AND INVOICE (COMBO REPORT)
(2) Inspection/acceptance location. The Contractor shall select the following inspection/acceptance location(s) in WAWF, as specified by the contracting officer.
INSPECTION: SOURCE
ACCEPTANCE: SOURCE
(3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in
WAWF when creating payment requests and receiving reports in the system.
Routing Data Table*
Field Name in WAWF Data to be entered in WAWF
Pay Official DoDAAC TBD
Issue By DoDAAC SPRRA1
Admin DoDAAC TBD
Inspect By DoDAAC TBD
Ship To Code W62G2T
Ship From Code TBD
Mark For Code TBD
Service Approver (DoDAAC) N/A
Service Acceptor (DoDAAC) N/A
Accept at Other DoDAAC N/A
LPO DoDAAC N/A
DCAA Auditor DoDAAC N/A
Other DoDAAC(s) N/A
19 48
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
(4) Payment request and supporting documentation. The Contractor shall ensure a payment request includes appropriate contract line item and subline item descriptions of the work performed or supplies delivered, unit price/cost per unit, fee (if applicable), and all relevant back-up documentation, as defined in DFARS Appendix F, (e.g. timesheets) in support of each payment request.
(5) WAWF email notifications. The Contractor shall enter the email address identified below in the "Send Additional Email
Notifications" field of WAWF once a document is submitted in the system.
TBD
(g) WAWF point of contact. (1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity's WAWF point of contact.
TBD
(2) For technical WAWF help, contact the WAWF helpdesk at 866-
618-5988.
(End of clause)
20 48
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
SECTION H - SPECIAL CONTRACT REQUIREMENTS
WOOD PACKING MATERIALS REQUIREMENTS
A. Wood packaging material (WPM) means wood pallets, skids, load boards, pallet collars, wooden boxes, reels, dunnage, crates, frame and cleats. The definition excludes materials that have undergone a manufacturing process, such as corrugated fiberboard, plywood, particleboard, veneer, and oriented strand board (OSD).
B. All Wood Packaging Material (WPM)) acquired by DOD must meet requirements of International Standards for
Phytosanitary Measures (ISPM) 15, "Guidelines for Regulating Wood Packaging Materials International Trade." DOD shipments inside and outside of the United States must meet ISPM 15 whenever WPM is used to ship DOD cargo.
(1) All WPM shall comply with the official quality control program for heat treatment (HT) or kiln dried heat treatment (KD HT) in accordance with American Lumber Standard Committee, incorporated (ALSC) Wood Packaging Material Program and
WPM Enforcement http://www.alsc.org/)
(2) All WPM shall include certification/quality markings in accordance with the ALSC standard. Marking shall be placed in an unobstructed area that will be readily visible to inspectors. Pallet markings shall be applied to the stringer or block on diagonally opposite sides of the pallet and be contrasting and clearly visible. All containers shall be marked on a side other than the top or bottom, contrasting and clearly visible. All dunnage used in configuring and/or securing the load shall also comply with ISPM 15 and be marked with an ALSC approved DUNNAGE stamp.
C. Failure to comply with the requirements of this restriction may result in refusal, destruction, or treatment at entry.
The Agency reserves the right to recoup from the Contractor any remediation costs incurred by the Government.
D. Replacement Preservative for Pentachlorophenol
If packaging requirements of this contract specify the use of wood products and a preservative is required, Pentachlorophenol, commonly referred to as "Penta" or "PCP" is prohibited. Replacement preservatives are 2 percent copper naphthenate, 3 percent zinc naphthenate or 1.8 percent copper 8 quinolinolate.
(1) Heat Treatment: Boxes/pallets and any wood used as inner packaging made of non-manufactured wood shall be heat-treated. All non-manufactured wood used in packaging shall be heat treated to a core temperature of 56 degrees Celsius for a minimum of 30 minutes. The box/pallet manufacturer and the manufacturer of wood used as inner packaging shall be affiliated with an inspection agency accredited by the board of review of the American Lumber Standard Committee. The box/pallet manufacturer and the manufacturer of wood used as inner packaging shall ensure traceability to the original source of heat treatment.
(2) Marking: Each box/pallet shall be marked to show the conformance to the International Plant Protection
Convention Standard. The quality mark shall be placed on both ends of the outter packaging, between the end cleats or end battens: on two sides of the pallet. Foreign manufacturers shall have the heat treatment of non-manufactured wood proces verified in accordance with their National Plant Protection Organization's compliance program. In addition, wood used as dunnage for blocking and bracing shall be ordered with ALSC certified marking for dunnage or the markings may be applied locally at two foot intervals.
SOURCES ELIGIBLE FOR AWARD CONSIDERATION
(a) Competition under this solicitation is restricted to the following sources:
(1) Approved Sources listed in Section B -- sources that have been approved by the prime manufacturer or the
Government for supply of item(s) listed in this solicitation, to assure the requisite safe, dependable, effective operation and support of military equipment;
(2) Sources that have been approved prior to award -- other than approved sources listed in Section B;
(3) Non-manufacturers--offers from non-manufacturers (distributors) will only be considered for award if the required item(s) is new material and has been or will be obtained from a source of supply which has been approved prior to award. The source and part number of the item the offeror intends to supply must be stated in the offer.
(4) Surplus Dealers--offerors of Government surplus in accordance with Section I clause entitled "Material
Requirements, FAR 52.211-5, will only be considered for award if the former Government surplus or residual inventory resulting from terminated contracts was originally manufactured by an approved source of supply.
(5)
(b) Only offers submitted by the above sources will be considered for award under this solicitation.
(c) Offerors (prospective manufacturers or non-manufacturers [distributors]) who wish to become an approved source of
21 48
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
supply for an item listed in this solicitation should proceed per the instructions set forth in paragraph (d) below. It is noted that offeror requests for source approval in conjunction with this procurement will not be a cause for delay in this solicitation action.
However, if it is determined that additional sources will clearly benefit the Government and that any delay incident to their approval would not impact readiness, a reasonable delay may be entertained. Whether or not such delay will occur will be solely at the discretion of the Government, and the time set for opening of the Invitation for Bids or the closing date of the Request for
Proposals may or may not be extended. An extension will be witnessed by issuance of an amendment to this solicitation.
(d) Offerors (prospective manufacturers or non-manufacturers [distributors]) seeking to obtain source approval, must submit a Source Approval Request (SAR) package, for review and approval, to the Engineering Directorate (ED), Quality Engineering
Division. Source approval must be obtained prior to being considered for contract award. Approvals are made on an individual part number basis for a specific manufacturing location (CAGE). Firms are encouraged to seek source approval in order to compete for future solicitations by following the SAR submission guidance provided on the website:
http://amcomdmz.redstone.army.mil/casl_cmo/casldba.casl_cmo_samsar
Questions concerning SAR submissions can be directed to the ED SAR Team at mailto:EDSAR@amrdec.army.mil or call the SAR Team at 256-
313-8978, 256-313-0341, or 256-313-8994.
(e) The Aviation and Missile Lifecycle Management Command (AMCOM) may require additional data, testing, or plant visits before it is able to completely evaluate a SAR. This may require the offeror (at no expense to the Government) to supply parts for testing, engine run up, or flight tests. In that event, the requestor will be so advised. AMCOM reserves the right to approve a contractor for award prior to completion of physical testing of the offered item. In such cases, the contractor shall perform any outstanding tests and provide all required documentation at no cost to the Government prior to entering upon full production. Lack of successful performance within the specified timeframe shall be grounds for a no cost termination.
(f) When a SAR is received, it will be processed for evaluation. If the evaluation and approval (including preparation or update of the requisite technical data package (TDP)) occurs before award, the requestor will be considered for award if a proposal was submitted per(d) above. If the evaluation/TDP preparation has not been completed prior to award, AMCOM will continue the process until complete. If the requestors SAR becomes approved, the requestor will be eligible for consideration on all future solicitations for the item.
(g) All approval or disapproval notices shall be officially provided to the contractor by the appropriate technical official.
(h) Non-manufacturers (distributors) seeking to supply an item from a non-approved source must first ensure that the source becomes approved in accordance with (d) above prior to contract award.
REVISIONS TO DRAWINGS/PART NUMBERS
(a) Sources in receipt of this solicitation are requested, at no cost to the Government, to immediately notify the
Contracting Officer if they are aware of any change(s)/revision(s) to the drawing(s) or part number(s) in this solicitation which have been approved by the Government for implementation. Notification of part number changes shall be supported by data which indicates the type of change, approving authority as required by ANSI EIA 649 MIL-STD-973 and date and method of submittal of provisioning documentation and drawings.
If complete data package has not been previously provided, the contractor shall, at no direct cost to the Government, immediately submit applicable drawings, along with a copy of the approval change authority, to the Contracting Officer, at the office symbol and mailing address listed in the "ISSUED BY" block on page one (1) of this document. The minimum acceptable data includes the next higher assembly and the item of Supply Detail Drawings which will allow provisioning, National Stock Number assignment and updating of AMCOM's data records.
(b) The contractor hereby verifies previous contractual submission of technical data: Contract No.: _
Contractor: _
Explanation of Data Rights: _
(c) The Government is not by this request soliciting, nor is the Government liable for cost incurred by the offeror in preparing or developing modifications, deviations, waivers, or other changes to drawings or part number(s). Furthermore, this request does not authorize changes to the drawing(s) or part number(s) for this acquisition, another contract, or for any other purpose.
Offerors performing any contract awarded as a result of this solicitation must comply with the drawing(s) and specifications as set forth herein, unless this solicitation is amended or any resulting contract is modified by the Contracting Officer.
(d) All proposed part number changes shall be submitted pursuant to the requirements of the clause entitled, "Engineering Change Proposal (ECP), Value Engineering Change Proposal (VECP), Request for Deviation (RFD), and Request for Waiver
(RFW) (USAAMCOM).
22 48
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
52.243-4000: ENG CHG PROPOSAL, VALUE ENG CHG PROPOSAL, REQUEST FOR DEVIATION
1. Contractor initiated Engineering Change Proposals (ECPs), Value Engineering Change Proposals (VECPs), Request for Deviations (RFDs), and Request for Variance (RFVs), collectively referred to as "proposals", shall be prepared, submitted and distributed in accordance with paragraphs 2, 3 and 4 below except as specified in paragraph 5 below.
2. Format.
a. Class 1 ECPs require the "Long Form Procedure" for documenting the change and describing the effects of the change on the suitability and supportability of the Configuration Item (CI). Class I ECPs should be limited to those that are necessary or offer significant benefit to the Government.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .