About this file

This modification of solicitation SPRHA4-23-R-0407-0001 from the Defense Logistics Agency Aviation seeks offers for a fixture assembly identified as item TE. Offerors must provide supply chain traceability documentation and certify their cost accounting practices and pricing comply with numerous FAR and DFAR clauses added by this amendment. Responses are due by June 15, 2023.

The solicitation requires certification of traceability documentation demonstrating the item conforms to technical requirements and originates from an approved manufacturer. Offerors must disclose cost accounting practices and submit pricing data in accordance with modified versions of FAR clauses 52.215-10, 52.215-12, and others addressing pension adjustments, post-retirement benefits, and limitations on pass-through charges. Additional DFARS clauses require disclosure of cost estimating systems, foreign military sales offsets, and restrictions on acquiring personal protective equipment from non-allied nations. Compliant proposals will be evaluated using the Supplier Performance Risk System and must include a proposal adequacy checklist.

View the file

Other files for this federal contract opportunity

Other files attached to Fixture Assembly, TE, newest first.
File Type Posted
SPRHA423R0407.pdf PDF
CDRL_CPP_EDA.PDF PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

J

2. AMENDMENT/MODIFICATION NO.

SPRHA4-23-R-0407-0001

3. EFFECTIVE DATE

30 MAY 2023

4. REQUISITION/PURCHASE REQ. NO.

FD20202300407

5. PROJECT NO (If applicable)

4920-01-537-5649 WF

6. ISSUED BY CODE

DLA AVIATION - OGDEN, DLR PROCUREMENT OPS/AUB

6051 GUM LANE BLDG 1225

HILL AIR FORCE BASE UT 84056-5820

BUYER: Kitty Lam/DLA kitty.lam@us.af.mil Phone: (385) 519- 8181 Fax: (000) 000-0000 No Collect Calls

7. ADMINISTERED BY (If other than item 6) CODESPRHA4

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

CODE

X

9A. AMENDMENT OF SOLICITATION NO.

SPRHA423R0407

9B. DATED (SEE ITEM 11)

1-MAR-2023

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended, is not extended. Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods. ( a ) By completing Items 8 and 15, and returning copies of the amendment; ( b ) By acknowledging receipt of this amendment on each copy of the offer submitted; or ( c ) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified. 15-JUN-2023 4:00 PM

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

ROUTINE

See page 2.

15A. NAME AND TITLE OF SIGNER (Type or print)

15B. CONTRACTOR/OFFEROR

BY ________________________________________________________

(Signature of person authorized to sign)

15C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16B. UNITED STATES OF AMERICA

BY ____________________________________________________

(Signature of Contracting Officer)

16C. DATE SIGNED

FACILITY CODE

NSN 7540-01-152-8070

PREVIOUS EDITION UNUSABLE

30-105 STANDARD FORM 30 (REV. 10-83)

PRESCRIBED BY GSA

FAR (48 CFR) 53.243

X

X X

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

SPRHA4-23-R-0407-0001

Continuation of block 14. DESCRIPTION OF AMENDMENT/MODIFICATION

The purpose of the amendment is to add the following clauses:

FAR 52.215-10, 52.215-12, 52.215-15, 52.215-18, 52.215-19, 52.215-23, 52.222-3, 52.222-4, 52.225-8, 52.230-2, 52.230-6, 52.230-1, 52.215-16, and 52.215-22.

DFAR 252.215-7002, 252.215-7014, 252.225-7061, 252.246-7007, 252.246-7008, 252.204-7024, 252.215-7009, 252.215-7010, 252.215-7010 Alt I, 252.215-7011, and 252.215-7012.

PART I - THE SCHEDULE

SECTION C

DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C03 Contractor Retention of Supply Chain Traceability Documentation (JUN 2020)

(1) By submitting a quotation or offer, the contractor is confirming it currently has, or will obtain before delivery, and shall retain supply chain traceability documentation, as described in paragraph

(2) of this procurement note, demonstrating the item conforms to the technical requirements, and, for part numbered items, is from an approved manufacturer.

(2) Supply Chain Traceability Documentation

(i) Supply chain traceability documentation shall include: basic item description; part number; drawing or specification; national stock number; manufacturing source; manufacturing source’s Commercial and Government Entity (CAGE) code; and clear identification of the name and location of all supply chain intermediaries between the manufacturer to the contractor to Government acceptance.

(ii) Supply chain traceability documentation shall also include, when available, the manufacturer's batch identification for the item(s), such as date codes, lot codes, or serial numbers.

For part numbered items, contractors can find examples of acceptable supply chain traceability documentation at the Counterfeit Detection and Avoidance Program (CDAP) website (http://www.dla.mil/LandandMaritime/Business/Selling/Counterfeit-Detection- AvoidanceProgram/).

(iii) In addition, the contractor will obtain, retain, and provide to the contracting officer written documentation of all inspections and tests necessary to substantiate that the supplies furnished under this contract conform to contract requirements, including any applicable technical requirements for specified manufacturers’ parts. Such records shall include, without limitation, test reports, test data, material certification, and manufacturing process sheets, in addition to any other information identified in the technical specifications applicable to the item.

(3) The contractor shall make supply chain traceability documentation available to the contracting officer within three business days upon the contracting officer’s request. The contracting officer determines the acceptability and sufficiency of documentation. The contractor shall retain supply chain traceability documentation for ten years after final payment under this contract for audit and other valid government purposes. If the contractor fails to retain or provide the documentation, or the contracting officer finds the documentation to be unacceptable, the contracting officer may take corrective action, including, but not limited to, cancellation of undelivered orders or rejection of delivered supplies.

PART II - CONTRACT CLAUSES

SECTION I

CONTRACT CLAUSES

52.215-10 PRICE REDUCTION FOR DEFECTIVE CERTIFIED COST OR PRICING DATA

(AUG 2011)

(IAW FAR 15.408(b))

52.215-12 SUBCONTRACTOR CERTIFIED COST OR PRICING DATA (JUN 2020)

(IAW FAR 15.408(d)(1))

52.215-15 PENSION ADJUSTMENTS AND ASSET REVERSIONS (OCT 2010)

(IAW FAR 15.408(g))

52.215-18 REVERSION OR ADJUSTMENT OF PLANS FOR POSTRETIREMENT BENEFITS (PRB)

OTHER THAN PENSIONS (JUL 2005)

(IAW FAR 15.408(j))

52.215-19 NOTIFICATION OF OWNERSHIP CHANGES (OCT 1997)

(IAW FAR 15.408(k))

52.215-23 LIMITATIONS ON PASS-THROUGH CHARGES (JUN 2020)

(IAW FAR 15.408(n)(2))

252.215-7002 COST ESTIMATING SYSTEM REQUIREMENTS (DEC 2012)

(IAW DFARS 215.408(1))

252.215-7014 EXCEPTION FROM CERTIFIED COST OR PRICING DATA REQUIREMENTS FOR

FOREIGN MILITARY SALES INDIRECT OFFSETS (DEC 2022)

(IAW DFARS 215.408 (8))

52.222-3 CONVICT LABOR (JUN 2003)

(IAW FAR 22.202)

52.222-4 CONTRACT WORK HOURS AND SAFETY STANDARDS--OVERTIME

COMPENSATION (MAY 2018)

(IAW FAR 22.305)

52.225-8 DUTY-FREE ENTRY (OCT 2010)

(IAW FAR 25.1101(e))

252.225-7061 RESTRICTION ON THE ACQUISITION OF PERSONAL PROTECTIVE EQUIPMENT

AND CERTAIN OTHER ITEMS FROM NON-ALLIED FOREIGN NATIONS (JAN 2023)

(IAW DFARS 225.7023-4)

52.230-2 COST ACCOUNTING STANDARDS (JUN 2020)

(IAW FAR 30.201-4(a)(1))

52.230-6 ADMINISTRATION OF COST ACCOUNTING STANDARDS (JUN 2010)

(IAW FAR 30.201-4(d)(1))

252.246-7007 CONTRACTOR COUNTERFEIT ELECTRONIC PART DETECTION AND AVOIDANCE

SYSTEM (JAN 2023)

(IAW DFARS 246.870-3(a))

252.246-7008 SOURCES OF ELECTRONIC PARTS (JAN 2023)

(IAW DFARS 246-870-3(b))

PART IV - REPRESENTATIONS AND INSTRUCTIONS

SECTION K

REPRESENTATIONS, CERTIFICATIONS, AND OTHER STATEMENTS

OF OFFERORS OR RESPONDENTS

52.230-1 COST ACCOUNTING STANDARDS NOTICES AND CERTIFICATION (JUN 2020)

(IAW FAR 30.201-3(a)) Note: This notice does not apply to small businesses or foreign governments. This notice is in three parts, identified by Roman numerals I through III.

Offerors shall examine each part and provide the requested information in order to determine Cost Accounting Standards (CAS) requirements applicable to any resultant contract.

If the offeror is an educational institution, Part II does not apply unless the contemplated contract will be subject to full or modified CAS coverage pursuant to 48 CFR 9903.201-2(c)(5) or 9903.201-2(c)(6), respectively.

I. DISCLOSURE STATEMENT--COST ACCOUNTING PRACTICES AND CERTIFICATION

(a) Any contract in excess of the lower CAS threshold specified in Federal Acquisition Regulation (FAR) 30.201-4(b) resulting from this solicitation will be subject to the requirements of the Cost Accounting Standards Board (48 CFR chapter 99), except for those contracts which are exempt as specified in 48 CFR 9903.201-1.

(b) Any offeror submitting a proposal which, if accepted, will result in a contract subject to the requirements of 48 CFR Chapter 99 must, as a condition of contracting, submit a Disclosure Statement as required by 48 CFR 9903.202. When required, the Disclosure Statement must be submitted as a part of the offeror's proposal under this solicitation unless the offeror has already submitted a Disclosure Statement disclosing the practices used in connection with the pricing of this proposal. If an applicable Disclosure Statement has already been submitted, the offeror may satisfy the requirement for submission by providing the information requested in paragraph (c) of Part I of this provision.

CAUTION: In the absence of specific regulations or agreement, a practice disclosed in a Disclosure Statement shall not, by virtue of such disclosure, be deemed to be a proper, approved, or agreed-to practice for pricing proposals or accumulating and reporting contract performance cost data.

(c) Check the appropriate box below:

[ ] (1) Certificate of Concurrent Submission of Disclosure Statement. The offeror hereby certifies that, as a part of the offer, copies of the Disclosure Statement have been submitted as follows:

(i) original and one copy to the cognizant Administrative Contracting Officer (ACO) or cognizant Federal agency official authorized to act in that capacity (Federal official), as applicable; and

(ii) one copy to the cognizant Federal auditor.

(Disclosure must be on Form No. CASB DS–1 or CASB DS–2, as applicable. Forms may be obtained from the cognizant ACO or Federal official.)

Date of Disclosure Statement: _______________________________ Name and Address of Cognizant ACO or Federal Official Where Filed:

The offeror further certifies that the practices used in estimating costs in pricing this proposal are consistent with the cost accounting practices disclosed in the Disclosure Statement.

[ ] (2) Certificate of Previously Submitted Disclosure Statement. The offeror hereby certifies that the required Disclosure Statement was filed as follows:

Date of Disclosure Statement: _______________________________ Name and Address of Cognizant ACO or Federal Official Where Filed:

The offeror further certifies that the practices used in estimating costs in pricing this proposal are consistent with the accounting practices disclosed in the applicable Disclosure Statement.

[ ] (3) Certificate of Monetary Exemption. The offeror hereby certifies that the offeror, together with all divisions, subsidiaries, and affiliates under common control, did not receive net awards of negotiated prime contracts and subcontracts subject to CAS totaling $50 million or more in the cost accounting period immediately preceding the period in which this proposal was submitted. The offeror further certifies that if such status changes before an award resulting from this proposal, the offeror will advise the Contracting Officer immediately.

[ ] (4) Certificate of Interim Exemption. The offeror hereby certifies that

(i) the offeror first exceeded the monetary exemption for disclosure, as defined in (3) of this subsection, in the cost accounting period immediately preceding the period in which this offer was submitted and

(ii) in accordance with 48 CFR 9903.202-1, the offeror is not yet required to submit a Disclosure Statement. The offeror further certifies that if an award resulting from this proposal has not been made within 90 days after the end of that period, the offeror will immediately submit a revised certificate to the Contracting Officer, in the form specified under subparagraph (c)(1) or (c)(2) of Part I of this provision, as appropriate, to verify submission of a completed Disclosure Statement.

CAUTION: Offerors currently required to disclose because they were awarded a CAS-covered prime contract or subcontract of $50 million or more in the current cost accounting period may not claim this exemption (4).

Further, the exemption applies only in connection with proposals submitted before expiration of the 90-day period following the cost accounting period in which the monetary exemption was exceeded.

II. COST ACCOUNTING STANDARDS--ELIGIBILITY FOR MODIFIED CONTRACT COVERAGE

If the offeror is eligible to use the modified provisions of 48 CFR 9903.201-2(b) and elects to do so, the offeror shall indicate by checking the box below. Checking the box below shall mean that the resultant contract is subject to the Disclosure and Consistency of Cost Accounting Practices clause in lieu of the Cost Accounting Standards clause.

[ ] The offeror hereby claims an exemption from the Cost Accounting Standards clause under the provisions of 48 CFR 9903.201-2(b) and certifies that the offeror is eligible for use of the Disclosure and Consistency of Cost Accounting Practices clause because during the cost accounting period immediately preceding the period in which this proposal was submitted, the offeror received less than $50 million in awards of CAS-covered prime contracts and subcontracts. The offeror further certifies that if such status changes before an award resulting from this proposal, the offeror will advise the Contracting Officer immediately.

CAUTION: An offeror may not claim the above eligibility for modified contract coverage if this proposal is expected to result in the award of a CAS-covered contract of $50 million or more or if, during its current cost accounting period, the offeror has been awarded a single CAS-covered prime contract or subcontract of $50 million or more.

III. ADDITIONAL COST ACCOUNTING STANDARDS APPLICABLE TO EXISTING CONTRACTS

The offeror shall indicate below whether award of the contemplated contract would, in accordance with subparagraph (a)(3) of the Cost Accounting Standards clause, require a change in established cost accounting practices affecting existing contracts and subcontracts.

[ ] YES [ ] NO

PART IV - REPRESENTATIONS AND INSTRUCTIONS

SECTION L

INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS OR RESPONDENTS

252.204-7024 NOTICE ON THE USE OF THE SUPPLIER PERFORMANCE RISK SYSTEM

(MAR 2023)

(IAW DFARS 204.7604)

(a) Definitions. As used in this provision—

Item risk means the probability that a product, based on intended use, will introduce performance risk resulting in safety issues, mission degradation, or monetary loss.

Price risk means a measure of whether a proposed price for a product or service is consistent with historical prices paid for that item or service.

Supplier risk means the probability that an award may subject the procurement to the risk of unsuccessful performance or to supply chain risk (see Defense Federal Acquisition Regulation Supplement 239.7301).

(b) The Supplier Performance Risk System (SPRS), available at https://piee.eb.mil/, will be used in the evaluation of the Quoter or Offeror’s performance. SPRS retrieves item, price, quality, delivery, and contractor information on contracts from Government reporting systems in order to develop risk assessments.

(c) The Contracting Officer will consider SPRS risk assessments during the evaluation of quotations or offers received in response to this solicitation as follows:

(1) Item risk will be considered to determine whether the procurement represents a high performance risk to the Government.

(2) Price risk will be considered in determining if a proposed price is consistent with historical prices paid for a product or a service or otherwise creates a risk to the Government.

(3) Supplier risk, including but not limited to quality and delivery, will be considered to assess the risk of unsuccessful performance and supply chain risk.

(d) SPRS risk assessments are generated daily. Quoters or Offerors are able to access their risk assessments by following the access instructions in the SPRS user’s guide available at https://www.sprs.csd.disa.mil/reference.htm.

Quoters and Offerors are granted access to SPRS for their own risk assessment classifications only. SPRS reporting procedures and risk assessment methodology are detailed in the SPRS user’s guide. The method to challenge a rating generated by SPRS is also provided in the user’s guide. SPRS evaluation criteria are available at https://www.sprs.csd.disa.mil/pdf/SPRS_DataEvaluationCriteria.pdf.

(e) The Contracting Officer may consider any other available and relevant information when evaluating a quotation or an offer.

52.215-16 FACILITIES CAPITAL COST OF MONEY (JUN 2003)

(IAW FAR 15.408(h))

52.215-22 LIMITATIONS ON PASS-THROUGH CHARGES--IDENTIFICATION OF SUBCONTRACT

EFFORT (OCT 2009)

(IAW FAR 15.408(n)(1))

252.215-7009 PROPOSAL ADEQUACY CHECKLIST (MAR 2023)

(IAW DFARS 215.408(4))

The offeror shall complete the following checklist, providing location of requested information, or an explanation of why the requested information is not provided. In preparation of the offeror's checklist, offerors may elect to have their prospective subcontractors use the same or similar checklist as appropriate.

PROPOSAL ADEQUACY CHECKLIST

REFERENCES SUBMISSION ITEM PROPOSAL

PAGE No If not provided EXPLAIN (may use continuation pages

GENERAL INSTRUCTIONS

1. FAR 15.408,

Table 15-2, Section I Paragraph A

Is there a properly completed first page of the proposal per FAR 15.408 Table 15-2 I.A or as specified in the solicitation?

2. FAR 15.408,

Table 15-2, Section I Paragraph A(7)

Does the proposal identify the need for Government-furnished material/tooling/test equipment? Include the accountable contract number and contracting officer contact information if known.

3. FAR 15.408,

Table 15-2, Section I Paragraph A(8)

Does the proposal identify and explain notifications of noncompliance with Cost Accounting Standards Board or Cost Accounting Standards (CAS); any proposal inconsistencies with your disclosed practices or applicable CAS; and inconsistencies with your established estimating and accounting principles and procedures?

4. FAR 15.408,

Table 15-2, Section I, Paragraph C(1)

Does the proposal disclose any other known activity that could materially impact the costs? This may include, but is not limited to, such factors as--

(1) Vendor quotations;

FAR 2.101, “Cost or pricing data”

(2) Nonrecurring costs;

(3) Information on changes in production methods and in production or purchasing volume;

(4) Data supporting projections of business prospects and objectives and related operations costs;

(5) Unit-cost trends such as those associated with labor efficiency;

(6) Make-or-buy decisions;

(7) Estimated resources to attain business goals; and

(8) Information on management decisions that could have a significant bearing on costs.

5. FAR 15.408,

Table 15-2, Section I Paragraph B

Is an Index of all certified cost or pricing data and information accompanying or identified in the proposal provided and appropriately referenced?

6. FAR 15.403-1(b) Are there any exceptions to submission of certified cost or pricing data pursuant to FAR 15.403-1(b)? If so, is supporting documentation included in the proposal?

(Note questions 18-20.)

7. FAR 15.408,

Table 15-2, Section I Paragraph C(2)(i)

Does the proposal disclose the judgmental factors applied and the mathematical or other methods used in the estimate, including those used in projecting from known data?

8. FAR 15.408,

Table 15-2, Section I Paragraph C(2)(ii)

Does the proposal disclose the nature and amount of any contingencies included in the proposed price?

9. FAR 15.408,

Table 15-2, Section II, Paragraph A or B

Does the proposal explain the basis of all cost estimating relationships (labor hours or material) proposed on other than a discrete basis?

10. FAR 15.408,

Table 15-2, Section I Paragraphs D and E

Is there a summary of total cost by element of cost and are the elements of cost cross-referenced to the supporting cost or pricing data? (Breakdowns for each cost element must be consistent with your cost accounting system, including breakdown by year.)

11. FAR 15.408,

Table 15-2, Section I Paragraphs D and E

If more than one Contract Line Item Number (CLIN) or sub Contract Line Item Number (sub-CLIN) is proposed as required by the RFP, are there summary total amounts covering all line items for each element of cost and is it cross-referenced to the supporting cost or pricing data?

12. FAR 15.408,

Table 15-2, Section I Paragraph F

Does the proposal identify any incurred costs for work performed before the submission of the proposal?

13. FAR 15.408,

Table 15-2, Section I Paragraph G

Is there a Government forward pricing rate agreement (FPRA)? If so, the offeror shall identify the official submittal of such rate and factor data. If not, does the proposal include all rates and factors by year that are utilized in the development of the proposal and the basis for those rates and factors?

COST ELEMENTS

MATERIALS AND SERVICES

14. FAR 15.408,

Table 15-2, Section II Paragraph A

Does the proposal include a consolidated summary of individual material and services, frequently referred to as a Consolidated Bill of Material (CBOM), to include the basis for pricing? The offeror's consolidated summary shall include raw materials, parts, components, assemblies, subcontracts and services to be produced or performed by others, identifying as a minimum the item, source, quantity, and price.

SUBCONTRACTS (Purchased materials or services)

15. DFARS

215.404-3 Has the offeror identified in the proposal those subcontractor proposals, for which the contracting officer has initiated or may need to request field pricing analysis?

16. FAR 15.404-3(c)

FAR 52.244-2

Per the thresholds of FAR 15.404-3(c), Subcontract Pricing Considerations, does the proposal include a copy of the applicable subcontractor's certified cost or pricing data?

17. FAR 15.408,

Table 15-2, Note 1; Section II Paragraph A

Is there a price/cost analysis establishing the reasonableness of each of the proposed subcontracts included with the proposal?

If the offeror's price/cost analyses are not provided with the proposal, does the proposal include a matrix identifying dates for receipt of subcontractor proposal, completion of fact finding for purposes of price/cost analysis, and submission of the price/cost analysis?

EXCEPTIONS TO CERTIFIED COST OR PRICING DATA

18. FAR 52.215-20

FAR 2.101,

“commercial product or commercial services”

Has the offeror submitted an exception to the submission of certified cost or pricing data for commercial products or commercial services proposed either at the prime or subcontractor level, in accordance with provision 52.215–20?

a. Has the offeror specifically identified the type of commercial product or commercial service claim (FAR

2.101 ‘‘commercial product’’ or ‘‘commercial service’’ definition), and the basis on which the commercial product or commercial service meets the definition?

b. For modified commercial products (FAR 2.101 ‘‘commercial product’’ definition); did the offeror classify the modification(s) as either—

i. A modification of a type customarily available in the commercial marketplace (paragraph (3)(i)); or

ii. A minor modification (paragraph (3)(ii)) of a type not customarily available in the commercial marketplace made to meet Federal Government requirements not exceeding the thresholds in FAR 15.403–1(c)(3)(iii)(B)?

c. For proposed commercial products ‘‘of a type’’, or ‘‘evolved’’ or modified (FAR 2.101 ‘‘commercial product’’ definition), did the contractor provide a technical description of the differences between the proposed item and the comparison item(s)?

19. [Reserved]

20. FAR 15.408,

Table 15-2, Section II Paragraph A(1)

Does the proposal support the degree of competition and the basis for establishing the source and reasonableness of price for each subcontract or purchase order priced on a competitive basis exceeding the threshold for certified cost or pricing data?

INTERORGANIZATIONAL TRANSFERS

21. FAR 15.408,

Table 15-2, Section II Paragraph A.(2)

For inter-organizational transfers proposed at cost, does the proposal include a complete cost proposal in compliance with Table 15-2?

22. FAR 15.408,

Table 15-2, Section II Paragraph A(1)

For inter-organizational transfers proposed at price in provide accordance with FAR 31.205-26(e), does the proposal an analysis by the prime that supports the exception from certified cost or pricing data in accordance with FAR 15.403-1?

DIRECT LABOR

23. FAR 15.408,

Table 15- 2, Section II Paragraph B

Does the proposal include a time phased (i.e.; monthly, quarterly) breakdown of labor hours, rates and costs by category or skill level? If labor is the allocation base for indirect costs, the labor cost must be summarized in order that the applicable overhead rate can be applied.

24. FAR 15.408,

Table 15-2, Section II Paragraph B

For labor Basis of Estimates (BOEs), does the proposal include labor categories, labor hours, and task descriptions--(e.g.; Statement of Work reference, applicable CLIN, Work Breakdown Structure, rationale for estimate, applicable history, and time-phasing)?

25. FAR subpart 22.10

If covered by the Service Contract Labor Standards statute (41 U.S.C. chapter 67), are the rates in the proposal in compliance with the minimum rates specified in the statute?

INDIRECT COSTS

26. FAR 15.408,

Table 15-2, Section II Paragraph C

Does the proposal indicate the basis of estimate for proposed indirect costs and how they are applied?

(Support for the indirect rates could consist of cost breakdowns, trends, and budgetary data.)

OTHER COSTS

27. FAR 15.408,

Table 15-2, Section II Paragraph D.

Does the proposal include other direct costs and the basis for pricing? If travel is included does the proposal include number of trips, number of people, number of days per trip, locations, and rates (e.g. airfare, per diem, hotel, car rental, etc)?

28. FAR 15.408,

Table 15-2, Section II Paragraph E

If royalties exceed $1,500 does the proposal provide the information/data identified by Table 15-2?

29. FAR 15.408,

Table 15-2, Section II Paragraph F

When facilities capital cost of money is proposed, does the proposal include submission of Form CASB-CMF or reference to an FPRA/FPRP and show the calculation of the proposed amount?

FORMATS FOR SUBMISSION OF LINE ITEM SUMMARIES

30. FAR 15.408,

Table 15-2, Section III

Are all cost element breakdowns provided using the applicable format prescribed in FAR 15.408, Table 15-2 III? (or alternative format if specified in the request for proposal)

31. FAR 15.408,

Table 15-2, Section III Paragraph B

If the proposal is for a modification or change order, have cost of work deleted (credits) and cost of work added (debits) been provided in the format described in FAR 15.408,Table 15-2.III.B?

32. FAR 15.408,

Table 15-2, Section III Paragraph C

For price revisions/redeterminations, does the proposal follow the format in FAR 15.408, Table 15-2.III.C?

OTHER

33. FAR 16.4 If an incentive contract type, does the proposal include offeror proposed target cost, target profit or fee, share ratio, and, when applicable, minimum/maximum fee, ceiling price?

34. FAR 16.203-4

and FAR 15.408,Table 15-2, Section II, Paragraphs A, B, C, and D

If Economic Price Adjustments are being proposed, does the proposal show the rationale and application for the economic price adjustment?

35. FAR 52.232-28 If the offeror is proposing Performance-Based Payments--did the offeror comply with FAR 52.232-28?

36. FAR 15.408(n)

FAR 52.215-22

FAR 52.215-23

Excessive Pass-through Charges--Identification of Subcontract Effort: If the offeror intends to subcontract more than 70%of the total cost of work to be performed, does the proposal identify: (i) the amount of the offeror's indirect costs and profit applicable to the work to be performed by the proposed subcontractor(s); and (ii) a description of the added value provided by the offeror as related to the work to be performed by the proposed subcontractor(s)?

252.215-7010 REQUIREMENTS FOR CERTIFIED COST OR PRICING DATA AND DATA OTHER

THAN CERTIFIED COST OR PRICING DATA-BASIC (JAN 2023)

(IAW DFARS 215.408(5)(i) and DFARS (5)(i)(A))

252.215-7010 REQUIREMENTS FOR CERTIFIED COST OR PRICING DATA AND DATA OTHER

THAN CERTIFIED COST OR PRICING DATA--ALTERNATE I (JAN 2023)

(IAW DFARS 215.408(5)(i) and DFARS 215.408(5)(i)(B))

252.215-7011 REQUIREMENT FOR SUBMISSION OF PROPOSALS TO THE ADMINISTRATIVE

CONTRACTING OFFICER AND CONTRACT AUDITOR (JAN 2018)

(IAW DFARS 215.408(5)(ii))

252.215-7012 REQUIREMENTS FOR SUBMISSION OF PROPOSALS VIA ELECTRONIC MEDIA

(JAN 2018)

(IAW DFARS 215.408(5)(iii))